MONTHYEARML20209H5051999-07-14014 July 1999 Proposed Tech Specs Pages 3.1-15 & 3.1-17 of Table 3.1.1 ML20209E0951999-07-0707 July 1999 Proposed Tech Specs,Changing Component Surveillance Frequencies to Indicate Frequency of Once Per Three Months ML20212H5441999-06-18018 June 1999 Proposed Tech Specs Reflecting Installation of Addl SFP Storage Racks That Will Accommodate Increase in Spent Fuel Assemblies Beyond Existing Storage Capacity of SFP as Described in Licensing Rept ML20195D0761999-06-0303 June 1999 Proposed Tech Specs,Permitting Plant Operation with Three Operable Recirculation Loops ML20205P8531999-04-15015 April 1999 Proposed Tech Specs,Modifying Number of Items in Sections 2 & 3 of Tss,Expanding Two Definitions in Section 1 & Modifying Bases Statements in Sections 2,3 & 4 ML20198K0671998-12-23023 December 1998 Proposed Tech Specs Pages 3.8-2 & 4.8-1,changed to Specify Surveillance Frequency of Once Per Three Months ML20195C6561998-11-10010 November 1998 Proposed Tech Specs Section 5.1.A,removing Restriction on Sale or Lease of Property within Exclusion Area ML20155J7501998-11-0505 November 1998 Proposed Tech Specs,Modifying Safety Limits & Surveillances of LPRM & APRM Sys & Related Bases to Ensure APRM Channels Respond within Necessary Range & Accuracy & to Verify Channel Operability ML20151V5091998-09-0303 September 1998 Proposed Tech Specs 3.4.A.10.e & 3.5.A.2.e Re Condensate Storage Tank Level ML20237D9591998-08-21021 August 1998 Proposed Tech Specs Removing Requirement for ADS Function of EMRV to Be Operable During Rv Pressure Testing & Correcting Note H of Table 3.1.1 ML20237B2221998-08-0606 August 1998 Proposed Revised Tech Specs Pages for Change Request 205,dtd 961031,correcting Minor & Inadvertent Editorial Changes in Locations Where Changes Have Not Been Proposed ML20236T1211998-07-23023 July 1998 Proposed Tech Specs Pages for Amend to License DPR-16,to Establish That Existing SLMCPR Contained in TS 2.1.A Is Applicable for Next Operating Cycle (Cycle 17) ML20236T4981998-07-21021 July 1998 Proposed Tech Specs Re Reactivity Control ML20236T4811998-07-21021 July 1998 Proposed Tech Specs Re Changes to Administrative Controls ML20236J1431998-06-30030 June 1998 Proposed Tech Specs,Consisting of Revised Page 3-5 Re RPV Pressure/Temp Limits ML20236H2181998-06-29029 June 1998 Proposed Tech Specs,Modifying EDG Insp Requirement Previously Submitted in Entirety ML20248K2851998-05-28028 May 1998 Proposed Tech Specs Re That Such First Type a Test Required by Primary Containment Leakage Rate Testing Program Be Performed During Refueling Outage 18R ML20197G2771997-12-23023 December 1997 Proposed Tech Specs Reflecting Change in Trade Name of Owner & Operator of Oyster Creek Nuclear Generating Station ML20197J2561997-12-10010 December 1997 Proposed Tech Specs Changing Pages 2.3-6,2.3-7,3.1-11, 3.1-14,3.1-16,3.4-8,3.8-2,3.8-3,4.3-1,4.5-13 & 6-1 ML20210L3311997-08-15015 August 1997 Proposed Tech Specs,Incorporating Note Which Indicates That Proposed Change to SL Mcrp Applicable for Current Operating Cycle (Cycle 16) Only ML20135C2001996-11-27027 November 1996 Proposed Tech Specs Pages 4.7-1,4.7-2,4.7-3 & 4.7-4 Re Surveillances for Station Batteries ML20129K3401996-11-12012 November 1996 Proposed Tech Specs,Consisting of Change Request 224, Implementing Revised 10CFR20, Stds for Protection Against Radiation Effective 910620 ML20134H0541996-10-31031 October 1996 Proposed Tech Spec,Requesting Deletion of Table 3.5.2 ML20129C0691996-10-10010 October 1996 Proposed Tech Specs,Clarifying Functional Requirement to Provide Interlock Permissive Which Ensures Source of Cooling Water Available Via Core Spray Sys Prior to Depressurization