EPID:L-2018-LLA-0096, NIST Center for Neutron Research Test Reactor - Request for Changes to Technical Specifications to Allow Low Power Testing (Approved, Closed) EPID:000955, NIST Center for Neutron Research Test Reactor - Request for Changes to Technical Specifications to Allow Low Power Testing (Approved, Closed) |
|
MONTHYEARML17277B2612017-10-24024 October 2017 Aerotest Radiography and Research Reactor, Request for Additional Information Regarding the Renewal of Facility Operating License No. R-98 Project stage: RAI ML17363A3032017-12-20020 December 2017 Submittal of Response to Request to Supplement the License Renewal Application Project stage: Supplement ML18010A5622018-02-0202 February 2018 Aerotest Radiography and Research Reactor - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML18054A2022018-02-21021 February 2018 Response to Request for Holding Information from Public Disclosure Project stage: Request ML18066A0802018-02-28028 February 2018 Submittal of Response to Request for Holding Information from Public Disclosure Project stage: Request ML18066A0752018-02-28028 February 2018 Submittal of Response to Request for Holding Information from Public Disclosure Project stage: Request ML18088A7532018-03-29029 March 2018 Draft Request for Additional Information for License Renewal of the Aerotest Radiography and Research Reactor Project stage: Request ML18093A3852018-03-29029 March 2018 Clarification of TS 6.6 Project stage: Request ML18074A1112018-04-0202 April 2018 Request for Withholding Information from Public Disclosure Response to Request to Aerotest Operations, Inc. to Supplement the License Renewal Application Project stage: Withholding Request Acceptance ML18088A7012018-04-24024 April 2018 Request for Additional Information Regarding the Renewal of Facility Operating License No. R-98 Project stage: RAI ML18127A0752018-04-30030 April 2018 Elimination of Technical Specification 6.6 Project stage: Request ML18129A0562018-05-16016 May 2018 Acceptance of Requested Licensing Action Regarding Technical Specification 6.6 for the Aerotest Radiography and Research Reactor Project stage: Acceptance Review ML18127B7032018-06-0808 June 2018 Review of the Restart Plan for the Aerotest Radiography and Research Reactor Project stage: Approval ML18201A1972018-07-17017 July 2018 Request for Additional Time Project stage: Request ML18198A4512018-07-23023 July 2018 Response to Request for Extension of Time to Respond to Request for Additional Information Regarding the Renewal of Facility Operating License No. R-98 Project stage: RAI ML18257A0752018-09-11011 September 2018 Request for Additional Time Beyond the Deadline to Answer Questions Project stage: Request ML18260A0452018-09-18018 September 2018 Response to Second Request for Extension of Time to Respond to Request for Additional Information Regarding the Renewal of Facility Operating License No. R-98 Project stage: RAI ML18277A2962018-10-15015 October 2018 Request for Additional Information Regarding the Operator Requalification Program for the Aerotest Radiography and Research Reactor Project stage: RAI ML18303A2912018-10-24024 October 2018 Aerotest Radiography and Research Reactor Response to RAI-ORP-7 Project stage: Request ML19015A3322019-01-25025 January 2019 Requests for Renewal of Facility Operating License No. R-98, Review of the Restart Plan, and Amendment to Technical Specification 6.6 for the Aerotest Radiography and Research Reactor Project stage: Approval ML20309A6762020-11-0404 November 2020 Missouri University of Science and Technology - Written Communication as Specified by 10 CFR 50.4 Requesting Approval of an Exigent Amendment to the Technical Specifications Appended to Facility Operating License R-79 Project stage: Request ML20314A3622020-11-12012 November 2020 Board of the Curators of the University of Missouri - Issuance of Amendment No. 22 to Renewed Facility Operating License No. R-79 to Extend the Period to Perform Visual Inspections of the Shim/Safety Rods Project stage: Approval ML21272A3762021-09-29029 September 2021 Kairos Power, LLC - Submittal of the Preliminary Safety Analysis Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes) Project stage: Request ML21306A1322021-10-31031 October 2021 