:on 961220,discovered Original Value for Strainers Head Loss Incorrect.Cause Could Not Be Determined. Training Provided for Operators to Recognize Pump Cavitation During Design Basis Accidents| ML20134A188 |
| Person / Time |
|---|
| Site: |
Quad Cities  |
|---|
| Issue date: |
01/22/1997 |
|---|
| From: |
Peterson C COMMONWEALTH EDISON CO. |
|---|
| To: |
|
|---|
| Shared Package |
|---|
| ML20134A173 |
List: |
|---|
| References |
|---|
| LER-96-025-01, LER-96-25-1, NUDOCS 9701280201 |
| Download: ML20134A188 (5) |
|
text
.
LICENSEE EVENT REPORT (LER)
Form Rev. 2.0 Facihty Name (ll' Docket Number (2)
Page (3) 1 Quad Cities Unit One ol5l0lol0l2l5l4 1 l of l 0 l 5 Tith (4)
Operibility calculations performed on Emergency Core Cooling System (ECCS) suction strainers with correct head loss values show that the design functions of the ECCS systems are met using a value of containment overpressure that is slightly greater than that shown in the Updated Fin:.1 S;fety Analysis Report (UFSAR).
Event Date (5)
LER Number (6)
Report Date (7)
Other Facibues involved (8)
Month Day Year Year Sequential Revision Month Day Year Facihty Docket Numberts) j Number Number Names Quad Clues Uni: 2 0l5l0l0l0l2l6l5 1l2 2l3 9l6 9l6 ol2l5 ol0 ol1 2l2 9l7 ol5lololol l
l t)PERATING THIS REPORT IS SUBMf!TED PURSUANT TO THE REQUIREMENTS OF 10CFR MODE (9)
(Check ota or more of the following) (11) j Pow:r Operation 1
20.402(b) 20.405(c) 50.73(a)(2)0v) 73.71(b)
POWER 20.405(a)(1)0) 50.36(c)(1) 50.73(a)(2)(v)
~73.71(c)
LEVEL
- - 20 405(a)(1)61) 50.36(c)(2) 50.73(a)(2)(vii)
Tother (S ecify P
(10) 1 l0l 0
- - 20.405(a)(1)0ii) 50.73(a)(2)0) 50.73(a)(2)(viii)(A) m Abstract 20.405(a)(1)0v) 50.73(a)(2)Oi) 50.73(a)(2)(viii)(B) below and in j
- - 20.405(a)(1)(v) 50.73(a)(2)0ii) 50.73(a)(2)(x)
Text)
LICENSEE CONTACT FOR Tills LER (li)
NAME TELEPHONE NUMBER AREA CODE Charles Peterson, Regulatory Affairs Manager, Ext. 36o2 3l0l9 6l5l4l-l2l2l4l1 COMPLETE ONE LINE FOR EACH COMPONENT FAILURE DE.5CRIBED IN TH15 REPORT (13)
CAUSE
SiSTIM COMNN ENT MANU FACWRER RU5RTABLE
CAUSE
SYSTEM COMNNENT MANUFACWRER REPORTABLE j
10 NPRDS TO NPRDS l
l 1
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I 5UP >IIMENTAL REPORT ENPEu w (14)
Expeded Month Day Year Submission lYES Of yes complete EXPECTED SUAUSSION DATO yo Date (15) l l
l AB5IRACr (1.mna so 1400 spaces, i.e., appronansiety hheen single-space typcenuen imee) (le)
ABSTRACT:
This report is being submitted as a voluntary Licensee Event Report.
On 122096, during preparations for a design change to install new Emergency Core Cooling System (ECCS) suction strainers, it was discovered that the original value for the strainers head loss was incorrect.
An operability evaluation and supporting calculations were performed in response to Problem Identification Form #96-3571.
The Net Positive Suction Head (NPSH) calculations for the ECCS pumps, using the correct strainer head loss, determined that the ECCS pumps would have performed their design function during a design bases accident.
As the result of discussions concerning the differences between the overpressure values, the small NPSH margins and the likelihood that additional analyses may or may not show that the current Updated Final Safety Analysis Report (UFSAR) overpressure value could be used, Quad Cities conservatively elected to make an ENS notification.
