Letter Sequence Response to RAI |
---|
EPID:L-2018-LLA-0300, License Amendment Request Proposing a Revised Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, ... (Approved, Closed) |
|
|
|
---|
Category:Letter type:RA
MONTHYEARRA-23-0325, Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEX2024-01-0808 January 2024 Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEX RA-23-0320, Notification of Deviation from MRP-227, Revision 1-A Baffle-to-Former Bolt Inspection Frequency2023-12-14014 December 2023 Notification of Deviation from MRP-227, Revision 1-A Baffle-to-Former Bolt Inspection Frequency RA-23-0318, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0404 December 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0182, Duke Energy Carolinas, LLC - License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program for a One-Time Extension of the Units 1, 2 and 3 Type a Leak Rate Test Frequency2023-11-16016 November 2023 Duke Energy Carolinas, LLC - License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program for a One-Time Extension of the Units 1, 2 and 3 Type a Leak Rate Test Frequency RA-23-0284, RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0304, Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 32 (Revision 0)2023-11-14014 November 2023 Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 32 (Revision 0) RA-23-0281, Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes2023-11-0101 November 2023 Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes RA-23-0275, Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI)2023-10-12012 October 2023 Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI) RA-23-0268, Transmittal of Sixth 10-Year Inservice Testing Interval Program Plan2023-09-29029 September 2023 Transmittal of Sixth 10-Year Inservice Testing Interval Program Plan RA-23-0234, Update to the Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations for Oconee Nuclear Station (ONS)2023-09-28028 September 2023 Update to the Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations for Oconee Nuclear Station (ONS) RA-23-0225, Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes2023-09-20020 September 2023 Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes RA-23-0228, Registration for Use of General License Spent Fuel Cask Number 1752023-09-14014 September 2023 Registration for Use of General License Spent Fuel Cask Number 175 RA-23-0223, Registration for Use of General License Spent Fuel Cask Numbers 173 and 1742023-08-23023 August 2023 Registration for Use of General License Spent Fuel Cask Numbers 173 and 174 RA-23-0222, On-Shift Staffing Analysis (Ossa), Revision 12023-08-23023 August 2023 On-Shift Staffing Analysis (Ossa), Revision 1 RA-23-0211, Reply to a Notice of Violation (NOV) 05000270/2023010-022023-08-17017 August 2023 Reply to a Notice of Violation (NOV) 05000270/2023010-02 RA-23-0154, Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0136, Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0186, Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 31 (Revision 3)2023-07-18018 July 2023 Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 31 (Revision 3) RA-23-0184, Registration for Use of General License Spent Fuel Cask Numbers 171 and 1722023-07-10010 July 2023 Registration for Use of General License Spent Fuel Cask Numbers 171 and 172 RA-23-0142, Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require2023-07-0707 July 2023 Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require RA-23-0146, Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI)2023-06-20020 June 2023 Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI) RA-23-0135, Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory2023-06-0707 June 2023 Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory RA-23-0041, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-30030 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations RA-23-0128, Refuel 32 (O1R32) Steam Generator Tube Inspection Report2023-05-18018 May 2023 Refuel 32 (O1R32) Steam Generator Tube Inspection Report RA-23-0018, Relief Request (RA-23-0018) to Utilize Code Case N-853 PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Susceptible to Primary Water Stress Corrosion Cracking Section XI, Division 12023-05-0404 May 2023 Relief Request (RA-23-0018) to Utilize Code Case N-853 PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Susceptible to Primary Water Stress Corrosion Cracking Section XI, Division 1 RA-23-0111, Withdrawal of License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-04-27027 April 2023 Withdrawal of License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies RA-23-0104, Response to Request for Additional Information (RAI) Regarding Oconee Unit 3, Refuel 31 (O3R31) Steam Generator Tube Inspection Report2023-04-26026 