Letter Sequence Acceptance Review |
---|
EPID:L-2022-LLA-0150, International, Submittal of License Amendment Request 9375-1 for the HI-STAR Atb 1T Non-Fuel Waste Transport System (Approved, Closed) EPID:L-2022-LLE-0030, International, Submittal of License Amendment Request 9375-1 for the HI-STAR Atb 1T Non-Fuel Waste Transport System (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement
Results
Other: ML22287A139, ML22287A141, ML22287A143, ML22287A146, ML22334A262, ML22334A263, ML22335A499, ML22335A501, ML22343A261, ML23068A377, ML23129A797, ML23206A199, ULNRC-06783, Enclosure 2: Affidavit for Withholding, ULNRC-06808, Affidavit
|
MONTHYEARML22050A0012022-02-18018 February 2022 International, Submittal of License Amendment Request 9375-1 for the HI-STAR Atb 1T Non-Fuel Waste Transport System Project stage: Request ML22130A7052022-05-10010 May 2022 International - Resubmittal of License Amendment Request 9375-1 for the HI-STAR Atb 1T Non-Fuel Waste Transport System Project stage: Request ML22161A0582022-06-0909 June 2022 International, Modification of License Amendment Request 9375-1 for the HI-STAR Atb 1T Non-Fuel Waste Transport System Project stage: Request ML22161A0592022-06-0909 June 2022 International, Modification of License Amendment Request 9375-1 for the HI-STAR Atb 1T Non-Fuel Waste Transport System Project stage: Request ML22235A1152022-08-25025 August 2022 Enc - 9375 RAI 2022 Project stage: RAI ML22235A1132022-08-25025 August 2022 RAIs for the Model No. HI-STAR Atb 1T Package Project stage: Request ML22235A1142022-08-25025 August 2022 Letter - Request for Additional Information for the Review of the Atb 1T Package - 2022 Project stage: RAI ULNRC-06768, Attachment 4 to Enclosure 1: Framatome Affidavits for Withholding from Public Disclosure2022-10-0707 October 2022 Attachment 4 to Enclosure 1: Framatome Affidavits for Withholding from Public Disclosure Project stage: Request ML22285A1152022-10-0707 October 2022, 12 October 2022 Application for Technical Specification Change and Exemption Request Regarding Use of Framatome Gaia Fuel (LDCN 22-0002) Project stage: Request ML22285A1222022-10-12012 October 2022 Attachment 5 to Enclosure 1: ANP-3947NP, Callaway Unit 1 License Amendment Request Inputs for Use of Framatome Fuel, Revision 3, Dated October 2022 Project stage: Request ML22285A1232022-10-12012 October 2022 Attachment 6 to Enclosure 1: ANP-3944NP, Callaway Realistic Large Break LOCA Analysis with Gaia Fuel Design, Revision 1, Dated October 2022 Project stage: Request ML22285A1242022-10-12012 October 2022 Attachment 7 to Enclosure 1: ANP-3943NP, Callaway Small Break LOCA Analysis with Gaia Fuel Design, Revision 1, Dated October 2022 Project stage: Request ML22287A1412022-10-14014 October 2022 Attachment 2 - HI-STAR Atb 1T Amendment Request 1 RAI Responses Project stage: Other ML22287A1462022-10-14014 October 2022 Affidavit of Kimberly Manzione Project stage: Other ML22287A1382022-10-14014 October 2022 Responses to HI-STAR Atb 1T Requests for Additional Information Project stage: Request ML22287A1432022-10-14014 October 2022 Attachment 4 - Safety Analysis Report on the HI-STAR Atb 1T Non-Fuel Waste Transport System Project stage: Other ML22287A1392022-10-14014 October 2022 Responses to HI-STAR Atb 1T Requests for Additional Information Project stage: Other ML22305A6042022-11-0101 November 2022 International - Supplemental Information for Responses to HI-STAR Atb 1T Requests for Additional Information Project stage: Supplement ML22335A4992022-11-16016 November 2022 Enclosure 1: Responses to Requested Information Project stage: Other ML22335A5012022-11-16016 November 2022 Enclosure 3: ANP-4012NP, Revision 1, Callaway Rod Ejection Accident Analysis Project stage: Other ML22335A4972022-11-16016 November 2022, 1 December 2022 Supplement to License Amendment and Exemption Request Regarding Use of Framatome Gaia Fuel (LDCN 22-0002) Project stage: Request ULNRC-06783, Enclosure 2: Affidavit for Withholding2022-11-16016 November 2022 Enclosure 2: Affidavit for Withholding Project stage: Other ML22322A0062022-11-17017 November 2022 NRR E-mail Capture - Final - LIC-109 Acceptance Review (Unacceptable for Review with Opportunity to Supplement) Callaway - LAR for Proposed Changes to TS and Exemption Request Use of Framatome Gaia Fuel - L-2022-LLA-0150 & L-2022-LLE-0030 Project stage: Acceptance Review ML22335A4982022-12-0101 December 2022 Supplement to License Amendment and Exemption Request Regarding Use of Framatome Gaia Fuel (LDCN 22-0002) Project stage: Supplement ML22343A2612022-12-0909 December 2022 International - Submittal of Final SAR for HI-STAR ATB-1T Amendment 1 Project stage: Other ML22334A2632022-12-13013 December 2022 Enclosure 1 - Certificate of Compliance Rev. No. 1 Project stage: Other ML22334A2642022-12-13013 December 2022 Enclosure 2 - Safety Evaluation Report Project stage: Approval ML22334A2612022-12-13013 December 2022 Certificate of Compliance No. 9375, Revision No. 1, for the Model No. HI-STAR ATB1T Package Project stage: Request ML22334A2622022-12-13013 December 2022 Cover letter- Certificate of Compliance No. 9375, Revision No. 1, for the Model No. HI-STAR ATB1T Package Project stage: Other ML22348A1162022-12-21021 December 2022 Acceptance of Requested Licensing Actions Application for License Amendment & Regulatory Exemptions for TS Change & Exemption Request Regarding Use of Framatome Gaia Fuel (EPID L-2022-LLA-0150 & EPID L-2022-LLE-0030) Project stage: Acceptance Review ML23068A3772023-03-20020 March 2023 Regulatory Audit Plan and Setup of Online Reference Portal for License Amendment Request and Exemption for Fuel Transition to Framatome Gaia Fuel (EPID L-2022-LLA-0150 and EPID L-2022-LLE-0030) - Nonproprietary Project stage: Other ML23107A1812023-04-17017 April 2023 NRR E-mail Capture - Regulatory Audit Questions - Callaway LAR and Exemption for Fuel Transition to Framatome Gaia Fuel - EPIDs - L-2022-LLA-0150 and L-2022-LLE-0030 Project stage: Approval ML23114A2302023-04-24024 April 2023 NRR E-mail Capture - Regulatory Audit Question - Callaway LAR and Exemption for Fuel Transition to Framatome Gaia Fuel - EPIDs - L-2022-LLA-0150 and L-2022-LLE-0030 Project stage: Approval ULNRC-06808, Affidavit2023-04-27027 April 2023 Affidavit Project stage: Other ML23129A7932023-04-27027 April 2023, 9 May 2023 Post-Audit Supplement to License Amendment Request and Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (Iepid L-2022-LLA-0150 and EPID L-2022-LLE-0030) Project stage: Request ML23118A3492023-05-0808 May 2023 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML23129A7942023-05-0909 May 2023 Post-Audit Supplement to License Amendment Request and Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (Iepid L-2022-LLA-0150 and EPID L-2022-LLE-0030) Project stage: Supplement ML23129A7972023-05-0909 May 2023 Response to Audit Questions Project stage: Other ULNRC-06821, Post-Audit Follow-Up Information in Support of Callaways License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301)2023-06-21021 June 2023 Post-Audit Follow-Up Information in Support of Callaways License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301) Project stage: Request ML23215A1972023-08-0303 August 2023 Supplement to License Amendment and Exemption Request Regarding Use of Framatome Gaia Fuel (LDCN 22-0002) Project stage: Supplement ULNRC-06829, Affidavit2023-08-0303 August 2023 Affidavit Project stage: Request ML23215A1962023-08-0303 August 2023, 31 August 2023 Supplement to License Amendment and Exemption Request Regarding Use of Framatome Gaia Fuel (LDCN 22-0002) Project stage: Request ML23219A1392023-08-15015 August 2023 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML23215A1992023-08-31031 August 2023 ANP-4012NP, Callaway, Unit 1, Rod Ejection Accident Analysis Revision 2, August 2023 Project stage: Request ML23206A1992023-09-15015 September 2023 Regulatory Audit Summary Regarding License Amendment and Regulatory Exemptions Request for Fuel Transition to Framatome Gaia Fuel (Epids L-2022-LLA-0150 and L-2022-LLE-0030) Project stage: Other ML23240A3692023-10-0505 October 2023 Issuance of Amendment No. 235 to Revise Technical Specifications to Use of Framatome Gaia Fuel (EPID L-2022-LLA-0150) (Non-Proprietary) Project stage: Approval ML23234A1522023-10-0505 October 2023 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2022-LLE-0030) (Letter) Project stage: Approval ML23234A1532023-10-0505 October 2023 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2022-LLE-0030) (Exemption) Project stage: Approval ML23234A1592023-10-0505 October 2023 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material Project stage: Request ML23234A1542023-10-11011 October 2023 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2022-LLE-0030) (FRN) Project stage: Approval 2022-08-25
