MONTHYEARIR 05000244/20244022024-12-20020 December 2024 R. E. Ginna Nuclear Power Plant - Cyber Security Inspection Report 05000244/2024402 (Cover Letter Only) RS-24-077, Application to Revise Technical Specifications for Clarification of a Frequency Example Using the Consolidated Line Item Improvement Process2024-12-0909 December 2024 Application to Revise Technical Specifications for Clarification of a Frequency Example Using the Consolidated Line Item Improvement Process IR 05000244/20244012024-11-20020 November 2024 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2024401 IR 05000244/20240032024-11-0808 November 2024 Integrated Inspection Report 05000244/2024003 ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000244/20243012024-10-22022 October 2024 Initial Operator Licensing Examination Report 05000244/2024301 ML24286A0022024-10-11011 October 2024 Core Operating Limits Report Cycle 45, Revision 0 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing RS-24-092, Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-09-25025 September 2024 Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000244/20245012024-09-24024 September 2024 LLC - Emergency Preparedness Biennial Exercise Inspection Report 05000244/2024501 IR 05000244/20240052024-08-29029 August 2024 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2024005) ML24234A0922024-08-21021 August 2024 Requalification Program Inspection IR 05000244/20240102024-08-19019 August 2024 Biennial Problem Identification and Resolution Inspection Report 05000244/2024010 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000244/20240022024-08-0505 August 2024 LLC - Integrated Inspection Report 05000244/2024002 and Independent Spent Fuel Storage Installation Report 07200067/2024001 ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24170A3852024-07-16016 July 2024 R. E. Ginna Nuclear Power Plant - Alternative Associated with Inservice Testing of B Auxiliary Feedwater Pump - PR-03 ML24197A0302024-07-15015 July 2024 LLC - Operator Licensing Examination Approval RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24143A0752024-05-22022 May 2024 Re. Ginna Nuclear Power Plant and Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License ISFSI Casks ML24136A1692024-05-14014 May 2024 And Independent Spent Fuel Storage Installation (ISFSI) - 2023 Annual Radioactive Effluent Release Report and 2023 Annual Radiological Environmental Operating Report ML24134A0042024-05-13013 May 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2024010 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests IR 05000244/20240012024-04-24024 April 2024 LLC - Integrated Inspection Report 05000244/2024001 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24101A0432024-04-10010 April 2024 2024 10 CFR 50.46 Annual Report IR 05000244/20240112024-04-10010 April 2024 LLC - Fire Protection Team Inspection Report 05000244/2024011 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24110A0122024-03-28028 March 2024 2023 Report of Individual Monitoring for R.E. Ginna Nuclear Power Plant LLC, License DPR-18 ML24088A2042024-03-28028 March 2024 R. E. Ginna Nuclear Power Plant - Response to NRC Request for Additional Information Regarding Relief Request Associated with Inservice Testing of ‘B’ Auxiliary Feedwater Pump 05000244/LER-2023-003-01, Re. Ginna Nuclear Power Plant, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam2024-03-0707 March 2024 Re. Ginna Nuclear Power Plant, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam IR 05000244/20230062024-02-28028 February 2024 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC, (Report 05000244/2023006) IR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of ‘B’ Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations 05000244/LER-2023-003, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam Generator Level2023-12-11011 December 2023 Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam Generator Level ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums 05000244/LER-2023-002, Overtemperature Delta Temperature Reactor Protection System and Auxiliary Feedwater System Actuations on Due to 100% Load Rejection Caused by Turbine Overspeed Circuit Card Failure2023-11-0808 November 2023 Overtemperature Delta Temperature Reactor Protection System and Auxiliary Feedwater System Actuations on Due to 100% Load Rejection Caused by Turbine Overspeed Circuit Card Failure. IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans 2024-09-25
[Table view] |
Text
200 Exelon Way Kennett Square, PA 19348 www.constellation.com 10 CFR 50.55a April 11, 2022 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 R. E. Ginna Nuclear Power Plant Renewed Facility Operating License Nos. DPR-18 NRC Docket No. 50-244
Subject:
Relief Request Associated with Inservice Testing of Refueling Water Storage Tank Outlet Valve In accordance with 10 CFR 50.55a, Codes and standards, paragraph (z)(2), Constellation Energy Generation, LLC (CEG) requests NRC approval of a proposed relief request associated with the Inservice Testing (IST) Program for the R. E. Ginna Nuclear Power Plant.
This request is associated with the testing of the Refueling Water Storage Tank Outlet Valve (896B).
CEG requests your approval of this request by April 11, 2023.
There are no regulatory commitments contained in this letter.
If you have any questions, please contact Tom Loomis at 610-765-5510.
