MONTHYEARPNO-III-18-002, Beaver Valley, Davis-Besse, Perry Notification of Bankruptcy Filing by Firstenergy Solutions2018-04-0404 April 2018 PNO-III-18-002: Beaver Valley, Davis-Besse, Perry Notification of Bankruptcy Filing by Firstenergy Solutions PNO-III-16-002, Perry Nuclear Power Plant: Unplanned Shutdown Greater than 72 Hours Due to Spurious Opening of Safety Relief Valves and Subsequent Plant Restart2016-02-18018 February 2016 PNO-III-16-002 Perry Nuclear Power Plant: Unplanned Shutdown Greater than 72 Hours Due to Spurious Opening of Safety Relief Valves and Subsequent Plant Restart PNO-III-16-001, A, Perry Nuclear Plant, Unplanned Shutdown Greater than 72 Hours Due to Reactor Coolant System Leakage Exceeding Technical Specification Limits and Subsequent Plant Restart2016-02-0505 February 2016 PNO-III-16-001A, Perry Nuclear Plant, Unplanned Shutdown Greater than 72 Hours Due to Reactor Coolant System Leakage Exceeding Technical Specification Limits and Subsequent Plant Restart ML16032A3942016-01-29029 January 2016 PNO-III-16-001 Perry Nuclear Power Plant, Unplanned Shutdown Greater than 72 Hours Due to Reactor Coolant System Leakage Exceeding Technical Specification Limits ML14316A5802014-11-12012 November 2014 PNO-lll-14-011: Unplanned Shutdown Greater than 72 Hours Due to a Loss of Feedwater ML14301A0342014-10-27027 October 2014 PNO-lll-14-009A Update to Unplanned Shutdown Greater than 72 Hours Due to a Loss of Feedwater PNO-III-14-009, Perry Nuclear Power Plant - Unplanned Shutdown Greater than 72 Hours Due to a Loss of Feedwater2014-10-24024 October 2014 PNO-III-14-009: Perry Nuclear Power Plant - Unplanned Shutdown Greater than 72 Hours Due to a Loss of Feedwater PNO-III-14-004, Perry Nuclear Power Plant Notification of Unusual Event Due to Toxic Chemical Leak2014-04-0303 April 2014 PNO-III-14-004: Perry Nuclear Power Plant Notification of Unusual Event Due to Toxic Chemical Leak ML13169A3672013-06-18018 June 2013 PNO-lll-13-005, Perry Nuclear Power Plant Shutdown Greater than 72 Hours Due to a Pressure Boundary PNO-III-13-001, Unplanned Shutdown Greater than 72 Hours Due to an Automatic Reactor Protection System Actuation2013-01-29029 January 2013 PNO-III-13-001, Unplanned Shutdown Greater than 72 Hours Due to an Automatic Reactor Protection System Actuation PNO-III-12-017, Perry Nuclear Power Plant Unusual Event Declared After Carbon Monoxide Detectors Alarmed in the Radwaste Building Control Room2012-11-29029 November 2012 PNO-III-12-017 - Perry Nuclear Power Plant Unusual Event Declared After Carbon Monoxide Detectors Alarmed in the Radwaste Building Control Room PNO-III-12-005, Perry Unplanned Shutdown Greater than 72 Hours2012-06-19019 June 2012 PNO-III-12-005 - Perry Unplanned Shutdown Greater than 72 Hours PNO-III-11-012, A - Perry Unplanned Shutdown Greater than 72 Hours (Update)2011-10-19019 October 2011 PNO-III-11-012A - Perry Unplanned Shutdown Greater than 72 Hours (Update) ML1127801372011-10-0505 October 2011 PNO-III-11-012 - Perry - Unplanned Shutdown Greater than 72 Hours PNO-III-10-006, A: Perry, - Update - Manual Reactor Scram Due to Loss of Control Rod Drive Charging Water Header Pumps2010-05-19019 May 2010 PNO-III-10-006A: Perry, - Update - Manual Reactor Scram Due to Loss of Control Rod Drive Charging Water Header Pumps ML1013407362010-05-14014 May 2010 PNO-III-10-006-Perry-Manual Reactor Scram Due to Loss of Control Rod Drive Charging Water Header Pumps PNO-III-10-005, A - Perry - Update - Turbine-Driven Feedwater Pump Fire Caused by Leak in Lube Oil System2010-03-31031 March 2010 PNO-III-10-005A - Perry - Update - Turbine-Driven Feedwater Pump Fire Caused by Leak in Lube Oil System PNO-III-09-012, A: Perry, Manual Reactor Scram During Planned Shutdown (Update)2009-11-0303 November 2009 PNO-III-09-012A: Perry, Manual Reactor Scram During Planned Shutdown (Update) ML0929203402009-10-19019 October 2009 PNO-III-09-012: Perry, Manual Reactor Scram During Planned Shutdown PNO-III-07-015, A: Perry, Update to Scram at Perry Nuclear Power Station and Feedwater Loss2007-12-0606 December 2007 PNO-III-07-015A: Perry, Update to Scram at Perry Nuclear Power Station and Feedwater Loss ML0733212692007-11-28028 November 2007 PNO-III-07-015: Scram at Perry Nuclear Power Station and Feedwater Loss PNO-III-07-009, A: Perry: Update to Unexpected Reactor Shutdown Exceeding 72 Hours Due to Problem with Reactor Recirculation Pump Motor2007-07-24024 July 