ML20086R554
ML20086R554 | |
Person / Time | |
---|---|
Site: | Beaver Valley |
Issue date: | 07/20/1995 |
From: | DUQUESNE LIGHT CO. |
To: | |
Shared Package | |
ML20086R552 | List: |
References | |
NUDOCS 9507310182 | |
Download: ML20086R554 (53) | |
Text
DPR-66 3/4,8 ELECTRICAL POWER SYSTEMS s
3/4.8.1 A.C. SOURCES OPERATING l
LIMITING CONDITION FOR OPERATION '
3.8.1.1 As a minimum, the following A.C. electrical power sources shall be OPERABLE
- l l
- a. Two physically independent circuits between the offsite transmission network and the onsite class 1E distribution ;
system, and '
- b. Two separate and independent diesel generators each with:
- 1. Separate day and engine-mounted fuel tanks containing a minimum of 900 gallons of fuel,
- 2. A separate fuel storage system'containing a minimum of 17,500 gallons of fuel, and
- 3. A separate fuel transfer pump.
APPLICABILITY: MODES 1,2,3 and 4.
hkCTION:
- a. With either an offsite circuit or diesel generator
- of the above required A.C. electrical power sources inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirements 4.8.1.1.1.a and i 4.8.1.1.2.a.5 within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; restore at least two offsite circuits and two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
- b. With one offsite circuit and one diesel generator
- of the above required A.C. electrical power sources inoperable, demonstrate 'the OPEEABILITY of the remaining A.C. sources by performing Surveillance Requirements 4.8.1.1.1.a and 4.8.1.1.2.a.5 within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; restore at least one of the inoperable sources to OPERABLE status within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or be in COLD SHUTDOWN '
within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Restore at least two offsite circuits and two diesel generators to OPERABLE status within SHUTDOWN 72hoursfromthetimeofinitiallossorbeinCOLD) within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. j
$EPL ACE (d O'N I N SER T "A" ,
I BEAVER VALLEY - UNIT 1 3/4 8-1 Amendment No.
9507310182 950720 *I*
t
f DPR-66 I s ELECTRICAL POWER SYSTEMS ~ bMb N ACTION (Continued)
@MT @h \, '
%1
- c. With two of the above required Offsite A.C. circuit inoperable, demonstrate the OPERABILITY of two diesel ;
generators by performing Surveillance Requirement 4.8.1.1.2.a.5 within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> ;
thereafter, unless the diesel generators are already ;
operating; restore at least one of the inoperable offsite !
sources -to OPERABLE Status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at '
least HOT STANDBY within the next 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. With only one offsite source restored, restore at least two offsite i circuits to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from time of i initial loss or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
- d. With two of the above required diesel generators * '
inoperable, demonstrate the OPERABILITY of two offsite A.C.
circuits by performing Surveillance Requirement 4.8.1.1.1.a i
within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; !
} restore at least one of the inoperable diesel generators to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Restore at least two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from time of )
initial loss or be in COLD SHUTDOWN within the next 36 ) !
hours. j i SURVEILLANCE REQUIREMENTS '
i 4.8.1.1.1 Two physically independent circuits between the offsite transmission network and the onsite Class 1E distribution system shall be:
- a. Determined OPERABLE at least once per 7 days by verifying ,
correct breaker alignments, indicated power availability, and j
- b. Demonstrated OPERABLE at least once per 18 months by I transferring (manually and automatically) unit power supply ,
from the unit circuit to the system circuit. ;
4.8.1.1.2 Each diesel generator shall be demonstrated OPERABLE:
- a. At least once per 31 days on a STAGGERED TEST BASIS by:
- 1. Verifying the fuel level in the day and engine-mounted I fuel tank,
- 2. Verifying the fuel level in the fuel storage tank, r
g
- Fuel oil contained in the storage tanks not meeting properties the] -
in accordance with 4.8.1.1.2.d.2 or 4.8.1.1.2.e be brought within the specified limits within 7 days.
shall )
f l BEAVER VALLEY - UNIT 1 3/4 8-2 Amendment No.
AEMtE wrTH (f tuon)." )
"T MEAT *A"
l i
Att'achment to A.C. Sources - Operatina I Insert "A" l l
ACTION:
I
- a. With one offsite circuit inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirement 4.8.1.1.1.a within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and at 1 least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter.
Restore the offsite circuit to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
- b. With one diesel generator (1) inoperable, demonstrate the OPERABILITY of the A.C. offsite sources by performing Surveillance Requirement 4.8.1.1.1.a within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; and if the diesel generator became inoperable due to any cause other than an independently testable component, testing or preplanned preventative maintenance, demonstrate the OPERABILITY of the remaining OPERABLE diesel generator by perform:
Surveillance Requirement 4.8.1.1.2.a.5 within 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />shgg>
unless the absence of any potential common mode failure for the remaining diesel generator is demonstrated. Restore the diesel generator to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
- c. With one offsite circuit and one diesel generator (1) inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; and if the diesel generator became inoperable 1 due to any cause other than an independently testable component, testing or preplanned preventative maintenance, demonstrate the OPERABILITY of the remaining OPERABLE diesel generator by performing (2) Surveillance Requirement 4.8.1.1.2.a.5 within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> unless the absence of any potential common mode failure for the remaining diesel generator is demonstrated. Restore one of the inoperable sources to OPERABLE status within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. Restore the other A.C. power source (offsite circuit or diesel generator) to OPERABLE status in accordance with the provisions of Action Statement a or b, as appropriate with the time requirement of that Action Statement based on the time of initial loss of the remaining inoperable A.C. power source. A successful test of diesel OPERABILITY per Surveillance Requirement 4.8.1.1.2.a.5 performed under this Action Statement for an OPERABLE diesel or a restored to OPERABLE diesel satisfies the diesel generator test requirement of Action Statement b.
BEAVER VALLEY - UNIT 1 (Proposed Wording) Page 1 of 2
i Att'achment to A.C. Sources - Operatina I
Insert "A" (Continued) j ACTION (Continued 1 ,
i
- d. With two of the required offsite A.C. circuits inoperable, restore one of the inoperable offsite sources to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. Following restoration of one offsite source, follow Action Statement a with the time requirement of that Action Statement based on the time of initial loss of the remaining inoperable offsite A.C. circuit.
- e. With two of the required diesel generators (l) inoperable, demonstrate the OPERABILITY of two offsite A.C. circuits by performing Surveillance Requirement 4.8.1.1.1.a within one hour and -at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; restore one of the inoperable diesel generators to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in at least HOT STANDBY within the next 6 hours and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. t Following restoration of one diesel' generator unit, follow Action Statement b with the time requirement of that Action Statement based on the time of initial loss of the remaining inoperable diesel generator. A successful test of. diesel OPERABILITY per Surveillance Requirement 4.8.1.1.2.a.5 performed under this Action Statement for a restored to OPERABLE diesel satisfies the diesel generator test requirement of Action Statement b.
(1) Fuel oil contained in the storage tanks not meeting the properties in accordance with 4.8.1.1.2.d.2 or 4.8.1.1.2.e shall be brought within the specified limits within 7 days.
(2) This action is required to be completed regardless of when the inoperable diesel generator is restored to OPERABILITY.
'f l
l l
l l
BEAVER VALLEY - UNIT 1 (Proposed Wording) Page 2 of 2
DPR-66 knd can begroc)% admN h #*
ELECTRICAL POWER SYSTEMS iosh*eo*3sf*d**
(ggbA,$HO6 4
i SURVEILIANCE REQUIREMENTS (Continued) ,4 Z 58.8 St.unus ad i Gl.to.d 6 ,
- 3. (Deleted)
- 4. Verifying the fuel transfer pump can be started and !
transfers fuel from the storage system to the day and engine-mounted tank, (66) }
- 5. Verifying the diesel starts from -'ient ernditirn,
- 6. Verifying the generator is synchronized, loaded to 7 21425 kw, and operates for 2 60 minutes, and i
- 7. Verifying .the diesel generator is aligned to provide standby power to the associated emergency busses. ,
At least once per 18 months during shutdown by:
b.
- 1. Subjecting the diesel to an inspection in accordance with procedures prepared in conjunction with its ,
manufacturer's recommendations for this class of standby service,
- 2. Verifying the generator capability to reject a load of 2450 kw without tripping, ,
i
- 3. Simulating a loss of offsite power in conjunction with a safety injection signal, and:
a) Verifying de-energization of the emergency busses i t
and load sheddincr
& h. tofrom see. 4 the
- 1) emergency busseh !
b) Verifyin the diesel starts :di;r..
@,6 @ g on the auto-start signal, energizes the emergency; busses with from ;
permanently connected loads F energizes the auto-connected emergency loads through the load sequencer and operates for k 5 minutes while its generator is loaded with the emergency loads.y j
- 4. Verifying that on a loss of power to the emergency busses, all diesel generator trips, except engine overspeed, generator differential and overcurrent, are ]
automatically disabled g A 4 r ent.cgit. d m oI kk e looA3 j
._. 4N s b,y si b. u.M p -4 A p .q SM\ 6 m. wbJ A 24406 vons .4 6 4%.%,
o.J 2 58 ,8 Rt. ..J i tt 2. H t.."
x A00 INSEtr " 6 'P -
BEAVER VALLEY - UNIT 1 3/4 8-3 Amendment No.
(frspsechUsrbs
i Att'achment to A.C. Sources - Oneratina l 4
Insert "B" (3) The values for voltage and frequency are analysis values and do not include measurement uncertainties.
(4) All diesel generator starts may be followed by a warmup period prior to loading.
(5) Diesel generator loadings may include gradual loading as recommended by the manufacturer.
(6) The frequency limits apply for the diesel generator at full accident loading. Extrapolation of test data at lower loads can be performed to meet criteria.
3 BEAVER VALLEY - UNIT 1 (Proposed Wording)
i
)
4 DPR-66 ;
ELECTRICAL POWER SYSTEMS 9
BASES .
A.C. SOURCES. D.C. SOURCES AND ONSITE POWER DISTRIBUTION SYSTEMS (Continued)
+
Verifying average electrolyte temperature above the minimum for ,
which the battery was sized, total battery terminal voltage on float l' charge, connection resistance values and the performance of battery service and discharge tests ensures the effectiveness of the charging system, the ability to handle high discharge rates and compares the battery capacity at that time with the rated capacity.
Table 3.8-1 specifies the normal limits for each designated pilot cell and each connected cell for electrolyte level, float voltage and specific gravity. The limits for the designated pilot cells float ,
voltage and specific gravity, greater than 2.13 volts and .015 below the manufacturer's full charge specif'ic gravity or a battery charger ,
current that had stabilized at a low value, is characteristic of a charged cell with adequate capacity. The normal limits for each :
connected cell for float voltage and specific gravity, greater than 2.13 . volts and not more than .020 below the manufacturer's full charge specific gravity with an average specific gravity of all the connected cells not more than .010 below the manufacturer's full c charge specific gravity, ensures the OPERABILITY and capability of s the battery. !
