MONTHYEARML21319A3542021-11-29029 November 2021 Acceptance of the Hermes Non-Power Test Reactor Construction Permit Application for Kairos Power LLC Project stage: Acceptance Review ML22024A4922022-01-10010 January 2022 Hermes CP RAI - Preliminary Questions on the Hermes PSAR, Email 1 Project stage: Request ML22028A0022022-02-0202 February 2022 Kairos Hermes Environmental Audit Plan Project stage: Other ML22041A3372022-02-0303 February 2022 Kairos Power LLC, Transmittal of Responses-to NRC Questions 2.3-1 and 2.3-2 on the Hermes Preliminary Safety Analysis Report Project stage: Request ML21364A0132022-02-0808 February 2022 Kairos Power LLC - Application for Construction Permit for Hermes Test Reactor Project stage: Other ML22040A3382022-02-0909 February 2022 Kairos Power LLC, Response to NRC Questions 2.5-1, 2.5-2, 2.5-3, and 2.5-4 for PSAR Section 2.5 on Hermes Construction Permit Application Project stage: Other ML22040A3362022-02-0909 February 2022 Kairos Power LLC, Submittal of Response to NRC Questions 2.5-1, 2.5-2, 2.5-3, and 2.5-4 for PSAR Section 2.5 on Hermes Construction Permit Application Project stage: Request ML21204A0392022-02-15015 February 2022 Federal Register Notice of Intent to Conduct Scoping and Prepare an EIS - Kairos Hermes CP Review Project stage: Request ML22039A2262022-02-17017 February 2022 Audit Plan for the Kairos Hermes Preliminary Safety Analysis Report (PSAR) Section 6.3 Decay Heat Removal System - February 2022 Project stage: Other ML22031A2892022-03-10010 March 2022 Request to Initiate Section 106 Consultation and Scoping Process for Kairos Power Hermes Non-Power Test Reactor Construction Permit Review Project stage: Request ML22091A0002022-03-23023 March 2022 Kairos Hermes Scoping Meeting Transcript Project stage: Request ML22089A1662022-04-0808 April 2022 Kairos Power LLC - Hermes Construction Permit Preliminary Safety Analysis Report I&C Repor (Chapter 7) Audit Plan (Cac/Epid No. 000955/05007513/L-2021-NEW-0011) Project stage: Other ML22110A0182022-05-0505 May 2022 Kairos Power LLC, Summary of March 23, 2022, Public Outreach Meeting on the Proposed Kairos Hermes Test Reactor with Designated Period for Receipt of Environmental Scoping Comments Project stage: Request ML22143B0162022-05-27027 May 2022 Audit Plan for Hermes Site Characteristics PSAR Chapter 2 Project stage: Other ML22230D0762022-08-0505 August 2022 Final RCI 349 on Salt Purity in the Chemistry Control System and the Inert Gas System Project stage: Other ML22227A1802022-08-0808 August 2022 Final RAI 348 on Shutdown Rod Reliability Project stage: RAI ML23158A2682023-06-13013 June 2023 Safety Evaluation for Hermes Construction Permit Application Project stage: Approval ML23158A2662023-06-13013 June 2023 Transmittal of Safety Evaluation for Hermes Construction Permit Application Project stage: Approval ML23181A1072023-07-18018 July 2023 Summary of August 25 and 30 2022 Public Meetings on the Kairos Hermes Preliminary Safety Analysis Report Project stage: Meeting ML23237B4652023-09-11011 September 2023 FRN: General Notice. Acceptance for Docketing of the Kairos Power LLC Hermes 2 Test Reactor Construction Permit Project stage: Request ML23353A0692024-01-0505 January 2024 Kairos Power, LLC-Hermes 2-Environmental Report Audit Plan Project stage: Other 2022-03-23
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24008A0802024-01-0808 January 2024 Kairos Power LLC, Summary of 11/2/2023, Public Meeting to Discuss Material Control and Accounting ML23305A0092023-11-0909 November 2023 Summary of the October 26, 2023 Meeting with Tennessee Historical Commission Regarding Section 106 Consultations ML23271A1362023-10-0303 October 2023 Summary of the September 12 and September 21, 2023 Closed Meetings with Kairos Power Regarding Section 106 Consultations ML23242A2422023-09-14014 September 2023 Summary of the August 10, 2023 Closed Meetings with Kairos Power Regarding Section 106 Consultations ML23241A0032023-08-31031 August 2023 And 07/25/2023 Summary of Closed Meetings with Kairos Power Regarding Section 106 Consultations Under Section 106 of the National Historic Preservation Act ML23181A1072023-07-18018 July 2023 Summary of August 25 and 30 2022 Public Meetings on the Kairos Hermes Preliminary Safety Analysis Report ML23189A0072023-07-11011 July 2023 June 28, 2023, Summary of the Observation Meeting Between the U.S. Nuclear Regulatory Commission Staff and Kairos Power, LLC to Provide an Overview of the Hermes 2 Construction Permit Application ML23181A0422023-07-0606 July 2023 June 6 and 14, 2023 Summary of the Closed Meetings with Kairos Power Regarding Section 106 Consultations ML23156A6682023-06-0606 June 2023 Summary of February 9, 2022, Public Meeting on the Kairos Herme Preliminary Safety Analysis Report ML23132A3042023-05-22022 May 2023 April 11, 2023 Summary of Closed Meeting with Kairos Power, LLC Regarding Consultations Under National Historic Preservation Act ML23031A1602023-03-21021 March 2023 Summary of Public Meeting for the Draft Environmental Impact Statement for the Kairos Hermes Test Reactor Construction Permit Application ML22110A0182022-05-0505 May 2022 Kairos Power LLC, Summary of March 23, 2022, Public Outreach Meeting on the Proposed Kairos Hermes Test Reactor with Designated Period for Receipt of Environmental Scoping Comments 2024-01-08
