MONTHYEARML20064N6341994-03-21021 March 1994 Affidavit of RW Schrauder in Support of Licensee Cross Motion for Summary Disposition & Answer to Ohio Citizens for Responsible Energy,Inc & SL Hiatt Motion for Summary Disposition.W/Certificate of Svc ML20064N9201994-03-21021 March 1994 Affidavit of RW Schrauder in Support of Licensee Cross Motion for Summary Disposition & Answer to Ohio Citizens for Responsible Energy,Inc & SL Hiatt Motion for Summary Disposition. W/Svc List ML20082P1681991-08-21021 August 1991 Affidavit of SL Hiatt Re Ocre Petition for Leave to Intervene.W/Certificate of Svc ML20065R8331990-09-26026 September 1990 Affidavit Requesting Withholding of 23A6492AA,Rev 0,Suppl 1, Supplemental Reload Licensing Submittal for Perry Nuclear Power Plant Unit 1,Reload 2,Cycle 3, Per 10CFR2.790 ML20059G1351990-07-23023 July 1990 Affidavit of Jd Pace Re DOJ 900613 Advice Ltr Re Util Petition for Amend to Plant License.Affiant Finds DOJ Advice Ltr Devoid of Economic Reasoning.Prof Background Statement Encl ML20055F5841990-06-29029 June 1990 Affidavit of D Fieno.* Advises That Generic Ltr 88-16 Does Not Affect Limitations Upon Reactor Core Operation Deemed Necessary to Obviate Possibility of Abnormal Situation to Public Health & Safety.W/Certificate of Svc ML20012E6831990-03-0808 March 1990 Affidavit of SL Hiatt.* Author Believes That OL Amend Requested by Util to Remove from Plant Tech Specs,cycle- Specific Fuel Info & Core Operating Limits Violates Right to Meaningful Participation in Changes to Plant Operations ML20154B9671988-08-31031 August 1988 Third Affidavit of DD Hulbert.* Discusses Issues Raised by Concerned Citizens Ltrs Re Emergency Planning.W/Certificate of Svc ML20148D0601988-01-0707 January 1988 Affidavit of SL Hiatt.* W/Certificate of Svc ML20207Q3341987-01-20020 January 1987 Affidavit of DD Hulbert in Opposition to Sunflower 2.206 Petition.* Affidavit of DD Hulbert Re Emergency Planning at Facility.Emergency Planning Meets or Exceeds All Applicable Regulations & Adequate to Protect Public Health & Safety ML20212P9351986-09-0202 September 1986 Affidavit of MR Edelman Re Ocre 860829 Motion for Continuance of Commission 860905 Meeting & That Full Power OL Not Be Issued ML20213E7571986-08-20020 August 1986 Affidavit of Tm Burling Re Survey Conducted in Geauga County,Oh Radiological Emergency Response Plan ML20198K2861986-05-18018 May 1986 Affidavit of Ta Ross Re Western Reserve Alliance 860204 2.206 Petition.Contents of Exhibit a Too Vague & General to Provide Sufficient Info for Util Investigation ML20154G5421986-03-0505 March 1986 Affidavit of P Sobel & L Reiter Re Assertions Concerning 860131 Earthquake in Northeast Ohio Noted in Ocre 860203 Motion to Reopen.No Significant Safety Issue Raised by Motion for Listed Reasons ML20154G5531986-03-0505 March 1986 Affidavit of Jh Lee Re Assertions Concerning Seismic Design of Plant Contained in Ocre 860203 Motion to Reopen. Earthquake Does Not Raise Significant Safety Question Concerning Operation of Plant or safety-related Equipment ML20153G7191986-02-24024 February 1986 Affidavit of RA Stratman Re Results of Extensive Plant Walkdowns & Insp Performed by Plant Personnel in Response to 860131 Earthquake.Supporting Documentation Encl ML20153G7901986-02-24024 February 1986 Affidavit of C Chen Re Background Info on Seismic Design of Nuclear Power Plants & Development of Seismic Design for Facilities.Supporting Documentation Encl ML20153G7801986-02-24024 February 1986 Affidavit of Kl Benuska Re Results of Analog Magnetic Tape Cassette Records from 860131 Earthquake.Supporting Documentation Encl ML20153G7391986-02-21021 February 1986 Affidavit of Rj Holt Re Results of Geological & Seismological Investigations of 860131 Earthquake.Supporting Documentation Encl ML20214C9991986-02-18018 February 1986 Affidavit of Ta Boss Re Dl Schlemmer 860204 2.206 Petition Requesting Plant Closure Due to Inadequate Seismic Design & Idcvp to Assess Integrity of Site QA Programs.Related