Letter Sequence ' |
|---|
EPID:L-2021-NEW-0012, NIST Center for Neutron Research Test Reactor - Request for Changes to Technical Specifications to Allow Low Power Testing (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement
|
MONTHYEARML17277B2612017-10-24024 October 2017 Aerotest Radiography and Research Reactor, Request for Additional Information Regarding the Renewal of Facility Operating License No. R-98 Project stage: RAI ML17363A3032017-12-20020 December 2017 Submittal of Response to Request to Supplement the License Renewal Application Project stage: Supplement ML18010A5622018-02-0202 February 2018 Aerotest Radiography and Research Reactor - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML18054A2022018-02-21021 February 2018 Response to Request for Holding Information from Public Disclosure Project stage: Request ML18066A0752018-02-28028 February 2018 Submittal of Response to Request for Holding Information from Public Disclosure Project stage: Request ML18066A0802018-02-28028 February 2018 Submittal of Response to Request for Holding Information from Public Disclosure Project stage: Request ML18093A3852018-03-29029 March 2018 Clarification of TS 6.6 Project stage: Request ML18088A7532018-03-29029 March 2018 Draft Request for Additional Information for License Renewal of the Aerotest Radiography and Research Reactor Project stage: Request ML18074A1112018-04-0202 April 2018 Request for Withholding Information from Public Disclosure Response to Request to Aerotest Operations, Inc. to Supplement the License Renewal Application Project stage: Withholding Request Acceptance ML18088A7012018-04-24024 April 2018 Request for Additional Information Regarding the Renewal of Facility Operating License No. R-98 Project stage: RAI ML18127A0752018-04-30030 April 2018 Elimination of Technical Specification 6.6 Project stage: Request ML18127B7032018-06-0808 June 2018 Review of the Restart Plan for the Aerotest Radiography and Research Reactor Project stage: Approval ML18201A1972018-07-17017 July 2018 Request for Additional Time Project stage: Request ML18198A4512018-07-23023 July 2018 Response to Request for Extension of Time to Respond to Request for Additional Information Regarding the Renewal of Facility Operating License No. R-98 Project stage: RAI ML18257A0752018-09-11011 September 2018 Request for Additional Time Beyond the Deadline to Answer Questions Project stage: Request ML18260A0452018-09-18018 September 2018 Response to Second Request for Extension of Time to Respond to Request for Additional Information Regarding the Renewal of Facility Operating License No. R-98 Project stage: RAI ML18277A2962018-10-15015 October 2018 Request for Additional Information Regarding the Operator Requalification Program for the Aerotest Radiography and Research Reactor Project stage: RAI ML18303A2912018-10-24024 October 2018 Aerotest Radiography and Research Reactor Response to RAI-ORP-7 Project stage: Request ML19015A3322019-01-25025 January 2019 Requests for Renewal of Facility Operating License No. R-98, Review of the Restart Plan, and Amendment to Technical Specification 6.6 for the Aerotest Radiography and Research Reactor Project stage: Approval ML21272A3762021-09-29029 September 2021 Kairos Power, LLC - Submittal of the Preliminary Safety Analysis Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes) Project stage: Request ML21306A1322021-10-31031 October 2021 Kairos Power LLC Submittal of the Environmental Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes) Project stage: Request ML21319A3542021-11-29029 November 2021 Acceptance of the Hermes Non-Power Test Reactor Construction Permit Application for Kairos Power LLC Project stage: Acceptance Review ML22028A0022022-02-0202 February 2022 Kairos Hermes Environmental Audit Plan Project stage: Other ML21364A0132022-02-0808 February 2022 Kairos Power LLC - Application for Construction Permit for Hermes Test Reactor Project stage: Other ML21204A0392022-02-15015 February 2022 Federal Register Notice of Intent to Conduct Scoping and Prepare an EIS - Kairos Hermes CP Review Project stage: Request ML21326A0592022-02-18018 February 2022 Kairos Hermes CP Review - Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement Project stage: Other ML22031A2892022-03-10010 March 2022 Request to Initiate Section 106 Consultation and Scoping Process for Kairos Power Hermes Non-Power Test Reactor Construction Permit Review Project stage: Request ML22091A0002022-03-23023 March 2022 Kairos Hermes Scoping Meeting Transcript Project stage: Request ML22089A1662022-04-0808 April 2022 Kairos Power LLC - Hermes Construction Permit Preliminary Safety Analysis Report I&C Repor (Chapter 7) Audit Plan (Cac/Epid No. 000955/05007513/L-2021-NEW-0011) Project stage: Other ML22110A0182022-05-0505 May 2022 Kairos Power LLC, Summary of March 23, 2022, Public Outreach Meeting on the Proposed Kairos Hermes Test Reactor with Designated Period for Receipt of Environmental Scoping