ML20069F982

From kanterella
Jump to navigation Jump to search
Brief in Response to ASLB 820902 Order Requesting Positions on Mootness of Low Power Issues.Aslb 820831 Initial Decision Does Not Moot Pending Appeal of Commission Authorization of Low Power License.Certificate of Svc Encl
ML20069F982
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 09/23/1982
From: Reynolds J
CENTER FOR LAW IN THE PUBLIC INTEREST, JOINT INTERVENORS - DIABLO CANYON
To:
NRC ATOMIC SAFETY & LICENSING APPEAL PANEL (ASLAP)
References
ISSUANCES-OL, NUDOCS 8209280314
Download: ML20069F982 (10)


Text

r DOLKETED USf4RC UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION s2 SEP 27 A10N9 BEFORE THE ATOMIC SAFETY AND LICENSING APPEAL BOARD 0FHCE Or bECRE

DCCS IWG A SIPD '

E3M' :t

)

In the Matter of )

)

PACIFIC GAS AND ELECTRIC COMPANY ) Docket Nos. 50-275 O.L.

) 50-323 0.L.

(Diablo Canyon Nuclear Power )

Plant, Units 1 and 2) )

)

)

JOINT INTERVENORS' BRIEF IN RESPONSE TO SEPTEMBER 2 ORDER By order dated September 2, 1982, the Atomic Safety and Licensing Appeal Board (" Appeal Board") requested all parties to the Diablo Canyon Nuclear Power Plant ("Diablo Canyon")

licensing proceeding to address the following question:

Whether the pending appeals from the July 17, 1981 Partial Initial Decision authorizing issuance of a low power operating license at Diablo Canyon are moot in light of (1) the August 31, 1982 Initial Decision authorizing full power licensing of the facility and (2) the November 19, 1981 suspension by the Commission of the low power operating license. For the reasons stated below, Joint Intervenors submit that the pending low power appeals are not moot.

6209280314 820923 PDR ADOCK 05000275 G PDR v503

In response to the Appeal Board's order, we have reviewed the issues raised and extensively briefed in Joint Intervenors' September 2, 1981 Brief in Support of Exceptions.

Those include:

(1) whether by its rejection of contentions the Licensing Board improperly denied Joint Intervenors' right to be heard under the Administrative Procedure Act, the Atomic Energy Act, and the Commission's December 18, 1980 Revised Statement of Policy and April 1, 1981 Order; (2) whether the Licensing Board erred in failing to require compliance with the Natural Environmental Policy Act prior to authorizing low power operations; (3) whether the Licensing Board's summary disposition of Joint Intervenors' contention thirteen

- regarding reactor vessel level indication was arbitrary and capricious; (4) whether the Licensing Board's conclusion regarding relief and safety valve testing was clearly erroneous; and (5) whether the Licensing Board erred in ruling that the state of emergency preparedness at Diablo Canyon complies with the Commission's revised emergency planning regulations.

In its August 31, 1982 Initial Decision regarding full power licensing, the Licensing Board considered contentions regarding (1) emergency preparedness and (2) the classification of certain reactor coolant system valves and pressurizer heaters. The issues considered related only to full power licensing; thus, their resolution by the Board did not by its terms dispose of pending low power issues. The question posed by the Appeal Board is, in essence, whether the Licensing Board's findings regarding full power licensing may have some bearing on aspects of the low nower proceeding appeal.

The first three low power appeal issues listed above are obviously unaffected by the Licensing Board's recent full power findings because they relate to matters outside the scope of the Initial Decision. Indeed, the Appeal Board, in footnote 2 of*its September 2 order, explicitly recognized that the ques-ion of a denial of contentions is a separable issue and will be dealt with accordingly. Similarly, the-low power appeal iacues relating to the failure to require compliance with the National Environmental Policy Act were not addressed by the Licensing Board in its recent decision on

. full power licensing and hence have not been mooted. Finally, Joint Intervenors' claim on appeal that the Licensing Board improperly granted summary di9p0aition of low power contention 13 is a question relating ini tb the low power proceeding. ,

The Licensing Board's ' G.2 ; .ct decision is, therefore, irrelevant to that issue.