Info Encl ML20153G7701986-02-13013 February 1986 Affidavit of PD Engdahl Re Results of Evaluation of Data from Seismic Instruments in Plant Recording Response Spectra & Peak Accelerations Associated w/860131 Earthquake. Supporting Documentation Encl ML20153G8051986-02-13013 February 1986 Affidavit of Jd Stevenson Re Results of Walkdown & Seismic Analysis of Data from 860131 Earthquake.Supporting Documentation Encl ML20198H9191986-01-28028 January 1986 Affidavit of a Notafrancesco Responding to Questions in Aslab 860103 Memorandum & Order Re Hydrogen Control Rule. Certificate of Svc Encl ML20136J4891986-01-0808 January 1986 Affidavit of EC Christiansen Re Main Bearing Failure on Tdi Standby Diesel Generator.Svc List Encl.Related Correspondence ML20141F7951986-01-0303 January 1986 Affidavit of G Thomas Re Ocre Contention That Plant Permitted to Operate W/Single Coolant Sys Recirculation Loop.Holtzclaws Affidavit Refers to Limiting Condition & Does Not Signify Approval ML20151P1951985-12-30030 December 1985 Affidavit of Kw Holtzclaw Re Five Proposed Contentions Covering Single Loop Operation of Recirculation Sys Contained in 851212 Motion to Reopen Record.Statement of Prof Qualifications & Certificate of Svc Encl ML20136F3801985-12-24024 December 1985 Joint Affidavit of Le Phillips & G Thomas Re Single Loop Operation Contentions Raised by Ocre.Supporting Documentation & Certificate of Svc Encl ML20138B4631985-10-10010 October 1985 Affidavit of Gr Leidich in Response to Ocre Motion for Stay Pendente Lite Re No Costs of Downtime ML20138B4701985-10-0909 October 1985 Affidavit of MR Edelman Summarizing Util Best Estimates for Achieving Full Power Operation of Unit 1 & Costs of Delay. Certificate of Svc Encl ML20138B4361985-10-0909 October 1985 Affidavit of Ld Hamilton Re Assertion by Intervenor That Normal Operation of Facility Will Cause Irreparable Injury to Ocre Due to Exposure to Routine Radioactive Emissions ML20138B4491985-10-0707 October 1985 Affidavit of DA Hankins Re Risk to Public Health & Safety of Operation of Unit 1 Before & After Full Operation ML20135H8541985-09-19019 September 1985 Affidavit of SL Hiatt Re Location of Facility,Including Distance from Residence,Comsuption of Food Grown in Vicinity of Facility,Use of Lake Erie Water & History of Cancer in Family.Certificate of Svc Encl ML20135H8501985-09-0505 September 1985 Affidavit of Cj Johnson Re Health Consequences of Exposure of Cancer Susceptible Persons to Radioactive Effluents to Be Routinely Emitted by Facility ML20132D7411985-09-0505 September 1985 Affidavit of Cj Johnson Re Health Consequences of Exposure of cancer-prone Persons to Radioactive Emissions from Site ML20129K1451985-07-19019 July 1985 Affidavit of WR Kanda Re 850505 Fire in Reactor Bldg & Actions Taken by Applicants ML20129K1511985-07-18018 July 1985 Affidavit of EC Christiansen Re Placement,Operation & Safety Parameters of Check Valves Used in Lube Oil Generators ML20128F1051985-05-23023 May 1985 Affidavit of MR Edelman in Response to Ohio Citizens for Responsible Energy Petition for Emergency Action.Union Agreements Converted from Const to maint-type Contracts Due to Completion of Const Work,Not Financial Problems ML20128F1211985-05-22022 May 1985 Affidavit of Eh Maugans Re Util Financial info.Co-owners Should Be Readily Able to Raise Addl Funds Required to Complete Unit 1 Const Due to Amount of Cash Required for Completion & Size of Companies Const Budget ML20117E9741985-05-0909 May 1985 Affidavit of EC Christiansen Re NRC Weekly Info Rept for Wk Ending 850322 Concerning Tdi Diesel Generators.Certificate of Svc Encl ML20107G4241985-02-23023 February 1985 Statement of PM Schmidt in Support of Contention That Radiological Emergency Plan Inadequate.Plan I Both Unofficial & Incomplete ML20107G3591985-02-23023 February 1985 Affidavit of RR Louth in Support of Contention B. Weather-related Driving Conditions Nullify Proposed Emergency Evacuation Plan ML20107G3501985-02-21021 