Respectfully, David T. Gudger Sr. Manager - Licensing and Regulatory Affairs Constellation Energy Generation, LLC
Attachment:
Relief Request VR Inservice Testing of Refueling Water Storage Tank Outlet Valve cc:
Regional Administrator - NRC Region I NRC Senior Resident Inspector - Ginna NRC Project Manager - Ginna
ATTACHMENT Relief Request VR Inservice Testing of Refueling Water Storage Tank Outlet Valve
10 CFR 50.55a Relief Request: VR-03 Revision 0 (Page 1 of 3)
Request for Relief VR-03 Inservice Testing of Refueling Water Storage Tank Outlet Valve In Accordance with 10 CFR 50.55a(z)(2)
- 1. ASME Code Component(s) Affected Component ID Description Code Class Category 896B Refueling Water Storage Tank Outlet to Containment Spray and Safety Injection Pumps (See Figure A) 2 A
The Refueling Water Storage Tank Outlet Valve (Figure A) provides a suction supply flow path to the Containment Spray and Safety Injection pumps when open for the injection phase and isolates the Refueling Water Storage Tank during Safety Injection in the recirculation phase. When the Refueling Water Storage Tank inventory reaches a low level during the injection phase, the pumps suction is realigned from the Refueling Water Storage Tank to the containment sump via the Residual Heat Removal system for recirculation.
When this transition occurs 896A and 896B are closed, isolating the Refueling Water Storage Tank and preventing the release of radioactivity to the atmosphere via the Refueling Water Storage Tank atmospheric vent.
- 2. Applicable Code Edition and Addenda American Society of Mechanical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants (OM Code) 2012 Edition with no Addenda.
3. Applicable Code Requirement
ISTC-3630, Leakage Rate for Other Than Containment Isolation Valves, ISTC-3630(b) states, in part, Valve seat tests shall be made with the pressure differential in the same direction as when the valve is performing its function.
4. Reason for Request
Pursuant to 10 CFR 50.55a, Codes and standards, paragraph (z)(2), an alternative to the requirement of ASME OM Code ISTC-3630(b) is proposed. The basis of the request is that compliance with the specified requirements results in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
When aligning leak testing in the accident direction 11 boundary valves must be used as a pressure barrier. Cumulative leakage from each of the 11 boundary valves can contribute to a false high leakage rate of 896B that must be investigated and resolved. This involves increased time to perform the testing and unnecessary radiation exposure to test personnel and results in a hardship without a compensating increase in the level of quality and safety.
10 CFR 50.55a Relief Request: VR-03 Revision 0 (Page 2 of 3)
5. Proposed Alternative and Basis for Use
896B is an Active Motor Operated 10-inch Split Wedge Gate Valve. As such, this valve is included in Mandatory Appendix III and has been previously evaluated and tested in the GL 89-10/96-05 MOV program. The motor operated valve closes against minimal differential pressure and is required to be leak tight against a differential pressure of 158 psid. The gate valve design inherently has two sealing surfaces (upstream and downstream disc faces) with both designed to provide shutoff; however, only one face needs to seal to provide leakage integrity. When closed, the motor operator provides sufficient seating thrust with margin to wedge the disc into the seat and prevent the system pressure from unseating the valve. Based on the gate valve design and adequate seating force, leakage will be the same across the disc when pressurized in either direction; therefore, leak testing this valve in the reverse direction at the required differential test pressure is an acceptable alternative and will provide equivalent results in the same direction as when the valve is performing its function. This alternative to the Code-required testing direction of the Refueling Water Storage Tank Outlet Valve (896B) is proposed pursuant to 10 CFR 50.55a(z)(2).
896B has passed its IST leakage, position indication, stroke open/close, and diagnostic testing since 2008. A search of the corrective action database, covering the last 20 years resulted in no events where 896B malfunctioned or failed to perform any of its required active open/close functions.
6. Duration of Proposed Alternative
This request, upon approval, will be applied to the R. E. Ginna Nuclear Power Plant sixth 10-year IST interval, which began on January 1, 2020, and is scheduled to end on December 31, 2029.
- 7. Precedent Letter from D. Wrona (U.S. Nuclear Regulatory Commission) to J. Gebbie (Indiana Michigan Power Company), Donald C. Cook Nuclear Plant, Units 1 and 2 - Relief Request REL-002 Associated with Valve Seat Leakage Testing (CAC Nos. MF6546 AND MF6547), dated March 4, 2016 (ML16054A572)
- 8. References None
10 CFR 50.55a Relief Request: VR-03 Revision 0 (Page 3 of 3)
Figure A Refueling Water Storage Tank Outlet Valve Diagram (896B)