j0$

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND ~ LICENS1NGilAPPEAL BOARD USNkC Administrative Judges:

Alan S. Rosenthal, Chairagh JL -3 P3 :33 July 3, 1986 Dr. W. Reed Johnson Thomas S. Moore FFICE CF LLudAkY dhhC M Mb

)

In the Matter of )

)

TEXAS UTILITIES ELECTRIC ) Docket No. 50-445-CPA COMPANY, ET AL. )

)

(Comanche Peak Steam Electric )

Station, Unit 1) )

)

' I ORDER The motion of Consolidated Intervenors (Citizens Association for Sound Energy and Meddie Gregory) for clarification and reconsideration of portions of our July 2, 1986 order is granted in part and denied in part. By way of clarification, pending the receipt of the Commission's i

response to the question posed in that order the applicants need not act upon any discovery request to which answers are due subsequent to today (July 3) -- irrespective of when the particular request may have been made. We see no cause, however, to reconsider that result. Suffice it to say that l

there appears to be no good reason why the applicants should be burdened with extensive discovery so long as a serious question remains whether the entire proceeding should be h fh G