Operation with a battery cell's parameter outside the normal 1~
limit but within the allowable value specified in Table 3.8-1 is permitted for up to 7 days. During this 7 day period: (1) the ;
allowable values for electrolyte level ensures no physical damage to the plates with an adequate electron transfer capability; (2) the :
allowable value for the average specific gravity of all the cells, not more than .020 below the manufacturer's recommended full charge specific gravity, ensures that the decrease in rating will be less :
than the safety margin provided in sizing; (3) the allowable value for an individual cell's specific gravity, ensures that an individual cell's specific gravity will not be more than .040 below the manufacturer's full charge specific gravity and that the overall capability of the battery will be maintained within an acceptable j limit; and (4) the allowable value for an individual cell's float voltage, greater than 2.07 volts, ensures the battery's capability to perform its d ign function.
Note provides clarification of Specification 3.8.1.1 action requirements when the diesel generators are inoperable as a result of i Surveillance Requirements 4. 8.1.1. 2.d. 2 and 4. 8.1.1.2.e in accordance with Regulatory Guide 1.137 Revision 1 Regulatory Position C.2.a.
A00 bsh BEAVER VALLEY - UNIT 1 B 3/4 8-2 Amendment No.
]
%.+Q . - _
Attachment to A.C. Sources, D.C. Sources and Onsite Power
' Distribution Systems Insert "C" For the purposes of SR 4.8.1.1.2.a.5 and SR 4.8.1.1.2.b.3.b testing, the diesel generators are started from standby conditions. Standby conditions for a diesel generator mean that the diesel engine oil is being continuously circulated and engine coolant and oil temperaturca are being maintained consistent with manufacturer recommendations.
BFAVER VALLEY - UNIT 1 (Proposed Wording)
ATTACHMENT A-2 Beaver Valley Power Station, Unit No. 2 Proposed Technical Specification Change No. 90 The following is a list of the affected pages:
Affected Pages: 3/4 8-1 3/4 8-2 3/4 8-3 3/4 8-4 3/4 8-5 B 3/4 8-3 l
t
. NPF-73 3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES i OPERATING LIMITING CONDITION FOR OPERATION 3.8.1.1 As a minimum, the following A.C. electrical power sources shall be OPERABLE:
- a. Two physically independent circuits between the offsite transmission network and the onsite Class 1E distribution system, and ;
- b. Two separate and independent diesel generators each with:
- 1. Separate day tank containing a minimum of 350 gallons of fuel,
- 2. A separate fuel storage system containing a minimum of 53,225 '
gallons of fuel,
- 3. A separate fuel transfer pump,
- 4. Lubricating oil storage containing a minimum total volume of 504 gallons of lubricating oil, and
- 5. Capability to transfer lubricating oil from storage to the diesel generator unit. /t 4 APPLICABILITY: MODES 1, 2, 3 and 4.
ACTION:
[ ~
]
- a. With either an offsite circuit or diesel generator
- of the above re-quired A.C. electrical power sources inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirements 4.8.1.1.1.a and 4.8.1.1.2.a.5 within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; restore at least two offsite cir-cuits and two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be_in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
- b. With one offsite circuit and one diesel generator
- of the above re-quired A.C. alectrical power sources inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirements 4.8.1.1.1.a and 4.8.1.1.2.a.5 within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; restore at least one of the in-operable sources to OPERABLE status within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Restore at least two offsite circuits and two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from the time of initial loss or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
BEAVER VALLEY - UNIT 2 3/4 8-1 Amendment No.
(Prof Web ^
'NPF-73 ELECTRICAL POWER SYSTEMS kEbbb MIR T(ERT "O "
LIMITING CONDITION FOR OPERATION (Continued)
- c. With two of the above required offsite A.C. circuits inoperable, demonstrate the OPERABILITY of two diesel generators by performing Surveillance Requirements 4.8.1.1.2.a.5 within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter, unless the diesel generators are already operating; restore at least one of the inoperable offsite sources to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least HOT STANDBY within the next 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. With only one offsite source restored, restore at
{
1 east two offsite circuits to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from time of initial loss or be in COLD SHUTOOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. {
- d. With two of the above required diesel generators inoperable *, demon-strate the OPERABILITY of two offsite A.C. circuits by performing Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; restore at least one of the inoperable diesel generators to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Restore at least two diesel gen- ,
erators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from time of initial loss !
i or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
SURVEILLANCE REOUIREMENTS I 4.8.1.1.1. Two physically independent circuits between the offsite trans-mission network and the onsite Class 1E distribution system shall be:
l
- a. Determine OPERABLE at least once per 7 days by verifying correct breaker alignment, indicated power availability, and l
- b. Demonstrated OPERABLE at least once per 18 months by transferring (manually and automatically) unit power supply from the unit circuit to the system circuit.
j 4.8.1.1.2 Each diesel generator shall be demonstrated OPERABLE:
- a. At least once per 31 days on a STAGGERED TEST BASIS *try:
- 1. Verifying the fuel level in the day tank,
~
- 2. Verifying the fuel level in the fuel storage tank,
- Fuel oil contained in the storage tanks not meeting the properties in accordance with 4.8.1.1.2.d.2 or 4.8.1.1.2.e shall be brought within the j specified limits within 7 days. >
W T REPLACE WTB /
INSERT "O BEAVER VALLEY - UNIT 2 3/4 8-2 Amendment No.
(frafcatb won
l 1
. Attachment to A.C. Sources - Operatina l 4
Insert "D" ACTION: l l
- a. With one offsite circuit inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirement 4.8.1.1.1.a within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter. Restore the offsite l circuit to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />,
- b. With one diesel generator (1) inoperable, demonstrate the OPERABILITY of the A.C. offsite sources by performing ,
Surveillance Requirement 4.8.1.1.1.a within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and at ,
least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; and if the diesel generator became inoperable due to any cause other than an independently testable component, testing or preplanned-preventative maintenance, demonstrate the OPERABILITY of the remaining OPERABLE diesel generator by performt Surveillance Requirement 4.8.1.1.2.a.5 within 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />shgg1 unless the absence of any potential common mode failure for the remaining diesel generator is demonstrated. Restore the !
diesel generator to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
- c. With one offsite circuit and one diesel generator (1) inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirement i 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> >
thereafter; and if the diesel generator became inoperable due to any cause other than an independently testable component, testing or preplanned preventative maintenance, demonstrate the OPERABILITY of the remaining OPERABLE diesel generator by performing (2) Surveillance Requirement 4.8.1.1.2.a.5 within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> unless the absence of any potential common mode failure for the remaining diesel generator is demonstrated. Restore one of the inoperable sources to OPERABLE status within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. Restore the other A.C. power t
source (offsite circuit or diesel generator) to OPERABLE status in accordance with the provisions of Action Statement a or b, as appropriate with the time requirement of that Action Statement based on the time of initial loss of the remaining inoperable A.C. power source. A successful test of diesel OPERABILITY per Surveillance Requirement ,
4.8.1.1.2.a.5 performed under this Action Statement for an OPERABLE diesel or a restored to OPERABLE diesel satisfies the diesel generator test requirement of Action Statement b.
BEAVER VALLEY - UNIT 2 (Proposed Wording) Page 1 of 2
Att'chment a to-A.Co Sources - Operatina Insert "D" (Continued) .g i
ACTION (Continuedl j
- d. With two of the required offsite A.C. circuits inoperable, i restore one of the inoperable offsite sources to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least' HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. Following restoration of one offsite source, follow Action Statement a with the time requirement of that Action Statement based on the time of initial loss !
of the remaining inoperable offsite A.C. circuit.
- e. With two of the required diesel generators (1) inoperable, I
demonstrate the OPERABILITY of two offsite A.C. circuits by performing Surveillance Requirement 4.8.1.1.1.a within one ,
hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; restore one of the inoperable diesel generators to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in at least HOT STANDBY within the next i 6 hours and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
Following restoration of one diesel generator unit, follow ;
Action Statement b with the time requirement of that Action :
Statement based on the time of initial loss of the remaining inoperable diesel generator. A successful test of diesel OPERABILITY per. Surveillance Requirement 4.8.1.1.2.a.5 j performed under this Action Statement for a restored to ;
OPERABLE diesel satisfies the diesel generator test ,
requirement of Action Statement b. !
(1) Fuel oil contained in the storage tanks not meeting the properties in accordance with 4.8.1.1.2.d.2 or 4.8.1.1.2.e shall be brought within the specified limits within 7 days.
(2) This action is required to be completed regardless of when the )
inoperable diesel' generator is restored to OPERABILITY. i l
l I
I j
i l
)
i BEAVER VALLEY - UNIT 2 (Proposed Wording) Page 2 of 2 i
- ELECTRICAL POWER SYSTEMS
{
q of258.4HiJMt.1h SURVEILLANCE REOUIREMENTS (Continued)
- 3. l (Deleted) <
- 4. Verifying the fuel transfer pump can be started and transfers ,
fuel f rom the storage system to the dav tan _k. 6iD
- g. ~ ti:nt.e.. g l
- 5. Verifying the diesel starts from ::ndit"-
- 6. Verifying the generator is synchronized, loade and operates for :t 1:
~>4,238 kw, e 0 minutes,
- 7. Verifying the diesel generator is aligned to provide standby i power to the associated emergency busses, and ,
t
- 8. Verifying the lubricating oil inventory in storage. l
- b. At least once per 18 month uring shutdown by: DEGTE
- 1. Subjecting the diesel to an inspection in accordance with pro- ,
cedures prepared in conjunction with its manufacturer's recom-mandations for this class of standby service, ;
- 2. Verifying the generator capability to reject a load of > 825 kw I without tripping, i
- 3. Simulating a loss of offsite power in conjunction with a safety injection signal, and: j a) Verifying de-energization of the emergency busses and load shedding from the emergency busses ,g,y g)}
b) Verifying the diesel starts from 'f: t :: diti:n on the auto-start signal, energizes the emergency busses with per--
4.
-
- T manently connected loadas energizes the auto-connected emergency loads through the load sequencer and operates for
> 5 minutes while its generator is loaded with the emergency Toads.f.
- 4. . Verifying that on a loss of power to the emergency busses, all '
D Et.OE diesel generat_oq trips, except engine overspeed, backup phase rault detectiotut, generator differential current, and generator overexcitation are automatically disabled d f D' f" S; ;g ;ifi;d 10 .;att. ;.rveiller.;e intervel d.rir.; tt.e firet feel cycle ;.y '
3.0,0*i.f..UN.IO
... s _ ,,, 20$,.'5$..
... ... i!$. 03..53!.?i.,;b..t3.. [!Ti31
$5}!.35 fN.3..1 m__
- t:rt; 're th: cred re'eMa; eMe. -
hu.\ Mu M hos ladr j kb Sktadv 3
- 8bM h minb g A r M nbad6 M *@
% y B 2 58.8 a ~3 ct.w 3
ALLEY - UNIT 2 3/4 8-3 Amendment No. ;
i A00 TNSEAT. ' O M* W*
( E .
l !
i
'Att'achment to A.C. Sources - Operatina Insert "E" (3) The values for voltage and frequency are analysis values and do '
not include measurement uncertainties. ,
(4) All diesel generator starts may be preceded by an_ engine prelube period and followed by a warmup period prior to loading.
(5) Diesel generator loadings may include gradual loading as ;
recommended by the manufacturer.
l (6) All diesel generator starts may be preceded by an engine prelube period.
t f
BEAVER VALLEY - UNIT 2 (Proposed Wording) ,
NPF-73 .
