Letter Sequence ' |
---|
EPID:L-2021-NEW-0012, Kairos Hermes NRC Staff Presentation at Nov 16 Public Meeting on the Draft Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor (Open) |
|
MONTHYEARML21319A3542021-11-29029 November 2021 Acceptance of the Hermes Non-Power Test Reactor Construction Permit Application for Kairos Power LLC Project stage: Acceptance Review ML22028A0022022-02-0202 February 2022 Kairos Hermes Environmental Audit Plan Project stage: Other ML21364A0132022-02-0808 February 2022 Kairos Power LLC - Application for Construction Permit for Hermes Test Reactor Project stage: Other ML21326A0592022-02-18018 February 2022 Kairos Hermes CP Review - Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement Project stage: Other ML22311A5532022-11-16016 November 2022 Kairos Hermes NRC Staff Presentation at Nov 16 Public Meeting on the Draft Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor Project stage: Request ML22329A0112022-11-16016 November 2022 Deis Public Meeting Transcript for Kairos Hermes Construction Permit Application Project stage: Meeting ML23031A1602023-03-21021 March 2023 Summary of Public Meeting for the Draft Environmental Impact Statement for the Kairos Hermes Test Reactor Construction Permit Application ML23031A1652023-03-21021 March 2023 Kairos Attendance List Project stage: Request ML23237B4652023-09-11011 September 2023 FRN: General Notice. Acceptance for Docketing of the Kairos Power LLC Hermes 2 Test Reactor Construction Permit Project stage: Request ML23353A0692024-01-0505 January 2024 Kairos Power, LLC-Hermes 2-Environmental Report Audit Plan Project stage: Other 2022-02-02
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24008A0802024-01-0808 January 2024 Kairos Power LLC, Summary of 11/2/2023, Public Meeting to Discuss Material Control and Accounting ML23305A0092023-11-0909 November 2023 Summary of the October 26, 2023 Meeting with Tennessee Historical Commission Regarding Section 106 Consultations ML23271A1362023-10-0303 October 2023 Summary of the September 12 and September 21, 2023 Closed Meetings with Kairos Power Regarding Section 106 Consultations ML23242A2422023-09-14014 September 2023 Summary of the August 10, 2023 Closed Meetings with Kairos Power Regarding Section 106 Consultations ML23241A0032023-08-31031 August 2023 And 07/25/2023 Summary of Closed Meetings with Kairos Power Regarding Section 106 Consultations Under Section 106 of the National Historic Preservation Act ML23181A1072023-07-18018 July 2023 Summary of August 25 and 30 2022 Public Meetings on the Kairos Hermes Preliminary Safety Analysis Report ML23189A0072023-07-11011 July 2023 June 28, 2023, Summary of the Observation Meeting Between the U.S. Nuclear Regulatory Commission Staff and Kairos Power, LLC to Provide an Overview of the Hermes 2 Construction Permit Application ML23181A0422023-07-0606 July 2023 June 6 and 14, 2023 Summary of the Closed Meetings with Kairos Power Regarding Section 106 Consultations ML23156A6682023-06-0606 June 2023 Summary of February 9, 2022, Public Meeting on the Kairos Herme Preliminary Safety Analysis Report ML23132A3042023-05-22022 May 2023 April 11, 2023 Summary of Closed Meeting with Kairos Power, LLC Regarding Consultations Under National Historic Preservation Act ML23031A1602023-03-21021 March 2023 Summary of Public Meeting for the Draft Environmental Impact Statement for the Kairos Hermes Test Reactor Construction Permit Application ML22110A0182022-05-0505 May 2022 Kairos Power LLC, Summary of March 23, 2022, Public Outreach Meeting on the Proposed Kairos Hermes Test Reactor with Designated Period for Receipt of Environmental Scoping Comments 2024-01-08
[Table view] Category:Memoranda
MONTHYEARML24185A0482024-07-0505 July 2024 Input for ACRS Review of Kairos Non-Power Reactor Hermes 2 Construction Permit Application - Safety Evaluation for Chapter 4, Reactor Description ML24185A0442024-07-0505 July 2024 Input for ACRS Review of Kairos Non-Power Reactor Hermes 2 Construction Permit Application - Draft Safety Evaluation for Chapters 7, Instrumentation and Control Systems and 8, Electric Power Systems ML24185A0462024-07-0505 July 2024 Input for ACRS Review of Kairos 2 Construction Permit Application - Draft Safety Evaluation for Chapter 13, Accident Analysis ML24185A0502024-07-0505 July 2024 Input for ACRS Review of Kairos Hermes 2 Non-Power Reactor Construction Permit Application - Draft Safety Evaluation for Chapter 5, Heat Transport Systems ML24008A0802024-01-0808 January 2024 Kairos Power LLC, Summary of 11/2/2023, Public Meeting to Discuss Material Control and Accounting ML23318A5162023-11-30030 November 2023 Implementation of Provisions from Consultations Under Section 106 of the National Historic Preservation Act on the Kairos Hermes Test Reactor CP Review ML23220A1992023-09-0707 September 2023 Consideration of New Information Regarding Potential Cumulative Impacts from the Proposed Kairos Hermes 2 Test Reactor on the Kairos Hermes Construction Permit Review ML23181A1072023-07-18018 July 2023 Summary of August 25 and 30 2022 Public Meetings on the Kairos Hermes Preliminary Safety Analysis Report ML23189A0072023-07-11011 July 2023 June 28, 2023, Summary of the Observation Meeting Between the U.S. Nuclear Regulatory Commission Staff and Kairos Power, LLC to Provide an Overview of the Hermes 2 Construction Permit Application ML23156A6682023-06-0606 June 2023 Summary of February 9, 2022, Public Meeting on the Kairos Herme Preliminary Safety Analysis Report ML23117A0052023-05-0101 May 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 3, Design of Structures, Systems and Components ML23117A0502023-04-29029 