Kairos Power LLC Submittal of the Environmental Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes) Project stage: Request ML21319A3542021-11-29029 November 2021 Acceptance of the Hermes Non-Power Test Reactor Construction Permit Application for Kairos Power LLC Project stage: Acceptance Review ML22028A0022022-02-0202 February 2022 Kairos Hermes Environmental Audit Plan Project stage: Other ML21364A0132022-02-0808 February 2022 Kairos Power LLC - Application for Construction Permit for Hermes Test Reactor Project stage: Other ML21204A0392022-02-15015 February 2022 Federal Register Notice of Intent to Conduct Scoping and Prepare an EIS - Kairos Hermes CP Review Project stage: Request ML21326A0592022-02-18018 February 2022 Kairos Hermes CP Review - Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement Project stage: Other ML22091A0002022-03-23023 March 2022 Kairos Hermes Scoping Meeting Transcript Project stage: Request ML22089A1662022-04-0808 April 2022 Kairos Power LLC - Hermes Construction Permit Preliminary Safety Analysis Report I&C Repor (Chapter 7) Audit Plan (Cac/Epid No. 000955/05007513/L-2021-NEW-0011) Project stage: Other ML22110A0182022-05-0505 May 2022 Kairos Power LLC, Summary of March 23, 2022, Public Outreach Meeting on the Proposed Kairos Hermes Test Reactor with Designated Period for Receipt of Environmental Scoping Comments Project stage: Request ML22329A0112022-11-16016 November 2022 Deis Public Meeting Transcript for Kairos Hermes Construction Permit Application Project stage: Meeting ML22311A5532022-11-16016 November 2022 Kairos Hermes NRC Staff Presentation at Nov 16 Public Meeting on the Draft Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor Project stage: Request ML23031A1602023-03-21021 March 2023 Summary of Public Meeting for the Draft Environmental Impact Statement for the Kairos Hermes Test Reactor Construction Permit Application ML23031A1652023-03-21021 March 2023 Kairos Attendance List Project stage: Request ML24284A1712023-07-14014 July 2023 NRC-002B - Kairos Power LLC, Construction Permit Application - General Information (July 14, 2023) Project stage: Other ML23195A1252023-07-14014 July 2023 Enclosure 3: Environmental Report H2-ER-0000001, Rev. 0 Project stage: Request ML23237B4652023-09-11011 September 2023 FRN: General Notice. Acceptance for Docketing of the Kairos Power LLC Hermes 2 Test Reactor Construction Permit Project stage: Request ML23353A0692024-01-0505 January 2024 Kairos Power, LLC-Hermes 2-Environmental Report Audit Plan Project stage: Other 2019-01-25
[Table View] |
Text
AEROTEST OPERATIONS, INC.
3455 FOSTORIA WAY
- SAN RAMON, CA 94583 * (925) 866-1212
- FAX (925) 866-1716 October 24, 2018 ATTENTION: Document Control Desk (per 10 CFR 50.4)
U.S. Nuclear Regulatory Commission White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 AEROTEST RADIOGRAPHY AND RESEARCH REACTOR DOCKET NO. 50-228/LICENSE NO. R-98.
RESPONSE TO RAI-ORP-7 Ladies and Gentlemen:
The response concerning the request for additional information, RAI-ORP-7, obtained in NRC letter dated October 15, 2018 is provided in this document. The response is governed by the cited NRC regulations and July 27, 2000 ARRR Requalification program on the subject. (The new ARRR requalification program submitted in 2017 remains under review for approval and therefore is not relevant.)
ARRR SROs have maintained active status according to 10 CFR 55.53(e). Each Senior Reactor Operator has performed SRO activities for more than the minimum 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per calendar quarter and is documented in the SRO's activity log. This regulation.does not specify a composition or percentage of an acceptable SRO workload. While the ARRR SROs have maintained active status, if an operator did not, a remedial program including, at a minimum of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> of supervised SRO work as detailed in 10 CFR 55.53{f) (and reinforced with similar verbiage found in ANSI/ANS 15.4-2016.) Again, required tasks and composition of SRO activities are not specified in these regulations and standards. Simply, providing specificity for SRO duties is difficult due to varying circumstances surrounding each test or research reactor.