April 2023 Response to Request for Additional Information (RAI) Regarding Oconee Unit 3, Refuel 31 (O3R31) Steam Generator Tube Inspection Report RA-23-0047, Duke Energy Annual Radiological Environmental Operating Report - 20222023-04-26026 April 2023 Duke Energy Annual Radiological Environmental Operating Report - 2022 RA-23-0044, Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.462023-04-26026 April 2023 Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.46 RA-23-0099, Subsequent License Renewal Application Second Annual Amendment to the License Renewal Application2023-04-25025 April 2023 Subsequent License Renewal Application Second Annual Amendment to the License Renewal Application RA-23-0046, Annual Radioactive Effluent Release Report - 20222023-04-24024 April 2023 Annual Radioactive Effluent Release Report - 2022 RA-22-0292, License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-04-0404 April 2023 License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies RA-23-0036, Biennial Decommissioning Financial Assurance Reports2023-03-30030 March 2023 Biennial Decommissioning Financial Assurance Reports RA-23-0040, Onsite Property Insurance Coverage2023-03-30030 March 2023 Onsite Property Insurance Coverage RA-23-0039, 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2023-03-30030 March 2023 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums RA-23-0037, Duke Energy - Decommissioning Funding Plan for Independent Spent Fuel Storage Installations (Isfsis)2023-03-30030 March 2023 Duke Energy - Decommissioning Funding Plan for Independent Spent Fuel Storage Installations (Isfsis) RA-23-0051, Response to Request for Additional Information (RAI) Regarding Proposed Alternative to Use American Society of Mechanical Engineers Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities2023-03-0909 March 2023 Response to Request for Additional Information (RAI) Regarding Proposed Alternative to Use American Society of Mechanical Engineers Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities RA-23-0052, Refuel 32 (O1R32) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval2023-02-22022 February 2023 Refuel 32 (O1R32) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval RA-22-0257, Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-02-17017 February 2023 Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) RA-22-0091, Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2023-02-16016 February 2023 Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RA-23-0001, Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI2023-02-0202 February 2023 Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI RA-22-0118, License Amendment Request to Revise Restrictive Technical Specification Surveillance Requirement Frequencies2023-02-0101 February 2023 License Amendment Request to Revise Restrictive Technical Specification Surveillance Requirement Frequencies RA-22-0256, Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2023-01-23023 January 2023 Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) RA-22-0335, Submittal of 30-Day Report Per 10CFR26.719(c)(1) - Unsatisfactory Performance of a Health & Human Services Certified Lab2022-12-0505 December 2022 Submittal of 30-Day Report Per 10CFR26.719(c)(1) - Unsatisfactory Performance of a Health & Human Services Certified Lab RA-22-0334, Refuel 31 (O3R31) Steam Generator Tube Inspection Report2022-11-21021 November 2022 Refuel 31 (O3R31) Steam Generator Tube Inspection Report RA-22-0329, Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 1 Cycle 33 (Revision 0 and Revision 1)2022-11-11011 November 2022 Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 1 Cycle 33 (Revision 0 and Revision 1) RA-22-0285, Subsequent License Renewal - Appendix E Environmental Report Supplement 22022-11-0707 November 2022 Subsequent License Renewal - Appendix E Environmental Report Supplement 2 RA-22-0313, Emergency Action Level (EAL) Technical Basis Document, Revision 4, EAL Wallchart, Revision 3 and Alternate TSC and OSC Renovations2022-10-27027 October 2022 Emergency Action Level (EAL) Technical Basis Document, Revision 4, EAL Wallchart, Revision 3 and Alternate TSC and OSC Renovations RA-22-0270, Response to Request for Additional Information Regarding License Amendment Request to Address Technical Specifications Mode Change Limitations2022-10-0707 October 2022 Response to Request for Additional Information Regarding License Amendment Request to Address Technical Specifications Mode Change Limitations RA-22-0192, Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4a2022-09-0202 September 2022 Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4a 2024-01-08