February 1985 Affidavit of M Boyd on Contention B.No Motion Brought Before Mentor City Council Re Availability of City Road Equipment to Augment Resources of Any Dept within Util Emergency Planning Zone ML20107G5161985-02-20020 February 1985 Affidavit of Rl Mctrusty Responding to Linneman 850205 Affidavit.Util Cavalier Dismissal of Radiation Hazards Reveals Incompetency.Certificate of Svc Encl ML20102C2521985-02-18018 February 1985 Affidavit of B Niznik Re Sunflower Alliance Contention Q Re Proposed Use of School Buses for Evacuation Purposes During Radiological Emergency.Training Offered to School Bus Drivers Concerning Evacuation Procedures Inadequate ML20107G3531985-02-18018 February 1985 Affidavit of Wa Brotzman on Contention B.Winter Storms Would Make Evacuation Impossible in Event of Nuclear Disaster ML20102A8181985-02-0707 February 1985 Affidavit of G Winters Supporting Motion for Summary Disposition of Contention B Re Potential Evacuation Route Impediments ML20106A0801985-02-0505 February 1985 Affidavit of Re Linnemann,Supporting Applicant Motion for Summary Disposition on Contention P.Procedures Adequate to Handle Medical Consequences of Accident at Plant.Certificate of Svc Encl ML20102A8361985-02-0505 February 1985 Affidavit of G Winters Re Contention Q.Prof Qualifications Encl ML20106E1811985-02-0404 February 1985 Affidavit of G Winters on Contention B Re Consideration of Potential Evacuation Route Impediments in Offsite Plans for Plume Exposure Pathway Emergency Planning Zone.Offsite Emergency Plans for Evacuation Impediments Adequate ML20106E3401985-02-0404 February 1985 Affidavit of G Winters on Contention Q Re Evacuation of Schools within Emergency Planning Zone in Single Trip.Ample Resources (School Buses & Drivers) Available to Evacuate Schools within Emergency Planning Zone in Single Trip 1994-03-21
[Table view] Category:LEGAL TRANSCRIPTS & ORDERS & PLEADINGS
MONTHYEARML20212J1581999-09-30030 September 1999 Order Approving Transfer of License & Conforming Agreement. Orders That License Transfer Approved,Subj to Listed Conditions ML20205D4901999-02-22022 February 1999 Transcript of 990222 Informal Public Hearing on 10CFR2.206 Petition in Rockville,Md.Pp 1-105.Supporting Documentation Encl ML20198D9711998-11-0909 November 1998 Petition Per 10CFR2.206 Requesting That Facility Be Immediately Shut Down & OL Be Suspended or Modified Until Such Time That Facility Design & Licensing Bases Properly Updated to Permit Operation with Failed Fuel Assemblies ML20155F4561998-08-26026 August 1998 Demand for Info Re False Info Allegedly Provided by Wh Clark to Two NRC Licensees.Nrc Considering Whether Individual Should Be Prohibited from Working in NRC-licensed Activities for Period of 5 Yrs ML20236V5261998-07-20020 July 1998 Computer Access & Operating Agreement Between Cleveland Electric Illuminating Co & NRC PY-CEI-NRR-2284, Comment Opposing Proposed Generic Communication, Lab Testing of Nuclear-Grade Activated Charcoal1998-05-21021 May 1998 Comment Opposing Proposed Generic Communication, Lab Testing of Nuclear-Grade Activated Charcoal ML20216B5111998-04-0909 April 1998 Order Imposing Civil Monetary Penalty.Denies Request for Remission of Violation C,Ea 97-430 & Orders Licensee to Pay Civil Penalty in Amount of $50,000 within Next 30 Days PY-CEI-NRR-2269, Comment on Proposed Rule 10CFR50.NRC Should Demonstrate That Not Only Is Code Process Flawed,But That Proposed Change Justified from Cost Versus Safety Protective1998-04-0303 April 1998 Comment on Proposed Rule 10CFR50.NRC Should Demonstrate That Not Only Is Code Process Flawed,But That Proposed Change Justified from Cost Versus Safety Protective ML20216G3821998-03-11011 March 1998 Order Approving Application Re Merger Agreement Between Duquesne Light Co & Allegheny Power Systems,Inc ML20217J0661998-03-11011 March 1998 Order Approving Application Re Merger Agreement Between Dqe, Inc & Allegheny Power System,Inc ML20198P9311997-11-0707 November 1997 Comments of American Municipal Power-Ohio,Inc.NRC Should Require Allegheny Power Sys,Inc to Affirm That Capco Antitrust License Conditions Will Be Followed ML20134L3401997-01-22022 January 1997 Resolution 96-R-85, Resolution Supporting Merger of Centerior Energy Corp & Ohio Edison Under New Holding Co Called Firstenergy ML20133B6941996-12-18018 December 1996 Submits Ordinance 850-96 Re Approval of Merger of Centerior & Oh Edison Into Firstenergy ML20135F4731996-12-0606 December 1996 Memorandum & Order CLI-96-13.