The NRC was notified by telephone on 122396 at 1552.
A 10CFR50.59 safety evaluation has been completed to revise the UFSAR to incorporate the correct value for the strainer head loss and reference to the 1993 containment overpressure analysis. No unreviewed safety question was identified by the 10CFR50.59 safety evaluation and the dose to the control room operators and the public would remain within design bases. Therefore, there was no safety significance for this event.
The root cause of the incorrect strainer head / loss could not be determined.
9701280201 970122 PDR ADOCK 05000254 S
PDR
. ~. - -
LICENSEE EVEKr REPORT (LER) TEXT CONTINUATION Form Rev. 2.0 i
F ACILITY N AME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (3)
Year Sequ;ntial Rsvision Number Number Quad Cities Unit One 0l5l0l0l0l2l5l4 9l6 0l2l5 0l0 2 lOFl 0 l 5 1
TEXT Energy Industry Identification System (EIIS) codes are identified in the text as [XX)
J
PLANT AND SYSTEM IDENTIFICATION
General Electric - boiling Water Reactor - 2511 MWt rated core thermal power.
EVENT IDENTIFICATION: Operability calculations performed on Emergency Core Cooling System (ECCS) suction strainers with correct head loss values show that the design functions of the ECCS systems are met using a value of containment overpressure that is slightly greater than that shown in the Updated Final Safety Analysis Report (UFSAR).
A.
CONDITIONS PRIOR TO EVENT
Unit:
One Event Date:
December 23, 1996 Event Time:
1510 Reactor Mode: 1 Mode Name:
Power Operation Po'wer Level:
100%
1 i
Unit:.Two Event Date: December 23, 1996 Event Time:
1510 Reactor Mode: 1 Mode Name:
Power Operation Power Level:
100%
This report was initiated by Licensee Event Report 254\\96-025.
POWER OPERATION (1) - Mode switch in the'Run position with average reactor coolant temperature at any temperature.
B.
DESCRIPTION OF EVENT
This report is being submitted as a voluntary LER.
On 122096, a 1983 vendor calculation that determined the structural adequacy of the Emergency Core Cooling System (ECCS)[B0, BM] suction :; trainers [STR] was discovered that identified the head loss across the ECCS suction strainers for both Unit 1 and 2 as 5.8 feet of water. This v., not consistent with the Updated Final Safety Analysis Report (UFSAR) and original vendor drawings which have identified the head loss across the strainers as 1 foot of water since the original construction and operation of the plant. The above head loss values are for 10,000 gallons per minute (gpm) flow.
Subsequent review of calculations revealed the 1983 calculation was correct.
A problem identification form (PIF) was initiated and analysis was also initiated to determine the effect that an additional 4.8 feet of head loss may have on the ECCS pumps net positive suction head (NPSH) margin. An issue screening of PIF 96-3571 determined that the required design functions were met but a concern existed;
~ therefore, a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> operability evaluation was initiated.
l LER254\\96\\025,WPF
LICENSEE EVENT REPORT (LER) TEXT CONTINUATION Form R:v. 2.0 F ACILffY N AME (1)
DOCKET NUMBER Z LER NUMBER (6)
PAG E (3)
Year sequintial R vision Number Number I
Quad Cities Unit One 0l5l0l0l0l2l5l4 9l6 0l2l5 0l0 3 lOFl 0 l 5 TEXT Energy Industry idernificatu>n System (Ells) codes are identified in the text as IXX)
The NPSH calculations evaluated two time periods, i.e. short term (first 10 minutes of a design basis accident) and long term. The calculations determined during the short term, that with maximum ECCS flow (two core spray (CS) pumps at run out and four low pressure coolant injection (LPCI) pumps injecting into a pipe break) the CS l
pumps would start to cavitate in about eight minutes.
For the long term the ECCS pumps would not cavitate when the pump flows are throttled by the operators as directed by the Emergency Operating Procedures (E0Ps).
Credit for containment overpressure was used for both the short term and long term analysis as described below. The flow rates used for ECCS pumps NPSH evaluation were conservatively higher i
than required to perform containment cooling and to provide adequate water to the core to maintain two thirds core height coverage.