+
ELECTRICAL POWER SYSTEMS l l
SURVEILLANCE REQUIREMENTS (Continued) I 1
- 5. Verifying the diesel generator operates for et leret 60
. minutes.while loaded to 2 4,238 kw g
- 6. Verifying that the auto-connected loads to e'ach diesel generator do not exceed the 2000 hour0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br /> rating of 4,535 l 1
kw
- 7. Verifying that the automatic load ssquence timer is OPERABLE with each load sequence time within 10% of :
its required value.
- c. Check for and remove accumulated water:
- 1. From the day tank, at least once per 31 days and after each operation of the diesel where the period of operation was greater than 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, and ;
- 2. From the fuel oil storage tank, at least once per 92 )
days.
- d. By sampling new fuel oil in accordance with ASTM D4057-81 )
prior to addition to the storage tanks and: i
- 1. By verifying in accordance with the test specified in.
ASTM D975-81 prior to addition te the storage tanks that the sample has: ,
a) An API Gravity of within 0.3 degrees at 60'F or a specific gravity of within 0.0016 at 60/60*F, when compared to the supplier's certificate or an absolute specific gravity at 60/60'F of greater ,
than or equal to 0.83 but less than or equal to '
O.89 or an API gravity at 60*F of greater than or equal to-27 degrees but less than or equal to 39 degrees, b) A kinematic viscosity at 40*C of greater than or equal to 1.9 centistokes, but less than or equal to 4.1 centistokes, if gravity was not determined by comparison with the supplier's certification, c) A flash point equal to or greater than 125'F, 4 d) A water and sediment content of less than or equal to 0.05% when tested in accordance with' ASTM D1796-83, and BEAVER VALLEY - UNIT 2 1/4 8-4 Amendment No. ,
(fraposeckUerSl
l l
NPF-73 ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued) e) A total particulate contamination level of less
, than 10 mg/ liter when tested in accordance with ASTM D2276-78, Method A.
acke utt , l'i -
L lO 5cc , unt('d
- 2. By .. verifying within 31 days of obtaining the sample that the other properties specified in Table 1 of ASTM
- qg y D975-81 are met when tested in accordance with ASTM
($ D975-81 except that the analysis for sulfur may be t- 4 3 6 % 0 o Ue s
L ~N At least once every 31 days by obtaining a sample of fuel oil from the storage tanks and day tanks in accordance with
- ASTM D2276-78, and verifying that total particulate
@N contamination is less than 10 mg/ liter when checked in g accordance with ASTM D2276-78, Method A. ,,3kgqce44.n3 f At least once per 10 years or after any modifications whic could affect diesel generator interdependence by startin v both diesel generators simultaneous 1v, during shutdown, an verifyina that betti diesel generatorNY : Cler:t t: t 12 st h () RETE- Sit rp= in lese than er e;"21 to 10 e ceede'. DELETE-gh At leas once per 10 years by h
@ Graining each main fuel oil storage tank, removing the accumulated sediment, and cleaning the tank using a s sodium hypochlorite solution r other appropriate cleaning solution, @ DEL
- 2) Perfor=ing prc::ur t::t, Of th::: p;rtion;cfthh dice:1 fu 1 011 c'j e t'a design-d te e ctica T T I', ,
69eection NO af +h= i=E coda, =* = +=e*
equel t: 110t Of th: :j eter derig pr:crur:! pree-"r=
, DELETE 1 (61 Mi J.e3e\ pub s6b y b=. p ececaed h om emine. peeM t. teed Y '; tie t :t ch:11 5 cenducted in ::: rd:nre Uith the m nuf :turer' rect- endatienc regarding engin prelub 2nd '
W80""P P"Ocrd"ree, and 2: :pplicable regarding leading l g.- y [3) Th voho be ve\%s d Ir ps*y are. on.\pa ud i.s a4 de wd tubh t wa ~hw., ,
BEAVER VALLEY - UNIT 2 3/4 8-5 Amendment No. l Ytojn1N % '
i
. NPF-73 3/4.8 ELECTRICAL POWER SYSTEMS BASES
=
3/4.8.1, 3/4.8.2 A.C. SOURCES AND ONSITE POWER DISTRIBUTION !
(Continued) gravity will not be more than 0.040 below the manufacturer's full I charge specific gravity and that the overall capability of the battery will be maintained within an acceptable limit; and 4) the allowable value for an individual cell's float voltage, greater than 2.07 volts, ensures the battery's capability to perform its design function.
i) 0FWE Note 67 ;;; 3/' 913Torovides clarification of Specification 3.8.1.1 Action requirements when the diesel generators are inoperable as a result of Surveillance Requirements 4.8.1.1.2.d.2 and ,
4.8.1.1.2.e in accordance with Regulatory Guide 1.137, Revision 1, Position C.2.a.
Ano T NJEAT " F "
i BEAVER VALLEY - UNIT 2 B 3/4 8-3 Amendment No.
(0.poyd Vorx\.
Att$chment to 3/4.8.1. 3/4.8.2 A.C. Sources and Onsite Power Distribution INSERT "F" For the purposes of SR 4.8.1.1.2.a.5, 4.8.1.1.2.b.3.b and 4.8.1.1.2.f testing, the diesel generators are started from standby conditions. Standby conditions for a diesel generator mean that the diesel engine coolant and oil are being continuously circulated and temperatures are being maintained consistent with manufacturer recommendations, i
BEAVER VALLEY - UNIT 2 (Proposed Wording)
ATTACHMENT B Beaver Valley Power Station, Unit Nos. 1 and 2 Proposed Technical Specification Change No. 221 and 90 REVISION OF SPECIFICATION 3.8.1.1 TITLED "A. C. SOURCES - OPERATING" A. DESCRIPTION OF AMENDMENT REQUEST The proposed changes would revise the action statements of Limiting Condition of Operation (LCO) 3.8.1.1, titled "A.C.
Sources-Operating." The proposed action statement "a" would provide actions to be taken with one offsite circuit of the required A.C. electrical power sources inoperable. The actions required when one diesel generator (D/G) is inoperable are being separated from this action statement and incorporated into an individual action statement "b." The present requirement in action statement "a" to perform Surveillance Requirement (SR) 4.8.1.1.2.a.5 within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter would be deleted.
The proposed action statement "b" would provide actions to be taken with one D/G inoperable. The performance of SR 4.8.1.1.2.a.5, will be perfvrmed once within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> on the remaining D/G. This test is required to be performed regardless of when the inoperable D/G is restored to operability. A provision would be added such that if the D/G has been -endered inoperable due to an independently testable component, te ting or preplanned preventative maintenance, the perforisrae of SR 4.8.1.1.2.a.5 would not be required. In addition, the performance of SR 4.8.1.1.2.a.5 on the remaining operable diesel generator would not be required if the absence of any potential common modo failure on that diesel generator can be demonstrated.
The proposed action statement "c" would provide actions to be taken with one offsite circuit and one D/G inoperable. In the existing LCO 3.8.1.1 specification, this is action statement "b" with the following revisions. SR 4.8.1.1.2.a.5 will be performed on the remaining D/G within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of declaring one D/G inoperable. The existing action statement "b" requires SR 4.8.1.1.2.a.5 to be performed within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter. A provision would be added such that if the D/G has been rendered inoperable due to an independently testable component, testing or preplanned preventative maintenance, the performance of SR 4.8.1.1.2.a.5 would not be required. In addition, the performance of SR 4.8.1.J.2.a.5 on the remaining operable diesel generator would not be required if the absence of any potential common mode failure on that diesel generator can be demonstrated. Also, guidance would be provided to enter the appropriate action statement "a" or "b" once either a D/G or offsite circuit has been restored to operable status. This action statement would also state that a successful test of diesel operability per Su'veillance
. Requirement 4.8.1.1.2.a.5 performed under this action statement for an operable diesel or restored to operable diesel satisfies the diesel generator test requirement of action ptatement "b."
B-1
i ATTACHHEnr B, continued
. Proposed Technical Specification Change Nos. 221 and 90 Page 2 The proposed action statement "d" would provide actions to be taken when two offsite power circuits are declared inoperable. i In the existing LCO 3.8.1.1 specification, this is action statement "c" with the following revisions. The existing action ;
statement "c" requirement to perform SR 4.8.1.1.2.a.5 within one ;
hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter would be deleted.
The requirement to be in Hot Standby within the next 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> ,
would be changed to require the plant to be in Hot Standby within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. Also, guidance would be provided to enter action statement "a" once a single offsite circuit has been restored to operable status.
The proposed action statement "e" would provide action to be taken when two diesel generators are declared inoperable. In the existing LCO 3.8.1.1 specification, this is action statement "d" with the addition of a statement which refers back to action "
statement "b" once one D/G is restored to operable status.
A new footnote designated by the number (2) would be added which applies to proposed action statements "b" and "c." The footnote '
would state the following: "This action is required to be completed regardless of when the inoperable diesel generator is restored to operability." The existing ,otnotes would be ,
designated by numbers instead of symbol- o ensure correct !
application. For Beaver Valley Power Station (BVPS) Unit No. 2 i only, the two footnotes contained on the present Page 3/4 8-3 would be deleted since they no longer apply. These two footnotes ;
were only applicable for the first and second fuel cycles. BVPS l Unit 2 is currently in its sixth fuel cycle. ;
Surveillance Requirements (SRs) 4.8.1.1.2.a.5 and 4.8.1.1.2.b.3.b ;
would also be modified. For BVPS Unit No. 1, SR 4.8.1.1.2.a.5 would bemodifiedbyreplacingtgg)w"ords"ambientcondition"with the words " standby conditions, . SR 4.8.1.1.2.a.5 would ;
also be modified by adding the words "and accelerated to synchronous speed with geney canbegraduay voltage > 2 4106 volts and 5 4368 volts and frequencylgpor i 1 58.8 Hz and 5 61.2 Hz." SR 4.8.1.1.2.b.3.b would be modified by replacing , the words " ambient condition" with the words " standby ! conditions." SR 4.8.1.1.2.b.3.b would also be modified by adding ; the words "in 5 10 seconds" a " t loads, the steady state voltagegg)Afterenergizattgpofthese and frequencyL shall be maintained gp"2 4106 volts and 5 4368 volts, and 2 58.8 Hz and ?
$ 61.2 Hz . For BVPS Unit No. 2, SR 4.8.1.1.2.a.5 would be modified by replacing the words " ambient condition" with the r words " standby conditions,(4}". SR 4.8.1.1.2.a.5 would also be modifie by adding the words "and achieves steady voltage 3) of 2 3994 volts and 5 4368 and frequency (gpate of )
- 2 58.8 Hz and 5 61.2 Hz." SR 4.8.1.1.2.b.3.b would be modified j by the " ambient condition" with the words l
" standby replacingconditionsyg{ds" . SR 4.8.1.1.2.b.3.b would also be j modified by adding the words "in 5 10 seconds" and "After B-2
ATTICHMENT B, continued
- Proposed Technical Specification Change Nos. 221 and 90 Page 3 of these loads, the steady state voltage (3) and energizat{g frequency shall be maintained at 2 3994 volts and 5 4368 volts and 2 58.8 Hz and 1 61.2 Hz."