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARRA-23-0275, Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI)2023-10-12012 October 2023 Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI) RA-23-0136, Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0154, Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0142, Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require2023-07-0707 July 2023 Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require RA-23-0146, Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI)2023-06-20020 June 2023 Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI) RA-23-0104, Response to Request for Additional Information (RAI) Regarding Oconee Unit 3, Refuel 31 (O3R31) Steam Generator Tube Inspection Report2023-04-26026 April 2023 Response to Request for Additional Information (RAI) Regarding Oconee Unit 3, Refuel 31 (O3R31) Steam Generator Tube Inspection Report RA-23-0051, Response to Request for Additional Information (RAI) Regarding Proposed Alternative to Use American Society of Mechanical Engineers Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities2023-03-0909 March 2023 Response to Request for Additional Information (RAI) Regarding Proposed Alternative to Use American Society of Mechanical Engineers Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities RA-22-0270, Response to Request for Additional Information Regarding License Amendment Request to Address Technical Specifications Mode Change Limitations2022-10-0707 October 2022 Response to Request for Additional Information Regarding License Amendment Request to Address Technical Specifications Mode Change Limitations RA-22-0192, Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4a2022-09-0202 September 2022 Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4a RA-22-0160, Subsequent License Renewal Application: Responses to ONS SLRA - Second Round RAIs - Trp 76 (Irradiation Structural) - FE 3.5.2.2.2.62022-07-25025 July 2022 Subsequent License Renewal Application: Responses to ONS SLRA - Second Round RAIs - Trp 76 (Irradiation Structural) - FE 3.5.2.2.2.6 RA-22-0193, Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4b2022-07-0808 July 2022 Subsequent License Renewal Application Response to ONS SLRA Second Round RAI B2.1.7-4b RA-22-0158, Subsequent License Renewal Application - Response to ONS SLRA Second Round RAI B2.1.9-2a2022-06-0808 June 2022 Subsequent License Renewal Application - Response to ONS SLRA Second Round RAI B2.1.9-2a RA-22-0159, Subsequent License Renewal Application Response to ONS SLRA Request for Additional Information (RAI) 3.1.2-12022-05-27027 May 2022 Subsequent License Renewal Application Response to ONS SLRA Request for Additional Information (RAI) 3.1.2-1 RA-22-0137, Subsequent License Renewal Application Response to ONS SLRA Second Round RAI 4.6.1-1a2022-05-20020 May 2022 Subsequent License Renewal Application Response to ONS SLRA Second Round RAI 4.6.1-1a RA-22-0147, Duke Energy Carolinas, LLC, and Duke Energy Progress, LLC, Response to Request for Additional Information (RAI) Regarding License Amendment Request for Relocating the Duke Energy Emergency Operations Facility2022-05-13013 May 2022 Duke Energy Carolinas, LLC, and Duke Energy Progress, LLC, Response to Request for Additional Information (RAI) Regarding License Amendment Request for Relocating the Duke Energy Emergency Operations Facility RA-22-0145, Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information - RAI 3.5.2.2.2.6-L2022-05-11011 May 2022 Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information - RAI 3.5.2.2.2.6-L RA-22-0124, Subsequent License Renewal Application Responses to NRC Request for Additional Information Set 42022-04-22022 April 2022 Subsequent License Renewal Application Responses to NRC Request for Additional Information Set 4 RA-22-0129, Subsequent License Renewal Application, Response to ONS SLRA 2nd Round RAI B4.1-32022-04-20020 April 2022 Subsequent License Renewal Application, Response to ONS SLRA 2nd Round RAI B4.1-3 RA-22-0089, Response to Request for Additional Information Regarding Application to Revise Technical Specification 3.7.7, Low Pressure Service Water System, to Extend the Completion Time for One Required Inoperable LPSW2022-04-14014 April 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specification 3.7.7, Low Pressure Service Water System, to Extend the Completion Time for One Required Inoperable LPSW RA-22-0111, Subsequent License Renewal Application, Follow-up Request for Additional Information Set 2 and 3 Updates2022-03-31031 March 2022 Subsequent License Renewal Application, Follow-up Request for Additional Information Set 2 and 3 Updates RA-22-0105, Subsequent License Renewal Application - Responses to NRC Requests for Confirmation of Information - Set 42022-03-22022 March 2022 Subsequent License Renewal Application - Responses to NRC Requests for Confirmation of Information - Set 4 ML22075A2032022-03-11011 