* Commission Reverses & Vacates ASLB LBP-95-17 Which Granted Motion for Summary Disposition Submitted by Ocre & Hiatt.W/Certificate of Svc.Served on 961206 ML20132A8461996-12-0202 December 1996 Resolution 20-1996 Supporting Merger of Ohio Edison & Centerior Corp Under New Holding Company Called Firstenergy ML20134M6191996-10-28028 October 1996 Proclamation of Support by City of Sandusky,Oh Re Merger of Ohio Edison and Centerior Energy Corp ML20112J8281996-06-18018 June 1996 Licensee Reply Brief on Review of Licensing Board Decision LBP-95-17.* W/Certificate of Svc ML20112D8721996-05-29029 May 1996 Intervenor Brief in Support of Commission Affirmation of LBP-95-17.* Commission Should Affirm Licensing Board Decision.W/Certificate of Svc ML20108D9571996-05-0303 May 1996 CEI Response to City of Cleveland 2.206 Petition.Nrc Should Deny Petition ML20108B7571996-04-26026 April 1996 Licensee Brief on Review of Licensing Board Decision LBP-95-17.* Recommends That Commission Reverse Board Memorandum & Order Issued 951004.W/Certificate of Svc & Svc List PY-CEI-NRR-2034, Comment Opposing Proposed Rule 10CFR20 Re Reporting Requirements for Unauthorized Use of Licensed Radioactive Matl1996-03-11011 March 1996 Comment Opposing Proposed Rule 10CFR20 Re Reporting Requirements for Unauthorized Use of Licensed Radioactive Matl ML20101B5841996-01-23023 January 1996 Motion of City of Cleveland,Oh for Partial Summary Judgement Or,In Alternative,For Severance of Issue & Expedited Hearing Procedures.W/Certificate of Svc ML20097B8721996-01-23023 January 1996 Petition of City of Cleveland,Oh for Expedited Issuance of Nov,Enforcement of License Conditions & Imposition of Appropriate Fines,Per 10CFR2.201,2.202,2.205 & 2.206 ML20097B8911996-01-23023 January 1996 Motion of City of Cleveland,Oh for Partial Summary Judgement or in Alternative,For Severance of Issue & Expedited Hearing Procedures ML20096E2471996-01-0303 January 1996 Comment on PRM 50-64 Re Stockpiling Ki for Use as Thyroid Protectant in Event of Nuclear Accident.Supports Distribution of Ki to Public ML20094N1951995-11-17017 November 1995 Oh Edison Application for License Transfer in Connection W/ Sale & Related Transactions ML20094M5941995-11-15015 November 1995 Intervenors Answer to Licensees Petition for Review.* Intervenor Conclude That Commission Should Not Review Board Decision.W/Certificate of Svc ML20094J9141995-11-0707 November 1995 Petition for Review.* Submits That Commission Review of Board Decision Appropriate Under 10CFR2.786. W/Certificate of Svc & Svc List ML20093N9491995-10-23023 October 1995 Licensee Request for Extension of Time to File Petition for Review.* Requests That Commission Grant Extension Until 951107 of Deadline for Filing Petition for Review. W/Certificate of Svc ML20065L3571994-04-0505 April 1994 Intervenors Answer to NRC Staff Response to Intervenors Motion for Summary Disposition & Licensees Cross Motion for Summary Disposition.* Urges Board to Deny Licensee Cross Motion.W/Certificate of Svc ML20064N6341994-03-21021 March 1994 Affidavit of RW Schrauder in Support of Licensee Cross Motion for Summary Disposition & Answer to Ohio Citizens for Responsible Energy,Inc & SL Hiatt Motion for Summary Disposition.W/Certificate of Svc ML20064N6081994-03-21021 March 1994 Licensee Cross Motion for Summary Disposition & Answer to Ohio Citizens for Responsible Energy,Inc & SL Hiatt Motion for Summary Disposition.