A new footnote, designated by the number (3), would be added to SR 4.8.1.1.2.a.5, 4.8.1.1.2.b.3.b and SR 4.8.1.1.2.f (for BVPS Unit No. 2 only), which states that the values for voltage and frequency are analysis values and do not include measurement uncertainties. For BVPS Unit No. 1 only, a new footnote designated by the number (4) would be added and state the following: "All diesel generator starts may be followed by a warmup period prior to loading." For BVPS Unit No. 2 only, a new footnote designated by the number (4) would be added and state the following: "All diesel generator starts may be preceded by an engine prelube period and followed by a warmup period prior to loading." A new footnote, designated by the number (5), would be added to SR 4.8.1.1.2.a.6 which states the following: " Diesel generator loadings may include gradual loading as recommended by the manufacturer." For BVPS Unit No. 1 only, a new footnote, designated by the number (6), would be added to SR 4.8.1.1.2.b.3.b which states the following: "The frequency limits apply for the diesel generator at full accident loading. Extrapolation of test data at lower , loads can be performed to meet criteria." For BVPS Unit No. 2 only, a new footnote designated by the number (6) would be added and state the following: "All diesel generator starts may be preceded by an engine prelube period." For BVPS Unit No. 2 only, SR 4.8.1.1.2.a.6 and SR 4.8.1.1.2.b.5 would be modified by replacing the words "at least" with the symbol "2". SR 4.8.1.1.2.f would be modified, for BVPS Unit No. 2 only, by replacing the current footnote, designated by the double asterisk, with footnote number (6). This is the same footnote previously mentioned under the Description of Change to SR for BVPS Unit No. 2. The words "from standby 4 . 8 .1.1. { gp". 3 . bwould
. be added following the word " starting."
conditions The words " verifying that both diesel generators" would be revised to state the following: " verifying that each diesel generator." Also, the words " accelerate to at least 514 rpm in ; less than or equal to 10 seconds" woul 3pereplacedwiththe words " achieves, in s 2 3994 volts and 5 l 4368 volts and, frequency {gseconds, 2 58.8 Hz voltage and < 61.2 Hz." i l l B-3
ATT$CHMENT B, continued
- Proposed Technical Specification Change Nos. 221 and 90 Page 4 SR 4.8.1.1.2.g would be modified, for BVPS Unit No. 2 only, by deleting the requirement to perform a pressure test on the diesel fuel oil system in accordance with the ASME code.
For BVPS Unit No. 2 only, the parentheses would be deleted from SR 4.8.1.1.2.e, f, and g designations. This change will make these designations consistent with the other surveillance designations contained in this LCo. The Bases section for 3/4.8.1 would be revised to reflect that the note designated by a single asterisk would be designated by the number (1). Bases words would be added which will define the words " standby conditions." The proposed wording varies slightly between BVPS Unit No. 1 and Unit No. 2 due to the diesel generators on BVPS Unit No. 1 not having a pump which continuously circulates engine coolant. In addition, BVPS Unit No. 1 LCO 3.8.1.1 does not contain SR 4.8.1.1.2.f. For BVPS Unit 2 only, the reference to page 3/4 8-2 would be deleted following reference to the footnote currently designated by a single asterisk. B. BACKGROUND BVPS Unit Nos. 1 and 2 each have two emergency diesel generators. Two diesels are fully dedicated to each plant, with one diesel assigned to each of the redundant electrical power divisions of each plant. With the exception of the specific statior, blackout breaker alignment, there is no sharing of diesel generators between units. Power from one diesel to one electrical division of each plant is sufficient to provide either for safe shutdown loads or for accident loads. The D/G's at BVPS Unit 1 are manufactured by General Motors Electro-Motive Division and BVPS Unit 2 D/G's are manufactured by Fairbanks Morse Engine Division of Colt Industries. BVPS technical specifications currently require starting the operable diesel within 1 hour and every 8 hours thereafter when specific conditions exist. Generic Letter (GL) 84-15, titled
" Proposed Staff Actions to Improve and Maintain Diesel Generator Reliability," and GL 93-05, titled "Line-Item Technical Specification Improvements To Reduce Surveillance Requirements For Testing During Power Operation" provide guidance for revising start frequencies for diesel generators under certain conditions to improve reliability. This proposed change incorporates Nuclear Regulatory Commission (NRC) guidance intended to improve diesel generator reliability.
The NRC notified Duquesne Light Company (DLC) in a letter dated April 26, 1993, that previously submitted Amendment Request Nos. 200 and 67 regarding diesel generator testing (TAC Nos. M84225 and M8422' were temporarily put on " Hold" pending completion of B-4
ATTACHMENT B, continued
. Proposed Technical Specification Change Nos. 221 and 90 Page 5 the DLC analysis of emergency diesel generator performance requirements. In reviewing Amendment Request Nos. 200 and 67, dated October 6, 1992, the staff determined that the current technical specifications for Unit Nos. 1 and 2 do not specify certain diesel test performance parameters such as voltage, frequency, and time to come up to speed. DLC agreed to provide these test parameters as part of a technical specification change once the appropriate values were determined.
DLC has completed the evaluation of these test parameters and has included them in this proposed amendment request. The previous submittal, Amendment Request Nos. 200 and 67, was withdrawn by a letter from DLC to the NRC, dated September 6, 1994. This amendment request, Nos. 221 and 90, represents the new proposed operating license change request mentioned in the September 6, 1994, DLC to NRC letter. C. JUSTIFICATION The proposed revisions to LCO 3.8.1.1 action statements are consistent with the action statements approved for Virginia Power Company North Anna Unit 1 and 2. The proposed changes to the action statements which eliminate certain surveillance requirements for the emergency diesel generators have been determined by the NRC to be unnecessary. This determination is reflected in GL 93-05. The proposed revisions are also similar to those contained in Appendix A of GL 84-15. The following is a discussion on the provision that would be added such that if the D/G has been rendered inoperable due to an independently testable component, testing or preplanned preventative maintenance, the performance of SR 4.8.1.1.2.a.5 would not be required. This provision would be added to proposed action statements "b" and "c." The current wording requires that the alternate train testing be performed, i.e., starting of the opposite train D/G, to provide a positive demonstration that a loss of safety function has not occurred. There are situations where reduced operability testing on the remaining diesel can exist when a diesel is made inoperable due to preplanned preventative maintenance or testing. The purpose for testing the remaining diesel 16 to assure that a common mode failure does not exist. Since the reason for D/G inoperability is known, i.e., preplanned preventative maintenance or testing, then a common mode failure on the remaining D/G does not exist. The NRC staff has recommended, per a memorandum dated February 11, 1991, (Entry Into A Technical Specification LCO During Performance of Surveillance Testing) that licensees change their current technical specification wording to eliminate the need for such testing if a D/G is taken out of service for preplanned preventative maintenance or testing. GL 93-05 also recommends this additional provision and expands the scope of exclusions to B-5
ATTICHMENT B, continued i i
- Proposed Technical Specification Change Nos. 221 and 90 Page 6 ,
include an inoperable support system and an independently 1
~
testable component. GL 93-05 also provides an exclusion.such that if the absence of any potential common mode failure for the remaining diesel generator is demonstrated, that diesel generator need not be started. The words "an inoperable support system" in the list of exceptions for performing SR 4.8.1.1.2.a.5 are not included. This decision was based on the fact that the words
" independently testable component" and the exclusion such that if ,
the absence of any potential common mode failure for the ! remaining diesel generator is demonstrated, the opposite train diesel generator need not be started, provide sufficient [ flexibility to minimize unnecessary starts on the remaining l operable diesel generator. In addition, adding the words "an L inoperable support system" would potentially make the required actions difficult to interpret due to the combination of systems, subsystems, and component variations associated with establishing ; the boundary between supported system and support system. ! Without a comprehensive list of plant equipment which is appropriate to include under the definition of a " support system," plant operations personnel may misapply this exception to the required starting of the opposite train diesel. Therefore, this wording is not included in this amendment request. In summary, the provision that would not require i performance of SR 4.8.1.1.2.a.5, if the D/G has been rendered inoperable due to an independently testable component, preplanned preventative maintenance or testing, or the absence of any potential common mode failure for the remaining diesel generator l 1s demonstrated, is proposed to be added to action statements "b" and "c." ; The present action statement "a" would be divided into two ! separate action statements based on GL 84-15. The present ! requirement to start each D/G within one hour and every 8 hours thereafter, due to a loss of an offsite power _ source, DLC believes to be excessive and will lead to accelerated D/G wear. This action is intended to verify the availability of a backup The D/Gs are designed and are intended to be power source. standby power sources. Under the present wording, in just one 72 hour period a total of nine D/G tests would be required per D/G. This repetitive type testing introduces accelerated D/G wear and provides little additional assurance of D/G availability than what was provided in the previous successful test. Additionally, , starting a diesel generator for the sole reason that an offsite j circuit became inoperable is unnecessary. The current surveillance testing schedule established- in accordance with , Regulatory Guide 1.9 (Revision 2, December 1979), titled
" Selection, Design, and Qualification of Diesel Generator Units Used As Standby (Onsite) Electrical Power Systems At Nuclear Power Plants," provides adequate assurance that the operable diesel generators will be capable of performing their intended safety functions even during the loss of offsite circuit (s).
Deleting the requirements to start the operable diesel B-6
ATTICHMENT B, continued Proposed Technical Specification Change Nos. 221 and 90 Page 7 generators, when an offsite circuit becomes inoperable, does not increase the probability that the operable diesel generators will be unable to perform their safety function. Therefore, in accordance with GL 93-05, this requirement can be deleted. The proposed action statement "b" provides the appropriate responses when declaring one D/G inoperable. The present wording requires that the opposite train be tested within 1 hour and at least once per 8 hours thereafter. The reason to perform a diesel test following the loss of one diesel is to assure that the remaining diesel will be operable and capable of starting as designed. Specifically, an operability test of the remaining diesel provides assurance that the remaining operable diesel is not subject to the same failure (i.e., common mode failure). Testing within 24 hours provides timely assurance of diesel operability while providing the additional time for inspection prior to testing. As stated in the discussion for the proposed action statement "a," repetitive testing every 8 hours following the initial confirmation of diesel operability is unnecessary. This change to require D/G testing within 24 hours is consistent with GL 84-15, as well as NUREG-1431, titled " Standard Technical Specification for Westinghouse Plants (ISTS)," and has been found to be an appropriate time frame for complying with the intent of GL 93-05. The proposed action statement "c" provides the appropriate responses to be taken upon declaring one offsite circuit and one diesel generator inoperable. Consistent with the proposed changes to action statements "a" and "b", the proposed changes to action statement "c" provide adequate assurance of diesel operability by one-time testing while eliminating repetitive testing. The performance of the D/G test within 8 hours provides adequate assurance of the availability of the remaining D/G while eliminating excessive starts and also providing added time for inspection prior to testing. The proposed action statement "d" provides the appropriate responses to be taken upon declaring two offsite power circuits inoperable. The proposed change is consistent with those made for action statement "a." As noted in the discussion for action statement "a," loss of an offsite circuit does not suggest that the diesels have become less reliable than demonstrated by previous surveillance tests. The proposed change to allow 6 hours versus 4 hours to reach Hot Standby is consistent with NUREG-0452, Revision 4, titled " Standard Technical Specifications for Westinghouse Pressurized Reactore," and ISTS. The proposed action statement "e" provides the appropriate responses to be taken upon declaring both D/Gs inoperable. The proposed change is the same as existing action statement "d." B-7
ATTACHMENT B, continued . Proposed Technical Specification Change Nos. 221 and 90 Page 8 The only difference in the proposed change is the use of distinct action statements based on the number of D/Gs inoperable (either one or both). The addition of the new footnote number (2) will ensure that this action is completed on the remaining operable diesel generator regardless of when the inoperable diesel generator is restored to operable status. This action will verify that a common mode failure does not exist on the remaining operable diesel. The proposed changing of the words " ambient condition" to
" standby conditions" will better define the initial configuration that the diesel generator is required to be in prior to starting. The current wording does not clearly define what initial configuration the diesel is required to be in prior to starting. The proposed wording will ensure that the periodic testing initial configuration is consistent with the accident response initial configuration. The revised Bases wording will define the requirements to meet the intent of the words " standby conditions."
