Issue date | Title | Topic | |
---|---|---|---|
NOC-AE-000675, Forwards Clarification on Items Included in 990531 Response to RAI Re Proposed License Amend Associated with Operator Action for Sbloca,As Requested | 21 October 1999 | Forwards Clarification on Items Included in 990531 Response to RAI Re Proposed License Amend Associated with Operator Action for Sbloca,As Requested | |
NOC-AE-000680, Forwards Rev 5 to 0PGP03-ZV-0001, Severe Weather Plan | 20 October 1999 | Forwards Rev 5 to 0PGP03-ZV-0001, Severe Weather Plan | |
NOC-AE-000683, Forwards 30-day Rept Concerning Significant Changes to Accepted Large Break Loss of Coolant Accident ECCS Evaluation Model for South Tx Project,Units 1 & 2,IAW 10CFR50.46(a)(3)(ii) | 19 October 1999 | Forwards 30-day Rept Concerning Significant Changes to Accepted Large Break Loss of Coolant Accident ECCS Evaluation Model for South Tx Project,Units 1 & 2,IAW 10CFR50.46(a)(3)(ii) | |
ML20217K934 | 15 October 1999 | Forwards SER Accepting Util 990609 Relief Request RR-ENG-2-4 for Relief from ASME Code,Section XI, Nondestructive Exam Requirements Applicable to Stp,Units 1 & 2,reactor Vessel Closure Head Nuts | |
ML20217K909 | 15 October 1999 | Forwards SER Accepting Util 990609 Relief Request RR-ENG-2-3 from ASME Code,Section Xi,Nondestructive Exam Requirements Applicable to South Texas Project,Units 1 & 2, Pressurizer Support Attachment Welds | Nondestructive Examination |
05000498/LER-1999-008, Forwards LER 99-008-00 Re Turbine Trip That Occurred While Performing Main Turbine Emergency Trip Test.Commitments Made by Licensee Are Listed in Corrective Actions Section of LER | 12 October 1999 | Forwards LER 99-008-00 Re Turbine Trip That Occurred While Performing Main Turbine Emergency Trip Test.Commitments Made by Licensee Are Listed in Corrective Actions Section of LER | |
NOC-AE-000674, Forwards Requested Estimates of Needs for Operator Licensing Exams,Per AL-99-03, Operator Licensing National Exam Schedule | 12 October 1999 | Forwards Requested Estimates of Needs for Operator Licensing Exams,Per AL-99-03, Operator Licensing National Exam Schedule | Generic Fundamentals Examination |
NOC-AE-000625, Requests Partial Relief from ASME Section XI Visual Exam Requirements of IWA-5242(a).Relief Request Is Based on Provisions of Draft ASME Section XI Code Case N-616,which Is Expected to Be Published in Near Future | 7 October 1999 | Requests Partial Relief from ASME Section XI Visual Exam Requirements of IWA-5242(a).Relief Request Is Based on Provisions of Draft ASME Section XI Code Case N-616,which Is Expected to Be Published in Near Future | Boric Acid VT-2 Scaffolding |
NOC-AE-000653, Requests Relief from ASME Section XI Code Requirements of Table IWE-2500-1 for VT-3 Visual Exam of Seals & Gaskets on Airlocks,Hatches & Other Devices Required to Assure Containment leak-tight Integrity,Per 10CFR50.55a(a)(3)(i) | 7 October 1999 | Requests Relief from ASME Section XI Code Requirements of Table IWE-2500-1 for VT-3 Visual Exam of Seals & Gaskets on Airlocks,Hatches & Other Devices Required to Assure Containment leak-tight Integrity,Per 10CFR50.55a(a)(3)(i) | |
NOC-AE-000610, Requests Relief from ASME Section XI Code Nondestructive Exam Requirements of IWA-5250(a)(2) for Second Inservice Insp Interval,Per Provisions of 10CFR50.55a(3)(i) | 7 October 1999 | Requests Relief from ASME Section XI Code Nondestructive Exam Requirements of IWA-5250(a)(2) for Second Inservice Insp Interval,Per Provisions of 10CFR50.55a(3)(i) | Nondestructive Examination |