* Moves for Decision in Licensee Favor on Ocre Contention ML20064N9201994-03-21021 March 1994 Affidavit of RW Schrauder in Support of Licensee Cross Motion for Summary Disposition & Answer to Ohio Citizens for Responsible Energy,Inc & SL Hiatt Motion for Summary Disposition. W/Svc List ML20063L4621994-02-0707 February 1994 Motion for Summary Disposition.* Intervenors Request That Board Grant Summary Disposition Favorably & Issue Declaratory Relief by Finding Challenged Portion of Amend 45 to Be in Violation of Aea.W/Certificate of Svc ML20058P4451993-12-13013 December 1993 Licensee Answer to Ohio Citizens for Responsible Energy,Inc & SL Hiatt Supplemental Petition for Leave to Intervene.* W/Certificate of Svc ML20059L9391993-11-12012 November 1993 Petitioners Supplemental Petition for Leave to Intervene.* Court Held That NRC May Not Eliminate Public Participation on Matl Issue in Interest of Making Process More Efficient. W/Certificate of Svc ML20059B1421993-10-19019 October 1993 Order.* Petitioners Shall File Supplemental Petition in Accordance W/Schedule in 931018 Order.W/Certificate of Svc. Served on 931020 ML20059B1761993-10-18018 October 1993 Order.* Informs That for Each Contention,Petitioners Shall Comply Fully W/Requirements of 10CFR2.714(b)(2)(i),(ii) & (III) & Their Filing Should Address Requirements Set Forth in Regulations.W/Certificate of Svc.Served on 931019 ML20059B0701993-10-12012 October 1993 Motion to Defer Consideration of Remanded Issue.* Requests That Licensing Board Defer Consideration of Remanded Issue Pending Outcome of Commission Review of 2.206 Process.W/ Certificate of Svc ML20058M8761993-09-30030 September 1993 Memorandum & Order CLI-93-21.* Appeal for Hearing Re Amend to Plant OL Denied.W/Certificate of Svc.Served on 930930 ML20057C0461993-09-21021 September 1993 Supplemental Director'S Decision DD-93-15 Involving 920929 Request for Certain Actions to Be Taken Re Proposed Construction of Interim onsite,low-level Radioactive Waste Facility at Plant.Request Denied ML20056C8951993-07-19019 July 1993 Order Extending Time within Which Commission May Rule on Petitions for Review of LBP-92-32.W/Certificate of Svc. Served on 930720 ML20045B5661993-06-0707 June 1993 Comment Re Proposed Generic Communication on Mod of TS Administrative Control Requirements for Emergency & Security Plans,As Published in Fr on 930401 (58FR17293).Believes Concept of Technical Review Not Addressed by STS ML20044E2781993-05-13013 May 1993 Comment Supporting Petition for Rulemaking PRM-50-58 Re VEPCO Petition to Change Frequency of Emergency Planning Exercise from Annual to Biennial ML20127A6171993-01-0606 January 1993 Order.* Time within Which Commission May Rule on Petitions for Review of Board Order LBP-92-32,dtd 921118,extended Until 930208.W/Certificate of Svc.Served on 930106 ML20126D5171992-12-23023 December 1992 City of Brook Park Answer to Petitions for Review.* Opposes Applicants 921208 Petitions for Review Based on Fact That ASLB Decision in proceeding,LBP-92-32,adequately Addressed Issues Raised in Petitions.W/Certificate of Svc ML20126F6501992-12-23023 December 1992 Answer of City of Cleveland,Oh,Intervenor,In Opposition to Petitions for Review of 921118 Decision of Aslb.* Petitioners Petitions for Review Should Be Denied. Certificate of Svc Encl ML20126D5461992-12-23023 December 1992 Answer of Cleveland Electric Illuminating Co & Toledo Edison Co to Limited Petition for Review of City of Cleveland,Oh of 921118 Decision of Aslb.* Commission Should Deny City of Cleveland Petition.W/Certificate of Svc ML20126D5781992-12-23023 December 1992 Answer of American Municipal Power-OH,Inc in Opposition to Petitions for Review of Oh Edison Co & Cleveland Electric Illuminating Co/Toledo Edison Co.* W/Certificate of Svc ML20126D5801992-12-23023 December 1992 NRC Staff Answer in Response to Petitions for Review Filed by Oh Edison Co,Cleveland Electric Illuminating Co,Toledo Edison Co & City of Cleveland.* W/Certificate of Svc 1999-09-30
[Table view] |
Text
.