The addition of the parameters for generator voltage, frequency and diesel starting time, to the existing surveillance requirements, will provide additional assurance that the diesel generators perform as assumed in the safety analysis. The proposed values for voltage and frequency were developed from a specific analysis to determine the required diesel voltage and frequency using the Electrical Transient Analyzer Program scftware. The proposed diesel start time of "in < 10 seconds" supports the value assumed in the Updated Final Safety Analysis Report (UFSAR). The proposed wording for SR 4.8.1.1.2.a.5 for BVPS Unit No. I differs for the proposed wording for BVPS Unit No. 2 due to diesel generator design differences. On BVPS Unit No. 1, the diesels are designed such that when started manually in the exercise mode, the engine initially obtains half speed of approximately 450 rpm. Full engine speed of approximately 900 rpm is then obtained by manually increasing the governor setting. The generator is then manually field flashed to obtain a voltage output. The BVPS Unit No. 2 diesels are designed such that when started manually in the exercise mode, the engine initially obtains full engine speed of approximately 514 rpm. In addition, the generator is automatically field flashed to obtain a voltage output. Due to these design differences, the proposed wording for SR 4.8.1.1.2.a.5 is slightly different. For BVPS Unit No. 1, the proposed addition of footnote number (6) to SR 4.8.1.1.2.b.3.b is necessary due to the design of the diesel generators. The BVPS Unit No. 1 aiesel generators utilize a , Woodward UG-8 mechanical governor. This governor and the diesel l generator control system is configured to allow both the monthly i surveillance runs, where the diesel generator is synchronized to I the electrical grid, and emergency operation, where the diesel generator is supporting the bus independently, without any B-8
1 I ATTACHMENT B, continued
. Proposed Technical Specification Change Nos. 221 and 90 Page 9 governor setpoint changes. To achieve both of these control functions, the speed droop setting is left " dialed in" as a permanent setting. This setting provides proper speed droop
(=3 - 5%) to allow stable operation during the monthly load tests and also provides acceptable frequency control when the diesel l generator responds to emergency loading. In the emergency mode of operation, the speed droop setting causes the diesel generator output frequency to drop as load is increased. Presently, the i [ the diesel generator is at =62 Hz settings are made such that while at zero load and 260 Hz at full load. The present control system and governor cannot be adjusted to provide isochronous operation with zero droop and support the monthly loading runs which require speed droop. This is due to the control system design to allow an idle cool down period following an engine run, while still being capable of responding to an emergency condition. The control system will automatically raise the governor to the high speed setting upon any emergency start signal. To allow isochronous operation with zero droop at 260 Hz would require a different high speed setting be applied to the 4 j governor. Since the governor speed is controlled by a speed I adjusting motor and limit switches, only one speed setting can be applied. Based on the above discussion on the operation of the UG-8 governor, the technical specification frequency limit during emergency operation should be based on the full load condition. Since the 18 month surveillance test, performed to satisfy the requirements of SR 4.8.1.1.2.b.3.b, does not provide full loading to the diesel generators, the required frequency value range may be exceeded especially during lower loading. Under these conditions, it is acceptable to examine the frequency response vs. loading and by evaluation, determine that the governor is responding properly and would fall within the required frequency band while at full accident loading. The reason this footnote is not applicable to BVPS Unit No. 2 should be noted. The BVPS Unit No. 2 diesel generators operate differently in that speed droop is automatically removed by the action of an isochronous relay when the diesel is not operating l connected to the grid. Speed droop is automatically initiated when the diesel is connected to the grid. Therefore, during performance of the monthly and 18 month surveillance testing, the frequency is maintained at 260 Hz. The proposed addition of footnote number (3), pertaining to voltage and frequency values stated in the surveillance requirements, will ensure that plant operators recognize that these values do not include measurement uncertainties. The measurement uncertainties will be included in plant procedures and allow for additional flexibility to use different instruments if the need should arise without requiring a change to the technical specifications. B-9
ATTACHMENT B, continued
. Proposed Technical Specification Change Nos. 221 and 90 Page 10 j The proposed addition of footnote number (4), pertaining to all diesel generator starts, will clarify that an engine prelube period and warmup period is permitted. This note is intended to i minimize the wear on the diesel iuring surveillance testing. An engine prelube consists of lubricating internal moving parts on ;
the diesel which normally do not get lubricated when the engine is not running. This task is accomplished by running an engine prelube -pump prior to starting the diesel. The action of ; prelubing a diesel does not invalidate the results of required i surveillance tests. The diesel will perform as demonstrated : during such tests with or without prelubing of the engine. Prelubing only serves to enhance diesel reliability by minimizing i diesel wear. The warmup period also does not invalidate the results of required surveillance tests. The diesel will continue to be fast started and loaded during performance of SR 4.8.1.1.2.b.3.b. It should be noted that the wording differs l betueen BVPS Unit No. 1 and 2. slightly BVPS Unit No. 1 does not have any additional diesel prelube steps which can be performed. Therefore, the words " preceded by an engine prelube" are not contained in the proposed footnote number (4) wording. This footnote is consistent with the ISTS wording and the recommendation provided in GL 84-15. ! The proposed addition of footnote number (5), pertaining to ; diesel generator loading, will clarify that gradual loading as i recommended by the manufacturer of the diesel generator is ! permitted. This note is intended to minimize the wear and l mechanical stress on the diesel. This footnote is consistent with ISTS wording and the recommendations contained in . NUREG-1366, titled " Improvements to Technical Specifications ! Surveillance Requirements." For BVPS Unit No. 2 only, the proposed addition of footnote . number (6) pertaining to engine prelube is intended to minimize wear on the diesel during surveillance testing. The . justification for the addition of footnote number (6) is the same as previously discussed for footnote number (4). This footnote is consistent with the ISTS wording and the recommendations provided in GL 84-15. For BVPS Unit No. 2 only, the proposed replacement of the current footnote denoted by double asterisk with the proposed footnote number (6) will make the footnote wording consistent in the specification. The current footnote wording pertaining to warmup l and loading is not applicable to SR 4.8.1.1.2.f since the diesel generators are fast started and are not loaded. Therefore, this wording can be deleted. The addition of the words "from standby i conditions" to SR 4.8.1.1.2.f will better describe the configuration that the diesel generators are required to be in ' prior to starting. These two changes are consistent with ISTS wording. B-10
ATTACHMENT B, continued
. Proposed Technical Specification Change Nos. 221 and 90 Page 11 The proposed revision to SR 4.8.1.1.2.f is consistent with ISTS.
The replacement of engine speed with voltage and frequency provide an equivalent verification of diesel performance. The addition of voltage and frequency is consistent with the proposed changes to SR 4.8.1.1.2.a.5 and SR 4.8.1.1.2.b.3.b as previously described. The proposed daletion of SR 4.8.1.1.2.g.2 pertaining to pressure testing of the fuel oil system is consistent with ISTS. Regulatory Guide 1.137, titled " Fuel-oil Systems for Standby
- Diesel Generators," states that Section 7.3 of ANSI N195-1976 requires that fuel oil systems shall provide- for inservice inspection and testing in accordance with ASME Section XI. In addition, for portions of the fuel oil systems for standby diesel generators that are designed to Section III, Subsection ND of the Code, an acceptable method of meeting the requirements of Section 7.3 is to ensure that the system arrangement would allow pressure testing of the fuel oil system to a pressure 1.10 times the system design pressure at ten year intervals. The current wording of SR 4.8.1.1.2.g.2 reflects this requirement to perform a pressure test. The current wording of SR 4.8.1.1.2.g.2 is very restrictive and does not allow use of alternative test methods permitted by the ASME Code. >
If this proposed elimination of SR 4.8.1.1.2.g.2 is approved by the NRC, the ten year Inservice Inspection (ISI) Plan for BVPS Unit No. 2 will include the following requirement:
"During each ten year interval of operation, a pressure test will be performed on the diesel generator fuel oil system. The test will be done according to ASME XI !
