ML20149D621

From kanterella
Jump to navigation Jump to search
Mgt Meeting Rept 50-213/97-03 on 970528.Areas Discussed: Actions in Response to Findings Detailed in NRC Insp Repts 50-213/96-12.96-201 & 97-01.Deficiencies Involved Implementation of Radiation Protection Program
ML20149D621
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 06/13/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20148L701 List:
References
50-213-97-03-MM, 50-213-97-3-MM, NUDOCS 9707170199
Download: ML20149D621 (3)


See also: IR 05000213/1997003

Text

. . . . _ . _ . _ . . _ - . . . . . . _ _ _ . . _ _ . _ . _ . _ _ _ _ .

7.__-._.__.-_.._

l 19J

n

1

l >

.

,

l. U.S. NUCLEAR REGULATORY COMMISSION

o

REGION I

I ,

, 'l

L

I Docket No.: 50-213

l License No.: DPR-61 I

L

i

.

.

Report No.: Management Meetmg

.

(Reference NRC Inspection Report No. 50-213/97-03) i

1

!

L

,

Licensee:- Connecticut Yankee Atomic Power Company

l - Hartford, CT 06141-0270 1

1

I

,

Facility: Haddam Neck Station I

t

i l

i Location: King of Prussia, Pennsylvania

!

. Date: May 28,1997 f  !

.

Prepared by: W. J. Raymond, Senior Resident inspector

1

l

Approved by: R. J.' Conte, Chief, Project Branch 8 l

Division of Reactor Projects j

Discussioni A management meeting was held at the NRC Region I office, King of Prussia,. j

Pennsylvania on May 28,1997. The purpose of the meeting was to discuss actions in

p ~ response to the findings detailed in NRC Inspection Report Nos. 50-213/96-12,96-201

L and 97-01, which described deficiencies involving the implementation of the radiation

protection program, maintaining the licensing basis and implementing effective corrective

actions. During the meeting, the licensee presented information and their assessment of

performance in the areas of concern, including causes'and corrective measures to improve

' performance. The radiation protection improvement program was discussed in particular.

_

.{

J- . The' meeting was open for public observation. '

1

i

1

i

!  ;

i

!'

!

1

u 9707170199 970613 >

.PDR ADOCK 05000213

G PDR  ;,

,

- . . . - . . . . .. .. .-- . - - ..

_ _ _. . _ . . . ._ ._. _ ..

.)-

.

Report Details

1.0 Attendees

'jdcensee

'

"

Russell A. Mellor, Director Site Operations & Decommissioning l

Gary Bouchard, Work Services Director 3

John D. Haseltine, Engineering Director '

Richard J. Sexton, Health Physics Manager  ;

Gerry van Noordennen, Licensing Manager

i

NRC. )

l

Richard Conte, Chief, Reactor Projects Branch 8, Division of Reactor Projects -i

'

John R. White, Chief, Radiation Safety Branch (RSB), Division of Reactor Safety I

Robert J. Bores, Senior Project Manager, Division of Reactor Safety

William J. Raymond, Senior Resident inspector, Division of Reactor Projects

, Ronald L. Nimitz, Senior Radiation Specialist, RSB

Jason Jang, Senior Radiation Specialist, Division of Reactor Safety l

S. Singh Bajwa, Chief, Decommissioning Section, Nuclear Reactor Regulation (NRR) l

Morton Fairtile, Project Manager, Decommissioning, NRR I

T. Fredrichs, Project Manager, NRR

i

Others.

Edward House, BWG, Inc.

2.0 Purpose l

The purpose of the meet:ng was to discuss actions in respor r.,e to the findings

detailed in NRC Inspection Report Nos. 50-213/96-12,96-201 and 97-01, which

described deficiencies involving the implementation of the radiation protection

program, maintaining the licensing basis and implementing effective corrective

actions. During the meeting, the licensee presented information and their j

assessment of performarice in the areas of concern, includino causes and corrective 1

measures to improve performance. The radiation protection improvement program l

was discussed in particular. The meeting was open for public observation, l

l

3.0- Meeting Discussions and Presentations l

The licensee summarized the present organization structure for decommissioning, i

and discussed actions to address problems in the areas of maintaining the licensing ]

and design bas;s and in maintaining control of the plant configuration, particularly I

as related to the spent fuelisland; in conecting problems with the effluent l

monitors, iraproving human performance and procedure quality; and, to addressing  ;

weaknesses in the corrective action prccess and the radiation protection program.

The licensee discussed initiatives to raise management standards, and to improve

monitoring of activities in the plant, such as through the work observation program

and trending activities through the use of the nuclear oversight organization and the 1

use of enhanced key performance indicators. The results of the recently completed

. .. . . .. . . .. . - . . . - . - .- - - . _ - _ . _ . . - - -.

4

.

2

independent assessment of the radiation protection program were discuse s d ni

i particular, and the aspects of the radiation protection improvement program that

will address the past concerns and irnprove performance.

1 Attachment 1 to this meeting report provides a copies of the slides and other

i presentation materials that were provided by the licensee to support the

discussions.

1

l

4

!'

i

i

e

1

2

1