Based on this NPSH calculation the operability evaluation determined that the ECCS pumps were operable.
The operability determination by operations concluded that the ECCS pumps were " operable, but degraded" and that no ENS call was required.
The Quad Cities NPSH calculation used the computer flow models developed for Dresden with corrections for differences between Dresden and Quad Cities Stations. The analysis performed in 1993 to determine the minimum containment overpressure that would be available in the long term used the models similar to those described in NRC Branch Technical Position CSB 6-1 as endorsed by NRC Information Notice 96-55. This analysis results in the minimum containment overpressure being slightly higher in the long term than the value shown in UFSAR Figure 6.3-42.
The short term overpressure analysis also employed a methodology which conservatively minimized (lowered) the calculated containment overpressure available. This analysis was performed in November 1996 for the Dresden Station. An evaluation of the Dresden and Quad Cities parameters used as inputs verified that the Dresden analysis could be conservatively used for Quad Cities As the result of discussions concerning the differences between the overpressure values, the small NPSH margins and the likelihood that additional analyses may or may not show that the current UFSAR overpressure value could be used, Quad Cities conservatively elected to make an ENS notification.
The NRC was notified by telephone on 122396 at 1552.
A 10CFR50.59 safety evaluation was initiated to revise the UFSAR to reflect the approximately six feet of head loss for the ECCS suction strainers.
During preparation of the safety evaluation it was also determined that the original containment overpressure information in the UFSAR could be revised to include the 1993 analysis.
This is based on the original NRC safety evaluation report (SER) which accepted use of containment overpressure, dated 082571.
Review of the Quad Cities submittal to the NRC and their SER dated 010477, reviewed the conditions of runout pump cavitation, was included in the 10CFR50.59 safety evaluation.
It determined that no unreviewed safety question exists.
Therefore, b'ased on the UFSAR change the ECCS pumps are operable, and no longer considered degraded.
l LER254\\96#.5.WPF
LICENSEE EVENT REPORT (LER) TEXT CONnNUATION Form R:v. 2.0 FACILITY NAME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAG E (3).
Year Sequential Rsvision Number Number Quad Cities Unit One 0l5l0l0l0l2l5l4 9l6 ol2l5 0l0 4 lOFl 0 l 5 TEXT Energy Industry Identification system (Ell 5) codes are identified in the text as [XXj l
C.
APPARENT CAUSE OF EVENT:
The 1983 calculation was discovered during a Design Basis Review associated with a proposed modification to the ECCS suction strainers that will be installed to meet the requirements from NRC Bulletin 96-03.
The ECCS suction strainers were modified as part of the Mark I containment program. The vendors structural calculation for the modification also evaluated the reduction in surface area and the resulting head loss increase from 5.5 feet to 5.8 feet.
The 5.5 feet head loss was based on a reference to the vendor's 1981 calculation which was determined from information provided by the original strainer supplier. The original strainer supplier could not locate records for the Quad Cities strainers but did provide date on testing of strainers for later vintage power plants.
The reason for the inaccuracy of the original one foot of water could not be determined. Therefore the root cause of the strainer suppliers incorrect information is unknown.
D.
SAFETY ANALYSIS OF EVENT-The safety significance of the event was minimal.
If a design bases accident had j
occurred, the health and safety of the public and control room operators would not have been impacted by this event since the ECCS pumps would have performed their j
function.
If an event had occurred which required ECCS injection, sufficient containment overpressure would have been present to ensure that the ECCS pumps would provide adequate cooling to the core.
Since the ENS call a 10CFR50.59 safety evaluation has been completed to revise the UFSAR to incorporate by reference later long term containment overpressure analysis.
Information was uncovered on CS and LPCI pump cavitation testing that indicates that cavitation operation of the pumps for a short time will not damage the pumps.
This information was reviewed and was accepted by the NRC in their 1977 SER.
