ML22131A023
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 05/11/2022
From: Snider S
Duke Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RA-22-0145
Download: ML22131A023 (7)


Text

Steven M. Snider Vice President Oconee Nuclear Station

Duke Energy ON01VP l 7800 Rochester Hwy Seneca, SC 29672 o:864.873.3478 f: 864.873.5791 RA-22-0145 Steve.Snider@duke-energy.com May 11, 2022 10 CFR 50.4 10 CFR Part 54

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Subject:

Duke Energy Carolinas, LLC (Duke Energy)

Oconee Nuclear Station (ONS), Units 1, 2, and 3 Docket Numbers 50-269, 50-270, 50-287 Renewed License Numbers DPR-38, DPR-47, DPR-55 Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information - RAI 3.5.2.2.2.6-L

References:

1. Duke Energy Letter (RA-21-0132) dated June 7, 2021, Application for Subsequent Renewed Operating Licenses, (ADAMS Accession Number ML21158A193)
2. NRC Letter dated July 22, 2021, Oconee Nuclear Station, Units 1, 2, and 3 - Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding Duke Energy Carolinas Application for Subsequent License Renewal (ADAMS Accession Number ML21194A245)
3. NRC E-mail dated November 4, 2021, Oconee SLRA - Requests for Confirmation of Information -

Set 1 (ADAMS Accession Number ML21313A233 and ML21313A234)

4. Duke Energy Letter dated December 2, 2021, Oconee Nuclear Station, Units 1, 2, and 3 -

Response to NRC Requests for Confirmation of Information - Set 1 (ADAMS Accession Number ML21336A001)

5. NRC E-mail dated November 23, 2021, Oconee SLRA - Requests for Confirmation of Information -

Set 2 (ADAMS Accession Number ML21330A018)

6. Duke Energy Letter dated December 17, 2021, Oconee Nuclear Station, Units 1, 2, and 3 -

Response to NRC Requests for Confirmation of Information - Set 2 (ADAMS Accession Number ML21351A000)

7. NRC E-mail dated January 5, 2022, Oconee SLRA - Requests for Confirmation of Information -

Set 3 (ADAMS Accession Number ML22010A112 and ML22010A113)

8. Duke Energy Letter dated January 21, 2022, Oconee SLRA - Response to NRC Requests for Confirmation of Information - Set 3 (ADAM Accession Number ML22021A000)
9. NRC E-mail dated March 8, 2022, Oconee SLRA - Requests for Confirmation of Information - Set 4 (ADAMS Accession Number ML22069A001)
10. Duke Energy Letter dated March 22, 2022, Oconee SLRA - Response to NRC Requests for Confirmation of Information - Set 4 (ADAM Accession Number ML22081A027)
11. NRC E-mail dated April 20, 2022, Oconee SLRA - Requests for Confirmation of Information - RCI 3.5.2.2.2.6-L (ADAMS Accession Numbers ML22112A004, ML22112A006 and ML22112A007)

U.S. Nuclear Regulatory Commission May 11, 2022 Page 2

By letter dated June 7, 2021 (Reference 1), Duke Energy Carolinas, LLC (Duke Energy) submitted an application for the subsequent license renewal of Renewed Facility Operating License Numbers DPR-38, DPR-47, and DPR-55 for the Oconee Nuclear Station (ONS), Units 1, 2, and 3 to the U.S. Nuclear Regulatory Commission (NRC). On July 22, 2021 (Reference 2), the NRC determined that ONS subsequent license renewal application (SLRA) was acceptable and sufficient for docketing. In emails from Angela X. Wu (NRC) to Steve Snider (Duke Energy) (References 3, 5, 7 and 9), the NRC transmitted Sets 1, 2, 3 and 4, respectively, of specific requests for confirmation of information (RCl) to support completion of the Safety Review. Duke Energy responded to the RCIs in letters dated December 2, 2021, December 17, 2021, January 21, 2022, and March 22, 2022 (References 4, 6, 8 and 10), respectively.

In an email from Marieliz Johnson (NRC) to Steve Snider (Duke Energy) dated April 20, 2022 (Reference 11), the NRC transmitted RCl 3.5.2.2.2.6-L to support completion of the Safety Review. The response to RCI 3.5.2.2.2.6-L is provided in Enclosure 1. Note that since the specific RCI request is proprietary, it was referenced, but not repeated in Enclosure 1.

Should you have any questions regarding this submittal, please contact Paul Guill at (704) 382-4753 or by email at paul.guill@duke-energy.com.

I declare under penalty of perjury that the foregoing is true and correct. Executed on May 11, 2022.