March 2022 Email from Duke to NRC - Follow-Up Items from March 7, 2022 Public Meeting ML22074A0022022-03-11011 March 2022 Email from Duke to NRC - Follow-up Item from March 7, 2022 Public Meeting - SSW Tendon AMP RA-22-0040, Subsequent License Renewal Application: Responses to NRC Request for Additional Information Set 32022-02-21021 February 2022 Subsequent License Renewal Application: Responses to NRC Request for Additional Information Set 3 RA-22-0023, Subsequent License Renewal Application - Response to NRC Requests for Confirmation of Information - Set 32022-01-21021 January 2022 Subsequent License Renewal Application - Response to NRC Requests for Confirmation of Information - Set 3 RA-22-0025, Supplemental Information for Relief Request to Utilize an Alternative Acceptance Criteria for Code Case, PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material2022-01-20020 January 2022 Supplemental Information for Relief Request to Utilize an Alternative Acceptance Criteria for Code Case, PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material RA-21-0332, Subsequent License Renewal Application Responses to NRC Request for Additional Information Set 1 and Second Round Request for Additional Information B2.1.27-1a2022-01-0707 January 2022 Subsequent License Renewal Application Responses to NRC Request for Additional Information Set 1 and Second Round Request for Additional Information B2.1.27-1a ML22019A1182022-01-0707 January 2022 Enclosures 1,2 & 3: Oconee Nuclear Station, Units 1, 2 & 3, Subsequent License Renewal Application, Appendix E, Environmental Report - Index of Duke Energy'S Responses, Responses to NRC Requests for Confirmation of Information and NRC Reque ML22019A1232022-01-0707 January 2022 Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information and Request for Confirmation of Information ML22019A1202022-01-0707 January 2022 Appendix K ML22019A1192022-01-0707 January 2022 Appendix 1-A - Oconee Nuclear Station 122.21(r)(2)-(13) Submittal Requirement Checklist ML22019A1242022-01-0707 January 2022 Attachment 1: Oconee Nuclear Station, Units 1, 2 & 3, Subsequent License Renewal Application, Appendix E - HDR, Inc., 2020 Clean Water Act Documents ML22019A1212022-01-0707 January 2022 Appendix 13-B Peer Reviewer Communication Log ML22019A1222022-01-0707 January 2022 Calculation of Permeability by the Falling Head Method RA-22-0002, Appendix 10-B - Pump and Pipe Selection Calculations for a Hypothetical Cooling Tower Retrofit at Oconee Nuclear Station2022-01-0707 January 2022 Appendix 10-B - Pump and Pipe Selection Calculations for a Hypothetical Cooling Tower Retrofit at Oconee Nuclear Station ML22007A0152022-01-0707 January 2022 Subsequent License Renewal Application, Appendix E Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information RA-21-0325, Response to NRC Requests for Confirmation of Information - Set 22021-12-17017 December 2021 Response to NRC Requests for Confirmation of Information - Set 2 RA-21-0307, Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information - Set 12021-12-0202 December 2021 Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information - Set 1 RA-21-0269, Response to Request for Additional Information Regarding Alternative Request to Utilize American Society of Mechanical Engineers (ASME) Code Case OMN-282021-11-0909 November 2021 Response to Request for Additional Information Regarding Alternative Request to Utilize American Society of Mechanical Engineers (ASME) Code Case OMN-28 RA-21-0270, Response to Second Request for Additional Information (RAI) Regarding Relief Request to Utilize an Alternative Acceptance Criteria for Code Case N-8532021-10-28028 October 2021 Response to Second Request for Additional Information (RAI) Regarding Relief Request to Utilize an Alternative Acceptance Criteria for Code Case N-853 RA-21-0242, Response to Request for Additional Information, Regarding Relief Request to Utilize an Alternative Acceptance Criteria for Code Case N-853, PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection2021-08-31031 August 2021 Response to Request for Additional Information, Regarding Relief Request to Utilize an Alternative Acceptance Criteria for Code Case N-853, PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection RA-21-0219, Response to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Intervals2021-08-0505 August 2021 Response to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Intervals RA-21-0063, 1, 2; Catawba Nuclear Station 1, 2; H. B. Robinson Steam Electric Plant 2; Mcgguire Nuclear Station 1, 2; Oconee Nuclear Station 1, 2, 3; Shearon Harris Nuclear Power Plant 1 - Response to RAI Re Amend for Emergency Plan2021-03-11011 March 2021 1, 2; Catawba Nuclear Station 1, 2; H. B. Robinson Steam Electric Plant 2; Mcgguire Nuclear Station 1, 