MONTHYEARML21084A8002021-03-25025 March 2021 Decommissioning Funding Status Report, Financial, Test and Independent Public Accountants Letter of Attestation Project stage: Request ML21131A1412021-05-10010 May 2021 Application for Order Approving Transfer of Control of KPS License and Conforming License Amendments Project stage: Request ML21145A0832021-05-13013 May 2021 Notification of Amended Post-Shutdown Decommissioning Activities Report (Revision 2) for Kewaunee Power Station Project stage: Request ML21148A0892021-06-0606 June 2021 Acknowledgement of Application for Order Approving Transfer of Control of Kewaunee Power Station License and Conforming License Amendments Project stage: Other ML21148A0742021-06-0606 June 2021 Energy Solutions Proposed Post Shutdown Decommissioning Activities Report with Financial and Planning Information Project stage: Other ML21168A3392021-06-17017 June 2021 Virgil C. Summer Nuclear Station, North Anna Power Station, Surry Power Station -Submission of Revision 30 of the Quality Assurance Topical Report Project stage: Request ML21218A1412021-08-10010 August 2021 Acceptance Review of Dominion Energy Kewaunee, Inc. - Kewaunee Ps Approval for Order Approving Transfer of Control of Kewaunee Ps License and Conforming License Amendments Project stage: Acceptance Review ML21277A2462021-09-29029 September 2021 Resubmittal of Solutions Decommissioning Quality Assurance Program (Dqap), Revision 0 Project stage: Request ML21257A0692021-09-30030 September 2021 Enclosure - Request for Additional Information - Application for Order Approving Transfer of Control of Kewaunee Power Station License and Conforming License Amendment Project stage: RAI ML21257A0622021-09-30030 September 2021 Approval for Order Approving Transfer of Control of Kewaunee Power Station License and Conforming License Amendments Project stage: Request ML21257A0682021-09-30030 September 2021 Request for Additional Information Regarding Application for Order Approving Transfer of Control of Kewaunee Power Station License and Conforming License Amendments Project stage: RAI ML21257A3492021-10-0505 October 2021 FRN - Kewaunee Power Station Approval for Order Approving Transfer of Control of Kewaunee Power Station License and Conforming License Amendments Project stage: Other ML21301A1782021-10-28028 October 2021 Response to Request for Additional Information Regarding Application for Order Approving Transfer of Control of Kewaunee Power Station License and Conforming License Project stage: Response to RAI ML21348A0522021-12-0303 December 2021 E-mail to P. Schmidt, State of Wisconsin, from K. Sturzebecher, NRC - Notification and Request Kewaunee Power Station License Transfer Project stage: Other ML22007A3182022-01-0707 January 2022 E-mail from C. Adams, State of Wisconsin, to K. Sturzebecher, NRC, Notification and Request Kewaunee Power Station License Transfer (L-2021-LLO-002) Project stage: Other ML22047A0572022-02-16016 February 2022 Supplement to License Transfer Application Related to Decommissioning Quality Assurance Program Project stage: Supplement ML22053A2992022-02-18018 February 2022 Email - Additional Time for Request for Additional Information Response Regarding Kewaunee Solutions Decommissioning Quality Assurance Program; NRC Response Included; (EPID L-2021-LLO-0002 and L-2021-DP3-0000) Project stage: RAI ML22060A1912022-02-25025 February 2022 Response to Request for Additional Information Related to Submittal for Approval of the Kewaunee Solutions Decommissioning Quality Assurance Program (Dqap), Revision O for Kewaunee Power Station (KPS) Project stage: Response to RAI ML22076A0652022-03-15015 March 2022 Energy Solutions and Dominion Energy Kewaunee - Supplement to License Transfer Application Related to Use of Existing Dominion Energy Quality Assurance Program Project stage: Supplement ML22014A3942022-03-31031 March 2022 Enclosure 3 - Kewaunee Power Station Safety Evaluation Report Project stage: Approval ML22014A3872022-03-31031 March 2022 Order Approving Transfer of the License for the Kewaunee Power Station License and Conforming Future License Amendment Project stage: Request ML22014A3932022-03-31031 March 2022 Enclosure 2 - Draft Confirming Amendment to Kewaunee Power Station Renewed Facility Operating License DPR-43 Project