Letter Sequence Meeting |
---|
EPID:L-2021-NEW-0011, Hermes CP RAI - Preliminary Questions on the Hermes PSAR, Email 1 (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
|
MONTHYEARML21319A3542021-11-29029 November 2021 Acceptance of the Hermes Non-Power Test Reactor Construction Permit Application for Kairos Power LLC Project stage: Acceptance Review ML22024A4922022-01-10010 January 2022 Hermes CP RAI - Preliminary Questions on the Hermes PSAR, Email 1 Project stage: Request ML22198A0012022-01-19019 January 2022, 25 January 2022 Summary of 21Jan2022 Phone Conversation W City of Oak Ridge Public Works Project stage: Request ML22041A3372022-02-0303 February 2022 Kairos Power LLC, Transmittal of Responses-to NRC Questions 2.3-1 and 2.3-2 on the Hermes Preliminary Safety Analysis Report Project stage: Request ML21364A0132022-02-0808 February 2022 Kairos Power LLC - Application for Construction Permit for Hermes Test Reactor Project stage: Other ML22040A3382022-02-0909 February 2022 Kairos Power LLC, Response to NRC Questions 2.5-1, 2.5-2, 2.5-3, and 2.5-4 for PSAR Section 2.5 on Hermes Construction Permit Application Project stage: Other ML22040A3362022-02-0909 February 2022 Kairos Power LLC, Submittal of Response to NRC Questions 2.5-1, 2.5-2, 2.5-3, and 2.5-4 for PSAR Section 2.5 on Hermes Construction Permit Application Project stage: Request ML22042A0952022-02-10010 February 2022 Kairos Power LLC, Transmittal of Changes to Hermes Construction Permit Application Project stage: Request ML22039A2262022-02-17017 February 2022 Audit Plan for the Kairos Hermes Preliminary Safety Analysis Report (PSAR) Section 6.3 Decay Heat Removal System - February 2022 Project stage: Other ML22106A0002022-02-28028 February 2022 Construction and Demonstration of a Prototype Mobile Microreactor Feis: Reference for Kairos Hermes CP Application Project stage: Other ML22060A2722022-03-0101 March 2022 Kairos Power, LLC, Transmittal of Changes to Maximum Hypothetical Accident Dose Results in Hermes Construction Permit Application Project stage: Request ML22031A2892022-03-10010 March 2022 Request to Initiate Section 106 Consultation and Scoping Process for Kairos Power Hermes Non-Power Test Reactor Construction Permit Review Project stage: Request ML22088A2942022-03-11011 March 2022 Scoping Comment (3) from Tennessee Historical Commission Kairos Hermes CP Application Review Project stage: Other ML22089A1662022-04-0808 April 2022 Kairos Power LLC - Hermes Construction Permit Preliminary Safety Analysis Report I&C Repor (Chapter 7) Audit Plan (Cac/Epid No. 000955/05007513/L-2021-NEW-0011) Project stage: Other ML22169A0092022-04-12012 April 2022 NPS Scoping Comments on Kairos Test Reactor Project stage: Request ML22107A0062022-04-17017 April 2022 Oak Ridge Reservation Annual Site Environmental Report 2017: Reference for Kairos Hermes CP Application Project stage: Other ML22115A2042022-04-22022 April 2022 Kairos Power, LLC, Transmittal of Reponses to NRC Requests for Confirmation of Information for the Review of the Hermes Environmental Report Project stage: Request ML22117A2152022-04-22022 April 2022, 27 April 2022 Kairos Power LLC, Transmittal of Supplemental Information for NRC Information Need HCUL-10 for the Hermes Environmental Review Project stage: Request ML22117A2182022-04-27027 April 2022 Kairos Power LLC, Transmittal of Changes to Hermes Environmental Report Resulting from NRC Environmental Review Audit Project stage: Request ML22110A0182022-05-0505 May 2022 Kairos Power LLC, Summary of March 23, 2022, Public Outreach Meeting on the Proposed Kairos Hermes Test Reactor with Designated Period for Receipt of Environmental Scoping Comments Project stage: Request ML22143B0162022-05-27027 May 2022 Audit Plan for Hermes Site Characteristics PSAR Chapter 2 Project stage: Other ML22181B1572022-06-30030 June 2022 Kairos Power LLC Transmittal of Changes to Construction Permit Application Project stage: Request ML22194A0142022-08-0101 August 2022, 31 August 2022 Kairos Hermes Construction Permit Application - Issuance of Environmental Scoping Summary Report Project stage: Request ML22230D0762022-08-0505 August 2022 Final RCI 349 on Salt Purity in the Chemistry Control System and the Inert Gas System Project stage: Other ML22227A1802022-08-0808 August 2022 Final RAI 348 on Shutdown Rod Reliability Project stage: RAI ML22196A3872022-08-24024 August 2022 Kairos Hermes CP Review - Environmental Audit Report Project stage: Request ML22272A5932022-09-29029 September 2022 Kairos Power, LLC - Submittal of the Preliminary Safety Analysis Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), Revision 1 Project stage: Request ML23019A3602022-11-0606 November 2022, 15 November 2022 Kairos Power LLC, Additional Information Related to Construction Permit Application - PSAR Chapter 1 Project stage: Request ML23019A3612022-11-15015 November 2022 Kairos Power LLC, Additional