[Table View] |
|
---|
Category:Acceptance Review Letter
MONTHYEARML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) ML22348A1162022-12-21021 December 2022 Acceptance of Requested Licensing Actions Application for License Amendment & Regulatory Exemptions for TS Change & Exemption Request Regarding Use of Framatome Gaia Fuel (EPID L-2022-LLA-0150 & EPID L-2022-LLE-0030) ML22301A1812022-11-0808 November 2022 Acceptance of Requested Licensing Actions License Amendment Regarding Proposed Technical Specification Changes for Spent Fuel Storage ML21342A3332021-12-10010 December 2021 Acceptance of Requested Licensing Actions License Amendment for Adoption of Alternate Source Term and Revision of Technical Specifications ML21160A1482021-06-10010 June 2021 Acceptance of Requested Licensing Actions License Amendment and Regulatory Exemptions for a Risk Informed Approach to Address Generic Safety Issue 191 and Respond to Generic Letter 2004-02 ML19130A0442019-04-16016 April 2019 Acceptance Review for (EPID L-2019-LLA-0054) TS Change Main Turbine Control Slave Relay LAR ML15294A2322015-10-28028 October 2015 Acceptance of Requested Licensing Action, Review and Approval of Quality Assurance Plan Change Per Nuclear Energy Institute (NEI) 14-05A, Revision 1 ML13281A4232013-10-0808 October 2013 Acceptance Review Email, Requests for Relief PR-04 and PR-06, ASME OM Code Requirements for Frequency for Relief Valves and Devices, Fourth 10-Year Inservice Testing Interval ML13281A4212013-10-0808 October 2013 Acceptance Review Email, Requests for Relief PR-01, PR-02, PR-03, and PR-05, ASME OM Code Cases for Group a and B Pumps for Fourth 10-Year Inservice Testing Interval ML13039A0932013-02-0808 February 2013 Acceptance Review Email, License Amendment Request to Revise Final Safety Analysis Report FSAR-SP Sections 3.7(B) and 3.7(N), Seismic Design to Use Regulatory Guide 1.61 Revision 1 ML1132604512011-11-22022 November 2011 Correction Acceptance Review Email, Request for License Amendment to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) ML1132602802011-11-22022 November 2011 Acceptance Review Email, Request for License Amendment to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) ML1129804802011-10-25025 October 2011 Acceptance Review Email, Revise Technical Specification 3.3.6, Containment Purge Isolation Instrumentation. ML1121505412011-08-0303 August 2011 Acceptance Review E-mail, License Amendment Request to Revise Technical Specification 3.6.6, Containment Spray and Cooling Systems, ML1101408492011-01-14014 January 2011 Acceptance Review Email, License Amendment Request to Add New Surveillance Requirement 3.3.8.6 to Technical Specification 3.3.8, Emergency Exhaust System (EES) Actuation Instrumentation ML1025905882010-09-16016 September 2010 Acceptance Review E-mail, License Amendment Request, Revise TSs to Adopt TSTF-425 Rev. 3, Relocate Surveillance Frequencies to Licensee Control-Risk Informed Technical Specification Task Force Initiative 5 ML1025906042010-09-16016 September 2010 Acceptance Review E-mail License Amendment Request, Revise License Condition and Approve Cyber Security Plan ML1014600722010-06-16016 June 2010 License Amendment Request for Approval of the Cyber Security Plan ML1009603372010-04-0606 April 2010 Acceptance Review Email, License Amendment Request (Exigent Circumstances), Revise Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation, for Function 6.G in TS Table 3.3.2-1 ML1001415002010-01-14014 January 2010 Acceptance Review Email, License Amendment