NL-10-0665, Nuclear Property Insurance Coverage as of April 1, 2010
ML100890396 | |
Person / Time | |
---|---|
Site: | Hatch, Vogtle, Farley |
Issue date: | 03/30/2010 |
From: | Ajluni M Southern Nuclear Operating Co |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
NL-10-0665 | |
Download: ML100890396 (2) | |
Category:Financial Assurance Document
MONTHYEARNL-23-0672, Licensee Guarantees of Payment of Deferred Premiums2023-08-10010 August 2023
[Table view]Licensee Guarantees of Payment of Deferred Premiums ML22333A0462022-11-10010 November 2022 Marsh USA, Inc., Certificate of Liability Insurance ML22237A0782022-08-0505 August 2022 American Nuclear Insurers, Notification of Change in the Number of Power Reactors in the Secondary Financial Protection (SFP) Program NL-21-0307, Report on Status of Decommissioning Funding2021-03-31031 March 2021 Report on Status of Decommissioning Funding ND-20-0243, Financial Assurance Requirements for Decommissioning2020-03-12012 March 2020 Financial Assurance Requirements for Decommissioning ND-19-1412, Financial Assurance Requirements for Decommissioning2019-11-21021 November 2019 Financial Assurance Requirements for Decommissioning NL-19-0283, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors2019-04-0101 April 2019 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors NL-19-0285, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors2019-04-0101 April 2019 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors NL-19-0284, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors2019-04-0101 April 2019 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors ML18324A5712018-10-30030 October 2018 Marsh USA, Inc., Certificate of Liability Insurance ML18319A0922018-10-29029 October 2018 Marsh USA, Inc., Certificate of Liability Insurance NL-17-0433, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors2017-03-30030 March 2017 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors NL-17-0432, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors2017-03-30030 March 2017 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors NL-16-0457, Units 1 and 2 - Nuclear Property Insurance Coverage as of April 1, 20162016-03-28028 March 2016 Units 1 and 2 - Nuclear Property Insurance Coverage as of April 1, 2016 NL-15-0577, Dalton Utilities Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2015-03-26026 March 2015 Dalton Utilities Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-15-0581, Dalton Utilities Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2015-03-26026 March 2015 Dalton Utilities Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-15-0574, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2015-03-26026 March 2015 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-15-0604, E.I. Hatch, J. M. Farley and Vogtle, Units 1 and 2 - Submits Nuclear Property Insurance Coverage as of April 1, 20152015-03-26026 March 2015 E.I. Hatch, J. M. Farley and Vogtle, Units 1 and 2 - Submits Nuclear Property Insurance Coverage as of April 1, 2015 NL-15-0577, Edwin I. Hatch, Units 1 and 2 - Georgia Power Company Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2015-03-16016 March 2015 Edwin I. Hatch, Units 1 and 2 - Georgia Power Company Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) ML16048A1292015-03-16016 March 2015 Georgia Power Company Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-15-0581, Vogtle, Units 1 and 2 - Georgia Power Company Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2015-03-16016 March 2015 Vogtle, Units 1 and 2 - Georgia Power Company Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) ML15167A4622015-03-16016 March 2015 Georgia Power Company Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-15-0581, Vogtle, Units 1 and 2 - Municipal Electric Authority of Georgia Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2015-03-0909 March 2015 Vogtle, Units 1 and 2 - Municipal Electric Authority of Georgia Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-15-0577, Edwin I. Hatch, Units 1 and 2 - Municipal Electric Authority of Georgia Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2015-03-0909 March 2015 Edwin I. Hatch, Units 1 and 2 - Municipal Electric Authority of Georgia Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) ML15167A4652015-03-0909 March 2015 Municipal Electric Authority of Georgia Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) ML16048A1312015-03-0909 March 2015 Municipal Electric Authority of Georgia Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) ML15167A4632015-03-0303 March 2015 Oglethorpe Power Corporation Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-15-0577, Edwin I. Hatch, Units 1 and 2 - Oglethorpe Power Corporation Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2015-03-0303 March 2015 Edwin I. Hatch, Units 1 and 2 - Oglethorpe Power Corporation Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) ML16048A1302015-03-0303 March 2015 Oglethorpe Power Corporation Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-15-0581, Vogtle, Units 1 and 2 - Oglethorpe Power Corporation Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2015-03-0303 March 2015 Vogtle, Units 1 and 2 - Oglethorpe Power Corporation Response on Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-14-0290, Units 1 & 2 and ISFSI - Decommissioning Funding