IR 05000423/1985060

From kanterella
(Redirected from ML20133Q118)
Jump to navigation Jump to search
Insp Rept 50-423/85-60 on 850826-30,0912-13 & 18-19.Major Areas Inspected:Engineering Assurance in-depth Technical Audit 59 Results & Corrective Actions
ML20133Q118
Person / Time
Site: Millstone Dominion icon.png
Issue date: 10/16/1985
From: Imbro E, Milhoan J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To:
Shared Package
ML20133Q110 List:
References
50-423-85-60, NUDOCS 8511010396
Download: ML20133Q118 (14)


Text

.

-

.

.-

__

-

,

.

.

U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT

.

Division of Quality Assurance, Vendor, and Technical Training Center Programs Report No.:

50-423/85-60 i

Docket No.:

50-423 Licensee:

Northeast Utilities Service Company i

Facility Name:

Millstone Unit No. 3 I

Inspection At:

Millstone Unit No. 3 Site, Waterford, Connecticut

Inspection Conducted:

August 26 through August 30, 1985 September 12 and 13, 1985 Septer.:er 18 and 19 1985 Inspection Team Members:

Team Leader:

E. Imbro, Senior Inspection Specialist, IE

,

Mechanical Systems:

T. DelGaizo, Consultant, WESTEC Services

Mechanical Components:

J. Blackman, Consultant, WESTEC Services Civil / Structural:

I. Husain, Consultant, SMA of Conn.

i A. Unsal, Consultant, HARSTEAD Engineering

'

Electrical:

C. Crane, Consultant, WESTEC Services G. Lewis, Inspection Specialist, IE Instrumentation and J. Kaucher, Consultant, WESTEC Services

~

Controls:

Present at August 30, 1985 J. Milhoan, Section Chief, IE j

Exit Briefing:

$ b 'h

/eff ff

Eugene V. Imbro Inspection Leader, IE i

('

Approved by:

nl L

s w l0lN/$I

,

a

'

& mes L. Milhoan'

ction Chief, QA Branch 8511010396 851020 PDR ADOCK 05000423 G

PDR

.

._

__

_

-

.

Mr. J. F. Opeka-4-Distribution J. M. Taylor, IE

.R.

H. Vollmer, IE B. K. Grimes, IE J. G. Partlow, IE G. T. Ankrum, IE

J. L. Milhoan, IE E. V. Imbro, IE G. S. Lewis, IE DCS 016 (Docket No. 50-423)

QAB Reading

DQAVT Reading j

E. C. Wenzinger, RI

.

B. J. Youngblood, NRR

'

B. Doolittle, NRR NRC PDR

"

Local PDR H. Thompson, NRR

',

T. E. Murley, RI R. Starostecki, RI T. M. Novak, NRR

W. Butler, NRR AEOD

'2LD NMSS i

RES ACRS (10)

NSIC NTIS

-

i Regional Administrators

,

Regional Division Directors

,

T. Speis, NRR

!

E. L. Jordan, IE i

J. Axelrad, IE

Team Members i

H. Boulden, DIA SECY OPE W. J. Dircks, ED0 H. R. Denton, NRR

,

OCA (3)

)$

h

'

IE:DQAVT: AB

QAVT:QAB IE-JAVT:QAB:C r0 VT:D EVImbro f-(d._

IE:DQAVT:QAB

/

J ilhoan n krum KG mes GSLewis:hmc 10/f/85 10/f/85 10 g /85 0 V85 10/t1/85

!

!

. _ _ _ _.. __

. -..

_ _..-

-___.

-- ___-- - -. _

_ _ _., - - - -

-.

- -.

..

..

.

.

_

_

_

_.

l

.

MILLSTONE UNIT N0. 3 Engineering Assurance In-Depth Technical Audit No. 59 Results and Corrective Action Inspection Report 50-423/85-60

.

August 26 through August 30, 1985

'

September 12 and September 13, 1985 September 18 and 19, 1985 1.

Background NRC inspection activities related to the Millstone 3 Engineering Assurance In-Depth Technical Audit were conducted in three phases:

!

1.

Inspection of program preparations 2.

Inspection of program implementation

!

3.

Inspection of audit results and corrective action The first phase of the inspection was accomplished on May 28 and May 29, 1985. The NRC's report of that inspection (50-423/85-29) was forwarded to Northeast Nuclear Energy Company (NNECo) via letter dated June 21, 1985 (B. K. Grimes [NRC] to J. F. Opeka [NNEco]).