Request, Revise Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation, for Extension of Completion Times ML0920901462009-07-28028 July 2009 Acceptance Review Email, License Amendment Request, Technical Specification Changes Consistent with TSTF-447, Revision 1, Elimination of Hydrogen Recombiner and Change to Hydrogen and Oxygen Monitors ML0917403962009-06-23023 June 2009 Acceptance Review Email, License Amendment Request, Revise Technical Specification 3.3.9, Boron Dilution Mitigation System (Bdms) ML0914105822009-05-21021 May 2009 Acceptance Review Email, Modify Technical Specifications to Adopt TSTF-511, Eliminate Working Hour Restrictions from TS 5.2.2 to Support Compliance with 10 CFR Part 26 ML0914105692009-05-21021 May 2009 Acceptance Review Email, Revise Technical Specification (TS) 3.7.3, Main Feedwater Regulating Valves (Mfivs) and Main Feedwater Regulating Valve Bypass Valves (Mfrvbvs), and TS 3.3.2, ESFAS Instrumentation ML0914104732009-05-21021 May 2009 Acceptance Review Email, Revise Technical Specification (TS) 3.7.2, Main Steam Isolation Valves (Msivs), and TS 3.3.2, ESFAS Instrumentation, and Add New TS 3.7.19, Secondary System Isolation Valves (Ssivs) ML0909701582009-04-0707 April 2009 Acceptance Review Email, Modify Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for One-time Extension of Integrated Leak Rate Test Interval ML0907504882009-03-16016 March 2009 Acceptance Review E-mail, License Amendment Request, Revise TS 3.8.4, DC Sources - Operating, & TS 3.8.5, DC Sources - Shutdown, to Revise Battery Connection Resistance Limits Surveillance Requirements-TAC ME0292 2024-01-19
[Table view] Category:Letter
MONTHYEARULNRC-06890, 10 CFR 50.55a(z)(1) Requests for Relief from Inservice Inspection Requirements of ASME Boiler Pressure Vessel Code, Section XI2024-12-19019 December 2024 10 CFR 50.55a(z)(1) Requests for Relief from Inservice Inspection Requirements of ASME Boiler Pressure Vessel Code, Section XI ML24354A1892024-12-19019 December 2024 NPDES Permit Renewal Application ML24353A2242024-12-18018 December 2024 Supplement to Status of ISFSI Decommissioning Funding Plan (ULNRC-O6798) ML24351A1382024-12-16016 December 2024 Inservice Testing Program and Snubber Program Plans for the Fifth Inservice Testing (IST) Interval IR 05000483/20240032024-10-23023 October 2024 Integrated Inspection Report 05000483/2024003 IR 05000483/20240132024-10-21021 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000483/2024013 IR 05000483/20244012024-10-0909 October 2024 Material Control and Accounting Program Inspection Report 05000483/2024401 Public ULNRC-06901, Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter)2024-10-0101 October 2024 Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter) ML24247A3042024-09-11011 September 2024 Regulatory Audit Questions for License Renewal Commitments 34 and 35 (EPID L-2024-LRO-0009) - Non-Proprietary IR 05000483/20244032024-08-28028 August 2024 Security Baseline Inspection 05000483-2024-403 IR 05000483/20240052024-08-14014 August 2024 Updated Inspection Plan for Callaway Plant (Report 05000483/2024005) IR 05000483/20253012024-08-0505 August 2024 Notification of NRC Initial Operator Licensing Examination 05000483/2025301 ML24212A2822024-08-0202 August 2024 Regulatory Audit Summary Concerning Review of Request No. C3R-01 for Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections IR 05000483/20240022024-07-18018 July 2024 And Independent Spent Fuel Storage Installation Integrated Inspection Report 05000483/2024002 and 07201045/2024001 ML24185A1032024-07-16016 July 2024 2024 Biennial Problem Identification and Resolution Inspection Report ULNRC-06891, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00052024-06-26026 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0005 ULNRC-06892, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00062024-06-26026 June 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0006 ULNRC-06885, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00032024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0003 ULNRC-06884, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00022024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0002 