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE TIIE ATOMIC SAFETY AND LICENSING APPEAL BOARD In the Matter of )
)
CLEVELAND ELECTRIC ) Docket Nos. 50-440 OL ILLUMINATING COMPANY, ET AL. ) 50-441 OL
)
(Perry Nuclear Power Plant, )
Units 1 and 2) )
AFFIDAVIT OF PHYLLIS SOBEL AND LFON REITER I, Phyllis Sobel, being duly sworn do depose and state as follows:
I am employed as a seismologist in the Division of Boiling Water Re-actor Licensing, Engineering Branch, of the Nuclear Regulatory Commis-sion. A statement of my professional qualifications is attached.
I, Leon Reiter, being duly sworn, do depose and state as follows:
I am employed as a senior reliability and risk analyst in the Division of Safety Review and Oversight, Reliability and Rick Assessment Branch, of the Nuclear Regulatory Commission. A statement of my professional qualifications is attached.
The purpose of our affidavit is to respond to assertions concerning the January 31, 1986 earthquake in northeast Ohio contained in a motion
. to reopen the record filed on February 3, 1986 by Ohio Citizens for Re-sponsible Energy (OCRE).
- 1. Ve have read the OCRE Motion and conclude that no significant safety issue is raised by the contents of the motion for the reasons ex-plained as follows.
8603100034 860305 PDR ADOCK 05000440 Q PDR
- 2. On January 31, 1986 at 11:46 a.m. EST a magnitude 5.0 (mbig) earthquake occurred about 10 miles south of the Perry plant in north-eastern Ohio. The U.S. Geological Survey (USGS) reports the epicenter was at 41.65'N and 81.160W. The maximum Modified Mercalli (MM) inten-sity of the earthquake is VI. At least five research teams deployed port-able seismometers and accelerometers near the epicenter and near the Perry plant to record aftershocks. Several aftershocks were recorded; the largest was about a magnitude 2.4 on February 6. The depth of the main event was probably shallow, since the aftershocks were 1 to 6 miles deep.
- 3. The January 31 earthquake triggered the in-plant seismic moni-toring instruments. Some of the recorded motions at high frequencies (above 15 hz) exceeded the Operating Basis Earthquake (ODE) and the Safe Shutdown Earthquake (SSE). The earthouake motion recorded at the reactor building foundation was of short duration (about one second) and containcri predominantly high frequency elements, flowever, these exceedances were all recorded by instruments on plant structures; the earthquake was not recorded in the free-field outside the plant. The SSE anchor developed for nuclear plants is a high frequency anchor point for e design response spectrum (a frequency dependent description of earth-
. cuake motion useful to design engineers). For most frequencies of the January earthquake data, the design spectrum of the SSE was conserva-tive. At high frequencies (above 15 hz) there were some inplant record-ings that showed exceedances of the OBE and SSE.
- 4. To assess what part of this high frequency exceedance was due to the earthquake source as distinguished from local site conditions or the
. response of the structure, we have asked the utility and the USGS to provide and assess all available ground motion recordings near the plant site and in the epicentral area of the January 31 event and its aftershocks.