The second phase of the

inspection was accomplished on June 24 through June 28, 1985.

The NRC's

!

report of that inspection (50-423/85-31) was forwarded to Northeast Nuclear Energy Company (NNECo) via letter dated July 19, 1985 (8. K. Grimes [NRC] to

J. F. Opeka [NNECo]). The third phase of the inspection which is the i

subject of this report was conducted in three segments on the dates shown

.

I in the heading.

2.

Purpose The purpose of this inspection was to accomplish the third phase of the NRC inspection, namely inspection of the audit results and corrective action.

Specifically, the objectives of this inspection were to (1) review the audit team findings, (2) ensure that the various resolutions of the findings were adequate, (3) ensure proposed corrective actions were adequate, and (4)

j verify that the items identified in inspection reports 50-423/85-29 and

,

50-423/85-31, were incorporated into the program or otherwise satisfactorily

'

resolved.

The purpose of this report is to provide resolution of the items

)

identified in the previous. inspection reports.

The results of the inspec-tion of the other aspects of the Millstone Unit 3 Engineering Assurance

!

In-Depth Technical Audit will be provided in a Supplemental Safety Evalua-tion Report (SSER).

l 3.

Personnel Contacted

!

A large number of NNECo and SWEC personnel were contacted during the course

of the NRC's inspection.

The following is a brief list of key personnel involved:

Name Organization Position

A. Capozzi SWEC Ass't Chief Engineer, EA 0. Malone SWEC

' Audit Team Leader i

R. Ackley SWEC Project Engineer

'

R. Fortier SWEC Mechanical Auditor T. Morse SWEC I&C Auditor C. Ferguson SWEC Pipe Stress Auditor R. Sexton SWEC Pipe Support Auditor N. Goldstein SWEC Equipment Qualification (Seismic) Auditor

!

. -.

..

.

-.

.

. _ -

. -..

.. -

.

. -

-

.

.

_ __

__

.

Name Organization Position F. Chin SWEC Structural Auditor i

A. Papp SWEC Electrical Auditor C. Morrell SWEC Hazards Program Auditor D. Norquist NNECo Manager, QA 4.

STATUS OF NRC INSPECTION ITEMS FROM INSPECTION REPORT 50-423/85-29 DATED

JUNE 21, 1985.

!

Item No.

Subject Status Original Comment / Resolution

!

Mechanical Systems 1.1 E&DCR and N&D Review Closed Wording of some attributes of E&DCR and N&D Review Plans was

open to interpretation.

Review Plans were reviewed and the

>

ambiguities were eliminated.

I 1.2 Calculations Review Closed Review Plan did not specifically Plan address:

(1) Assumptions needing later verification, and (2) Assess-i ment of the appropriateness of computer codes.

Review Plans were revised to incorporate these comments.

1.3 Calculations Closed Some non-safety-related equipment was selected for review.

The non-safety-related equipment was dropped from the review and additional

.1 safety-related equipment was added.

-

.

1.4 Hazards Review Plan Closed Audit was not reviewing the design I

process for Seismic II/I hazards l

protection.

Applicant took a different approach to the Seismic

II/I design, that is similar to

.

that used for SEP plants.

,

This item has been referred to NRR i

for resolution as an open licensing issue.

It is closed for purposes l

of this report.

Mechanical Components 2.1 Scope of Equipment Closed The scope of review of the equipment Qualification Review qualification area (seismic) was too Plan narrow to draw meaningful conclusions.

The Review Plan was revised to encompass all requirements and expand on interfaces.

-2-

. -. -

.

-

-

.

-.

- _ - _ _. - -..

_ _ _ - - _. _ -..

- -....... - -. - - - _. - _ _ -

-

. - _.

._..

-

-

_

__

'Y

.

.

Item No.

Subject Status Original Comment / Resolution

. 2. 2 RP #1907-1-Seismic Closed A checklist specifically for seismic i

Qualification and pressure boundary considerations was not developed.

m,

Checklists were developed for seismic and pressure boundary

' s considerations.

,

2.3 RP #1901 - Consistency Closed Inclusion of NRC Regulatory Guides Between Design and 1.60 and 1.122 was not germane to FSAR Subject Chosen the review of pipe stress and pipe support design.

Other suitable Regulatory Guides

,

i were included.

2.4 Selection of NSSS Closed The items selected for review Criteria Items appeared to be limited.

'

The NSSS interface was expanded to l

include modeling requirements.

l

!