2; Oconee Nuclear Station 1, 2, 3; Shearon Harris Nuclear Power Plant 1 - Response to RAI Re Amend for Emergency Plan RA-21-0032, Duke Energy - Response to Requests for Additional Info for Request to Use a Provision of Later Edition & Addenda of the ASME Boiler & Pressure Vessel Code, Section XI for Repair/Replacement Activities in Accordance with 10 CFR 50.55a(g)(42021-02-11011 February 2021 Duke Energy - Response to Requests for Additional Info for Request to Use a Provision of Later Edition & Addenda of the ASME Boiler & Pressure Vessel Code, Section XI for Repair/Replacement Activities in Accordance with 10 CFR 50.55a(g)(4)( RA-20-0267, Proposed License Amendment Request to Revise Oconee Nuclear Station Current Licensing Basis for High Energy Line Breaks Outside of Containment Building - Responses to Request for Additional Information2020-09-17017 September 2020 Proposed License Amendment Request to Revise Oconee Nuclear Station Current Licensing Basis for High Energy Line Breaks Outside of Containment Building - Responses to Request for Additional Information RA-19-0281, Response to NRC Request for Additional Information for the Fall 2018 Oconee Unit 1 Steam Generator Tube Rupture Inspection Report (RA-19-0093)2019-07-31031 July 2019 Response to NRC Request for Additional Information for the Fall 2018 Oconee Unit 1 Steam Generator Tube Rupture Inspection Report (RA-19-0093) RA-19-0301, Proposed Amendment to Renewed Facility Operating Licenses Regarding Revisions to Final Safety Analysis Report Sections Associated with Oconee Tornado Licensing Basis -Responses to Request for Additional Information2019-07-31031 July 2019 Proposed Amendment to Renewed Facility Operating Licenses Regarding Revisions to Final Safety Analysis Report Sections Associated with Oconee Tornado Licensing Basis -Responses to Request for Additional Information RA-19-0134, Duke Energy Response to NRC Request for Additional Information (RAI) Related to Oconee License Amendment Request 2018-052019-03-0707 March 2019 Duke Energy Response to NRC Request for Additional Information (RAI) Related to Oconee License Amendment Request 2018-05 RA-19-0116, Duke Energy Response to NRC Request for Additional Information (RAI) Related to Oconee License Amendment Request 2017-052019-02-26026 February 2019 Duke Energy Response to NRC Request for Additional Information (RAI) Related to Oconee License Amendment Request 2017-05 RA-19-0026, Response to Request for Additional Information (RAI) Regarding Proposed Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 2 and 10 (18-GO-001)2019-02-11011 February 2019 Response to Request for Additional Information (RAI) Regarding Proposed Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 2 and 10 (18-GO-001) 2023-07-07
[Table view] |
Text
J. Ed Burchfield, Jr.
Vice President Oconee Nuclear Station Duke Energy ON01VP l 7800 Rochester Hwy Seneca, SC 29672 o: 864.873.3478 f: 864.873.5791 Ed.Burchfield@duke-energy.com RA-19-0134 March 7, 2019 Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Duke Energy Carolinas, LLC (Duke Energy)
Oconee Nuclear Station (ONS), Units 1, 2, and 3 Docket Numbers 50-269, 50-270, 50-287 Renewed License Numbers DPR-38, DPR-47, DPR-55
Subject:
Duke Energy Response to NRC Request for Additional Information (RAI) Related to Oconee License Amendment Request 2018-05
References:
- 1. Duke Energy Letter to USNRC, License Amendment Request Proposing a Revised Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods that Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3, Footnote 11; License Amendment Request No. 2018-05, dated November 1, 2018 (ML18318A320).
- 2. NRC Email, A. Klett (NRC) to A. Zaremba (Duke Energy), NRC Request for Additional Information for Oconee LAR 2018-05 (L-2018-LLA-0300), dated February 19, 2019.
By letter dated November 1, 2018, Duke Energy submitted a License Amendment Request (LAR) to the U.S. Nuclear Regulatory Commission (NRC) proposing to revise the facility as described in the Oconee Updated Final Safety Analysis Report with respect to the fission gas gap release fractions calculated for high burnup fuel rods. By email dated February 19, 2019 (Reference 2), the NRC requested additional information associated with the Reference 1 LAR. The NRC request for additional information (RAI) and the Duke Energy responses are provided in the enclosure to this letter.
The responses to the RAIs do not affect the conclusions of the No Significant Hazards Consideration provided in the Reference 1 LAR.
RA-19-0134 March 7, 2019 This letter contains no new or revised commitments. Should you have any questions regarding this submittal, please contact Mr. Art Zaremba, Fleet Nuclear Licensing Manager, at (980) 373-2062.
I declare under penalty of perjury that the foregoing is true and correct. Executed on March 7, 2019.