ML20217C322 | 7 October 1999 | Forwards Insp Repts 50-498/99-16 & 50-499/99-16 on 990808-0918.No Violations Noted.Insp Generally Characterized by safety-conscious Operations,Sound Engineering & Maint Practices & Careful Radiological Work Controls | |
ML20212L165 | 30 September 1999 | Responds to STP Nuclear Operating Co 981012 & s Which Provided Update to TS Bases Pages B 3/4 8-14 Through B 3/4 8-17.NRC Staff Found Change Consistent with TS 3/4.8.2 DC Sources. Staff Found & Deleted Typographical Error | Battery sizing |
05000499/LER-1999-006, Forwards LER 99-006-00,re Entry Into TS 3.0.3.Licensee Commitments Listed in Corrective Actions Section of Attachment | 30 September 1999 | Forwards LER 99-006-00,re Entry Into TS 3.0.3.Licensee Commitments Listed in Corrective Actions Section of Attachment | |
NOC-AE-000664, Forwards Rev 1 to STP Electric Generating Station Unit 1 Cycle 9 COLR & Rev 1 to STP Electric Generating Station Unit 2 Cycle 7 Colr | 30 September 1999 | Forwards Rev 1 to STP Electric Generating Station Unit 1 Cycle 9 COLR & Rev 1 to STP Electric Generating Station Unit 2 Cycle 7 Colr | |
ML20212J714 | 29 September 1999 | Forwards Insp Repts 50-498/99-15 & 50-499/99-15 on 990920-24 at South Texas Project Electric Generating Station.No Violations Noted.Insp Covered Requalification Training Program & Observation of Requalification Activities | |
NOC-AE-000646, Informs NRC That STP Nuclear Operating Co Is Y2K Ready IAW Nei/Nusmg 97-07 Guidelines & Also Provides Response to NRC Ltr | 28 September 1999 | Informs NRC That STP Nuclear Operating Co Is Y2K Ready IAW Nei/Nusmg 97-07 Guidelines & Also Provides Response to NRC Ltr | |
ML20212J065 | 27 September 1999 | Discusses Licensee 980330 Response to GL 97-06, Degradation of SG Internals. Concludes That Response to GL Provides Reasonable Assurance That Condition of SG Internals in Compliance with Current Licensing Bases for Facility | |
ML20212F179 | 24 September 1999 | Discusses 990923 Meeting Conducted in Region IV Ofc Re Status of Activities to Support Confirmatory Order, ,modifying OL & to Introduce New Director,Safety Quality Concerns Program.List of Attendees Encl | |
ML20212E909 | 23 September 1999 | Discusses GL 98-01, Year 2000 Readiness of Computer Sys at Npps, Supplement 1 & STP Nuclear Operating Co Response for STP Dtd 990629.Understands That at Least One Sys or Component Listed May Have Potential to Cause Transient | |
ML20212F211 | 22 September 1999 | Forwards Review of SG 90-day Rept, South Texas Unit-2 Cycle 7 Voltage-Based Repair Criteria Rept, Submitted by Util on 990119 | |
NOC-AE-000633, Forwards Rev 3 to SG-99-04-005, STP 1RE08 Outage Condition Monitoring Rept & Final Operational Assessment. Rept Satisfies Reporting Requirements of NEI 97-06,dtd Dec 1997 | 21 September 1999 | Forwards Rev 3 to SG-99-04-005, STP 1RE08 Outage Condition Monitoring Rept & Final Operational Assessment. Rept Satisfies Reporting Requirements of NEI 97-06,dtd Dec 1997 | |
NOC-AE-000634, Forwards Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Povs. MOV design-basis Review Checklist,Encl | 21 September 1999 | Forwards Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Povs. MOV design-basis Review Checklist,Encl | Stroke time |
NOC-AE-000649, Forwards Current Annual Financial Data for STP Electric Generating Station Per 10CFR50.71(b),acting on Behalf of Central Power & Light Co,City of Austin,Tx,City Public Svc Board of San Antonio & Hl&P | 21 September 1999 | Forwards Current Annual Financial Data for STP Electric Generating Station Per 10CFR50.71(b),acting on Behalf of Central Power & Light Co,City of Austin,Tx,City Public Svc Board of San Antonio & Hl&P | |