Examining the 10 CFR 55.59 requalification requirements, the ARRR SROs are also in compliance. Section
( c )(3)(i) requires that ".... the requalification programs must contain a commitment that each individual shall perform or participate in a combination of reactivity manipulations based on the availability of plant equipment and systems." (It also states that "senior operators are credited with these activities if they direct control manipulations as they are performed.")
The NRC ordered the ARRR shutdown on July 24 2013, thus eliminating the availability of the plant equipment and systems for the compliance with this obligation. The order was lifted shortly after the license transfer on July 17 2017. The plant equipment and systems needed to satisfy (c)(3)(i) (control manipulations) remain unavailable due to evaluation and preventive/corrective maintenance before the ARRR restart.
Based on the NRC regulations cited, the NRC staff conclusion "none of the Aerotest's licensed personnel currently hold an active status" is in error.
As part of the ARRR restart plan two activities were performed to re-familiarize with the control console instruments/systems and their function.
- 1. The TRIGA reactor response to the insertion of reactivity approach to criticality, low-power, and high power operations (including tthe impact of the fuel's negative temperature coefficient).
The licensed ARRR SRO, Chris Bauman completed SRO training activities on September 20, 2018 at Reed Research Reactor under the auspices of Director Melinda Krahenbuhl, PhD. Below are the activities performed include 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> of operation with a minimum of 10 reactivity manipulations of the control rods.
- 1. Briefed on security and safety for entrance.
- 2. Toured the control room, reactor, and related ancillary equipment.
- 3. Reviewed the console layout operation limits (scram settings), the start-up, normal shutdown, and emergency shutdown procedures.
- 4. ARRR SRO brought the reactor to 5 Watt, stabilized and recorded the power level.
(The Reed SRO noted the actions and instrument responses while the ARRR SRO initially withdrew the control rods.) Mr. Bauman was instructed to perform "power steps" at his discretion.
- 5. Starting from 5 Watts power, the ARRR SRO performed a series of reactivity manipulations by altering the position of the control rod to increase/decrease the power level. At each level (step), the power was stabilized and recorded before moving to the next requested power. The Reed SRO monitored the chosen power levels based on his/her understanding of equipment and instrument capabilities.
- 6. The Reed SRO discussed the shutdown process while Mr. Bauman performed that task.
- 7. A debriefing of the training session occurred shortly thereafter to ensure meeting the regulatory obligations.
An objective and performance of the activities are summarized in fulfilment of Section VI of the ARRR Re-Start Plan. The activity was recorded in the SRO activity logbook with activity summaries placed in Chris Bauman SRO's file.
- 2. ARRR 's unique layout of instruments and familiarity of switching sequences and the eye and hand coordination needed to successfully bring the reactor to criticality and sustain power operation.
The licensed ARRR SRO and Reactor Supervisor, A. Meren provided lectures and practicums of the ARRR checkout, Startup and Shutdown procedures to re-familiarize the operators with the reactor console.
Lectures were held on dates 5-30-18 (checkout), 6-5-18 (start-up), and 6-13-18 (shutdown) with individual practicums performed with Mr. Meren shortly after each lecture. An objective of the activities performed are summarized in fulfilment of Section VI of the ARRR Re-Start Plan. The activity is documented in SRO activity logbook and operators file.
I declare under penalty of perjury that the statements above are correct and truthful. Should you have any questions or require additional information regarding this submission, please contact AO President and Reactor Administrator David M. Slaughter, Ph.D. at (801) 631-5919 or dmsraven@gmail.com
~y~
~t--'r'~~~--~
David M. Slaughter, Ph.D.
President and Reactor Administrator Aerotest Operations, Inc.