ML20129A5731996-10-10010 October 1996 Proposed Tech Specs,Revising Addl Group of Surveillances Where Justification Completed Following Receipt of Amend 144 ML20134F4101996-10-0404 October 1996 Proposed Tech Specs 2.1.A & 3.10.C to Reflect Change in SLMCPR & Revise Operating CPR Limit for Stability, Respectively ML20117E7061996-08-23023 August 1996 Proposed Tech Specs,Proposing New pressure-temp Limits Up to 22,27 & 32 EFPY Based on Predicted Nilductility Adjusted Ref Temp for Corrresponding EFPY of Operation ML20115G2101996-07-17017 July 1996 Proposed Tech Specs,Allowing Implementation of 10CFR,App J, Option B ML20113A8641996-06-19019 June 1996 Proposed Tech Specs Table of Contents,1.24 Re Footnote to definition,1.25 Re Definition,Section 3.5.A.3b Re Containment,Section 4.5 Re Containment,Bases for Section 4.5 & Section 6.9.3.b Re Reporting Requirements ML20111A3841996-05-0707 May 1996 Proposed Tech Specs,Adopting Provisions of STS NUREG-1433, Rev 1,dtd 950407,Sections SR 3.0.1,3.0.3 & Associated Bases ML20107E7751996-04-15015 April 1996 Proposed Tech Specs 5.3.1 Re Handling Heavy Loads Over Irradiated Fuel ML20101J7681996-03-28028 March 1996 Proposed Tech Specs,Modifying Statements in TS & Bases to Correctly Reflect Ref Parameter for Anticipatory Scram Signal Bypass ML20101J6091996-03-25025 March 1996 Proposed Tech Specs,Deleting Spec Which Requires Thorough Insp of EDG Every 24 Months During Shutdown ML20100J9151996-02-23023 February 1996 Proposed Tech Specs Re Implementation of 10CFR50,App J, Option B ML20100H9971996-02-22022 February 1996 Proposed Tech Specs 3.7-1,3.7-2,4.7-1 & 4.7-2 Re Deletion of TS Requirement to bi-annually Inspect EDG & Mod of Spec Re AOT ML20095C1031995-12-0505 December 1995 Proposed Tech Specs Re Rev of Submittal Date for Annual Exposure Data Rept Bringing Plant Into Conformance w/10CFR20.2206 & Relaxing Overly Restrictive Administrative Requirement ML20086A7161995-06-26026 June 1995 Proposed Tech Specs Re Performance of Reactor Shutdown & Drywell to Inspect Snubbers in Svc for Only 12 Months ML20080P6501995-02-28028 February 1995 Proposed Tech Specs Change Request 225 Re Change to Page 6-4 of Tech Spec Section 6.5.1.12.Change Consistent w/NUREG-1433,STSs General Electric Plants,BWR/4,Rev 0,dtd 920928 ML20078N3791995-02-0808 February 1995 Proposed Tech Specs Re Oyster Creek Spent Fuel Pool Expansion ML20078Q6481994-12-15015 December 1994 Revised TS & Bases Pages to Section 3.1 of TS Change Request 191 ML20078M1431994-11-25025 November 1994 Proposed TS 5.3.1.E,allowing 2,645 Fuel Assemblies to Be Stored in Fuel Pool ML20072S2921994-09-0202 September 1994 Proposed Tech Specs Supporting Rev of APRM Channel Calibr Interval from Weekly to Quarterly ML20072L4741994-08-19019 August 1994 Proposed Tech Specs Control Rod Exercising & Standby Liquid Control Pump Operability Testing ML20070E3411994-07-0808 July 1994 Proposed Tech Specs Re Improved Protection to Safety Related Electrical Equipment from Loss of Capability ML20078A7731994-06-24024 June 1994 Proposed Tech Specs Reflecting Removal of Recirculation Flow Scram ML20069M8231994-06-15015 June 1994 Proposed Tech Spec 2.3.D, Reactor High Pressure,Relief Valve Initiation ML20070R5261994-05-12012 May 1994 Proposed TS Sections 3.1 & 4.1 for Protective Instrumentation ML20029E0451994-05-0606 May 1994 Proposed Tech Specs Clarifying Requirements for Demonstrating Shutdown Margin ML20065M9991994-04-19019 April 1994 Proposed Tech Specs Updating & Clarifying TS 3.4.B.1 to Be Consistent W/Existing TS 1.39 & 4.3.D Re Five Electromatic Relief Valves Pressure Relief Function Inoperable or Bypassed During Sys Pressure Testing ML20029C7571994-04-15015 April 1994 Proposed TS Change Request 215,deleting Audit Program Frequency Requirements from TS 6.5.3 & Utilize Operational QA Plan as Controlling Document 1999-07-07