Sincerely,

Steven M. Snider Site Vice President Oconee Nuclear Station

Enclosures:

Responses to Requests for Confirmation of Information - RCI 3.5.2.2.2.6-L

U.S. Nuclear Regulatory Commission May 11, 2022 Page 3

CC: W/O

Enclosures:

Laura A. Dudes Regional Administrator U.S. Nuclear Regulatory Commission - Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257

Angela X. Wu, Project manager (by electronic mail only)

U.S. Nuclear Regulatory Commission Mail Stop 11 G3 11555 Rockville Pike Rockville, Maryland 20852

Shawn A. Williams, Project Manager (by electronic mail only)

U.S. Nuclear Regulatory Commission Mail Stop 8 B1A 11555 Rockville Pike Rockville, Maryland 20852

Jared Nadel (by electronic mail only)

NRC Senior Resident Inspector Oconee Nuclear Station

Anuradha Nair (by electronic mail only: naira@dhec.sc.gov)

Bureau Environmental Health Services Department of Health & Environmental Control 2600 Bull Street Columbia, South Carolina 29201

U.S. Nuclear Regulatory Commission May 11, 2022 Page 4

BCC: W/O

Enclosures:

T.P. Gillespie K. Henderson S.D. Capps T.M. Hamilton P.V. Fisk H.T. Grant D.A. Wilson M.C. Nolan S.M. Snider R.K. Nader G.D. Robison T.M. LeRoy P.F. Guill R.V. Gambrell File: (Corporate)

Electronic Licensing Library (ELL)

ENCLOSURE 1

OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 SUBSEQUENT LICENSE RENEWAL APPLICATION RESPONSES TO REQUESTS FOR CONFIRMATION OF INFORMATION - RCI 3.5.2.2.2.6-L

Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Responses to Requests for Confirmation of Information - RCI 3.5.2.2.2.6-L

Enclosure 1 Subsequent License Renewal Application Responses to Requests for Confirmation of Information - RCI 3.5.2.2.2.6-L

Regulatory Basis:

Part 54 of Title 10 of the Code of Federal Regulations (10 CFR), Requirements for Renewal of Operating Licenses for Nuclear Power Plants, is designed to elicit application information that will enable the U.S. Nuclear Regulatory Commission (NRC) staff to perform an adequate safety review and the Commission to make the necessary findings. Reliability of application information is important and advanced by requirements that license applications be submitted in writing under oath or affirmation and that information provided to the NRC by a license renewal applicant or required to be maintained by NRC regulations be complete and accurate in all material respects. Information that must be submitted in writing under oath or affirmation includes the technical information required under 10 CFR 54.21(a) related to assessment of the aging effects on structures, systems, and components subject to an aging management review. Thus, both the general submission requirements for license renewal applications and the specific technical application information requirements require that submission of information material to NRCs safety findings (see 10 CFR 54.29 standards for issuance of a renewed license) be submitted by an applicant as part of the application.

Background:

By letter dated June 7, 2021 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML21158A193), as supplemented by letters dated October 22, 2021 (ADAMS Accession No. ML21295A035), October 28, 2021 (ADAMS Accession No. ML21302A208), November 11, 2021 (ADAMS Accession No. ML21315A012), December 2, 2021 (ADAMS Accession No. ML21336A001),

December 15, 2021 (ADAMS Accession No. ML21349A005), December 17, 2021 (ADAMS Accession No. ML21351A000), January 7, 2022 (ADAMS Accession No. ML22010A129), January 21, 2022 (ADAMS Accession No. ML22021A000), February 14, 2022 (ADAMS Accession No. ML22045A021),

February 21, 2022 (ADAMS Accession No. ML22052A002), March 22,2022 (ADAMS Accession No. ML22081A027), and March 31, 2022 (ADAMS Accession No. ML22090A046), Duke Energy Carolinas, LLC (Duke Energy) submitted to the U.S. Nuclear Regulatory Commission (NRC or staff) an application to renew the Renewed Facility Operating License Nos. DPR-38, DPR-47, and DPR-55 for Oconee

1

Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Responses to Requests for Confirmation of Information - RCI 3.5.2.2.2.6-L

Nuclear Station (ONS), Units 1, 2, and 3. Duke Energy submitted the application pursuant to 10 CFR Parts 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, for subsequent license renewal.

Request:

To the best of the staffs knowledge, this information is not on the docket. Any information used to reach a conclusion in the SER must be included on the docket by the applicant. We request that you submit confirmation that the information gathered from the documents and listed below is correct or provide the associated corrected information.

Request for Confirmation of Information (RCI) 3.5.2.2.2.6-L:

The proprietary request for RCl 3.5.2.2.2.6-L is contained in the email from Marieliz Johnson (NRC) to Steve Snider (Duke Energy) dated April 20, 2022 (ADAMS Accession Numbers ML22112A004, ML22112A006, and ML22112A007).

Response to RCI 3.5.2.2.2.6-L:

The proprietary information provided in the request of the RCI email from the NRC dated April 20, 2022 (ADAMS Accession Numbers ML22112A004, ML22112A006 and ML22112A007), has been confirmed to be correct as stated.