See also: IR 05000423/1985060
Text
I
.Dcs
.
8
'o
UNITED STATES
g
E
NUCLEAR REGULATORY COMMISSION
g
E
W ASHINGToN, D. C. 20555
g
\\...../
OCT 2 3 1985
Northeast Utilities Service Company
ATTN:
Mr. J. F. Opeka
Senior Vice President
Nuclear Engineering and Operations
P. O. Box 270
Hartford, CT 06141-0270
Gentlemen:
SUBJECT:
MILLSTONE UNIT 3 PROJECT AUDIT NO. 59 RESULTS AND
CORRECTIVE ACTIONS INSPECTION REPORT 50-423/85-60
This letter conveys the results and conclusions of the inspection of the audit
results and corrective actions of Northeast Utilities Service Company's (NUSCO)
Engineering Audit No. 59 of Millstone Unit 3 Project dated August 16, 1985.
The inspection was conducted by the NRC's Office of Inspection and Enforcement
from August 26 through August 30, 1985, September 12 and 13, 1985, and
September 18 and 19, 1985, at the NUSCO Millstone Unit 3 Project construction
site in Waterford, Connecticut.
The inspection team was composed of personnel
from NRC's Office of Inspection and Enforcement and consultants.
The specific objectives of this inspection were to (1) review the audit team
findings, (2) ensure the resolution of the findings were adequate, (3) ensure
proposed corrective actions were adequate, and (4) verify that the items identi-
fied in NRC Inspection Reports 50-423/85-29 and 50-423/85-31, were incorporated
"
into the program or otherwise satisfactorily resolved.
The purpose of this
report is to provide the status of NRC Inspection Items identified in the
previous inspection reports.
The results of the inspection of the other aspects
of Millstone Unit 3 Engineering Assurance In-Depth Technical Audit will be pro-
vided in a Supplemental Safety Evaluation Report (SSER).
The status of NRC Inspection Items from Inspection Reports 50-423/85-29 dated
June 21, 1985 and 50-423-31 dated July 19, 1985 are given in the attached
j
inspection report.
All NRC action items identified in these two previous
inspection reports were closed.
Stone and Webster Engineering Corporation has published two additional reports
in order to complete the Engineering Assurance Program for Millstone Unit 3
f
Project; a Corrective Action Status Report and a Phase II Report.
Your correc-
.
tive action status report will be evaluated to determine whether resolution of
I
audit observations from Technical Audit No. 59 has been accomplished and the
safety significance of any resulting hardware changes has been assessed.
The
,
Millstone EA Phase II report will be assessed by the staff to reach an overall
,
!
'
8511010392 851028
ADOCK 05000423
G
- - . . - .
_ - _ - , , - -
, _ - - - . _ - . - _ _ - _ . - _ . - _ - - _ . _ - -
.-
.- .
.
_ ..
.
_- -
.-
- - .
..
.-
.
.
l'
1
i
Mr. J. F. Opeka
-2-
1
conclusion on the adequacy and implementation of the design process for the
Millstone Unit 3 project.
The results of our review of these reports will
'
l
be addressed by the SSER.
.
Sincerely,
!
c>
'
'
j
/
~
!
m
Brian K. Grimes, Director
'
Division of Quality Assurance, Vendor,
and Technical Training Center Programs
Office of Inspection and Enforcement
,
.
Enclosure:
{
Results and Corrective Actions
4
Inspection Report 50-423/85-60
cc: w/ enclosure