2.5 RP 1903-1 - Additional Closed The pipe stress analysis checklist

!

Requirements Regarding did not address a number of techni-Calculton Review cal areas which are normally essential to adequate design.

The checklist was revised to include the additional areas of concern.

2.6 Small Bore Piping Closed The basis for maximum span length Calculation Review tables used in the design and

,

l installation of small bore piping

'

'

was not reviewed.

,

Only one piping run was designed per the spacing tables; therefore, the above review was not necessary.

2.7 Comprehensive Review Closed Questions concerning the correct of the Use of Computer app 1' cation of the computer codes Codes (NUPIPE and STRUDL) and the determination of the effects of known errors found in the code were

.

not addressed.

A review of NUPIPE and STRUDL was performed.

2.8 Adequacy of E&DCR and Closed The review of E&DCR's and N&D's did N&D Preparation not consider the' completeness of the

!

problem posed and whether all inter-

'

discipline considerations had been included,

-

i

!

-3-

.

. -

_

_, _ _ -_. _ _ _

_

_ _ _ _ _,

_ _ _. _ _ _ _ ~.

__..

-..

.

.

Item No.

Subject Status Original Comment / Resolution

.

The scope of review was revised to

.

i include problem description and interdiscipline review.

!

Civil / Structural

3.1 Containment Liner Closed The containment liner is subject i

Plate Analysis to pressure and thermal expansion /

contraction loads.

It was therefore

.

,

important to verify that adequate

'

design calculations had been per-formed to ensure the integrity of the liner plate.

,

The EA team reviewed the appropriate calculations and found them to be adequate.

3.2 Seismic Analysis of Closed The adequacy of the seismic analysis Containment Structure of the containment structure needed to be verified.

The seismic analysis and response spectra development was verified by the audit team.

j 3.3 Verification of Closed The computer programs used in the Computer Programs seismic analysis and in generating

-

seismic spectra were not being i

verified.

The computer programs used in seismic analysis have been reviewed for

~

verification and qualification, j

3.4 Design Verification of Closed The design criteria and design calcu-

!.

the Refueling Water lations for the RWST were not being Storage Tank (RWST)

reviewed to verify the tank's ability to withstand tornado missile and l

seismic loads.

Further, the ability

of the model of the RWST to adequately account for sloshing of water inside the tank during a seismic event was not being reviewed.

'

'

The review of the analysis and design of the RWST was included in the audit team review.

.

h 4-

-

~.

.

, _,

, ~ - - - -. _ _,. _. _ _. -

_

_. -

_ _.

.., _. - -

_~,,---._,,,,.,,m._,---u

._._v_

, _ ~. _

,,

y

,

.

.-

_

..

.

Item No.

Subject Status Original Comment / Resolution

  • 3. 5 FSAR Requirement Closed Analytical documentation concern-ing whether gaps provided between adjacent structures were adequate to preclude impacting during a seismic event was not being reviewed.

The audit team reviewed the shake space requirements for the con-tainment structure.

3.6 Conduit / Cable Tray Closed Cable tray design criteria documents Supports were not being reviewed to verify consistency with analytical and test work.

Also the data transmitted between electrical, EMD, and the structural group was not being reviewed for consistency.

The audit team included these items in their review of the design of conduit and cable tray supports.

Electric Power and Instrumentation and Controls 4.1 Items Not Included Closed The scope of the review plans did

,

in Review not always include all items or

elements considered to be essential.

"

The review plans were revised to address additional items and elements of the design process.

.

i 5.

STATUS OF NRC INSPECTION ITEMS FROM INSPECTION REPORT 50-424/85-31 DATED JULY 19, 1985.

Item No.

Subject Status Original Comment / Resolution 1.

Mechanical Systems t

1.1 Calculation Review Closed Several calculations were reviewed by the NRC reviewer to see if NRC would arrive at the same con-clusions as those reached by the EA audit team.

No concerns were identified by this review so that this item was closed out in the original inspection report.

-5-

-. _.

_

_

_

_

__

_ _ _ _ _.

_- -

.

-

_

_

.

Item No.

Subject Status Original Comment / Resolution

  • 1. 2 Environmental Closed A review of the Equipeent Qualifi-Qualification cation Report to demonstrate the of RSS Pumps environmental qualification of the RSS pumps determined that the report used the environmental temperature of the cubicle (120 F) rather than that of the recirculating fluid (peak temp. 240 F with temperatures above 150 F for 30 minutes).