- 5. It is not unusual in an earthquake to have high amplitude high frequency peak accelerations of limited duration. In recent SERs for eastern U.S. sites (for example, Seabrook) high frequency ground mo-tions were discussed. Evaluations of eastern U.S. data suggest that the presence of high frequency ground motion is more likely a local site phe-nomenon (conditions at the recording site) than a source condition .
These high frequency peak accelerations have not been used and should not be used in scaling and applying Regulatory Guide 1.60 design spectra because they are usually of short duration and little energy and are not representative of spectral response at the lower more significant frequen-cies . Preliminary analysis of data from the January 31 earthquake aftershocks indicates that the recorded ground motions in the free-field include high frequencies similar to ground motions recorded at New Brunswick, Arkansas, Monticello Reservoir and Anza, California. As at Perry these earlier events did not result in any significant damage.
fi . The Perry site is located in the Central Stable Region tectonic province. Pfost of the seismic Category I structures, including the reac-tor building, are founded on Upper Devonian Chagrin shale bedrock.
Paleozoic sedimentary rock formations about 5,000 feet thick overlie PreCambrhin crystalline basement. Pleistocene glaciation induced localized shallow faults and folds in +he shale strata in the site vicinity. There are no known capable faults in the site region. Seismic activity in the site region is typical of that in the Central Stable Region.
. Since earthquake activity around the vicinity of the site is not substantially different from that of the Central Stable Region, the staff concluded in the SER that the controlling earthquake for the Perry e!te is the largest earthquake which is not associated with a tectonic structure, i.e., a magnitude 5.3 event similar to past earthquakes in Anna, Ohio and Sharpsburg, Kentucky.
- 8. In the OL review the staff evaluated the site ground motion pro-duced by a nearby magnitude 5.3 event. The free-field ground motion at the foundation level of the Category I structures was compared to the Perry SSE. The Perry SSE (a Pegulatory Guide 1.60 spectrum anchored to 0.15g) was found acceptable since it execeded the 84th percentile ground motion spectrum from a set of recordings from magnitude 5.3 i 0.5 events. The accelerograms were recorded at an epicentral distance of less than 16 miles (25 km) and at sites with rock foundation conditions similar to the Perry site. The applicant used Regulatory Guide 1.60 de-sign spectra anchored to 0.075g for the OBE. This represents half the SSE neccleration and is consistent with Appendix A to 10 CFR Part 100.
- 9. As previously indicated, the January 31, 1986 earthquake was magnitude 5.0 and maximum MM intensity VI. The size and proximity of this event are consistent with observations of historical seismicity in the
. Central Steble Region. As discussed earlier, the staff had compared the Perry SSE design spectrum to a larger event (magnitude 5.3) occurring near the plant.
- 10. I To date there has been no association established with a known geological structure for the recent earthquake. The utility is continuing to examine geological, geophysical and seismic data in the epicentral area
for any possible associated structures. However, a preliminary report of geological investigations done by the utility consultants in the epicentral area of the earthquakes indicates no significant tectonic structures were observed in bedrock or overlying surficial deposits. As part of ongoing studies, the information to be provided by the utility and other research-ers will be examined with respect to statements in the SER.
- 11. Because the staff had already assessed the effects of a larger carthquake (magnitude 5.3) at the Perry site and because ground motions at short durations and high frequencies have been recorded in other events and did not result in significant damage, we conclude that no sig-nificant safety issue is raised by the allegations made in OCRE's motion.
We attest the foregoing is true and accurate to the best of our knowledge and belief.
Wlw
aL Phylp Sobel / Leon Reiter N Engiueering Branch Reliability and Risk Assessment Division of Boiling Water Branch Recctor Licensing Division of Safety Review and Oversight
. Subscribed and sworn to before me this Jrt- day of March,1986.
D.r y ' lrJUsi-Notar Public
/
uy c - ,;s,on a ,,es. ~ ~ ~ - .. ~ , ,,,,
PHYLLIS SOBEL, PH.D.
ENGINEERING BRANCH DIVISION OF BWR LICENSING U.S. NUCLEAR REGULATORY COMMISSION My name is Phyllis Sobel and I am employed as a Geophysicist in the
. Engineering Branch, Division of BWR Licensing, Office of Nuclear Reactor Regulation, Washington, D. C. 20555.