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML20212B5741999-09-0505 September 1999 Rev 11 to 2000-ADM-4532.04, Oyster Creek Emergency Offsite Dose Calculation Manual ML20209H5051999-07-14014 July 1999 Proposed Tech Specs Pages 3.1-15 & 3.1-17 of Table 3.1.1 ML20209E0951999-07-0707 July 1999 Proposed Tech Specs,Changing Component Surveillance Frequencies to Indicate Frequency of Once Per Three Months ML20212H5441999-06-18018 June 1999 Proposed Tech Specs Reflecting Installation of Addl SFP Storage Racks That Will Accommodate Increase in Spent Fuel Assemblies Beyond Existing Storage Capacity of SFP as Described in Licensing Rept ML20195D0761999-06-0303 June 1999 Proposed Tech Specs,Permitting Plant Operation with Three Operable Recirculation Loops ML20205P8531999-04-15015 April 1999 Proposed Tech Specs,Modifying Number of Items in Sections 2 & 3 of Tss,Expanding Two Definitions in Section 1 & Modifying Bases Statements in Sections 2,3 & 4 ML20198K0671998-12-23023 December 1998 Proposed Tech Specs Pages 3.8-2 & 4.8-1,changed to Specify Surveillance Frequency of Once Per Three Months ML20195C6561998-11-10010 November 1998 Proposed Tech Specs Section 5.1.A,removing Restriction on Sale or Lease of Property within Exclusion Area ML20155J7501998-11-0505 November 1998 Proposed Tech Specs,Modifying Safety Limits & Surveillances of LPRM & APRM Sys & Related Bases to Ensure APRM Channels Respond within Necessary Range & Accuracy & to Verify Channel Operability ML20151V5091998-09-0303 September 1998 Proposed Tech Specs 3.4.A.10.e & 3.5.A.2.e Re Condensate Storage Tank Level ML20237D9591998-08-21021 August 1998 Proposed Tech Specs Removing Requirement for ADS Function of EMRV to Be Operable During Rv Pressure Testing & Correcting Note H of Table 3.1.1 ML20237B2221998-08-0606 August 1998 Proposed Revised Tech Specs Pages for Change Request 205,dtd 961031,correcting Minor & Inadvertent Editorial Changes in Locations Where Changes Have Not Been Proposed ML20236T1211998-07-23023 July 1998 Proposed Tech Specs Pages for Amend to License DPR-16,to Establish That Existing SLMCPR Contained in TS 2.1.A Is Applicable for Next Operating Cycle (Cycle 17) ML20236T4811998-07-21021 July 1998 Proposed Tech Specs Re Changes to Administrative Controls ML20236T4981998-07-21021 July 1998 Proposed Tech Specs Re Reactivity Control ML20236J1431998-06-30030 June 1998 Proposed Tech Specs,Consisting of Revised Page 3-5 Re RPV Pressure/Temp Limits ML20236H2181998-06-29029 June 1998 Proposed Tech Specs,Modifying EDG Insp Requirement Previously Submitted in Entirety ML20248K2851998-05-28028 May 1998 Proposed Tech Specs Re That Such First Type a Test Required by Primary Containment Leakage Rate Testing Program Be Performed During Refueling Outage 18R ML20197G2771997-12-23023 December 1997 Proposed Tech Specs Reflecting Change in Trade Name of Owner & Operator of Oyster Creek Nuclear Generating Station ML20197J2561997-12-10010 December 1997 Proposed Tech Specs Changing Pages 2.3-6,2.3-7,3.1-11, 3.1-14,3.1-16,3.4-8,3.8-2,3.8-3,4.3-1,4.5-13 & 6-1 ML20210L3311997-08-15015 August 1997 Proposed Tech Specs,Incorporating Note Which Indicates That Proposed Change to SL Mcrp Applicable for Current Operating Cycle (Cycle 16) Only ML20135C2001996-11-27027 November 1996 Proposed Tech Specs Pages 4.7-1,4.7-2,4.7-3 & 4.7-4 Re Surveillances for Station Batteries ML20129K3401996-11-12012 November 1996 Proposed Tech Specs,Consisting of Change Request 224, Implementing Revised 10CFR20, Stds for Protection Against Radiation Effective 910620 ML20134H0541996-10-31031 