Some components of the RSS pump are qualified for 194 F.

In addition, the generic implications needed to be addressed.

An Action Item was generated by the audi', team regarding this item.

The Prvject's response was rejected.

An audit observation was issued by the EA team which includes generic

!

implications to track this item.

l

'

1.3 Hazards (HELB/MELB)

Closed The HELB/MELB portion of the hazards review plan was not ready for review.

The implementation portion of the plan could not be verified.

The hazards review plan is now com-plete including the implementation portion of the plan.

1.4 RSS Thermal Closed Calculation US(B)-273 Rev 3, which Performance should verify that the RSS is capable

-

of meeting design commitments, had not been reviewed by the EA audit team.

,

Calculation US(B)-273 Rev 3 has been reviewed by the EA audit team.

l 1. 5 ESF Building Closed The EA team auditor had questioned Environment the project's assertion that there are no high energy line breaks to be considered in the ESF Building, however no action item vas prepared to track this item.

An action item was prepared to document and track this concern.

-6-

__

_

.

.

Itym No.

Subject Status Original Comment / Resolution 1.6

Inspection Report

Closed

As of the date of the inspection

No. 50-423/85-29

Observation No. 1.4, relative to

non auditing of the Seismic II/I

hazards protection, was unchanged

and remained an open item.

This item has been referred to NRR

for resolution as an open licensing

issue.

It is closed for purposes

of this report.

2.

Mechanical Components

l

2.1

Mechanical

Closed

The mechanical qualification

Qualification

aspects (seismic and ASME III Code

of Equipment

conformance) of the equipment

qualification review plan were

unauditable.

The review plans were revised to

be more comprehensive and are now

acceptable.

2.2

E&DCR Review - Piping

Closed

The review of piping E&DCRs did

not verify that changes were ade-

quately reflected in appropriate

design documents.

The audit was expanded to address

this concern.

,

2.3

Implementation of

Closed

Several pipe support related

.

FSAR Commitments

licensing commitments referenced in

,

the FSAR were found to be absent

from the project implementation

document.

The reviewer had not

.

determined this from his review.

This indicated a need for a more

thorough review of the FSAR

commitments.

Review plan 1901 now thoroughly

examines the FSAR commitments.

-7-

... -

_.

_ _ _.

_

_

-.

_-

-. _

_-

-..

- - _ _ -

_

.

I

Item No.

Subject

Status

Original Comment / Resolution

  • 2.4

Pipe Support

Closed

A pipe support calculation

Calculations

had been reviewed by the

EA audit team and was found

adequate.

However, the NRC

reviewer found the combination

of loads was not developed in

a conservative manner, and

that several attributes basic

to confirming the calculation

adequacy were not reviewed.

The EA audit team has now per-

formed a comprehensive review

of the pipe support calculat. ions

to satisfy the review checklist

requirements and found them

to be satisfactory.

Civil / Structural

l

3.1

Containment Liner

Closed

NRC reviewer indicated additional

review of EA audit team action

item S-010 and the project response

was needed.

This action item dealt

with calculations EA-11 and EA-15.

The EA audit team performed an

additional review and found the

'

two above calculations appropriate

for the containment liner design.

This removes NRC concern on this

matter.

'

,

b

-8-

._

-

_

...

.

--

- -. - - - - -

--.-.

-

-

..

.-.

.

.

Item No.

Subject

Status

Original Comments / Resolution

  • 3.2

Structural Steel

Closed

It was not apparent that the

Connection Design

structural steel load tracking

program addressed structe al

steel connections and anchorage

loads.

The EA audit team reviewed the

steel connection design.

4.

Electric Power

4.1

Motor Data

Closed

The results of a review of

Specification 2362.200-164

were not correlated with the

data obtained from a walkdown

of the system.

The NRC

reviewer noted the valve data

sheet, electric motor and load

list, vendor drawings and one

line drawings have motor data

different from the nameplate

data.

An action item was prepared to

track this observation.

The

project has initiated a walk-

down procedure to verify motor

nameplate data.

"

4.2

Reduced Voltage

Closed

The EA reviewer noted a 70%

Starting of Motor

minimum starting voltage for

Operated Valves (MOV)

MOVs in the review of Specifi-

cation 2362.200-164.

However,

,

no further review was conducted

to determine whether the MOVs

supplied were in compliance

with this specification.