Sincerely,
~[)~/
J. Ed Burchfield, Jr.
Vice President Oconee Nuclear Station
Enclosure:
Duke Energy Response to NRC Request for Additional Information (RAI)
Page2
RA-19-0134 March 7, 2019 Cc (w/enclosure):
Ms. Catherine Haney, Administrator, Region II U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 Ms. Audrey Klett, Project Manager Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-8G9A 11555 Rockville Pike Rockville, Maryland 20852 Mr. Eddy Crowe NRC Senior Resident Inspector Oconee Nuclear Station Page 3
Enclosure to Duke Energy Letter RA-19-0134 Page 1 of 3 Duke Energy Response to NRC Request for Additional Information (RAI)
By application dated November 1, 2018 (Agencywide Documents Access and Management System Accession Numbers ML18318A320), Duke Energy Carolinas, LLC (the licensee) proposed changes to the licensing basis for Oconee Nuclear Station, Units 1, 2, and 3 (Oconee). The licensee proposed to revise the facility as described in the updated final safety analysis report (UFSAR) to provide gap release fractions for high-burnup fuel rods (i.e., greater than 54 gigawatt days per metric ton of uranium (GWD/MTU)) that exceed the 6.3 kilowatt per foot (kW/ft) linear heat generation rate (LHGR) limit detailed in Table 3 of Regulatory Guide (RG) 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, dated July 2000.
During the U.S. Nuclear Regulatory Commission (NRC) staffs review the NRC staff determined that more information was needed to complete the review. The staff emailed a draft request for additional information (RAI) to the licensee on February 11, 2019. Based on an email from Mr. Chris Wasik of the licensees staff dated February 12, 2019, the staff determined that it needed to clarify the RAI. The email correspondence is in ADAMS at Accession No. ML19050A220. As discussed with Mr. Chris Wasik on February 14, 2019, the staff is requesting the licensee to respond to this request within 30 days of receipt.
Regulatory Analysis Basis Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Section 50.67, Accident source term, Paragraph (b)(2) states, in part, that the NRC may issue the amendment only if the applicants analysis demonstrates with reasonable assurance that:
(i) An individual located at any point on the boundary of the exclusion area for any 2-hour period following the onset of the postulated fission product release, would not receive a radiation dose in excess of 0.25 Sv (25 rem) total effective dose equivalent (TEDE).
(ii) An individual located at any point on the outer boundary of the low population zone, who is exposed to the radioactive cloud resulting from the postulated fission product release (during the entire period of its passage), would not receive a radiation dose in excess of 0.25 Sv (25 rem) TEDE.
(iii) Adequate radiation protection is provided to permit access to and occupancy of the control room under accident conditions without personnel receiving radiation exposures in excess of 0.05 Sv (5 rem) TEDE for the duration of the accident.
RG 1.183 provides the methodology for analyzing the radiological consequences of several design basis accidents to show compliance with 10 CFR 50.67.
Enclosure to Duke Energy Letter RA-19-0134 Page 2 of 3 10 CFR 50.36, Technical specifications, in part, requires that the technical specifications (TSs) be derived from the analyses and evaluation included in the safety analysis report, and amendments thereto and includes items in following categories: (1) safety limits, limiting safety systems settings, and limiting control settings; (2) limiting conditions for operation; (3) surveillance requirements; (4) design features; (5) administrative controls; (6) decommissioning; (7) initial notifications; and (8) written reports.
Technical Basis for RAI-1 In its application, the licensee proposed gap release fractions for high-burnup fuel rods (i.e.,
greater than 54 GWD/MTU) that exceed the 6.3 kW/ft LHGR limit in Footnote 11 of Table 3, Non-LOCA [loss of coolant accident] Fraction of Fission Product Inventory in Gap, in RG 1.183.
The non-LOCA gap fractions stated in Table 3 of RG 1.183 are applied to the non-LOCA accidents if fuel failure occurs during the accident. The following accidents at Oconee assume fuel failure: fuel handling accident, fuel cask handling accident, locked rotor accident, and control rod ejection accident. In its application, the licensee stated that no non-LOCA accidents that may result in departure from nucleate boiling are considered (e.g., locked rotor accident or rod ejection accident) because the fuel cycles for Oconee are designed so that no fuel rod predicted to enter departure from nucleate boiling will have been operated beyond the current limit in RG 1.183, Footnote 11 for maximum LHGR. Because of this, the NRC would be approving a change to the gap fractions for only the FHA. However, the application does not incorporate this new design requirement into the licensing basis as reflected in the UFSAR, nor does it place a requirement in Oconees TSs, such as Section 5.0, Design Features, or any other document controlled under 10 CFR 50.59, such as the Core Operating Limits Report (COLR).