Information Related to Construction Permit Application - PSAR Chapter 1 Project stage: Other ML22342B2822022-12-0808 December 2022 Kairos Power LLC, Transmittal of Reponses to NRC Question on Hermes Preliminary Safety Analysis Report Project stage: Request ML22353A6252022-12-19019 December 2022 Kairos Power LLC, Transmittal of Changes to Preliminary Safety Analysis Report Chapter 6 and Response to NRC Question on Dhrs Testing Project stage: Request ML23055A6722023-02-24024 February 2023, 28 February 2023 Kairos Power LLC, Submittal of the Preliminary Safety Analysis Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), Revision 2 Project stage: Request ML23151A7432023-05-31031 May 2023 Kairos Power, LLC, Submittal of the Preliminary Safety Analysis Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), Revision 3 Project stage: Request ML23158A2682023-06-13013 June 2023 Safety Evaluation for Hermes Construction Permit Application Project stage: Approval ML23158A2652023-06-13013 June 2023 Safety Evaluation for the Kairos Power LLC Construction Permit Application for the Hermes Non-Power Test Reactor Project stage: Request ML23158A2662023-06-13013 June 2023 Transmittal of Safety Evaluation for Hermes Construction Permit Application Project stage: Approval ML23181A1072023-07-18018 July 2023 Summary of August 25 and 30 2022 Public Meetings on the Kairos Hermes Preliminary Safety Analysis Report Project stage: Meeting 2022-04-12
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24008A0802024-01-0808 January 2024 Kairos Power LLC, Summary of 11/2/2023, Public Meeting to Discuss Material Control and Accounting ML23305A0092023-11-0909 November 2023 Summary of the October 26, 2023 Meeting with Tennessee Historical Commission Regarding Section 106 Consultations ML23271A1362023-10-0303 October 2023 Summary of the September 12 and September 21, 2023 Closed Meetings with Kairos Power Regarding Section 106 Consultations ML23242A2422023-09-14014 September 2023 Summary of the August 10, 2023 Closed Meetings with Kairos Power Regarding Section 106 Consultations ML23241A0032023-08-31031 August 2023 and 07/25/2023 Summary of Closed Meetings with Kairos Power Regarding Section 106 Consultations Under Section 106 of the National Historic Preservation Act ML23181A1072023-07-18018 July 2023 Summary of August 25 and 30 2022 Public Meetings on the Kairos Hermes Preliminary Safety Analysis Report ML23181A0422023-07-0606 July 2023 June 6 and 14, 2023 Summary of the Closed Meetings with Kairos Power Regarding Section 106 Consultations ML23156A6682023-06-0606 June 2023 Summary of February 9, 2022, Public Meeting on the Kairos Herme Preliminary Safety Analysis Report ML23132A3042023-05-22022 May 2023 April 11, 2023 Summary of Closed Meeting with Kairos Power, LLC Regarding Consultations Under National Historic Preservation Act ML23031A1602023-03-21021 March 2023 Summary of Public Meeting for the Draft Environmental Impact Statement for the Kairos Hermes Test Reactor Construction Permit Application ML22110A0182022-05-0505 May 2022 Kairos Power LLC, Summary of March 23, 2022, Public Outreach Meeting on the Proposed Kairos Hermes Test Reactor with Designated Period for Receipt of Environmental Scoping Comments 2024-01-08
[Table view] Category:Memoranda
MONTHYEARML24008A0802024-01-0808 January 2024 Kairos Power LLC, Summary of 11/2/2023, Public Meeting to Discuss Material Control and Accounting ML23318A5162023-11-30030 November 2023 Implementation of Provisions from Consultations Under Section 106 of the National Historic Preservation Act on the Kairos Hermes Test Reactor CP Review ML23220A1992023-09-0707 September 2023 Consideration of New Information Regarding Potential Cumulative Impacts from the Proposed Kairos Hermes 2 Test Reactor on the Kairos Hermes Construction Permit Review ML23181A1072023-07-18018 July 2023 Summary of August 25 and 30 2022 Public Meetings on the Kairos Hermes Preliminary Safety Analysis Report ML23156A6682023-06-0606 June 2023 Summary of February 9, 2022, Public Meeting on the Kairos Herme Preliminary Safety Analysis Report ML23117A0052023-05-0101 May 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 3, Design of Structures, Systems and Components ML23117A0502023-04-29029 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 12, Conduct of Operations ML23117A0272023-04-28028 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 10, Experimental Facilities and Utilization ML23117A0112023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 6, Engineered Safety Features ML23117A0172023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 8, Electric Power Systems ML23117A0022023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 1, the Facility ML23117A0082023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 4, Reactor Description ML23117A0032023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 2, Site Characteristics