Staff Requirements Memo Re 890206 Briefing in Rockville,Md Re Status of Plant.Licensee Requested to Discuss Restart Plan & Mgt Challenges for 1989 at Future Briefing
ML20235J112
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 02/16/1989
From: Chilk S
NRC OFFICE OF THE SECRETARY (SECY)
To: Stello V
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
References
REF-10CFR9.7 M890206, NUDOCS 8902240178
Download: ML20235J112 (2)


Text

-_--__x-- -_ - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ~

w f- *~ p

}jea arouq'o$ .

.]*

UNITED STATES NUCLEAR REGULATORY COMMISSION IN RESPONSE, PLEASE:

REFER TO: M890206

{' ,

WASHINGTON, D.C. 20555 9.

.o f

February 16, 1989 OFFICE OF THE SECRETARY MEMORANDUM FOR: Victor Stello, Jr.

Executive Director for Op ations FROM: Samuel J. Chilk, Secretag

SUBJECT:

k STAFF REQUIREMENTS - BRIbF 3 ON STATUS OF-PEACH BOTTOM, 2:00 P.M., MONDAY, FEBRUARY 6, 1989, COMMISSIONERS' CONFERENCE ROO.M, ONE WHITE FLINT NORTH, ROCKVILLE, MARYLAND (OPEN TO PUBLIC ATTENDANCE)

The Commission was briefed by representatives _of the Philadelphia Electric Company on the status of the Peach Bottom Atomic Power Station.

Representing Philadelphia Electric Company were:

- Joseph F. Paquette, Jr.

Chairman and CEO

- Corbin A. McNeill,_Jr.

Executive Vice President - Nuclear

- Dickinson M. Smith Vice President - Peach Bottom

- John F. Franz Plant Manager - Peach Bottom The conmission requested a future briefing by both the licensee (Philadelphia Electric Company (PEco)) and the staff on the readiness to restart Peach Bottom. At that briefing, the licensee is requested to discuss:

a. PECo's restart plan for Peach Bottom (e.g., test program, self-evaluations, special training, etc.), and
b. Management challenges for 1989 (e.g., restart of Peach Bottom, Units 2 and 3, as well as reload and restart of Limerick, Units 1 and 2).

8902'240178 890216 p '

PDR 10CFR PT9.7 PDC'

. d.

! 1

_.2 -

At that briefing, the staff should discuss: J

a. The results of its Integrated Assessment Team Tnspection;-
b. Any outstanding restart items that remain to be completed;
c. The ACRS views concerning readiness for Peach Bottom'to -)

restart; and

d. The staff's recommendations concerning readiness for Peach Bottom to restart. l (EDO) (SECY Suspense: 4/89) cc: Chairman Zech Commissioner. Roberts Commissioner Carr Commissioner Rogers Commissioner Curtiss OGC GPA PDR - Advance DCS - P1-124 l.