PROFESSIONAL QUALIFICATIONS In 1969 I received a B.S. degree in Geological Sciences from the Pennsylvania State University. I also pursued graduate studies at Princeton University and the University of Minnesota. In 1978 I received a Ph.D. degree in Geophysics from the University of Minnesota.
From 1970 to 1973 I was a teaching assistant and research assistant at the University of Minnesota. I taught undergraduate laboratories in physical geology, historical geology, and oceanography courses. My activity as a research assistant was in the development and use of a program to simulate marine magnetic anomalies. My interests in graduate school included all areas of geophysics, structural geology, and marine geology. My dissertation was a study of seismic phases reflecting off structures below the Earth's crust under several geographic regions.
From 1973 to 1977 I was employed by Teledyne Geotech in Alexandria, Virginia as a research geophysicist. At this corporation's research laboratory I worked on a variety of research problems in seismology related to the detection of nuclear explosions, including the use of filters to extract signals from seismograms, the propagation of Rayleigh waves through hetero-geneities, and the characteristics of earthquakes in areas of proposed underground nuclear testing in Asia.
I am a member of the American Geophysical Union and the Seismological Society of America. I have authored or co-authored ten papers published as Teledyne Geotech reports or in the Bulletin of the Seismological Society of America. I have authored or co-authored two papers presented at meetings of the Seismological Society of America.
From October 1977 to March 1978 I was employed as a seismologist by the NRC Office of Standards Development in the revision and development of new regulatory guides and standards. Since March 1978 I have been employed by
, the Office of Nuclear Reactor Regulation in the evaluation of the seismo-logical and geophysical data submitted to the NRC in support of a proposed seismic design basis for nuclear facilities. In addition, I have supervised technical,' assistance contracts related to generic croblems found in the licensing process.
LEON REITER SENIOR RELIABILITY AND RISK ANALYST RELIABILITY AND RISK ASSESSMENT BRANCH DIVISION OF SAFETY REVIEW AND OVERSIGHT U. S. NUCLEAR REGULATORY COMMISSION My name is Leon Reiter. I presently reside at 1960 Dundee Road, Rockville, Maryland 20850 and am employed as a Senior Rel. 'ility and Risk Analyst in the Reliability and Risk Assessment Branch, Division uf Safety Review and Oversight, Office of Nuclear Reactor Regulation, Washington, D.C. 20555.
PROFESSIONAL QUALIFICATIONS I received a Bachelor of Arts degree in Geology from Brooklyn College in 1958, a Master of Science degree in Geology (Geophysics) from the University of Michigan in 1968, a Master of Arts degree in Mathematics from the University of Michigan in 1970 and a Ph.D. in Geology (Geophysics) from the University of Michigan in 1971. In the year following receipt of my Ph.D. I was a National Science Foundation Post-Doctoral Fellow at the Institute of Geophysics and Planetary Ceophysics in La Jolla, California. From 1972 to 1976 I was an Assistant Professor of Geophysics at the University of Oklahoma. During the summer of 1975 I was a visiting scientist of the U.S. Geological Survey National Center for Earthquake Research in Menlo Park, California. I joined the NRC in August, 1976 as a Seismologist and in August 1979 I became Leader of the Seismology Section in the Geosciences Branch of the Division of Engineering. In December 1985, I became a Senior Reliability and Risk Analyst in the Reliability and Risk Assessment Branch of the Division of Safety Review and Oversight.
My research during try academic career has included the areas of crustal exploration, seismic wave attenuation, nidcontinent seismicity and tectonics, earthcuake prediction and the application of seismic techniques to engineering problerrs . At NRC I have been actively involved in review of sites for nuclear facilities in all parts of the United States and in several foreign countries. I have also taken a lead responsibility for studies in the fields of strong motion seismology, near-field ground motion, and probabilistic risk assessment.
I am a member of the American Geophysical Union, the Seismological Society of America, the Society of Exploration Geophysicists and the Earthquake Engineering Research Institute. I have served as a member of the Plate Interiors Working Group of the U.S. Geodynamics Committee, the Interagency Committee on Seismic Safety in Construction and the Panel on National Regional and Local Seismograph Networks and the Panel on Seismic Hazard Analysis of the National Research Council-National Academy of Sciences. I have authored l or co-authored papers published in the Bulletin of the Seismological Society i of America, the Journal of the Acoustical Society of America, and many i conference proceedings.
I i