[Table view] Category:Memoranda
MONTHYEARML24185A0482024-07-0505 July 2024 Input for ACRS Review of Kairos Non-Power Reactor Hermes 2 Construction Permit Application - Safety Evaluation for Chapter 4, Reactor Description ML24185A0442024-07-0505 July 2024 Input for ACRS Review of Kairos Non-Power Reactor Hermes 2 Construction Permit Application - Draft Safety Evaluation for Chapters 7, Instrumentation and Control Systems and 8, Electric Power Systems ML24185A0462024-07-0505 July 2024 Input for ACRS Review of Kairos 2 Construction Permit Application - Draft Safety Evaluation for Chapter 13, Accident Analysis ML24185A0502024-07-0505 July 2024 Input for ACRS Review of Kairos Hermes 2 Non-Power Reactor Construction Permit Application - Draft Safety Evaluation for Chapter 5, Heat Transport Systems ML24008A0802024-01-0808 January 2024 Kairos Power LLC, Summary of 11/2/2023, Public Meeting to Discuss Material Control and Accounting ML23318A5162023-11-30030 November 2023 Implementation of Provisions from Consultations Under Section 106 of the National Historic Preservation Act on the Kairos Hermes Test Reactor CP Review ML23220A1992023-09-0707 September 2023 Consideration of New Information Regarding Potential Cumulative Impacts from the Proposed Kairos Hermes 2 Test Reactor on the Kairos Hermes Construction Permit Review ML23181A1072023-07-18018 July 2023 Summary of August 25 and 30 2022 Public Meetings on the Kairos Hermes Preliminary Safety Analysis Report ML23189A0072023-07-11011 July 2023 June 28, 2023, Summary of the Observation Meeting Between the U.S. Nuclear Regulatory Commission Staff and Kairos Power, LLC to Provide an Overview of the Hermes 2 Construction Permit Application ML23156A6682023-06-0606 June 2023 Summary of February 9, 2022, Public Meeting on the Kairos Herme Preliminary Safety Analysis Report ML23117A0052023-05-0101 May 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 3, Design of Structures, Systems and Components ML23117A0502023-04-29029 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 12, Conduct of Operations ML23117A0272023-04-28028 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 10, Experimental Facilities and Utilization ML23117A0022023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 1, the Facility ML23117A0032023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 2, Site Characteristics ML23117A0172023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 8, Electric Power Systems ML23117A0162023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 7, Instrumentation and Control Systems ML23117A0082023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 4, Reactor Description ML23117A0102023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 5, Heat Transport Systems ML23117A0112023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 6, Engineered Safety Features ML23117A0192023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 9, Auxiliary Systems ML23117A0302023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 11, Radiation Protection and Waste Management ML23117A0522023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 13, Accident Analysis ML23117A0612023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 14, Technical Specifications ML23117A0652023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 16, Other License Considerations ML23117A0692023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 17, Decommissioning and Possession-Only License Amendments ML23031A1602023-03-21021 March 2023 Summary of Public Meeting for the Draft Environmental Impact Statement for the Kairos Hermes Test Reactor Construction Permit Application ML22196A3882022-08-24024 August 2022 Memorandum from T.Dozier to K.Erwin - Summary Report for Environmental Audit of the Kairos Hermes Test Reactor Construction Permit Application ML22193A2402022-08-0101 August 2022 Issuance of Environmental Scoping Summary Report for the Review of the Kairos Hermes Test Reactor Construction Permit Application ML22169A0092022-04-12012 April 2022 NPS Scoping Comments on Kairos Test Reactor 2024-07-05
[Table view] |
Text
July 18, 2023
MEMORANDUM TO: W illiam Jessup, Chief Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation
FROM: Samuel Cuadrado, Project Manager /RA/
Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF AUGUST 25 AND 30, 2022, PUBLIC MEETINGS ON THE KAIROS HERMES PRELIMINARY SAFETY ANALYSIS REPORT (EPID NO. L-2021 - NEW- 0011 )
Meeting Information:
Applicant: Kairos Power, LLC (Kairos)
Docket/Project No.(s): 05007513 Public Meeting Notice Agencywide Documents Access and Management System (ADAMS)
Accession Nos.: ML22227A186 and ML22238A338 Meeting Attendees: See the enclosure for a list of meeting attendees.
