Forwards Schedule for ACRS Subcommittee on Midland Plant 820429 Meeting in Washington,Dc to Discuss Util Remedial Action Re Soils & Structural Settlement Issues
ML20140G912
Person / Time
Site: Midland, 05000000
Issue date: 04/14/1982
From: Fischer D
NRC
To: Seiss C
Advisory Committee on Reactor Safeguards
Shared Package
ML19255C661 List: ... further results
References
FOIA-85-602 NUDOCS 8510080143
Download: ML20140G912 (4)


Text

,

( 't < H Lau April 14, 1982 MEMORANDtti FOR: C. Siess, Acting Chairman, ACRS Subcommittee on Midland Plant Units 1 & 2 FROM: D. Fischer, Reactor Engineer

SUBJECT:

TENTATIVE SCHEDULE FOR THE ACRS SUBCOPt(ITTEE MEETING ON MIDLAND PLANT UNITS 1 & 2 - APRIL 29,1982 -

WASHINGTON, DC Attached is a tentative schedule for the subject meeting. The purpose of the meeting is to discuss remedial action being taken by Constsners Power Company regarding the Midland soils and structural settlement issues.

The meeting will begin at 8:30 a.m. and will be held in Room 1046 at 1717 H Street, NW, Washington, DC. Attendance by the following ACRS members and consultants is anticipated and hotel reservations have been made for the night and hotel indicated below. If you are unable to make the meeting, please call us or the hotel and cancel your res-ervations so that we are not billed.

C. Siess Park Central (202-393-4700) 28th R. Axtmann Park Central 28th J. Osterberg None R. Scavuzzo None Z. Zudans None By copy of this memo, members of the NRC Staff and other participants who will be making presentations to the Subcomittee are reminded of the Subcomittee's need for twenty hard copies of all slides, training aids, and papers presented to the Subcomittee.

Attachment:

8510080143 850930 Tentative Schedule @yyA 02 m  %$ k 5 AE 2'

cc: ACRS Members E. Goodwin, NRR f R. Fraley, ACRS R. DeYoung, IE M. Gaske, ACRS R. Minogue, RES M. Libarkin, ACRS D. Eisenhut, NRR T. McCreless, ACRS R. Vollmer, NRR ~

t[

J. Mc Kinley, ACRS J . Keppler, NF R omce > .. s...s..g $st.schre;yer, ..ncgs.- -. . . . . - . ..-. -.5 .-Tedesco, H R---- --- -

sunsme > .. B .. . .W 1.te .ACRS...... . . . . . . . . . . . . . . . . . ..........I ... Adensam...NF R..................... ....................

onepj.I[./LM.Va nderholt, ACFS 0 . Hood, NRR

'***T ''He'6 n","WRF

  • * * " " " " * ' ' ' ' ' ' ' ' ' " " ~ ~ ~ ' " " '

. . . . .. . .. . .H "' M't'2"," M * * * * *

  • NRC FORM 318 (10-80) NRCMk240 Case, NMK OFFICIAL RECORD GOPV9ht, NRE mos o. i i-mm

, ( I TENTATIVE SCHEDULE FOR i APRIL 29, 1982 i ACRS SUBCOMMITTEE MEETING ON MIDLAND PLANT UNITS 1 & 2 H ROOM 1046, 1717 H ST. , NW, WASHINGTON, DC APPROXIMATE TIME i

8:30 a.m. I. CHAIRMAN'S OPENING STATEMENT A. Discussion of Schedule B. Meeting Goals 8:45 a.m. II. STAFF INTRODUCTION /0VERVIEW (NRR/DL)

A. General Discussion of the Soils and Structural Settlement Issues (Including Why No Problem With Reactor Building) at Midland B. Identification of the Safety Significance of These Issues C. Brief Chronology Regarding Plant Fill Deficiencies, Including ASLB Hearing Status D. Why the ACRS Has Been Asked to Review These Issues At This Time E. General Discussion of the Proposed and Implemented Corrective Actions Including Relationship to Seismic Site-Specific Spectra (Phased Program)

F. Staff General Comments on the Proposed Fixes and Schedule of Future Events G. Discussion 10:00 a.m. BREAK 10:10 a.m. III. CONSLNERS POWER COMPANY OVERVIEW 0F SOILS AND

$TRUCTlRAL SETTLEMENT ISSUES AT MIDLAND, INCLt0ING THEIR EFFECT ON THE LICENSING SCHEDULE IV. TECHNICAL DISCUSSION A. Auxiliary Building and Feedwater Isolation Valve Pit 10:25 a.m. 1. Consumers Power Company

a. Statement of problems
b. Corrective actions taken and those proposed 11:25 a.m. 2. NRC Staff (DE)
a. Statement of problems
b. How the NRC Staff believes these problems i can be solved, criteria used .
c. NRC Staff evaluation of CPC corrective I actions
d. Future NRC Staff actions 12:00 noon LUNCH

. ( (

. TENTATIVE SCHEDULE MIDLAND .

APRIL 29, 1982 APPROXIMATE TIME I

B. Service Water Pump Structure 1:00 p.m. 1. Consumers Power Company

a. Statement of problems
b. Corrective actions taken and those proposed 1:20 p.m. 2. NRCStaff(DE)
a. Statement of problems
b. How the NRC Staff believes these problems can be solved, criteria used
c. NRC Staff evaluation of CPC corrective actions
d. Future NRC Staff actions C. Borated Water Storage Tank 1:40 p.m. 1. Consumers Power Company
a. Statement of problems
b. Corrective actions taken and those proposed 2:10 p.m. 2. NRC Staff (DE)
a. Statement of problems
b. How the NRC Staff believes these problems can be solved, criteria used
c. NRC Staff evaluation of CPC corrective actions
d. Future NRC Staff actions D. Diesel Generator Building 2:30 p.m. 1. Consumers Power Company
a. Statement of problems
b. Corrective actions taken and those proposed 3:00 p.m. 2. NRC Staff (DE) l 1
a. Statement of problems
b. How the NRC Staff believes these problems can be solved, criteria used
c. NRC Staff evaluation of CPC corrective l actions
d. Future NRC Staff actions

( ( .

. TENTATIVE SCHEDULE l MIDLAND APRIL 29,1982

=

E. Underground Utilities, Pipes. Etc.

3:30 p.m. 1. Consumers Power Company

a. Statement of problems
b. Corrective actions taken and those proposed 4:00 p.m. 2. NRC Staff (DE)
a. Statement of problems
b. How the NRC Staff believes these problems can be solved, criteria used

, c. NRC Staff evaluation of CPC corrective actions

~

d. Future NRC Staff actions 4:30 p.m. V. OPEN EXECUTIVE SESSION / CHAIRMAN'S CLOSING REMARKS 5:00 p.m. ADJOURNMENT I