-.-.,-...-,.-,----e. - , , , . ,

,__-,,-,,_,,an n -- , , , . , - . - , - . , , . .- ..-.-c , - - . - - - - - - -.,,-.-,,-,,.,.p,,.m -,p.,-- -

The fourth issue on appeal in the low power proceeding {

I challenges the Licensing Board's findings regarding the status of relief and safety valve testing. Because such testing was I discussed brief'.y by the Licensing Board in its August 31 Initial Decision, its factual findings are potentially relevant to the low power appeal to the extent that subsequent events may have eliminated the factual basis for Joint Intervenors' appeal. Significantly, however, in its Initial Decision, the Licensing Board has again based its approval of valve qualification and testing on results and documentation which "will" be submitted at some future date after the record has been closed. Initial Decision, at 84, 214. Thus, the Board is once again premising its decision on the expected submittal of test results by EPRI and the expected submittal of plant-specific-reports by the applicant. Such expectation does not provide adequate assurance for licensing of Diablo Canyca at any level of power.

Moreover, questions regarding the seismic design and qualification of the relief and safety valves have been raised as part of the ongoing design verification program, questions yet unresolved. It is inappropriate, therefore, for the Licensing Board to authorize licensing for low or full power operation until the proper design and qualification of these valves has been verified. The relevance of EPRI test results and, more generally, the basis for the necessary assurance of safety cannot be established either as a factual or legal

l I

matter until such verification has been completed. Hence, Joint Intervenors'-contention on appeal regarding valve testing and qualification is not moot.

Emergency preparedness at Diablo Canyon is a primary focus both of Joint Intervenors' low power appeal and of the Licensing Board's full power licensing Initial Decision.

However, in some respects -- for example, the failure of the

)

various emergency plans to address the complications of an earthquake on emergency response -- the Initial Decision is i

clearly irrelevant to the low power appeal because that issue was not addressed. Indeed, the Licensing Board refused even ,

to allow testimony on the issue in the' full power proceeding.

Its failure, therefore, to require thcc the various Diablo Canyon emergency plans consider the effects of earthquakes 1

must be reviewed by the Appeal Board as part of the low power 4 licensing appeal.

More broadly, Joint Interveaors' challenge to the adequacy of emergency preparedness at Diablo Canyon remains unchanged. The factual findings upon which the Licensing Board relied in authorizing low power licensing remain the

" law of the case"; the Commission's decision to issue the low I power license in September 1981 was predicated on those same findings. Because they constitute the sole basis for the j agency's final action, Joint Intervenors' challenge to those i

l findings on appeal remains a live controversy which has not L

l been mooted by the Licensing Board's full power decision.

i

Moreover, 10 C.F.R. S 2.764 establishes that an Initial Decision becomes effective only once the Commission has reviewed it and determined that it should become effective immediately. The Commission conducted such a review in the low power proceeding and based its decision to issue a license on that review. No similar review of the Licensing Board's August 31 Initial Decision on full power licensing has been conducted. Thus, the decision is not yet effective and cannot provide the basis for licensing at either low or full power.

The critical findings for purposes of the low power appeal continue to be those contained in the July 17, 1981 Partial Initial Decision, which was reviewed by the Commission prior to issuance of the now-suspended license.

Nor do the more recent factual findings of the Board regarding emergency preparedness, set forth in the August 31 Initial Decision, supply a basic sufficient to justify licensing even for low pc9er operation. At both the low and full power hearings, numerous deficiencies in compliance with the Commission's regulations were established, deficiencies so significant that denial of either of PGandE's license applications is warranted as a matter of law. While the development of emergency plans is now progressing, they are far from complete, particularly with respect to critical standard operating procedures, letters of agreement, public education programs, and the installation and/or repair of essential communications equipment. See Joint Intervenors' k

i Proposed Findings of Fact and Conclusions of Law (March 19, 1982); Joint Intervenors' Exceptions to the Licensing Board's Augur' 31, 1982 Initial Decision (September 16, 1982). PGandE has failed to demonstrate a level of preparedness for licensing at any level of power. Thus, even considering the most recent findings of the Licensing Board regarding PGandE's full power licensing application, Joint Intervenors' appeal of the Licensing Board's authorization of a low power license is not moot.