The UFSAR currently states that the fuel cycle design ensure that none of these fuel pins experience DNB following any design basis accident. This sentence refers to the non-DNB fuel pins that exceed the rod power/burnup criteria of Footnote 11 in RG 1.183 and the new proposed gap fractions provided in the application, which apply to FHA only. The application does not explicitly state that the fuel cycle design ensures that no fuel rod predicted to experience DNB in any other non-LOCA accidents will have operated beyond the power/burnup criteria of Footnote 11 in Regulatory Guide 1.183 and that the gap fractions used in these non-LOCA accidents analyses remain those stated in Table 3 of RG 1.183. The current UFSAR only explains that the rods will not experience DNB following any DBA, but it does not clearly state that the gap fractions in the locked rotor and rod ejection accident remain those in Table 3 of RG 1.183 and that the exceeding the power/burnup criteria in Footnote 11 in RG 1.183 does not apply to these accidents.
Enclosure to Duke Energy Letter RA-19-0134 Page 3 of 3
RAI-1
The staff requests the licensee to either describe how it will incorporate the new design requirement into the Oconee licensing basis, as reflected in the UFSAR, TSs, or any other document controlled under 10 CFR 50.59 (such as the COLR); or provide the revised radiological consequence analyses for the other design basis accidents that assume fuel failure (such as locked rotor accident, control rod ejection accident, etc.)
that demonstrate that the regulatory limits will be met with the new proposed gap fractions for high-burnup fuel rods.
Duke Energy Response to RAI-1 Duke Energy will incorporate the new design requirement into the Oconee licensing basis via the attached proposed revision to the Updated Final Safety Analysis Report (UFSAR). The attached UFSAR mark-up (2 pages) supersedes the UFSAR Section 15.1.10 mark-up included in the November 1, 2018 license amendment request. The remainder of the originally proposed UFSAR changes are not affected by this RAI response.
Oconee Nuclear Station UFSAR Chapter 15
- 4. Many of the transient and accident analyses involve control rod movement. These analyses credit the normal withdrawal sequence, overlap, and rod speed, which are controlled by non-safety control systems.
- 5. For certain failures in the EFW System, credit is taken for realigning EFW flow through the non-safety MFW System.
- 6. Steaming of the steam generators with manual non-safety atmospheric dump valves is credited.
- 7. Deleted per 2003 update
- 8. The capability to remotely throttle certain valves is credited. Some of the controls required to remotely throttle these valves are not safety-grade.
- 9. Electrical bus voltage and frequency control are credited. These are controlled by non-safety components.
- 10. The Integrated Control System trips both main feedwater pumps on a high steam generator level indication. A high level indication may occur following a main steam line break due to the pressure drops that result from the blowdown of the steam generator. Tripping of the main feedwater pumps will be assumed to occur in the steam line break analysis only if the plant response is more limiting.
15.1.10 Environmental Consequences Calculation Methodology Environmental Consequences A summary of the offsite doses is presented in Table 15-16. A description of each accident analysis is given in the appropriate section.
Fission Product Inventories Inventory in the Core: Fission product inventories within the core are calculated based on the ORIGEN methodology (e.g., ORIGEN-ARP or SAS2H/ORIGEN-S of the SCALE computer code)(Section 15.1 , Ref. 27). The core inventories for the Maximum Hypothetical Accident are shown in Table 15-15.
Inventory in the Reactor Coolant: The quantity of fission products released to the reactor coolant during steady state operation is based on the use of escape rate coefficients (sec- 1 )
derived from experiments involving purposely defected fuel elements. (Section 15.1 ,
References 29, 30, .fil_, 32) These coefficients represent the fraction of the activity in the fuel (31 DEC 2017) 15.1 - 7
Insert A:
For non-DNB fuel pins that exceed the rod power/burnup criteria of Footnote 11 in RG 1.183, the gap fractions from RG 1.183 are increased by a factor of 4 for Kr-85, Cs-134, and Cs-137. The gap fractions for all other isotopes remain at their pertinent RG 1.183, Table 3 values (References 46 and 47). The fuel cycle design ensures that none of these fuel pins experience DNB following any design basis accident.
The fuel cycle design also ensures that no fuel rod predicted to experience DNB in any other non-LOCA accidents (e.g., locked rotor accident or rod ejection accident) will have operated beyond the power/burnup criteria of Footnote 11 in Regulatory Guide 1.183 and that the gap fractions used in these non-LOCA accident analyses remain those stated in Table 3 of RG 1.183.