In conclusion, there is no safety significance of this event since the ECCS pumps would have performed their safety function and that the NPSH calculations are within Quad Cities design bases as evaluated in the UFSAR safety evaluation, l
i LER254\\m025,WPF 4
LICENSEE EVENT REPORT (LER) TEXT CONTINUATION Form Rev. 2.0 F ACILITY N AME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
P AGE (3)
Year sequmnal R3 vision
=
Number Number 0l2l5 0l0 5 lOFl 0 l 5 Quad Cities Unit One 0l5l0l0[0[2l5l4 9l6 TEXT Energy Industry Idenn6 canon System (EU5) codes are idennfied in the text as [XX)
E.
CORRECTIVE ACTIONS
Corrective Action Completed:
1.
As a compensatory action, just in time training was provided for operators to recognize pump cavitation during design basis accidents.
This was performed prior to each person assuming shift duties.
2.
As a compensatory action, QCOP 1000-30, " Post-Accident RHR Operation" has been revised to provide direction to throttle flow rate when pump cavitation is indicated and provide caution to assure core cooling.
3.
A 10CFR50.59 safety evaluation has been prepared to update the UFSAR to show that the ECCS suction strainers have a head loss of approximately 6 feet at 10,000 gpm and add reference to the long term containment overpressure analysis.
Safety evaluation SE-97-001 for UFSAR change completed 011097.
Corrective Actions To Be Completed:
7 The site Plant Operations Review Committee will determine how 1.
much, if any to lower the administrative limits for torus water temperature, to improve NPHS margin in the actual plant response to design bases event (s).
Correlation between initial torus water temperature and NPSH margin will be determined prior to 033197.
(NTS 2541809602501, Design Engineering)
F.
PREVIOUS EVENTS:
A search was conducted for prior similar occurrences of this event relating to the ECCS suction strainers. No previous events were found.
G, COMP 0NENT FAILURE DATA:
Not applicable.
i LER25496M5.WPF
|
|---|
|
|
| | | Reporting criterion |
|---|
| 05000254/LER-1996-001-07, :on 960303,B CR HVAC Sys Inoperable Due to Malfunctioning Relay Which Prevented Isolation of Air Handling Unit Fan.Ems Replaced Relay & Forwarded Damaged Relay to Engineering for Evaluation |
- on 960303,B CR HVAC Sys Inoperable Due to Malfunctioning Relay Which Prevented Isolation of Air Handling Unit Fan.Ems Replaced Relay & Forwarded Damaged Relay to Engineering for Evaluation
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation | | 05000265/LER-1996-001, Forwards LER 96-001-00.Listed Commitments Made,Including Event Will Be Included as Part of Continuing Training for Both Licensed Operators & Engineering Dept | Forwards LER 96-001-00.Listed Commitments Made,Including Event Will Be Included as Part of Continuing Training for Both Licensed Operators & Engineering Dept | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000265/LER-1996-001-10, :on 960417,HPCIS Was Declared Inoperable Due to Procedural Deficiency Which Allowed Isolation of Turbine Exhaust Vacuum.Licensed Operators Have Been Trained on Procedure Changes |
- on 960417,HPCIS Was Declared Inoperable Due to Procedural Deficiency Which Allowed Isolation of Turbine Exhaust Vacuum.Licensed Operators Have Been Trained on Procedure Changes
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000265/LER-1996-002, Forwards LER 96-002-00.Licensee Revised Qcop 2300-1 to Ensure That Piping Downstream of Sys Isolation Valve Is Filled & Vented After Maint | Forwards LER 96-002-00.Licensee Revised Qcop 2300-1 to Ensure That Piping Downstream of Sys Isolation Valve Is Filled & Vented After Maint | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000265/LER-1996-002-10, :on 961009,HPCI Sys Declared Inoperable.Caused by Improper Filling & Venting After Aug 1996 Maint.Air Purged from Sys & line-up Procedure Revised to Ensure Filling & Venting of Piping |