05000499/LER-1999-005, Forwards LER 99-005-00,re Esfa Following Loss of Power to Standby Transformer 2 Due to Electrical Fault.Licensee Commitments Are Listed in Corrective Actions Section of LER | 20 September 1999 | Forwards LER 99-005-00,re Esfa Following Loss of Power to Standby Transformer 2 Due to Electrical Fault.Licensee Commitments Are Listed in Corrective Actions Section of LER | |
ML20212D917 | 16 September 1999 | Informs That on 990818,NRC Completed Midcycle PPR of South Texas Project & Identified No Areas in Which Performance Warranted Insp Beyond Core Insp Program.Details of Insp Plan Through Mar 2000 & Historical Listing of Plant Issues,Encl | |
ML20216F547 | 15 September 1999 | Discusses 990914 Meeting Conducted at Region Iv.Meeting Was Requested by Staff to Introduce New Management Organization to Region IV & to Discuss General Plant Performance & Mgt Challenges | |
IR 05000498/1999012 | 14 September 1999 | Forwards Insp Repts 50-498/99-12 & 50-499/99-12 on 990816-19.Three Violations Occurred & Being Treated as Ncvs. Areas Examined During Insp Included Portions of Access Authorization & Physical Security Programs | |
05000498/LER-1999-007, Forwards LER 99-007-00 Re Train 'B' CR Makeup & Cleanup Filtration Sys Being Inoperable for Greater than Aot.Util Intends to Append Addl Info Section of LER with Brief Description of Test Results,Rather than Submit Separate LER | 13 September 1999 | Forwards LER 99-007-00 Re Train 'B' CR Makeup & Cleanup Filtration Sys Being Inoperable for Greater than Aot.Util Intends to Append Addl Info Section of LER with Brief Description of Test Results,Rather than Submit Separate LER | Time of Discovery |
ML20211P787 | 9 September 1999 | Forwards Safety Evaluation Re First 10-yr Interval Inservice Insp Program Plan Request for Relief RR-ENG-31 | Hydrostatic |
ML20211P767 | 9 September 1999 | Forwards SER Authorizing Licensee 990517 Alternative Proposed in Relief Request RR-ENG-2-8 to Code Case N-491-2 for Second 10-year Insp Interval of South Texas Project, Units 1 & 2,pursuant to 10CFR50.55a(a)(3)(i) | |
ML20211P820 | 9 September 1999 | Forwards SE Authorizing 990224 Submittal of First 10-year Interval ISI Program Plan - Relief Request RR-ENG-24,from ASME Section XI Code,Table IWC-2500-1 | |
NOC-AE-000638, Forwards License Renewal Applications & Certifications of Medical Exam for Seven Listed Licensed Operators at Stp,Per 10CFR55.57.Encl Withheld,Per 10CFR2.790(a)(6) | 9 September 1999 | Forwards License Renewal Applications & Certifications of Medical Exam for Seven Listed Licensed Operators at Stp,Per 10CFR55.57.Encl Withheld,Per 10CFR2.790(a)(6) | |
IR 05000498/1999014 | 3 September 1999 | Forwards Insp Repts 50-498/99-14 & 50-499/99-14 on 990627-0807.Apparent Violations Identified & Being Treated as Noncited Violations Consistent with App C of Enforcement Policy | |
NOC-AE-000562, Requests Relief from Contruction Code non-destructive Exam Requirements for Repair/Replacement Activities During Second Inservice Insp Interval of Units 1 & 2,IAW Provisions of 10CFR50.55a(a)(3)(i) | 31 August 1999 | Requests Relief from Contruction Code non-destructive Exam Requirements for Repair/Replacement Activities During Second Inservice Insp Interval of Units 1 & 2,IAW Provisions of 10CFR50.55a(a)(3)(i) | Nondestructive Examination |