Meeting Summary:
On August 25 and 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) staff held partially closed meetings via webinar with Kairos. The U.S. Nuclear Regulatory Commission (NRC) staff conducted the meetings in accordance with NRC Management Directive 3.5, Attendance at NRC Staff-Sponsored Meetings (ADAMS Accession No. ML21180A271). The purpose of the meetings was to discuss the NRCs safety review of the Kairos Hermes test reactor construction permit application. Specifically, the staff provided clarification to Kairos for the following requests for additional information (RAIs):
- RAI 339, on inspection of vessel internals and the natural circulation flow path (ML222 20A299)
- RAI 350, on a ir ingress into the primary heat transport system (ML 22227A192)
CONTACT: Samuel Cuadrado, NRR/DANU/UAL1 301-415-2 946 W. Jessup 2
During the meetings, Kairos discussed its draft responses to the three RAIs. The NRC staff provided clarification and was able to identify a few areas of the responses in need of additional detail. Kairos understood the clarifications provided and took action to incorporate the additional detail into its formal responses. Kairos also noted several changes that would be made to the PSAR. The NRC staff concluded that Kairos was on a satisfactory path to provide adequate responses to the RAIs in a timely manner. Kairos submitted its formal responses to RAIs 339 and 348 on August 31, 2022, ( ML22243A247 ) and to RAI 350 on September 1, 2022, ( ML22252A149), as originally expected (within 30 days of issuance of the RAIs).
No regulatory decisions were made as a result of this meeting.
Docket No. 05007513
Enclosure:
List of Attendees
W. Jessup 3
SUBJECT:
SUMMARY
OF AUGUST 25 AND 30, 2022, PUBLIC MEETINGS ON THE KAIROS HERMES PRELIMINARY SAFETY ANALYSIS REPORT (EPID NO. L-2021 - NEW- 0011)
DATE: JULY 18, 2023
DISTRIBUTION:
PUBLIC RidsNrrDanuUal1 Resource RidsNrrDanu Resource WJessup, NRR MHiser, NRR EHelvenston, NRR
ADAMS Accession Number: ML23181A107 NRC- 001 OFFICE NRR/DANU/UAL1/PM NRR/DANU/UAL1/BC NRR/DANU/UAL1/PM NAME SCuadrado WJessup SCuadrado DATE 7/18/2023 7/18/2023 7/18/2023 OFFICIAL RECORD COPY
List of Attendees
Name Organization Ben Beasley U.S. Nuclear Regulatory Commission (NRC)
Meg Audrain NRC Alex Chereskin NRC Stephen Philpott NRC Ed Helvenston NRC Jeff Schmidt NRC Samuel Cuadrado NRC Darrell Gardner Kairos Power LLC Drew Peebles Kairos Power LLC Jim Tomkins Kairos Power LLC Chong Chen Kairos Power LLC Gus Merwin Kairos Power LLC Jordan Hagaman Kairos Power LLC Ka-Yen Kairos Power LLC Nicole Schlichting Kairos Power LLC Michael Ellet Kairos Power LLC Delaney Simmons Kairos Power LLC Quan Zhou Kairos Power LLC Tim Drzewiecki Kairos Power LLC Anthonie Cilliers Kairos Power LLC Ian Gifford TerraPower Michael Montecalvo TerraPower Paul Ouellette Engineering Planning and Management, Inc.
Brandon Hartle X-Energy Steve Vaughn X-Energy Brandon Norris X-Energy