- on 961009,HPCI Sys Declared Inoperable.Caused by Improper Filling & Venting After Aug 1996 Maint.Air Purged from Sys & line-up Procedure Revised to Ensure Filling & Venting of Piping
| | | 05000254/LER-1996-002-04, :on 960220,CR HVAC Sys Inoperable.Caused by Design Oversight Involving Toxic Gas Anlayzer.On 960223 Procedure Change to Qcop 5750-09, CR Ventilation Sys, Made to Allow for Operation of Booster Fans |
- on 960220,CR HVAC Sys Inoperable.Caused by Design Oversight Involving Toxic Gas Anlayzer.On 960223 Procedure Change to Qcop 5750-09, CR Ventilation Sys, Made to Allow for Operation of Booster Fans
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2) | | 05000265/LER-1996-003-01, :on 961112,Unit 2 LPCI Was Declared Inoperable. Caused by Failure of 2D RHR Pump Discharge Check Valve.Lpci Kf Pressure Was re-established within One Hour |
- on 961112,Unit 2 LPCI Was Declared Inoperable. Caused by Failure of 2D RHR Pump Discharge Check Valve.Lpci Kf Pressure Was re-established within One Hour
| | | 05000265/LER-1996-003-13, :on 961112,Unit 2 LPCI Was Declared Inoperable to 2D RHR Pump Discharge Check Valve Failure.Lpci Kf Was re-established within 1 Hour & Operability Determination Was Completed for PIF 96-3196 |
- on 961112,Unit 2 LPCI Was Declared Inoperable to 2D RHR Pump Discharge Check Valve Failure.Lpci Kf Was re-established within 1 Hour & Operability Determination Was Completed for PIF 96-3196
| | | 05000265/LER-1996-003, Forwards LER 96-003-00 Submitted IAW Requirements of 10CFR50.73(a)(2)(v)(D).Commitments Made by Ltr,Submitted | Forwards LER 96-003-00 Submitted IAW Requirements of 10CFR50.73(a)(2)(v)(D).Commitments Made by Ltr,Submitted | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000254/LER-1996-003-02, :on 960222,unanticipated Start Occurred on Unit 1 Edg.Caused by Inadequate Guidance within Procedure Qcmms 6600-03.Procedure Qcmms 6600-03 Will Be Revised to Clarify Switch Settings |
- on 960222,unanticipated Start Occurred on Unit 1 Edg.Caused by Inadequate Guidance within Procedure Qcmms 6600-03.Procedure Qcmms 6600-03 Will Be Revised to Clarify Switch Settings
| 10 CFR 50.73(a)(2) | | 05000254/LER-1996-003, Forwards LER 96-003-00 Re Unit 1 Start of Egd Due to Inadequate Procedure | Forwards LER 96-003-00 Re Unit 1 Start of Egd Due to Inadequate Procedure | 10 CFR 50.73(a)(2)(iv), System Actuation | | 05000254/LER-1996-004-01, :on 960130,HPCI Sys Declared Inoperable Due to Gland Exhauster Breaker Trip.Hpci Gland Exhauster Breaker Replaced & Tested for Proper Operation & AOP Time Delay Bypass Switches in Starting Circuit Replaced |
- on 960130,HPCI Sys Declared Inoperable Due to Gland Exhauster Breaker Trip.Hpci Gland Exhauster Breaker Replaced & Tested for Proper Operation & AOP Time Delay Bypass Switches in Starting Circuit Replaced
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2) | | 05000254/LER-1996-005-07, :on 960203,B CR HVAC Sys Declared Inoperable Due to Outside Air Temp.Submitted TS Change Requesting That Heater Power Be Measured Instead of Differential Temp Across Heater to Determine Operability |
- on 960203,B CR HVAC Sys Declared Inoperable Due to Outside Air Temp.Submitted TS Change Requesting That Heater Power Be Measured Instead of Differential Temp Across Heater to Determine Operability
| | | 05000254/LER-1996-006, :on 960210,TS 3.0.A Incorrectly Invoked Due to Procedural & Operator Knowledge Deficiencies.Policy Statement Developed & Presented to Licensed Operator Re Expectations for Use & Entry Into TS 3.0.A |
- on 960210,TS 3.0.A Incorrectly Invoked Due to Procedural & Operator Knowledge Deficiencies.Policy Statement Developed & Presented to Licensed Operator Re Expectations for Use & Entry Into TS 3.0.A
| 10 CFR 50.73(a)(2)(i) | | 05000254/LER-1996-007-02, :on 960510,secondary Containment Damaged.Caused by Tornado.Initiated Shutdown,Ac Power Restored to Prompt Notification Sys & Station Blackout Bldg Cables Spliced Per Er 9603099 |