rule approved at the time of the tests." , By placing the pressure test requirement in the ISI Plan, the use of alternative test methods allowed by ASME would be permitted, therefore allowing additional testing flexibil'ity while still ; ensuring the integrity of the fuel oil system. The changes in the designations of SR 4.8.1.1.2.e, f, and g are administrative in nature and does not affect plant safety. ! The revisions to the Bases section for 3/4.8.1, except for the , adding of the definition of standby conditions, are editorial in : nature and reflect the proposed changes to LCO 3.8.1.1. The deletion of the reference to page 3/4 8-2, for BVPS Unit 2'only, i eliminates an unnecessary page reference since the footnote will ; now be designated by a unique number. The change to the existing footnotes, by designating them with ! numbers instead of symbols, the replacing of the words "at least" 1 with the symbol "2" for BVPS Unit No. 2 only, along with the l l ) l B-11
ATTACHMENT B, continued Proposed Technical Specification Change Nos. 221 and 90 Page 12 deletion of two footnotes on Page 3/4 8-3 for BVPS Unit No. 2 only, is administrative in nature and does not affect plant safety. D. SAFETY ANALYSIS The A.C. electrical power sources are designed to provide sufficient capacity, capability, redundancy, and reliability to ensure the availability of necessary power to engineered safety feature (ESF) systems so that the fuel, reactor coolant system,. and containment design limits are not exceeded. The proposed changes to LCO 3.8.1.1 action statements and associated surveillance requirements will continue to ensure that the A.C. electrical power sources will perform as designed. The capacity, capability, and redundancy of the electrical power sources is not affected by this proposed change. The specific number of offsite circuits and diesel generators that are required to be operable remains unchanged. The length of time and number of components that can be inoperable for continued plant operation remains unchanged. The specific parameters, contained in the surveillance requirements, that each component must meet to be determined operable, will be enhanced. Specific criteria for diesel generator voltage, frequency, and starting time will be added. The addition of footnote number (6), for BVPS Unit No. 1 ! only, will allow the extrapolation of test data which is not within the required frequency range. This will ensure that the frequency obtained during testing is consistent with safety analysis assumptions for full loading without requiring additional starting and loading of the diesel generator. The net ' result will be improved diesel reliability, due to less wear from testing, and the verification that accident assumptions for diesel frequency response are met. The proposed changes will provide additional assurance that the diesel generators are performing as assumed in safety analysis. The addition of footnotes number (4), (5) and, for BVPS Unit No. 2 only, number (6), will clarify that certain diesel testing evolutions are permitted which will result in less wear and mechanical stress on the diesels. The proposed changes are intended to enhance diesel generator reliability by eliminating excessive testing which can lead to premature diesel failures. The elimination of the requirement to start a diesel generator, when an offsite circuit becomes inoperable, will not reduce the reliability of the . diesels. An operability concern does not exist for the diesels l' when offsite circuits are inoperable. The current testing schedule for the diesels provides adequate assurance that the operable diesel generators will be capable of performing their intended safety functions during a loss of the offsite circuit (s). When a D/G is made inoperable due to preplanned preventative maintenance or testing, there is not a concern that a common mode failure exists on the remaining D/G. The reason for D/G inoperability is known. When a diesel generator is B-12
ATTACHMENT B, continued . Proposed Technical Specification Change Nos. 221 and 90 Page 13 rendered inoperable due to an independently testable component, the opposite train diesel can be verified not to have the same failure mode without the starting of the diesel. Therefore, requiring the starting of the remaining D/G within 1 hour and at least once per 8 hours thereafter, provides no additional safety benefits and can lead to premature diesel failures. Also, the present requirement to perform nine D/G starts in a 72 hour period does not provide any additional safety benefits. This repetitive type testing introduces accelerated D/G wear and provides little additional assurance of D/G availability than what was provided in the previous successful test. A one time start of a D/G, while in an action statement, is sufficient to ensure a loss of safety function has not occurred. The use of the words " standby conditions" in surveillance requirements will ensure that the various surveillance tests are performed at the conditions which reflect accident response conditions. The Bases change will ensure the intent of these words are consistently applied. The proposed deletion of SR 4.8.1.1.2.g.2, for BVPS Unit No. 2 only, does not affect plant safety since this surveillance will be required to be performed under the ten year ISI Plan for BVPS Unit No. 2. Therefore, this change is considered safe based on continued ability of the A.C. electrical power sources to provide sufficient capacity, capability, redundancy, and reliability to ensure the availability of power to ESF systems. The proposed changes are intended to enhance D/G reliability by eliminating excessive testing and permitting additional test evolutions which result in less diesel wear and mechanical stress. The overall result of this change is to enhance the ability of A.C. electrical power sources to perform as originally designed to ensure continued safe plant operation. i i E. NO SIGNIFICANT HAZARDS EVALUATION l The no significant hazard considerations involved with the ! proposed amendment have been evaluated, focusing on the three ' standards set forth in 10 CFR 50.92(c) as quoted below: The Commission may make a final determination, pursuant to the procedures in paragraph 50.91, that a proposed amendment to an operating license for a facility licensed under paragraph 50.21(b) or paragraph 50.22 or for a testing facility involves no significant hazards consideration, if operation of the facility in accordance with the proposed amendment would not: 1 B-13 _1
ATTNCHMENT B, continued !
. Proposed Technical Specification change Nos. 221 and 90_ ;
Page 14 j l i
-(1) Involve- a significant increase in the probability or '
consequences of an accident previously evaluated; or (2) Create -the possibility. of a new'or different kind of ; accident from any accident previously evaluated; or l f (3) Involve a significant reduction in a margin of_ safety. ? The following evaluation is provided for the no significant + hazards consideration standards. ; i 1.. Does the change involve a significant increase in the probability or consequences of an accident previously
- evaluated? ;
The probability of occurrence of a previously evaluated accident is not increased because the allowable outage times : for the offsite circuits and diesel generators remain , unchanged. The consequences of an accident previously evaluated is not increesed because reducing the diesel generator test frequency and permitting additional ~ test i evolutions are intended to minimize diesel wear and-mechanical. stress. By eliminating excessive testing, which ! can- lead to premature diesel failures and minimizing diesel l . wear and mechanical stress, the diesel generator reliability ; is increased. The consequences of an' accident previously ! evaluated is also not increased because the addition of the parameters for generator voltage, frequency, and diesel starting time to the surveillance requirement will. provide. additional assurance that the diesel generators are performing as assumed in the safety analysis. This proposed i change does not affect the availability or reliability of j the offsite circuits. i Therefore, this change will not increase the probability or consequences of an accident previously evaluated due to the l continued availability and reliability of the A.C. electrical power sources. !
- 2. Does the change create the possibility of a new or different kind of accident from any accident previously evaluated? '
The proposed changes do not alter the method of operating the plant. The changes do not introduce any new failure ! modes and are intended to increase the diesel generator- i reliability and provide additional _ assurance that the diesels are performing as assumed in the safety. analysis. l The revision to- the. Various action statements and ! , surveillance requirements. provide assurance that the diesel l' generators will be able to power their respective safety , systems if required. The proposed changes do not impact the 1 performance of any safety system. l B-14 l
~- --
I ATTACHMENT B, continued . Proposed Technical Specification Change Nos. 221 and 90 l Page 15 Therefore, this proposed change does not create the possibility of a new or different kind of accident from any accident previously evaluated.
- 3. Does the change involve a significant reduction in a margin of safety? l l
The margin of safety is not reduced because the A.C. ! electrical power sources will continue to provide sufficient ! capacity, capability, redundancy, and reliability to ensure l availability of necessary power to engineered safety feature (ESP) systems. The ESF systems will continue to function, as assumed in the safety analyses, to ensure that the fuel, reactor coolant system and containment design limits are not exceeded. The elimination of excessive testing on the diesel generators and permitting additional test evolutions, which result in less diesel wear and mechanical stress, are intended to increase diesel reliability. The increased reliability of the diesels adds to the ability of the A.C. electrical power source to provide power to ESF systems. The proposed additions to the surveillance requirements will provide additional assurance of the ability of the A.C. electrical power sources to provide power to ESF systems. Therefore, this proposed change does not involve a significant reduction in a margin of safety. F. NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION Based on the considerations expressed above, it is concluded that the activities associated with this license amendment request satisfies the no significant hazards consideration standards of 10 CFR 50.92(c) and, accordingly, a no significant hazards consideration finding is justified. B-15
. ATTACHMENT C-1 Beaver Valley Power Station, Unit No. 1 Proposed Technical Specification Change No. 221 Applicable Typed Pages ,
7 1 E
,--- ,,,-+ , . . , . , . ., - _ , , ,. . . , . , . .
ATTACHMENT TO LICENSE AMENDMENT NO. FACILITY OPERATING LICENSE NO. DPR-66 DOCKET NO. 50-334 Replace the following pages of Appendix A, Technical Specifications, with the enclosed pages as indicated. The revised pages are identified by amendment number and contain vertical lines indicating the areas of change. Remove Insert 3/4 8-1 3/4 8-1 3/4 8-2 3/4 8-2 3/4 8-3 3/4 8-3 3/4 8-4 3/4 8-4 3/4 8-4a 3/4 8-4a 3/4 8-4b B 3/4 8-2 B 3/4 8-2 l l l (Proposed Wording) i
D'PR-66 . 3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES OPERATING LIMITING CONDITION FOR OPERATION 3.8.1.1 As a minimum, the following A.C. electrical power sources shall be OPERABLE:
- a. Two physically independent circuits between the offsite transmission network and the onsite Class 1E distribution system, and
- b. Twc :eparate and independent diesel generators each with:
- 1. Separate day and engine-mounted fuel tanks containing a minimum of 900 gallons of fuel,
- 2. A separate fuel storage system containing a minimum of 17,500 gallons of fuel, and
- 3. A separate fuel transfer pump.
APPLICABILITY: MODES 1, 2, 3 and 4. ACTION:
- a. With one offsite circuit inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirement 4.8.1.1.1.a within 1 hour and at j least once per 8 hours thereafter. Restore the offsite circuit to OPERABLE status within 72 hours or be in at least HOT STANDBY within the next 6 hours and COLD SHUTDOWN within the following 30 hours.
- b. With one diesel generator m inoperable, demonstrate the OPERABILITY of the A.C. offsite sources by performing Surveillance Requirement 4. 8.1.1.1. a within 1 hour and at least once per 8 hours thereafter; and if the diesel generator became inoperable due to any cause other than an independently testable component, testing or preplanned preventative maintenance, demonstrate the OPERABILITY of the remaining OPERABLE diesel generator by performing (1) Fuel oil contained in the storage tanks not meeting the l properties in accordance with 4.8.1.1.2.d.2 or 4.8.1.1.2.e shall be brought within the specified limits within 7 days. j BEAVER VALLEY - UNIT 1 3/4 8-1 Amendment No.
(Proposed Wording) I l
DPR-66
. ELECTRICAL POWER SYSTEMS LIMITING CONDITION FOR OPERATION ACTION (Continued)
Surveillance Requirement 4.8.1.1.2.a.5 within 24 hours'*' unless the absence of any potential common mode failure for the remaining diesel generator is demonstrated. Restore the diesel generator to OPERABLE status within 72 hours or be in at least HOT STANDBY within the next 6 hours and in COLD SHUTDOWN within the following 30 hours, l
- c. With one offsite circuit and one diesel generator'"
inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours thereafter; and if the diesel generator became inoperable due to any cause other than an independently testable component, testing or preplanned preventative maintenance, demonstrate the OPERABILITY of the remaining OPERABLE diesel generator by performing Surveillance Requirement i 4.8.1.1.2.a.5 within 8 hours *8 unless the absence of any potential common mode failure for the remaining diesel generator is demonstrated. Restore one of the inoperable sources to OPERABLE status within 12 hours or be in at least HOT STANDBY within the next 6 hours and in COLD SHUTDOWN within the following 30 hours. Restore the other A.C. power source (offsite circuit or diesel generator) to OPERABLE status in accordance with the provisions of Action Statement a or b, as appropriate with the time requirement of that Action Statement based on the time of initial loss of the remaining inoperable A.C. power source. A successful test of diesel OPERABILITY per Surveillance Requirement 4.8.1.1.2.a.5 performed under this Action Statement for an OPERABLE diesel or a restored to OPERABLE diesel satisfies i the diesel generator test requirement of Action Statement b. (1) Fuel oil contained in the storage tanks not meeting the l properties in accordance with 4.8.1.1.2.d.2 or 4.8.1.1.2.e shall ! be brought within the specified limits within 7 days. (2) This action is required to be completed regardless of when the inoperable diesel generator is restored to OPERABILITY. BEAVER VALLEY - UNIT 1 3/4 8-2 Amendment No. (Proposed Wording) \ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ -_.
DPR-66 . ELECTRICAL POWER SYSTEMS LIMITING CONDITION FOR OPERATION I ACTION (Continued) l
- d. With two of the required offsite A.C. circuits inoperable, l restore one of the inoperable offsite sources to OPERABLE status within 24 hours or be in at least HOT STANDBY within ;
the next 6 hours. Following restoration of one offsite source, follow Action Statement a with the time requirement of that Action Statement based on the time of initial loss l of the remaining inoperable offsite A.C. circuit. l
- e. With two of the required diesel generators m inoperable, demonstrate the OPERABILITY of two offsite A.C. circuits by performing Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours thereafter; restore one of the inoperable diesel generators to OPERABLE status within 2 hours or be in at least HOT STANDBY within the next 6 hours and in COLD SHUTDOWN within the following 30 hours.