Comments Project stage: Request ML22329A0112022-11-16016 November 2022 Deis Public Meeting Transcript for Kairos Hermes Construction Permit Application Project stage: Meeting ML22311A5532022-11-16016 November 2022 Kairos Hermes NRC Staff Presentation at Nov 16 Public Meeting on the Draft Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor Project stage: Request ML23031A1602023-03-21021 March 2023 Summary of Public Meeting for the Draft Environmental Impact Statement for the Kairos Hermes Test Reactor Construction Permit Application ML23031A1652023-03-21021 March 2023 Kairos Attendance List Project stage: Request ML24284A1712023-07-14014 July 2023 NRC-002B - Kairos Power LLC, Construction Permit Application - General Information (July 14, 2023) Project stage: Other ML23195A1252023-07-14014 July 2023 Enclosure 3: Environmental Report H2-ER-0000001, Rev. 0 Project stage: Request ML23237B4652023-09-11011 September 2023 FRN: General Notice. Acceptance for Docketing of the Kairos Power LLC Hermes 2 Test Reactor Construction Permit Project stage: Request ML23353A0692024-01-0505 January 2024 Kairos Power, LLC-Hermes 2-Environmental Report Audit Plan Project stage: Other 2019-01-25
[Table View] |
"Draft Meeting" is not in the list (Request, Draft Request, Supplement, Acceptance Review, Meeting, Withholding Request, Withholding Request Acceptance, RAI, Draft RAI, Draft Response to RAI, ...) of allowed values for the "Project stage" property.
Text
MEMORANDUM TO:
Kenneth Erwin, Chief Environmental Review New Reactors Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguard FROM:
Tamsen Dozier, Project Manager Environmental Review New Reactors Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguard
SUBJECT:
SUMMARY
OF THE NOVEMBER 16, 2022 PUBLIC MEETING FOR THE DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR THE KAIROS HERMES TEST REACTOR CONSTRUCTION PERMIT APPLICATION (EPID NO.: L-2021-NEW-0012)
On November 16, 2022, the U.S. Nuclear Regulatory Commission (NRC) staff held a comment-gathering hybrid public meeting in Oak Ridge, TN. The purpose of this meeting was to provide an opportunity for the staff to describe the environmental review of the construction permit application from Kairos Power for the Hermes test reactor and to solicit comments from the public on the draft environmental impact statement (EIS) from attendees both in-person and virtually through the Microsoft TEAMS application. This meeting allowed the NRC staff to meet directly with individuals to receive comment from participants to ensure that the staff understands their views and concerns.
The meeting notice and agenda are available in the NRCs Agencywide Documents Access and Management System (ADAMS) at Accession No. ML22314A017. The NRC staffs presentation slides are also in ADAMS at Accession No. ML22311A553. In addition, a transcript of the meeting is in ADAMS at Accession No. ML22329A011. A list of attendees is provided in the Enclosure to this summary. A total of 102 attendees were recorded, with 60 of those attending in-person in Oak Ridge and 42 attendees participating via the Microsoft TEAMS application.
During the meeting, following the NRC staff introductions and welcoming remarks, staff from the NRCs Offices of Nuclear Materials Safety and Safeguards and Nuclear Reactor Regulation provided a presentation that gave an overview of the NRCs mission, described the Hermes facility that Kairos is planning to construct in Oak Ridge, Tennessee, and described the NRCs safety and environmental review process. The NRC staffs presentation provided a summary of the draft EIS and described the process for interested persons to submit comments during the comment period, which ended on December 6, 2022.
CONTACT:
Tamsen Dozier, NMSS/REFS 301-415-2272 March 20, 2023 Signed by Dozier, Tamsen on 03/20/23
K. Erwin After the NRC staff presentation, the NRC staff answered two questions on its review processes. During the comment portion of the meeting, both in-person and virtual attendees provided a total of thirteen verbal comments. The comments were generally supportive of the NRCs review, primarily emphasizing the potential benefits of new nuclear technology and encouraged the NRCs streamlining and modernizing of the licensing process. The suggestion was made that the NRCs no action alternative should include the environmental impacts from not realizing this carbon reducing technology option in the power sector. The verbal comments provided during the meeting and any written comments the NRC staff received during the scoping period will be considered in the NRC staffs development of its final EIS for the Hermes application.
Docket No. 50-7513
Enclosure:
List of Attendees cc: w/enclosure:
see next page
ML23031A160 (document),
ML23031A165(Enclosure), ML23030B852 (package)
- via email OFFICE PM:REFS/ENRB LA:REFS/ERMB BC:REFS/ENRB PM:REFS/ENRB NAME TDozier AWalker-Smith*
KErwin TDozier DATE 02/7/2023 03/7/2023 03/10/2023 03/20/2023