stage: Draft Other ML22014A3922022-03-31031 March 2022 Enclosure 1 - Order Approving Indirect Transfer of the License for the Kewaunee Power Station License and Approving Conforming Amendment Project stage: Other ML22166A3392022-06-13013 June 2022 Notification of Nuclear Insurance Project stage: Request ML22172A2332022-06-21021 June 2022 Notification of Transaction Closing Date Project stage: Request ML22172A2452022-06-22022 June 2022 Notification of Planned Closing Date and Required Regulatory Approvals for the Kewaunee License Transfer Transaction Project stage: Request ML22160A5282022-06-28028 June 2022 Enclosure 2 - Amendment No. 11 to Indemnity Agreement B-53 Project stage: Other ML22160A5162022-06-28028 June 2022 Issuance of Conforming License Amendment Regarding Indirect Transfer of License from Dominion Energy Kewaunee, Inc. to Kewaunee Solutions, Inc. Project stage: Request ML22160A5272022-06-28028 June 2022 Enclosure 1 - Amendment No. 221 to Renewed Facility Operating License No. DPR-43 Project stage: Other ML22160A5262022-06-28028 June 2022 Letter - KPS - Issuance of Conforming License Amendment Regarding Indirect Transfer of License from DEK, Inc. to Kewaunee Solutions, Inc Project stage: Approval 2021-09-30
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Craig D. Sly Manager - Nuclear Fleet Licensing Nuclear Regulatory Affairs Dominion Energy Services, Inc.
5000 Dominion Blvd Glen Allen, VA 23060
SUBJECT:
DOMINION ENERGY KEWAUNEE, INC. - KEWAUNEE POWER STATION ACKNOWLEDGEMENT OF APPLICATION FOR ORDER APPROVING TRANSFER OF CONTROL OF KEWAUNEE POWER STATION LICENSE AND CONFORMING LICENSE AMMENDMENTS (EPID L-2021-LLO-0002)
Dear Mr. Sly:
This letter is to acknowledge the receipt of your letter docketed on May 10, 2021 (Agencywide Documents Access and Management System [ADAMS] Accession Number ML21131A141),
providing the U.S. Nuclear Regulatory Commission (NRC) an application to transfer control of Kewaunee Power Station (KPS) license and conforming license amendments. As part of the acceptance review of your submittal, the NRC will provide a preliminary review, hours, and anticipated completion date based upon our current review schedules. Your request has been assigned Enterprise Project Identifier (EPID) L-2019-LLA-0002. Please reference this number in any future correspondence associated with this request.
The NRC staff will evaluate your submittal and determine if the KPS application contains sufficient information to allow the staff to begin the detailed review. If the application does not contain sufficient information for the staff, then a Request for Supplemental Information (RSI) will be issued and the staff will provide Dominion an opportunity to discuss the RSI and to clarify a final resolution.
In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
June 6, 2021
C. Sly 2
If you have any questions regarding this matter, please contact me or Mr. Karl Sturzebecher by telephone at 301-415-8534, or via email to Karl.Sturzebecher@nrc.gov.
Sincerely, Bruce Watson, Chief Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery, and Waste Programs Office of Nuclear Material Safety and Safeguards Docket No. 50-305, 72-64 License No. DPR-43 cc:
Via Listserv Daniel G. Stoddard President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc.
5000 Dominion Blvd Glen Allen, VA 23060 daniel.g.stoddard@dominionenergy.com William S. Blair General Counsel Dominion Energy Kewaunee, Inc.
120 Tredegar St.
Richmond, VA 23219 william.s.blair@dominionenergy.com Paul M. Bessette Morgan, Lewis & Bockius LLP 1111 Pennsylvania Avenue, NW Washington, DC 20004-2541 paul.bessette@morganlewis.com Kenneth W. Robuck President and Chief Executive Officer EnergySolutions, LLC 121 West Trade Street, Suite 2700 Charlotte, North Carolina 28202 kwrobuck@energysolutions.com Signed by Watson, Bruce on 06/06/21
C. Sly 3
Russell G. Workman General Counsel Secretary EnergySolutions, LLC 299 South Main Street, Suite 1700 Salt Lake City, UT 84111 rgworkman@energysolutions.com Daniel F. Stenger Hogan Lovells US LLP 555 13th St NW Washington, D.C. 20004 daniel.stenger@hoganlovells.com Gerard P. Van Noordennen Senior Vice President Regulator Affairs EnergySolutions, LLC 121 West Trade Street Charlotte, North Carolina 28202 gpvannoordennen@energysolutions.com