2007 PNO-III-07-009-A: Perry: Update to Unexpected Reactor Shutdown Exceeding 72 Hours Due to Problem with Reactor Recirculation Pump Motor ML0718606072007-07-0505 July 2007 PNO-III-07-009: Perry: Unexpected Reactor Shut Down Exceeding 72 Hours Due to Problem with Reactor Recirculation Pump Motor PNO-III-06-016, Perry Nuclear Power Plant Unusual Event Declared Due to Earth Quake2006-06-21021 June 2006 PNO-III-06-016 Perry Nuclear Power Plant Unusual Event Declared Due to Earth Quake PNO-III-06-009, Perry Nuclear Power Plant Low Level Tritium Identified in Underdrain System2006-04-0606 April 2006 PNO-III-06-009 - Perry Nuclear Power Plant Low Level Tritium Identified in Underdrain System PNO-III-04-015, Perry Nuclear Power Plant, Inadvertent Discharge of CO2 Fire Protection System in Turbine Building2004-11-12012 November 2004 PNO-III-04-015: Perry Nuclear Power Plant, Inadvertent Discharge of CO2 Fire Protection System in Turbine Building PNO-III-04-014, Perry Nuclear Power Plant, Chemical Spill in Water Treatment Building2004-11-0404 November 2004 PNO-III-04-014: Perry Nuclear Power Plant, Chemical Spill in Water Treatment Building PNO-III-04-007, Perry, Alert Declared Because of Malfunctioning Radiation Monitor2004-07-20020 July 2004 PNO-III-04-007: Perry, Alert Declared Because of Malfunctioning Radiation Monitor PNO-III-03-022, Perry-Alert Declared Due to High Radiation Alarm in Fuel Handling Building2003-04-24024 April 2003 PNO-III-03-022: Perry-Alert Declared Due to High Radiation Alarm in Fuel Handling Building PNO-III-02-039, Reactor Scram During Main Turbine Testing Leads to Shutdown Greater than 72 Hours2002-09-23023 September 2002 PNO-III-02-039: Reactor Scram During Main Turbine Testing Leads to Shutdown Greater than 72 Hours 2018-04-04
[Table view] |
PRELIMINARY NOTIFICATION January 29, 2013 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE - PNO-III-13-001 This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. Some of the information may not yet be fully verified or evaluated and is basically all that is known by the Region III staff on this date.
Facility Licensee Emergency Classification Perry Nuclear Power Plant Notification of Unusual Event FirstEnergy Nuclear Operating Company Alert Perry, OH Site Area Emergency Docket No.: 05000440 General Emergency License No.: NPF-58 X Not Applicable
SUBJECT:
UNPLANNED SHUTDOWN GREATER THAN 72 HOURS DUE TO AN AUTOMATIC REACTOR PROTECTION SYSTEM ACTUATION On Saturday, January 26, 2013, at 12:34 p.m. EST, the Perry operators restarted the reactor following repairs to the Volt AC electrical system that had caused a transient in the feedwater system resulting in an unplanned shutdown. The unit synchronized to the grid at 3:43 p.m. EST on January 27, 2013.
Previously, on January 22, 2013, at approximately 3:32 a.m. EST, an automatic Reactor Protection System (RPS) actuation occurred at the Perry Nuclear Power Plant, Unit 1. At the time of the event, the plant was in Mode 1 at 100 percent power. All control rods inserted into the reactor core and the plant reached cold shutdown at approximately 8:36 p.m. on January 23.
The RPS actuation was initiated by a low reactor water level (Level 3 - 178") signal. In response to the RPS actuation and subsequent reactor Level 2 (130") signal, the High Pressure Core Spray (HPCS) system and Reactor Core Isolation Cooling (RCIC) system both actuated and injected to maintain reactor coolant level. The reactor level was maintained in its normal band by the feedwater system and decay heat was removed by turbine bypass valves to the condenser (both HPCS and RCIC had been returned to standby). The plant was in the normal electrical line-up with all three Emergency Diesel Generators operable and available, if needed.
The NRC resident inspectors responded to the site when the event occurred and closely monitored the licensee's activities, including plant startup.
This preliminary notification is issued for information only.
The State of Ohio has been informed.
Region III received initial notification of this occurrence by a telephone call from Perry to the senior resident inspector (SRI) at approximately 3:32 a.m. EST on January 22, 2013 (refer to Event Notification 48688).
The information herein has been discussed with the licensee, and is current as of 10:19 a.m.
EST on January 29, 2013.
ADAMS Accession Number: ML13029A646
Contact:
M. Kunowski (630) 829-9618 Michael.Kunowski@nrc.gov