- on 960510,secondary Containment Damaged.Caused by Tornado.Initiated Shutdown,Ac Power Restored to Prompt Notification Sys & Station Blackout Bldg Cables Spliced Per Er 9603099
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(1) 10 CFR 50.73(e)(2)(vii) | | 05000254/LER-1996-008-02, :on 960607,TS Required Pressure Not Met During Local Leak Rate Testing.Caused by Procedural Deficiency. Procedure Changes Submitted & Check Valves Retested Using Appropriate Vent Paths |
- on 960607,TS Required Pressure Not Met During Local Leak Rate Testing.Caused by Procedural Deficiency. Procedure Changes Submitted & Check Valves Retested Using Appropriate Vent Paths
| 10 CFR 50.73(a)(2)(viii)(B) | | 05000254/LER-1996-008, Forwards LER 96-008,Rev 00 & Makes Following Commitment: Procedure Qcts 0600-34 Will Be Revised to Ensure Appropriate Vent Path Exists When Leak Rate Testing 2251(2)-81A/B Panels | Forwards LER 96-008,Rev 00 & Makes Following Commitment: Procedure Qcts 0600-34 Will Be Revised to Ensure Appropriate Vent Path Exists When Leak Rate Testing 2251(2)-81A/B Panels | 10 CFR 50.73(a)(2)(1) | | 05000254/LER-1996-009-01, :on 960523,noted Discrepancy in Cable Length Modeled in Existing Degraded Voltage Calculations.Caused by Design Analysis Deficiency.Performed Design Changes to Correct Voltage Problems |
- on 960523,noted Discrepancy in Cable Length Modeled in Existing Degraded Voltage Calculations.Caused by Design Analysis Deficiency.Performed Design Changes to Correct Voltage Problems
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(B) | | 05000254/LER-1996-010-02, :on 960611,discovered Installed Gallery Steel Configuration Lacked Required Cross Bracing.Caused by Deficiency in Original Design Configuration Control Process. Installed Gallery Cross Bracing |
- on 960611,discovered Installed Gallery Steel Configuration Lacked Required Cross Bracing.Caused by Deficiency in Original Design Configuration Control Process. Installed Gallery Cross Bracing
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) | | 05000254/LER-1996-011, Forwards LER 96-011-00.Circuit Mods & Procedure Changes Will Be Implemented Prior to Startup & Review of Sample of Assumptions from Safe Shutdown Repts & Calculations Investigated | Forwards LER 96-011-00.Circuit Mods & Procedure Changes Will Be Implemented Prior to Startup & Review of Sample of Assumptions from Safe Shutdown Repts & Calculations Investigated | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000254/LER-1996-011-02, :on 960708,determined Postulated Fire Could Have Caused Disabling Damage to Selected Motor Operated Valves.Caused by Inadequate Design Analysis Review.Movs Analyzed for Susceptibility to Single Failure |
- on 960708,determined Postulated Fire Could Have Caused Disabling Damage to Selected Motor Operated Valves.Caused by Inadequate Design Analysis Review.Movs Analyzed for Susceptibility to Single Failure
| | | 05000254/LER-1996-012-02, :on 960620,diesel Fuel Oil Transfer Piping Noted in Unanalysed Condition Due to an Incomplete Safety Classification Upgrade.Minor Mod Has Been Completed Which Removes Autofill Capability for Fire Pump Day Tanks |
- on 960620,diesel Fuel Oil Transfer Piping Noted in Unanalysed Condition Due to an Incomplete Safety Classification Upgrade.Minor Mod Has Been Completed Which Removes Autofill Capability for Fire Pump Day Tanks
| | | 05000254/LER-1996-012, Forwards LER 96-012-00,for Quad Cities Nuclear Power Station.Review Plan Will Be Prepared to Identify Open Items within Component Classification Program & Ensure Resolution of Items.Plan Will Be Completed by 970301 | Forwards LER 96-012-00,for Quad Cities Nuclear Power Station.Review Plan Will Be Prepared to Identify Open Items within Component Classification Program & Ensure Resolution of Items.Plan Will Be Completed by 970301 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000254/LER-1996-013-01, :on 960808,zebra Mussels Were Discovered on Fire Pump Suction Strainers.Caused by Inadequate Insp Frequency of Fire Pump Suction Strainers.Divers Removed & Cleaned Zebra Mussels from Fire Pump Suction Strainers |