Plan2014-03-31031 March 2014 Units 1 & 2 and ISFSI - Decommissioning Funding Plan NL-14-0441, Edwin I Hatch, Joseph M. Farley and Vogtle, Units 1 & 2 - Nuclear Property Insurance Coverage as of April 1, 20142014-03-24024 March 2014 Edwin I Hatch, Joseph M. Farley and Vogtle, Units 1 & 2 - Nuclear Property Insurance Coverage as of April 1, 2014 NL-13-0676, Financial Assurance Requirements for Decommissioning, Nuclear Power Reactors (10 CFR 50.75(f)(1))2013-03-29029 March 2013 Financial Assurance Requirements for Decommissioning, Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-13-0675, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2013-03-29029 March 2013 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-13-0677, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(0(1))2013-03-29029 March 2013 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(0(1)) ML1123800202011-11-14014 November 2011 2010 DFS Report Analysis for Vogtle (Alvin W.) Nuclear Plant, Unit 2 ML1123800182011-11-14014 November 2011 2010 DFS Report Analysis for Vogtle (Alvin W.) Nuclear Plant, Unit 1 ML1123601282011-11-14014 November 2011 2010 DFS Report Analysis for Farley (Joseph M.) Nuclear Plant, Unit 2 ML1123601262011-11-14014 November 2011 2010 DFS Report Analysis for Farley (Joseph M.) Nuclear Plant, Unit 1 ML1123700182011-11-14014 November 2011 2010 DFS Report Analysis for Hatch (Edwin I.) Nuclear Plant, Unit 2 ML1123700162011-11-14014 November 2011 2010 DFS Report Analysis for Hatch (Edwin I.) Nuclear Plant, Unit 1 NL-11-1013, Edwin I Hatch, Joseph M. Farley, and Vogtle, Nuclear Property Insurance Coverage as of April 1, 20112011-05-27027 May 2011 Edwin I Hatch, Joseph M. Farley, and Vogtle, Nuclear Property Insurance Coverage as of April 1, 2011 NL-11-0449, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2011-03-29029 March 2011 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-10-0665, Nuclear Property Insurance Coverage as of April 1, 20102010-03-30030 March 2010 Nuclear Property Insurance Coverage as of April 1, 2010 NL-09-1150, Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21)2009-07-29029 July 2009 Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21) NL-09-1042, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1) -Supplemental Information2009-07-0202 July 2009 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1) -Supplemental Information NL-08-0623, Annual Submission Reports2009-04-27027 April 2009 Annual Submission Reports NL-09-0431, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1))2009-03-30030 March 2009 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)) NL-09-0428, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1)2009-03-30030 March 2009 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1) ML0909007192009-03-30030 March 2009 Vogtle Electric Generating Plant, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10 CFR 50.75(f)(1) 2023-08-10 Category:Letter type:NL MONTHYEARNL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024
[Table view]Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. NL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R232024-01-29029 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error NL-24-0011, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-01-11011 January 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-23-0901, 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers2023-12-15015 December 2023 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers NL-23-0908, Cycle 30 Core Operating Limits Report2023-12-13013 December 2023 Cycle 30 Core Operating Limits Report NL-23-0889, Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems2023-12-0606 December 2023 Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems NL-23-0879, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0877, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0841, Update to Notice of Intent to Pursue Subsequent License Renewal2023-11-20020 November 2023 Update to Notice of Intent to Pursue Subsequent License Renewal NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 NL-23-0825, Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection2023-11-14014 November 2023 Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0745, Refueling Outage 1R24 Steam Generator Tube Inspection Report2023-09-22022 September 2023 Refueling Outage 1R24 Steam Generator Tube Inspection Report NL-23-0739, Response to NRC Inspection Report and Preliminary White Finding2023-09-0808 September 2023 Response to NRC Inspection Report and Preliminary White Finding NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2) NL-23-0666, License Amendment Request: Remove Combined License Appendix C (LAR 23-008)2023-08-28028 August 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-008) NL-23-0713, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0716, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0704, Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-22022 August 2023 Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0670, Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-144832023-08-11011 August 2023 Response to Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 NL-23-0672, Licensee Guarantees of Payment of Deferred Premiums2023-08-10010 August 2023 Licensee Guarantees of Payment of Deferred Premiums NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-23-0628, Readiness for Supplemental Inspection EA-22-1012023-07-26026 July 2023 Readiness for Supplemental Inspection EA-22-101 NL-23-0611, Core Operating Limits Report, Cycle 11 Version 12023-07-19019 July 2023 Core Operating Limits Report, Cycle 11 Version 1 NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0584, Preservice Inspection Program Owner'S Activity Report2023-07-10010 July 2023 Preservice Inspection Program Owner'S Activity Report NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement NL-23-0506, to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications2023-07-0505 July 2023 to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications NL-23-0541, Inservice Inspection Program Owners Activity Report for Outage 1R242023-06-28028 June 2023 Inservice Inspection Program Owners Activity Report for Outage 1R24 NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0339, Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1)2023-06-13013 June 2023 Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1) NL-23-0455, Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report2023-06-12012 June 2023 Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use NL-23-0467, Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1)2023-06-0909 June 2023 Response to Request for Additional Information Regarding License Amendment Request: Timing of Unit 4 Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005S1) NL-23-0449, National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application2023-06-0202 June 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application NL-23-0422, Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R272023-05-30030 May 2023 Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R27 NL-23-0346, License Amendment Request for Exception to Regulatory Guide 1.163 (LAR 23-007)2023-05-25025 May 2023 License Amendment Request for Exception to Regulatory Guide 1.163 (LAR 23-007) NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. NL-23-0385, License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006R1)2023-05-17017 May 2023 License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006R1) NL-23-0398, Withdrawal of Request of License Amendment Request Regarding More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006)2023-05-16016 May 2023 Withdrawal of Request of License Amendment Request Regarding More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006) NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 NL-23-0337, Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.52023-05-0505 May 2023 Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.5 NL-23-0360, Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2023-05-0505 May 2023 Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel NL-23-0326, Response to Apparent Violation in NRC Inspection Report 05000424, 425/2023090; EA-22-1082023-05-0101 May 2023 Response to Apparent Violation in NRC Inspection Report 05000424, 425/2023090; EA-22-108 NL-23-0217, License Amendment Request to Revise Technical Specification Surveillance Requirement 3.4.14.1 and Proposed Inservice Testing Alternative ALT-VR-022023-05-0101 May 2023 License Amendment Request to Revise Technical Specification Surveillance Requirement 3.4.14.1 and Proposed Inservice Testing Alternative ALT-VR-02 2024-01-30 |
Text
Southern NUG!eat Operating Company, inc SOUTHERN'\
March 30,2010 COMPANY Docket Nos.: 50-321 50-348 50-424 NL-10-0665 50-366 50-364 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant Joseph M. Farley Nuclear Plant Vogtle Electric Generating Plant Nuclear Property Insurance Coverage as of April 1, 2010 Ladies and Gentlemen:
In accordance with the nuclear property insurance reporting requirement specified in 10 CFR 50.54 (w)(3), the current levels and sources of insurance on Edwin I. Hatch Nuclear Plant, Joseph M. Farley Nuclear Plant, and Vogtle Electric Generating Plant are hereby submitted.
The policies held by Alabama Power Company and Georgia Power Company (including the co-owner licensees as the insured), respectively, are:
Primary Coverage Insurance Nuclear Electric Insurance $500,000,000 Ltd. - NEIL Primary Property Policy No.: Farley: P10-001, Hatch' P10-023, Vogtle: P10-024 Excess Coverage Insurance Nuclear Electric Insurance $2,250,000,000 in excess Ltd. - NEIL Excess Property of $500,000,000 Policy No.: Farley: X1 0-001, Hatch: X10-018, Vogtle: X10-074 The policies listed above provide a total nuclear property coverage limit of
$2,750,000,000 for each site.
U. S. Nuclear Regulatory Commission NL-10-0665 Page 2 This letter contains no NRC commitments. If you have any questions, please advise.
Sincerely,
~~r M. J. Ajluni Manager - Nuclear Licensing MJAITWS/phr cc: Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. J. R. Johnson, Vice President - Farley Mr. D. R. Madison, Vice President - Hatch Mr. T. E. Tynan, Vice President - Vogtle Ms. P. M. Marino, Vice President - Engineering RType: CFA04.054; CHA02.004; CVC7000 U. S. Nuclear Regulatory Commission Mr. L. A. Reyes, Regional Administrator Mr. R. E. Martin, NRR Project Manager - Farley, Hatch and Vogtle Mr. P. Boyle, NRR Project Manager Mr. E. L. Crowe, Senior Resident Inspector - Farley Mr. J. A. Hickey, Senior Resident Inspector - Hatch Mr. M. Cain, Senior Resident Inspector - Vogtle