ULNRC-06886, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00042024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0004 ML24144A0492024-06-11011 June 2024 Requests for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML24178A1132024-06-0606 June 2024 Ameren Missouris Intent to Adopt Revision 1 to Amendment 0 of Certificate of Compliance No. 1040 as Applicable to the ISFSI at the Callaway Plant Site ULNRC-06880, Application to Revise Technical Specifications to Adopt Tstf-569, Rev. 2, Revise Response Time Testing Definition (LDCN 24-0008)2024-06-0606 June 2024 Application to Revise Technical Specifications to Adopt Tstf-569, Rev. 2, Revise Response Time Testing Definition (LDCN 24-0008) ML24143A1632024-05-23023 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Storage Canister HGMPC0001 ML24137A2342024-05-16016 May 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Canister HGMPC0011 ULNRC-06882, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00122024-05-16016 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0012 ML24122A1502024-05-0707 May 2024 Audit Plan to Support Review of Steam Generator License Renewal Response to Commitment Nos 34 and 35 IR 05000483/20244022024-05-0606 May 2024 Security Baseline Inspection Report 05000483/2024402 (Full Report) ULNRC-06877, Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 252024-05-0606 May 2024 Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 25 ULNRC-06856, CFR 50.59 and 10 CFR 72.48 Summary Report2024-05-0101 May 2024 CFR 50.59 and 10 CFR 72.48 Summary Report IR 05000483/20240112024-05-0101 May 2024 NRC Post-Approval Site Inspection for License Renewal (Phase 2) Report 05000483/2024011 ULNRC-06869, Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report ML24122A1132024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radioactive Effluent Release Report ULNRC-06876, Registration of Dry Spent Fuel Storage Canister HGMPC00102024-04-25025 April 2024 Registration of Dry Spent Fuel Storage Canister HGMPC0010 ULNRC-06872, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00082024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0008 ULNRC-06871, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00072024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0007 ML24108A1082024-04-17017 April 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0009 ULNRC-06866, Submittal of Cycle 26 Commitment Change Summary Report2024-04-17017 April 2024 Submittal of Cycle 26 Commitment Change Summary Report IR 05000483/20240012024-04-16016 April 2024 Integrated Inspection Report 05000483/2024001 IR 05000483/20244042024-04-0909 April 2024 Cyber Security Inspection Report 05000483/2024404 ML24088A3212024-04-0101 April 2024 Notification of Commercial Grade Dedication Inspection (05000483/2024013) and Request for Information ML24086A5132024-03-26026 March 2024 CFR 50.46 Annual Report Regarding ECCS Evaluation Model Revisions ULNRC-06863, Submittal of Annual Exposure Report for 20232024-03-20020 March 2024 Submittal of Annual Exposure Report for 2023 ML24079A1622024-03-19019 March 2024 Re Nuclear Property Insurance Reporting ML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ULNRC-06852, Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 262024-03-0505 March 2024 Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 26 IR 05000483/20230062024-02-28028 February 2024 Annual Assessment Letter for Callaway Plant Report 05000483/2023006 ML24052A3662024-02-26026 February 2024 Regulatory Audit Plan in Support of Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections IR 05000483/20230022024-02-21021 February 2024 Amended Integrated Inspection Report 05000483/2023002 ULNRC-06858, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-02-21021 February 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation 2024-09-11
[Table view] |
Text
December 21, 2022 Mr. Fadi Diya Senior Vice President and Chief Nuclear Officer Ameren Missouri Callaway Energy Center 8315 County Road 459 Steedman, MO 65077
SUBJECT:
CALLAWAY PLANT, UNIT NO. 1 ACCEPTANCE OF REQUESTED LICENSING ACTIONS RE: APPLICATION FOR LICENSE AMENDMENT AND REGULATORY EXEMPTIONS FOR TECHNICAL SPECIFICATION CHANGE AND EXEMPTION REQUEST REGARDING USE OF FRAMATOME GAIA FUEL (EPID L-2022-LLA-0150 AND EPID L-2022-LLE-0030)
Dear Mr. Diya:
By letter dated October 12, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22285A115), supplemented by letter dated December 1, 2022 (ML22335A497), Union Electric Company, doing business as Ameren Missouri (the licensee),
pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 50.90, Application for amendment of license, construction permit, or early site permit, requested an amendment for the technical specification (TS) change and regulatory exemptions regarding use of Framatome GAIA fuel. The proposed amendment would revise the TS to allow use of Framatome GAIA fuel with M51 as a fuel cladding material. Since the Framatome GAIA fuel will use M5 fuel rod cladding, a 10 CFR 50.46 and 10 CFR Part 50, Appendix K exemption request is included as part of this licensing amendment request LAR.
By an email dated November 17, 2022 (ML22322A006), the U.S. Nuclear Regulatory Commission (NRC) staff provided the results of the acceptance review as Unacceptable with Opportunity to Supplement, and included the request for supplemental information. In order to make the license amendment and regulatory exemptions application complete, the NRC staff requested that the licensee supplement the application to address the information requested to enable the NRC staff to begin its detailed technical review. By letter dated December 1, 2022, the licensee submitted the requested supplemental information.
The purpose of this letter is to provide the results of the NRC staffs acceptance review of this amendment request and regulatory exemptions. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with 10 CFR 50.90, an application for an amendment to a license (including the TSs) must fully describe the changes requested, and following, as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
Consistent with 10 CFR 50.12, the Commission may, upon application by any interested person or upon its own initiative, grant exemptions from the requirements of the regulations of this part, which are authorized by law, will not present an undue risk to the public health and safety, and are consistent with the common defense, and security. The Commission will not consider granting an exemption unless special circumstances are present, as specified in 10 CFR, Section 50.12(a)(2).
The NRC staff has reviewed your application and the supplemental information and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
Based on the information provided in your submittal and discussions during the pre-licensing meeting on September 12, 2022 (meeting summary dated October 12, 2022 (ML22259A119)),
the NRC staff has estimated that this licensing request will take approximately 1,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for the license amendment request and 400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br /> for the exemptions to be completed. The NRC staff expects to complete this review in approximately 9 months, which is September 30, 2023.
These estimates are based on the NRC staffs initial review of the application, and they could change due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Any significant changes in the forecasted hours and/or the forecasted completion date, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
If you have any questions regarding this matter, please contact me at 301-415-8371 or via email at Mahesh.Chawla@nrc.gov.
Sincerely,
/RA/
Mahesh L. Chawla, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-483 cc: Listserv
ML22348A116
- by email OFFICE NRR/DORL/LPL4/PM NRR/DORL/LPL4/LA*
NRR/DRO/IQVB/BC NAME MChawla PBlechman (RButler for)
FVega for KKavanagh DATE 12/20/2022 12/20/2022 12/21/2022 OFFICE NRR/DSS/SFNB/BC*
NRR/DSS/SNSB/BC (A)*
NMSS/REFS/ELRB/(BC)*
NAME SKrepel DWoodyatt TSmith (JRikhoff for)
DATE 12/20/2022 12/20/2022 12/20/2022 OFFICE NRR/DORL/LPL4/BC*
NRR/DORL/LPL4/PM*
NAME JDixon-Herrity MChawla DATE 12/21/2022 12/21/2022