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 12, Conduct of Operations ML23117A0272023-04-28028 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 10, Experimental Facilities and Utilization ML23117A0022023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 1, the Facility ML23117A0032023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 2, Site Characteristics ML23117A0172023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 8, Electric Power Systems ML23117A0162023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 7, Instrumentation and Control Systems ML23117A0082023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 4, Reactor Description ML23117A0102023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 5, Heat Transport Systems ML23117A0112023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 6, Engineered Safety Features ML23117A0192023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 9, Auxiliary Systems ML23117A0302023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 11, Radiation Protection and Waste Management ML23117A0522023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 13, Accident Analysis ML23117A0612023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 14, Technical Specifications ML23117A0652023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 16, Other License Considerations ML23117A0692023-04-27027 April 2023 Kairos Non-Power Reactor Hermes Construction Permit Application - Safety Evaluation for Chapter 17, Decommissioning and Possession-Only License Amendments ML23031A1602023-03-21021 March 2023 Summary of Public Meeting for the Draft Environmental Impact Statement for the Kairos Hermes Test Reactor Construction Permit Application ML22196A3882022-08-24024 August 2022 Memorandum from T.Dozier to K.Erwin - Summary Report for Environmental Audit of the Kairos Hermes Test Reactor Construction Permit Application ML22193A2402022-08-0101 August 2022 Issuance of Environmental Scoping Summary Report for the Review of the Kairos Hermes Test Reactor Construction Permit Application ML22169A0092022-04-12012 April 2022 NPS Scoping Comments on Kairos Test Reactor 2024-07-05
[Table view] |
Text
MEMORANDUM TO: Kenneth Erwin, Chief Environmental Review New Reactors Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguard FROM: Tamsen Dozier, Project Manager Environmental Review New Reactors Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguard
SUBJECT:
SUMMARY
OF THE NOVEMBER 16, 2022 PUBLIC MEETING FOR THE DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR THE KAIROS HERMES TEST REACTOR CONSTRUCTION PERMIT APPLICATION (EPID NO.: L-2021-NEW-0012)
On November 16, 2022, the U.S. Nuclear Regulatory Commission (NRC) staff held a comment-gathering hybrid public meeting in Oak Ridge, TN. The purpose of this meeting was to provide an opportunity for the staff to describe the environmental review of the construction permit application from Kairos Power for the Hermes test reactor and to solicit comments from the public on the draft environmental impact statement (EIS) from attendees both in-person and virtually through the Microsoft TEAMS application. This meeting allowed the NRC staff to meet directly with individuals to receive comment from participants to ensure that the staff understands their views and concerns.
The meeting notice and agenda are available in the NRCs Agencywide Documents Access and Management System (ADAMS) at Accession No. ML22314A017. The NRC staffs presentation slides are also in ADAMS at Accession No. ML22311A553. In addition, a transcript of the meeting is in ADAMS at Accession No. ML22329A011. A list of attendees is provided in the Enclosure to this summary. A total of 102 attendees were recorded, with 60 of those attending in-person in Oak Ridge and 42 attendees participating via the Microsoft TEAMS application.
During the meeting, following the NRC staff introductions and welcoming remarks, staff from the NRCs Offices of Nuclear Materials Safety and Safeguards and Nuclear Reactor Regulation provided a presentation that gave an overview of the NRCs mission, described the Hermes facility that Kairos is planning to construct in Oak Ridge, Tennessee, and described the NRCs safety and environmental review process. The NRC staffs presentation provided a summary of the draft EIS and described the process for interested persons to submit comments during the comment period, which ended on December 6, 2022.
CONTACT: Tamsen Dozier, NMSS/REFS 301-415-2272March 20, 2023 Signed by Dozier, Tamsen on 03/20/23 K. Erwin
After the NRC staff presentation, the NRC staff answered two questions on its review processes. During the comment portion of the meeting, both in-person and virtual attendees provided a total of thirteen verbal comments. The comments were generally supportive of the NRCs review, primarily emphasizing the potential benefits of new nuclear technology and encouraged the NRCs streamlining and modernizing of the licensing process. The suggestion was made that the NRCs no action alternative should include the environmental impacts from not realizing this carbon reducing technology option in the power sector. The verbal comments provided during the meeting and any written comments the NRC staff received during the scoping period will be considered in the NRC staffs development of its final EIS for the Hermes application.
Docket No. 50-7513
Enclosure:
List of Attendees
cc: w/enclosure:
see next page
ML23031A160 (document),
ML23031A165(Enclosure), ML23030B852 (package) *via email OFFICE PM:REFS/ENRB LA:REFS/ERMB BC:REFS/ENRB PM:REFS/ENRB
NAME TDozier AWalker-Smith* KErwin TDozier
DATE 02/7/2023 03/7/2023 03/10/2023 03/20/2023