ML20212A435 | 27 August 1999 | Discusses Investigation Rept OI-4-1999-009 Re Activites at South Texas Project.Oi Investigation Initiated in Response to Alleged Employment Discrimination Complaint. Allegation Not Substantiated.No Further Action Planned | |
ML20211J251 | 26 August 1999 | Discusses Proposed TS Change on Replacement SG Water Level Trip Setpoint for Plant,Units 1 & 2 | |
NOC-AE-000617, Forwards semi-annual Fitness for Duty Program Performance Rept for 990101-990630,IAW 10CFR26.71(d) | 26 August 1999 | Forwards semi-annual Fitness for Duty Program Performance Rept for 990101-990630,IAW 10CFR26.71(d) | Fitness for Duty |
NOC-AE-000585, Provides Notification That South Texas Project Has Completed Integrity Evaluation of Units 1 & 2 Reactor Coolant Pump Casings Required by Paragraph (D) of Code Case N-481 | 25 August 1999 | Provides Notification That South Texas Project Has Completed Integrity Evaluation of Units 1 & 2 Reactor Coolant Pump Casings Required by Paragraph (D) of Code Case N-481 | VT-2 |
ML20211F442 | 24 August 1999 | Forwards SE Authorizing Licensee 990513 Request for Relief RR-ENG-2-13,seeking Relief from ASME B&PV Code Section Xi,Exam Vessel shell-to-flange Welds for Second ISI Intervals | |
ML20211F503 | 23 August 1999 | Forwards SE Authorizing Licensee 990315 Request for Relief RR-ENG-30,seeking Relief from ASME B&PV Code,Section Xi,Nde Requirements Applicable to Stp,Unit 2 SG Welds | Nondestructive Examination |
ML20212A439 | 17 August 1999 | Discusses Investigation Rept OI-4-1999-023 Re Activities at South Texas Project.Oi Investigation Initiated in Response to Alleged Employment Discrimination for Initiating Condition Report to Document Unauthorized Work Practices | |
ML20210U127 | 16 August 1999 | Forwards Insp Repts 50-498/99-08 & 50-499/99-08 on 990517-21 & 0607-10.No Violations Noted.Corrective Action Program Was Reviewed | |
ML20211A950 | 12 August 1999 | Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl | |
ML20211B788 | 10 August 1999 | Transmits Summary of Two Meetings with Risk-Informed TS Task Force in Rockville,Md on 990514 & 0714 | Shutdown Margin Missed surveillance Large early release frequency |
ML20210L146 | 3 August 1999 | Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams | Generic Fundamentals Examination |
NOC-AE-000603, Informs of Addition of Restriction to SRO License 42658, for KM Espinoza,Effective 990721,per 10CFR50.74.Encl Info Withheld,Per 10CFR2.790(a)(6) | 29 July 1999 | Informs of Addition of Restriction to SRO License 42658, for KM Espinoza,Effective 990721,per 10CFR50.74.Encl Info Withheld,Per 10CFR2.790(a)(6) | |
NOC-AE-000470, Forwards Amend 12 to STP Fire Hazards Analysis Rept. Summary of Changes Made Under Provision of 10CFR50.59 Also Encl | 28 July 1999 | Forwards Amend 12 to STP Fire Hazards Analysis Rept. Summary of Changes Made Under Provision of 10CFR50.59 Also Encl | |
NOC-AE-000599, Forwards STP Unit 1,Cycle 9 Startup Testing Summary Rept. No New Licensing Commitments Contained in Ltr | 28 July 1999 | Forwards STP Unit 1,Cycle 9 Startup Testing Summary Rept. No New Licensing Commitments Contained in Ltr | |
ML20210F385 | 26 July 1999 | Forwards Exam Repts 50-498/99-301 & 50-499/99-301 on 990706- 15.Exam Included Evaluation of 9 Applicants for SO Licenses & 8 Applicants for RO Licenses | |
05000498/LER-1999-006, Forwards LER 99-006-00 Re Automatic Reactor Trip Due to over-temp delta-temp Actuation.Licensee Commitments Are Listed in Corrective Actions Section of LER | 26 July 1999 | Forwards LER 99-006-00 Re Automatic Reactor Trip Due to over-temp delta-temp Actuation.Licensee Commitments Are Listed in Corrective Actions Section of LER |