Following restoration of one diesel generator unit, follow Action Statement b with the time requirement of that Action Statement based on the time of initial loss of the remaining inoperable diesel generator. A successful test of diesel OPERABILITY per Surveillance Requirement 4.8.1.1.2.a.5 performed under this Action Statement for a restored to OPERABLE diesel satisfies the diesel generator test requirement of Action Statement b. SURVEILLANCE REQUIREMENTS 4.8.1.1.1 Two physically independent circuits between the offsite transmission network and the onsite Class 1E distribution system shall be:
- a. Determined OPERABLE at least once per 7 days by verifying correct breaker alignments, indicated power availability, and
- b. Demonstrated OPERABLE at least once per 18 months by transferring (manually and automatically) unit power supply from the unit circuit to the system circuit.
(1) Fuel oil contained in the storage tanks not meeting the l properties in accordance with 4.8.1.1.2.d.2 or 4.8.1.1.2.e shall be brought within the specified limits within 7 days. BEAVER VALLEY - UNIT 1 3/4 8-3 Amendment No. (Proposed Wording)
DPR-66 . ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued) 4.8.1.1.2 Each diesel generator shall be demonstrated OPERABLE:
- a. At least once per 31 days on a STAGGERED TEST BASIS by:
- 1. Verifying the fuel level in the day and engine-mounted fuel tank,
- 2. Verifying the fuel level in the fuel storage tank,
- 3. (Deleted)
- 4. Verifying the fuel transfer pump can be started and transfers fuel from the storage system to the day and engine-mounted tank,
- 5. Verifying the diesel starts from standby conditions,")
and can be gradually accelerated to synchronous speed with generator voltage"' 2 4106 volts and $ 4368 volts and frequency"' 2 58.8 Hz and 5 61.2 Hz 3
- 6. Verifying the generator is synchronized, loaded"' to l 2 1425 kw, and operates for 2 60 minutes, and
- 7. Verifying the diesel generator is aligned to provide standby power to the associated emergency busses.
- b. At least once per 18 months during shutdown by:
- 1. Subjecting the diesel to an inspection in accordance with procedures prepared in conjunction with its manufacturer's recommendations for this class of standby service,
- 2. Verifying the generator capability to reject a load of 2450 kw without tripping, (3) The values for voltage and frequency are analysis values and do not include measurement uncertainties.
(4) All diesel generator starts may be fellowed by a warmup period i prior to loading. l (5) Liesel generator loadings may include gradual loading as recommended by the manufacturer. BEAVER VALLEY - UNIT 1 3/4 8-4 Amendment No. (Proposed Wording) i i
1 DPR-66
. ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS:(Continued)
- 3. Simulating a loss of offsite power in conjunction with a safety injection signal, and:
a) Verifying de-energization of the emergency busses and load shedding from the emergency busses. b) - Verifying the diesel starts from standby conditions l on the auto-start signal, energizes the emergency busses 'with permanently connected loads in s 10 seconds, energizes the auto-connected emergency loads through the load sequencer and operates for 2 5 minutes while its generator is loaded with the emergency loads. After energization of these loads, the steady state voltage8 and freque.ncy8 shall be maintained at 2 4? O6 volts and s (368 volts, and 2 58.8 Hz and 5 61.2 Hz."8
- 4. Verifying that on a loss of power to the emergency-busses, all diesel generator trips, except engine overspeed, generator differential and overcurrent, are automatically disabledy l
- 5. Verifying the diesel generator operates for > 60 minutes while loaded to 2 2750 kw y (
- 6. Verifying that the auto-connected loads to each-diesel generator do not exceed the 2000 hour rating of 2850 kw jad I_
- 7. Verifying that ' the automatic load sequence timer is OPERABLE with each load sequence time within 10% of its required value.
- c. Check for and remove accumulated water:-
- 1. From,the day tank, at least once per 31 days and after each operation of the diesel where the period of operation was greater than 1 hour, and
- 2. From the fuel oil storage tank, at least once per 92 days.
(3) The values for voltage and frequency are analysis values and do not include measurement uncertainties. (6) The frequency limits apply for the diesel generator at full accident loading. Extrapolation of test data at lower loads can be performed to meet criteria. BEAVER VALLEY - UNIT 1 3/4 8-4a Amendment No. (Proposed Wording)
DPR-66 ) , ELECTRICAL POWER SYSTEMS ! SURVEILLANCE REQUIREMENTS (Continued)
- d. By sampling new fuel oil in accordance with ASTM D4057-81 prior to addition to the storage tanks and:
- 1. By verifying in accordance with the tests specified in ASTM D975-81 prior to addition to the storage tanks that !
the sample has: a) An API Gravity of within 0.3 degrees at 60*F or a specific gravity of within 0.0016 at 60/60*F, when compared to the supplier's certificate or an absolute specific gravity at 60/60*F of greater than or equal to 0.83 but less than or equal to 0.89 or an API gravity at 60*F of greeter than or equal to 27 degrees but less than or equal to 39 degrees, b) A kinematic viscosity at 40*C of greater than or equal to 1.9 centistokes, but less than or equal to 4.1 centistokes, if gravity was not determined by comparison with the supplier's certification, c) A flash point equal to or greater than 125*F, d) A water and sediment content of less than or equal to 0.05% when tested in accordance with ASTM D1796-83, and e) A total particulate contamination level of less than 10 mg/ liter when tested in accordance with ASTM D2276-78, Method A.
- 2. By verifying within 31 days of obtaining the sample that the other properties specified in Table 1 of ASTM D975-81 are met when tested in accordance with ASTM D975-81 except that the analysis for sulfur may be performed in accordance with ASTM D1552-79 or ASTM D2622-82.
- e. At least once every 31 days by obtaining a sample of fuel oil from the storage tanks and day tanks in accordance with ASTM D2276-78, and verifying that total particulate contamination is less than 10 mg/ liter when checked in accordance with ASTM D2276-78, Method A.
i BEAVER VALLEY - UNIT 1 3/4 8-4b Amendment No. l (Proposed Wording)
DPR-66 ELECTRICAL POWER SYSTEMS BASES A.C. SOURCES. D.C. SOURCES AND ONSITE POWER DISTRIBUTION SYSTEMS (Continued) Verifying average electrolyte temperature above the minimum for which the battery was sized, total battery terminal voltage on float charge, connection resistance values and the performance of battery service and discharge tests ensures the effectiveness of the charging system, the ability to handle high discharge rates and compares the battery capacity at that time with the rated capacity. Table 3.8-1 specifies the normal limits for each designated pilot cell , and each connected cell for electrolyte level, float voltage and specific gravity. The limits for the designated pilot cells float ' voltage and specific gravity, greater than 2.13 volts and .015 below - the manufacturer's full charge specific gravity or a battery charger current that had stabilized at a low value, is characteristic of a charged cell with adequate capacity. The normal limits for each connected cell for float voltage and specific gravity, greater than 2.13 volts and not more than .020 below the manufacturer's full charge specific gravity with an average specific gravity of all the connected cells not more than .010 below the manufacturer's full charge specific gravity, ensures the OPERABILITY and capability of the battery. Operation with a battery cell's parameter outside the normal limit but within the allowable value specified in Table 3.8-1 is permitted for up to 7 days. During this 7 day period: (1) the allowable values for electrolyte level ensures no physical damage to the plates with an adequate electron transfer capability; (2) the allowable value for the average specific gravity of all the cells, not more than .020 below the manufacturer's recommended full charge specific gravity, ensures ' that the decrease in rating will be less than the safety margin provided in sizing; (3) the allowable value for an individual cell's specific gravity, ensures that an individual cell's specific gravity will not be more than .040 below the manufacturer's full charge specific gravity and that the overall capability of the battery will be maintained within an acceptable limit; and (4) the allowable value , for an individual cell's float voltage, greater than 2.07 volts, l ensures the battery's capability to perform its design function. l Note (1) provides clarification of Specification 3.8.1.1 action l requirements when the diesel generators are inoperable as a result of Surveillance Requirements 4.8.1.1.2.d.2 and 4.8.1.1.2.e in accordance with Regulatory Guide 1.137 Revision 1 Regulatory Position C.2.a. For the purposes of SR 4.8.1.1.2.a.5 and SR 4.8.1.1.2.b.3.b testing, the diesel generators are started from standby conditions. Standby conditions for a diesel generator mean that the diesel engine oil is being continuously circulated and engine coolant and oil temperatures are being maintained consistent with manufacturer recommendations. BEAVER VALLEY - UNIT 1 B 3/4 8-2 Amendment No. (Proposed Wording)
ATTACHMENT C-2 Beaver Valley Power Station, Unit No. 2 . Proposed Technical Specification Change No. 90 l 1 l l Applicable Typed Pages . l 1 l 1 l 1 i 1 1 J l I l
ATTACHMENT TO LICENSE AMENDMENT NO. FACILITY OPERATING LICENSE NO. NPF-73 i DOCKET NO. 50-412 Replace the following pages of Appendix A, Technical Specifications, , with the enclosed pages as indicated. The revised pages are ; identified by amendment number and contain vertical lines indicating l the areas of change. i i Remove ID. sert . 3/4 8-1 3/4 8-1 3/4 8-2 3/4 8-2 3/4 8-3 3/4 8-3 3/4 8-4 3/4 8-4 3/4 8-5 3/4 8-5 3/4 8-Sa 3/4 8-5b B 3/4 8-3 B 3/4 8-3 t i i (Proposed Wording) < t
NPF-73 3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES e OPERATING LIMITING CONDITION FOR OPERATION 3.8.1.1 As a minimum, the following A.C. electrical power sources shall be OPERABLE:
- a. Two physically independent circuits between the offsite transmission network and the onsite Class 1E distribution system, and
- b. Two separate and independent diesel generators each with:
- 1. Separate day tank containing a minimum of 35G gallons of fuel,
- 2. A separate fuel storage system containing a minimum of 53,225 gallons of fuel,
- 3. A separate fuel transfer pump,
- 4. Lubricating oil storage containing a minimum total volume of 504 gallons of lubricating oil, and
- 5. Capability to transfer lubricating oil from storage to the diesel generator unit.
APPLICABILITY: MODES 1, 2, 3 and 4. ACTION:
- a. With one offsite circuit inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirement 4.8.1.1.1.a within 1 hour and at least once per 8 hours thereafter. Restore the offsite circuit to OPERABLE status within 72 hours or be in at least HOT STANDBY within the next 6 hours and COLD SHUTDOWN within the following 30 hours,
- b. With one diesel generhtor"3 inoperable, demonstrate the OPERABILITY of the A.C. offsite sources by performing Surveillance Requirement 4. 8.1.1.1. a within 1 hour and at least once per 8 hours thereafter; and if the diesel (1) Fuel oil contained in the storage tanks not meeting the l ;
properties in accordance with 4.8.1.1.2.d.2 or 4.8.1.1.2.e shall l be brought within the specified limits within 7 days. J 1 BEAVER VALLEY - UNIT 2 3/4 8-1 Amendment No. l (Proposed Wording)
NPF-73 , ELECTRICAL POWER SYSTEMS LIMITING CONDITION FOR OPERATION ACTION (Continued) generator became inoperable due to any cause other than an independently testable component, testing or preplanned preventative maintenance, demonstrate the OPERABILITY of the remaining OPERABLE diesel generator by performing Surveillance Requirement 4.8.1.1.2.a.5 within 24 hours' , unless the absence of any potential common mode failure for the remaining diesel generator is demonstrated. Restore the diesel generator to OPERABLE status within 72 hours or be in at least HOT STANDBY within the next 6 hours and in COLD SHUTDOWN within the following 30 hours.