- on 960808,zebra Mussels Were Discovered on Fire Pump Suction Strainers.Caused by Inadequate Insp Frequency of Fire Pump Suction Strainers.Divers Removed & Cleaned Zebra Mussels from Fire Pump Suction Strainers
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(B) | | 05000254/LER-1996-013, Forwards LER 96-013,Rev 0 IAW Requirements of 10CFR50.73(a)(2)(i)(B).Commitments Made by Ltr,Listed | Forwards LER 96-013,Rev 0 IAW Requirements of 10CFR50.73(a)(2)(i)(B).Commitments Made by Ltr,Listed | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000254/LER-1996-014, Forwards LER 96-014-00.All Personnel Will Be Briefed in Event by 961215,reinforcing Expectations to Initiate Procedure Changes When Needed | Forwards LER 96-014-00.All Personnel Will Be Briefed in Event by 961215,reinforcing Expectations to Initiate Procedure Changes When Needed | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000254/LER-1996-014-03, :on 960927,electrical Distribution Weekly Surveillance Did Not Document Voltage Verification Due to an Inadequate Procedure.Qcos 0005-06 Has Been Revised to Ensure Verification of Proper Voltages |
- on 960927,electrical Distribution Weekly Surveillance Did Not Document Voltage Verification Due to an Inadequate Procedure.Qcos 0005-06 Has Been Revised to Ensure Verification of Proper Voltages
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000254/LER-1996-015-01, :on 960816,HPCI Sys Jet Impingement Support Baseplate/Concrete Expansion Anchors Were Improperly Installed,Due to Ineffective Work Practices & QA Program. Review Will Be Completed |
- on 960816,HPCI Sys Jet Impingement Support Baseplate/Concrete Expansion Anchors Were Improperly Installed,Due to Ineffective Work Practices & QA Program. Review Will Be Completed
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) | | 05000254/LER-1996-015, Forwards LER 96-015-00.Commits to Completion Review of All Pipe Whip & Vibration Restraint Configuations by 961231 | Forwards LER 96-015-00.Commits to Completion Review of All Pipe Whip & Vibration Restraint Configuations by 961231 | 10 CFR 50.73(a)(2)(1) | | 05000254/LER-1996-016-01, :on 960823,secondary Containment Would Not Have Satisfied All UFSAR Requirements,Due to Siding Explosion Bolts Which Were Damaged by Either High Winds or Ineffective Work Pratices.Damaged Bolts Replaced |
- on 960823,secondary Containment Would Not Have Satisfied All UFSAR Requirements,Due to Siding Explosion Bolts Which Were Damaged by Either High Winds or Ineffective Work Pratices.Damaged Bolts Replaced
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000254/LER-1996-017, Forwards LER 96-017-00,for Quad Cities Nuclear Power Station.Review Plan Will Be Prepared to Identify Open Items | Forwards LER 96-017-00,for Quad Cities Nuclear Power Station.Review Plan Will Be Prepared to Identify Open Items | 10 CFR 50.73(a)(2)(iv), System Actuation | | 05000254/LER-1996-017-01, :on 960825,manual Scram Taken During Reactor Startup When Reactor Water Level Increased Following Unplanned Opening of All Main Turbine Bypass Valves Occurred,Due to Inadequate Procedures.Procedures Revised |
- on 960825,manual Scram Taken During Reactor Startup When Reactor Water Level Increased Following Unplanned Opening of All Main Turbine Bypass Valves Occurred,Due to Inadequate Procedures.Procedures Revised
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2) | | 05000254/LER-1996-018, Forwards Supplemental Info Re LER 96-018-00,correcting Editorial Error | Forwards Supplemental Info Re LER 96-018-00,correcting Editorial Error | | | 05000254/LER-1996-018-01, :on 960903,TS Surveillance Requirements Were Misinterpreted Due to Conservative Misunderstanding of Requirement.Memo Was Written to Explain Which Min TS Surveillances Must Be Performed Re Mode Switch |