In

addition, the environmental

qualification test report

indicated that the lowest

voltage these MOVs were tested

to was 490 V ac. Action should

have been taken to ensure these

valves are qualified.

,

_9_

.

.

Item

Subject

Status

Original Comment / Resolution

4.2

Closed

for operation at reduced

voltage accident conditions.

Follow-up review was expanded

to include MOVs furnished by

other vendors to ensure that

the environmental qualifica-

tion of those MOVs and the

supporting documentation

demonstrated that the MOVs will

function as required under

reduced voltage conditions

consistent with the FSAR,

design commitments and

specifications.

4.3

Environmental

Closed

The equipment being reviewed for

Qualification

environmental qualification were

of Equipment

essentially in mild environment

areas.

It was recommended that

power cables and control cables

located in harsh environments be

evaluated.

The EQ review plan was revised to

include equipment in harsh environ-

ments.

5.

Instrumentation and

Controls

5.1

Calculations Selected

Closed

The controls discipline selected

for Review

one calculation for review and it

,

was found to be deficient in a number

of areas.

Consequently, it was

recommended that additional calcu-

lations be reviewed to determine if

there are generic problems in the

performance of controls discipline

calculations.

Audit Observat.an 161 was written

to track this observation.

Additional

calculations were reviewed.

Since

this item is being tracked by

A0 161, it is closed for purposes

of this report.

- 10 -

.-

.

.

-

_

-. -

.

.

Item No.

Subject

Status

Original Comment / Resolution

.

5.2

Barton Flow Instrument

Closed

The EA auditor found that 3RSS*FIS

Switch (FIS) Environ-

38A (control switch for the minimum

i

'

mental Qualification

flow recirculation valve) environ-

mental qualification documentation

was inadequate.

The required audit

forms were not completed and no

action item was generated on the

noted deficiency.

The project had previously issued

E&DCR T-C-05967 which will replace

'

the Barton FIS with a Rosemount

Model 1154 transmitter.

Rosemount

report D8400102 qualifies this model

to the requirements of IEEE 323 & 324

for use in Class 1E applications.

5.3

Use of Underrated

Closed

N&D 11,436 allows the use of under-

Terminal Blocks

rated terminal blocks (360V vs.

480t) for 3RSS*MOV 23C valve operator.

It is not clear that the EA team

should have accepted the conclusion

that the terminal blocks were

adequate for use without further

evaluation of the technical basis.

Adequate technical justification

was obtained by the EA audit team

for the use of underrated terminal

blocks.

The MOVs inside containment

have been modified to eliminate the

use of Marathon terminal blocks and

~

that Marathon terminal blocks have

been qualified for 460V motor leads

in non-LOCA and non-HELB areas.

5.5

Qualified Life of

Closed

The environmental qualification

Equipment Items

package for the pressure transmitter

3RSS*PT 25A (Rosemount Model 1153)

does not establish a qualified

life of the item.

The environ-

mental qualification reviewer did

not question the absence of this

information nor did he prepare an

action item questioning qualified

life.

The EA audit team review of the

environmental qualification

package for pressure transmitter

3RSS*PT 25A was subsequently found

acceptable.

- 11 -

--.

___

_ -

.

..

.

-

<

.

.

Mr. J. F. Opeka

-3-

.

cc:

Gerald Garfield, Esq.

Day, Berry & Howard

City Place

'

Hartford, Connecticut 06103-3499

Mr. Maurice R. Scully, Executive Director

Connecticut Municipal Electric

Energy Corporation

268 Thomas Road

Groton, Connecticut 06340

Robert W. Bishop, Esq.

Corporate Secretary

Northeast Utilities

Post Office Box 270

Hartford, Connecticut 06141

Mr. T. Rebelowski

Senior Resident Inspector Office

U.S. Nuclear Regulatory Commission

Millstone III

P.O. Box 615

-

'

Waterford, Connecticut 06385

Mr. Michael L. Jones, Manager

Project Management Department

Massachusetts Municipal Wholesale

'

Electric Company

P.O. Box 426

-

Ludlow, Massachusetts 01056

r

WLu

Regional Administrator

U.S. NRC, Region I

631 Park Avenue

King of Prussia, Pennsylvania 19406

Mr. Karl Abraham

Public Affairs Office

U.S. Nuclear Regulatory Commission

Region I

King of Prussia, Pennsylvania 19406

l

- - -

_

-

_ - _.

..