ML23117A0102023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 5, Heat Transport Systems ML23117A0192023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 9, Auxiliary Systems ML23117A0302023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 11, Radiation Protection and Waste Management ML23117A0522023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 13, Accident Analysis ML23117A0612023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 14, Technical Specifications ML23117A0652023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 16, Other License Considerations ML23117A0692023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 17, Decommissioning and Possession-Only License Amendments ML23031A1602023-03-21021 March 2023 Summary of Public Meeting for the Draft Environmental Impact Statement for the Kairos Hermes Test Reactor Construction Permit Application ML22196A3882022-08-24024 August 2022 Memorandum from T.Dozier to K.Erwin - Summary Report for Environmental Audit of the Kairos Hermes Test Reactor Construction Permit Application ML22193A2402022-08-0101 August 2022 Issuance of Environmental Scoping Summary Report for the Review of the Kairos Hermes Test Reactor Construction Permit Application ML22169A0092022-04-12012 April 2022 NPS Scoping Comments on Kairos Test Reactor 2024-01-08
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
July 18, 2023 MEMORANDUM TO: William Jessup, Chief Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation FROM: Samuel Cuadrado, Project Manager /RA/
Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF AUGUST 25 AND 30, 2022, PUBLIC MEETINGS ON THE KAIROS HERMES PRELIMINARY SAFETY ANALYSIS REPORT (EPID NO. L-2021-NEW-0011)
Meeting Information:
Applicant: Kairos Power, LLC (Kairos)
Docket/Project No.(s): 05007513 Public Meeting Notice Agencywide Documents Access and Management System (ADAMS)
Accession Nos.: ML22227A186 and ML22238A338 Meeting Attendees: See the enclosure for a list of meeting attendees.
Meeting Summary:
On August 25 and 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) staff held partially closed meetings via webinar with Kairos. The U.S. Nuclear Regulatory Commission (NRC) staff conducted the meetings in accordance with NRC Management Directive 3.5, Attendance at NRC Staff-Sponsored Meetings (ADAMS Accession No. ML21180A271). The purpose of the meetings was to discuss the NRCs safety review of the Kairos Hermes test reactor construction permit application. Specifically, the staff provided clarification to Kairos for the following requests for additional information (RAIs):
- RAI 339, on inspection of vessel internals and the natural circulation flow path (ML22220A299)
- RAI 350, on air ingress into the primary heat transport system (ML22227A192)
CONTACT: Samuel Cuadrado, NRR/DANU/UAL1 301-415-2946
W. Jessup 2 During the meetings, Kairos discussed its draft responses to the three RAIs. The NRC staff provided clarification and was able to identify a few areas of the responses in need of additional detail. Kairos understood the clarifications provided and took action to incorporate the additional detail into its formal responses. Kairos also noted several changes that would be made to the PSAR. The NRC staff concluded that Kairos was on a satisfactory path to provide adequate responses to the RAIs in a timely manner. Kairos submitted its formal responses to RAIs 339 and 348 on August 31, 2022, (ML22243A247) and to RAI 350 on September 1, 2022, (ML22252A149), as originally expected (within 30 days of issuance of the RAIs).
No regulatory decisions were made as a result of this meeting.
Docket No. 05007513
Enclosure:
List of Attendees
W. Jessup 3
SUBJECT:
SUMMARY
OF AUGUST 25 AND 30, 2022, PUBLIC MEETINGS ON THE KAIROS HERMES PRELIMINARY SAFETY ANALYSIS REPORT (EPID NO. L-2021-NEW-0011)
DATE: JULY 18, 2023 DISTRIBUTION:
PUBLIC RidsNrrDanuUal1 Resource RidsNrrDanu Resource WJessup, NRR MHiser, NRR EHelvenston, NRR ADAMS Accession Number: ML23181A107 NRC-001 OFFICE NRR/DANU/UAL1/PM NRR/DANU/UAL1/BC NRR/DANU/UAL1/PM NAME SCuadrado WJessup SCuadrado DATE 7/18/2023 7/18/2023 7/18/2023 OFFICIAL RECORD COPY
List of Attendees Name Organization Ben Beasley U.S. Nuclear Regulatory Commission (NRC)
Meg Audrain NRC Alex Chereskin NRC Stephen Philpott NRC Ed Helvenston NRC Jeff Schmidt NRC Samuel Cuadrado NRC Darrell Gardner Kairos Power LLC Drew Peebles Kairos Power LLC Jim Tomkins Kairos Power LLC Chong Chen Kairos Power LLC Gus Merwin Kairos Power LLC Jordan Hagaman Kairos Power LLC Ka-Yen Kairos Power LLC Nicole Schlichting Kairos Power LLC Michael Ellet Kairos Power LLC Delaney Simmons Kairos Power LLC Quan Zhou Kairos Power LLC Tim Drzewiecki Kairos Power LLC Anthonie Cilliers Kairos Power LLC Ian Gifford TerraPower Michael Montecalvo TerraPower Paul Ouellette Engineering Planning and Management, Inc.
Brandon Hartle X-Energy Steve Vaughn X-Energy Brandon Norris X-Energy