- on 960903,TS Surveillance Requirements Were Misinterpreted Due to Conservative Misunderstanding of Requirement.Memo Was Written to Explain Which Min TS Surveillances Must Be Performed Re Mode Switch
| 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) | | 05000254/LER-1996-019, Forwards LER 96-019 IAW Requirements of 10CFR50.73(a)(2)(ii)(B) & Discusses Listed Commitments | Forwards LER 96-019 IAW Requirements of 10CFR50.73(a)(2)(ii)(B) & Discusses Listed Commitments | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000254/LER-1996-019-01, :on 960904,main Steam Line Radiation Monitor Functional Test Was Not Performed within Frequency Established for TS When in Refueling Mode Due to Incomplete Documentation of TS Interpretation.Qcap 2300-11 Was Changed |
- on 960904,main Steam Line Radiation Monitor Functional Test Was Not Performed within Frequency Established for TS When in Refueling Mode Due to Incomplete Documentation of TS Interpretation.Qcap 2300-11 Was Changed
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000254/LER-1996-020, Forwards LER 96-020-00.Commitments Included in LER & Submitted | Forwards LER 96-020-00.Commitments Included in LER & Submitted | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000254/LER-1996-020-01, :on 960907,CR Emergency Filtration Sys Declared Inoperable.Caused by Operator Knowledge Weakness.Operators Declared CR Emergency Filtration Sys Inoperable & Entered 14-day LCO |
- on 960907,CR Emergency Filtration Sys Declared Inoperable.Caused by Operator Knowledge Weakness.Operators Declared CR Emergency Filtration Sys Inoperable & Entered 14-day LCO
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000254/LER-1996-021-01, :on 961011,B CR HVAC Sys Was Declared Inoperable Due to Crankcase Heater Power Supply Design Deficiency.Design Change Notice 9600380 Issued,Which Replaced Crankcase Heater W/Safety Related Heater |
- on 961011,B CR HVAC Sys Was Declared Inoperable Due to Crankcase Heater Power Supply Design Deficiency.Design Change Notice 9600380 Issued,Which Replaced Crankcase Heater W/Safety Related Heater
| | | 05000254/LER-1996-021, Forwards LER 96-021-00,for Quad Cities Nuclear Power Station.No Commitments Being Made | Forwards LER 96-021-00,for Quad Cities Nuclear Power Station.No Commitments Being Made | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000254/LER-1996-022-01, Extends Commitment Date for Completing Rev to Plant CR Dose Analysis of Record,Per LER 96-022-01 | Extends Commitment Date for Completing Rev to Plant CR Dose Analysis of Record,Per LER 96-022-01 | | | 05000254/LER-1996-023-01, :on 961124,CR Emergency Filtration Sys Failed to Maintain Required Airflow Due to Cognitive Personnel Error.Instrument Loop for Gauge Fi 1/2-5795-307 Calibr |
- on 961124,CR Emergency Filtration Sys Failed to Maintain Required Airflow Due to Cognitive Personnel Error.Instrument Loop for Gauge Fi 1/2-5795-307 Calibr
| | | 05000254/LER-1996-023, Provides Commitments Re LER 96-023.Predefined Model Work Request Which Initiates Perodic Maint Procedure Initiated | Provides Commitments Re LER 96-023.Predefined Model Work Request Which Initiates Perodic Maint Procedure Initiated | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000254/LER-1996-025, Forwards LER 96-025-00 Re Operability Calculations Performed on ECCS Suction Strainers W/Incorrect Head Loss Values | Forwards LER 96-025-00 Re Operability Calculations Performed on ECCS Suction Strainers W/Incorrect Head Loss Values | | | 05000254/LER-1996-025-01, :on 961220,discovered Original Value for Strainers Head Loss Incorrect.Cause Could Not Be Determined. Training Provided for Operators to Recognize Pump Cavitation During Design Basis Accidents |
- on 961220,discovered Original Value for Strainers Head Loss Incorrect.Cause Could Not Be Determined. Training Provided for Operators to Recognize Pump Cavitation During Design Basis Accidents
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) |
|