- c. With one offsite circuit and one diesel generator
- inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirement
- 4. 8.1.1.1.a within one hour and at least once per 8 hours thereafter; and if the diesel generator became inoperable due to any cause other than an independently testable component, testing or preplanned preventative maintenance, demonstrate the OPERABILITY of the remaining OPERABLE diesel generator by performing
- Surveillance Requirement 4.8.1.1.2.a.5 within 8 hours unless the absence of any potential common mode failure for the remaining diesel L generator is demonstrated. Restore one of the inoperable sources to OPERABLE status within 12 hours or be in at least -
HOT STANDBY within the next 6 hours and in COLD SHUTDOWN within the following 30 hours. Restore the other A.C. power source (offsite circuit or diesel generator) to OPERABLE status in accordance with the provisions of Action Statement a or b, as appropriate with the time requirement of that Action Statement based on the time of initial loss of the remaining inoperable A.C. power source. A successful test- , OPERABILITY Requirement of diesel per Surveillance 4.8.1.1.2.a.5 performed under this Action Statement for an OPERABLE diesel or a restored to OPERABLE diesel satisfies the diesel generator test requirement of Action Statement b. (1) Fuel oil contained in the storage tanks not meeting the l properties in accordance with 4.8.1.1.2.d.2 or 4.8.1.1.2.e shall be brought within the specified limits within 7 days. (2) This action is required to be completed regardless of when the inoperable diesel generator is restored to OPERABILITY. BEAVER VALLEY - UNIT 2 3/4 8-2 Amendment No. (Proposed Wording)
t NPF-73. ! ELECTRICAL POWER SYSTEMS , i LIMITIha CONDITION.FOR OPERATION ; ACTION (Continued) ,
- d. With two of the required offsite A.C. circuits inoperable, restore one of the inoperable offsite sources to OPERABLE status within 24 hours or be in at least HOT STANDBY within the next 6 hours. Following restoration of one offsite source, follow Action Statement a with the time requirement of that Action Statement based on the time of initial loss i of the remaining inoperable offsite A.C. circuit.
- e. With two of the required diesel generators
- inoperable, I demoF L, ate the OPERABILITY of two offsite A.C. circuits by performing Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours thereafter; restore one of the inoperable diesel generators to OPERABLE status within 2 hours or be in at least HOT STANDBY within the next 6 hours and in COLD SHUTDOWN within the following 30 hours.
Following restoration of one diesel generator unit, follow Action Statement b with the time requirement of that Action i Statement based on the time of initial loss of the remaining inocerable diesel generator. A successful test of diesel OPERABILITY per Surveillance Requirement 4.8.1.1.2.a.5
- performed under this Action Statement for a restored to OPERABLE diesel satisfies the diesel generator test .
requirement of Action Statement b. j C SURVFILLA.' ICE REQUIREMENTS 4.8.1.* 1 Two physically independent circuits between the offsite ! transmission network and the on.3ite Class 1E distribution system shall l
- a. Determined OPERABLE at least once per 7 days by verifying '
correct breaker alignment, indicated power availability, and
- b. Demonstrated OPERABLE at least once per 18 months by transferring (manually and automatically) unit power supply from the unit circuit to the system circuit.
(1) Fuel oil contained in the storage tanks not meeting the l properties in accordance with 4.8.1.1.2.d.2 or 4.8.1.1.2.e shall l be brought within the specified limits within 7 days. ! BEAVER VALLEY - UNIT 2 3/4 8-3 Amendment No. (Proposed Wording) ,
NPF-73 ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued) 4.8.1.1.2 Each diesel generator shall be demonstrated OPERABLE:
- a. At least once per 31 days on a STAGGERED TEST BASIS by:
- 1. Verifying the fucl level in the day tank,
- 2. Verifying the fuel level in the fuel storage tank, '
- 3. (Deleted)
- 4. Verifying the fuel transfer pump can be started and transfers fuel from the storage system to the day tank,
- 5. Verifying the diesel starts from standby conditions,"3 and achieves steady state voltage"' of 2 3994 volts and 5 4368 volts and frequency'" of 2 58.8 Hz and 5 61.2 Hz)
- 6. Verifying the generator is s,1chronized, loaded") to 2 4,238 kw, and operates for 2 60 minutes,
- 7. Verifying the diesel generator is aligned to provide standby power to the associated emergency busses, and
- 8. Verifying the lubricating oil inventory in storage.
- b. At least once per 18 months during shutdown by: l
- 1. Subjecting the diesel to an inspection in accordance with procedures prepared in conjunction with its manufacturer's recommendations for this class of standby service,
- 2. Verifying tim nenerator capability to reject a load of 2 825 kw witnant tripping,
- 3. Simulating a loss of offsite power in conjunction with a safety injection signal, and:
a) Verifying de-energization of the emergency busses and load shedding from the emergency busses. (3) The values for voltage and frequency are analysis values and do not include measurement uncertainties. (4) All diesel generator starts may be preceded by an engine prelube period and followed by a warmup period prior to loading. I (5) Diesel generator loadings may include gradual loading as recommended by the manufacturer. , i BEAVER VALLEY - UNIT 2 3/4 8-4 Amendment No. (Proposed Wording)
NPF-73 l ... FLFCTRICAL POWER SYSTEMS j SURVEILLANCE REQUIREMENTS (Continued) ! l b) Verifying conditions
the diesel starts from standby on the auto-start signal, energizes the l
emergency busses with permanently connected loads in : 5 10 seconds, energizes the auto-connected emergency loads through the load sequencer and operates for ; 2 5 minutes while its generator is loaded with the - emergency loads. After energization of these loads, ! the steady state voltage'" and frequency'M shall be maintained at 2 3994 volts and 5 4368 volts, and i 2 58.8 Hz and 5 61.2 Hz.
- 4. Verifying that on a loss of power to the emergency ;
busses, all diesel generator trips, except engine ; overspeed, backup phase fault detection, generator l ; differential current, and generator overexcitation are automatically disabled) 1
- 5. Verifying the diesel generator operates for 2 60 minutes l !
while loaded to 2 4,238 kwy l
- 6. Verifying that the auto-connected loads to each diesel i generator do not exceed the 2000 hour rating of 4,535 kwf.dl
- 7. Verifying that the automatic load sequence timer is !
OPERABLE with each load sequence time within 110% of its ! required value. I
- c. Check for and remove accumulated water: ;
- 1. From the day tank, at least once per 31 days and after each operation of the diesel where the period of !
operation was greater than 1 hour, and !
- 2. From the fuel oil storage tank, at least once per 92 days. i
- d. By sampling new fuel oil in accordance with ASTM D4057-81 i prior to addition to the storage tanks and:
( (3) The values for voltage and frequency are analysis values and do not include measurement uncertainties. i (6) All diesel generator starts may be preceded by an engine prelube period. 1 1 BEAVER VALLEY - UNIT 2 3/4 8-5 Amendment No. (Proposed Wording)
] : 'MPF-73' ELECTRICAL POWER SYSTEMS i
SURVEILLANCE REQUIREMENTS (Continued)
- 1. By verifying in accordance with the test specified in ASTM D975-81 prior to addition to the storage tanks that ;
the sample has: a) An API Gravity of_within 0.3 degrees at 60*F or a specific gravity of within 0.0016 at 60/60*F, when , compared to the supplier's certificate or an absolute specific gravity at 60/60*F of greater than : or equal to 0.83 but less than or equal to 0.89 or ; an API gravity at 60*F of greater than or equal to ! 27 degrees but less than or equal to 39 degrees, , b) A kinematic viscosity at 40*C of greater than or ! equal to 1.9 centistokes, but less than or equal to ; 4.1 centistokes, if gravity was not determined by l comparison with the supplier's certification, ! c) A flash point equal to or greater than 125*F, d) A water and sediment content of less than or equal l to 0.05% when tested in accordance with ASTM D1796-83, and ; e) A total particulate contamination level of less than i 10 mg/ liter. When tested in accordance with ASTM , D2276-78, Method A.
- 2. By verifying within 31 days of obtaining the sample that the other properties specified in Table 1 of ASTM D975-81 are met when tested in accordance with ASTM D975-81 ,
except that the analysis for sulfur may be performed in accordance with ASTM D1552-79 or ASTM D2622-82. i
- e. At least once every 31 days by obtaining a sample of fuel l l oil from the storage tanks and day tanks in accordance with ASTM D2276-78, and verifying that total particulate contamination is less than 10 mg/ liter when checked in accordance with ASTM D2276-78, Method A.
i BEAVER VALLEY - UNIT 2 3/4 8-Sa Amendment No. l (Proposed Wording) , I,
NPF-73
- ,
- ELECTRICAL POWEP SYSTEMS SURVEILLANCE REQUIREMENTS (Continued)
- f. At least once per 10 years or after any modifications which {
could affect diesel generator interdependence by starting from standby conditions'" both diesel generators simultaneously, during shutdown, and verifying that each diesel generator achieves, in i 10 seconds, voltage 2 3994 volts and 5 4368 volts, and frequency'" 2 58.8 Hz and 5 61.2 , Hz.
- g. At least once per 10 years by draining each main fuel oil l storage tank, removing the accumulated sediment, and cleaning the tank using a sodium hypochlorite solution or other appropriate cleaning solution. l l l
l l l (3) The values for voltage and frequency are analysis values and do not include measurement uncertainties. 7 (6) All diesel generator starts may be preceded by an engine prelube period. l 1 i l { l l I BEAVER VALLEY - UNIT 2 3/4 8-Sb Amendment No. l (Proposed Wording)
l 1 i UPF-73 l s
3/4.8 ELECTRICAL POWER SYSTEMS 1 BASES i
3/4.8.1. 3/4.8.2 A.C. SOURCES AND ONSITE POWER DISTRIBUTION J (Continued) ! gravity will not be more than 0.040 below the manufacturer's full , charge specific gravity and that the overall capability of the battery i will be maintained within an acceptable limit; and 4) the allowable-value for an individual cell's float voltage, greater than 2.07 volts, j ensures the battery's capability to perform its design function. l. Note (1) provides clarification of Specification 3.8.1.1 Action l r I requirements when the diesel generators are inoperable as a result of Surveillance Requirements 4.8.1.1. 2.d.2 and 4. R .1.1.2.e in accordance j with Regulatory Guide 1.137, Revision 1, Position C.2.a. - For the purposes of SR 4.8.1.1.2.a.5, 4.8.1.1.2.b.3.b and j 4.8.1.1.2.f testing, the diesel generators are started from standby L conditions. Standby conditions for a diesel generator mean that the diesel engine coolant and oil are being continuously circulated and i temperatures are being maintained consistent with manufacturer i recommendations. , l t t t t i i l BEAVER VALLEY - UNIT 2 B 3/4 8-3 Amendment No. (Proposed Wording)
) . . - ..- _ . _ _ _ _}}