///

///

///

Accordingly, for all of the reasons stated, Joint Intervenors submit that the August 31, 1982 Initial Decision of the Licensing Board does not render moot their pending appeal of the Commission's authorization of licensing for low power operation.

DATED: September 23, 1982 Respectfully submitted, JOEL R. REYNOLDS, ESQ JOIIN R. PIIILLIPS , ESQ.

Center for Law in the Public Interest 10951 W. Pico Boulevard Los Angeles, CA 90064 (213)470-3000 DAVID S. FLEISCIIAKER, ESQ.

P.O. Box 1178 Oklahoma City, OK 73101 By EL R. REYlj0LDS Attorneys for Joint Inter-venors SAN LUIS OBISPO MOTIIERS FOR

! PEACE SCENIC SIIORELINE PRESERVATION CONFERENCE, INC.

ECOLOGY ACTION CLUB SANDRA SILVER ELIZABETII APFELBERG JOIIN J. FORSTER l

l l

l l

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING APPEAL BOARD

'I

)

In the Matter of )

)

l PACIFIC GAS AND ELECTRIC COMPANY ) Docket Nos. 50-275 0.L.

)- 50-323 O.L.

(Diablo Canyon Nuclear Power )

Plant, Units 1 and 2) )

)

)

i CERTIFICATE OF SERVICE I hereby certify that on this 23rd day of September, 1982, I have served copies of the foregoing JCINT INTERVENORS' BRIEF IN RESPONSE TO SEPTEMBER 2 ORDER, mailing them through the U.S.

mails, first class, postage prepaid.

  • Thomas S. Moore, Chairman i Atomic Safety & Licensing Appeal Board Mr. Fredrick Eissler U.S. Nuclear Regulatory Scenic Shoreline Preservation Commission Conference, Inc.

Washington, D.C. 20555 4623 More Mesa Drive Santa Barbara, CA 93105

+Dr. W. Reed Johnson Atomic Safety & Licensing Malcolm H. Furbush, Esq.

Appeal Board Vice President & General
U.S. Nuclear Regulatory Counsel Commission Philip A. Crane, Esq.

Washington, D.C. 20555 Pacific Gas & Electric Company Post Office Box 7442

  • Dr. John H. Buck San Francisco, CA 94106 Atomic Safety & Licensing '

j Appeal Board U.S. Nuclear Regulatory Commission Washington, D.C. 20555 i

  • By Express Mail l

- . . ~ . - . - - .

'3

  • Docket & Service Branch David S. Fleischaker Office of the Secretary Post Office Box 1178 U.S. Nuclear Regulatory Oklahoma City, OK 73101 ,

< Commission Washington, D.C. 20555 MHB Technical Associates 1723 Hamilton Avenue Bradley Jones, Esq. S"ite K DonaJJ F. Hassell, Esq. San Jose, CA 95725 Lawrence Chandler, Esq.

Office of the Executive Legal Arthur C. Gehr, Esq.

Director - BETH na? Snell & Wilmer U.C Nuclear Regulatory 3100 Valley Center Commi sion Phoenix, AZ 85073 Washington, D.C. 20555 Virginia and Gordon Bruno Herbert Brown, Esq. Pecho Ranch Lawrence Coe-Lanpher, Esq. Post Office Box 6289 Alan Dynner, Esq. Los Osos, CA 93402 11111, Christopher &

l Phillips Sandra and Gordon Silver 1900 M Street, N.W. 1760 Alisal Street Washington, D.C. 20036 San Luis Obispo, CA 93401 1

Byron Georgiou, Esq. Bruce Norton, Esq.

Legal Affairs Secretary to 3216 N. Third Street the Governor Suite 202 i State Capitol Building Phoenix, AZ 85012

Sacramento, CA 95814 Nancy Culver Jance E. Kerr, Esq. 192 Luneta i Lawrence Q. Garcia, Esq. San Luis Obispo, CA 93401 J. Calvin Simpson, Esq.

l California public Utilities Carl Neiburger d

Commissica Telegram Tribune i 5246 McAllister Street Post Office Box 112 San Francisco, CA 94102 San Luis O..ispo, CA 93402 l

I I

i l

ACLAhC_. 60MW AMANDA VARONA

  • By Express Mail

-.