October 1996 Proposed Tech Spec,Requesting Deletion of Table 3.5.2 ML20129C0691996-10-10010 October 1996 Proposed Tech Specs,Clarifying Functional Requirement to Provide Interlock Permissive Which Ensures Source of Cooling Water Available Via Core Spray Sys Prior to Depressurization ML20129A5731996-10-10010 October 1996 Proposed Tech Specs,Revising Addl Group of Surveillances Where Justification Completed Following Receipt of Amend 144 ML20134F4101996-10-0404 October 1996 Proposed Tech Specs 2.1.A & 3.10.C to Reflect Change in SLMCPR & Revise Operating CPR Limit for Stability, Respectively ML20117E7061996-08-23023 August 1996 Proposed Tech Specs,Proposing New pressure-temp Limits Up to 22,27 & 32 EFPY Based on Predicted Nilductility Adjusted Ref Temp for Corrresponding EFPY of Operation ML20115G2101996-07-17017 July 1996 Proposed Tech Specs,Allowing Implementation of 10CFR,App J, Option B ML20113A8641996-06-19019 June 1996 Proposed Tech Specs Table of Contents,1.24 Re Footnote to definition,1.25 Re Definition,Section 3.5.A.3b Re Containment,Section 4.5 Re Containment,Bases for Section 4.5 & Section 6.9.3.b Re Reporting Requirements ML20111A3841996-05-0707 May 1996 Proposed Tech Specs,Adopting Provisions of STS NUREG-1433, Rev 1,dtd 950407,Sections SR 3.0.1,3.0.3 & Associated Bases ML20107E7751996-04-15015 April 1996 Proposed Tech Specs 5.3.1 Re Handling Heavy Loads Over Irradiated Fuel ML20101P1561996-03-31031 March 1996 Rev 9 to Oyster Creek Nuclear Generating Station Pump & Valve IST Program ML20101J7681996-03-28028 March 1996 Proposed Tech Specs,Modifying Statements in TS & Bases to Correctly Reflect Ref Parameter for Anticipatory Scram Signal Bypass ML20101J6091996-03-25025 March 1996 Proposed Tech Specs,Deleting Spec Which Requires Thorough Insp of EDG Every 24 Months During Shutdown ML20100J9151996-02-23023 February 1996 Proposed Tech Specs Re Implementation of 10CFR50,App J, Option B ML20100H9971996-02-22022 February 1996 Proposed Tech Specs 3.7-1,3.7-2,4.7-1 & 4.7-2 Re Deletion of TS Requirement to bi-annually Inspect EDG & Mod of Spec Re AOT ML20095C1031995-12-0505 December 1995 Proposed Tech Specs Re Rev of Submittal Date for Annual Exposure Data Rept Bringing Plant Into Conformance w/10CFR20.2206 & Relaxing Overly Restrictive Administrative Requirement ML20086A7161995-06-26026 June 1995 Proposed Tech Specs Re Performance of Reactor Shutdown & Drywell to Inspect Snubbers in Svc for Only 12 Months ML20080P6501995-02-28028 February 1995 Proposed Tech Specs Change Request 225 Re Change to Page 6-4 of Tech Spec Section 6.5.1.12.Change Consistent w/NUREG-1433,STSs General Electric Plants,BWR/4,Rev 0,dtd 920928 ML20078N3791995-02-0808 February 1995 Proposed Tech Specs Re Oyster Creek Spent Fuel Pool Expansion ML20078Q6481994-12-15015 December 1994 Revised TS & Bases Pages to Section 3.1 of TS Change Request 191 ML20078M1431994-11-25025 November 1994 Proposed TS 5.3.1.E,allowing 2,645 Fuel Assemblies to Be Stored in Fuel Pool ML20073F9501994-09-26026 September 1994 Revised Plan for Long Range Planning Program for Oyster Creek Nuclear Generating Station ML20073F9411994-09-26026 September 1994 Revised Plan for Long Range Planning Program for TMI Nuclear Station Unit 1 ML20072S2921994-09-0202 September 1994 Proposed Tech Specs Supporting Rev of APRM Channel Calibr Interval from Weekly to Quarterly ML20072Q4251994-08-20020 August 1994 Rev 0 to Oyster Creek Nuclear Generating Station Sea Turtle Surveillance,Handling & Reporting Instructions for Operations Personnel ML20072L4741994-08-19019 August 1994 Proposed Tech Specs Control Rod Exercising & Standby Liquid Control Pump Operability Testing ML20070J7971994-07-31031 July 1994 Rev 8 to Oyster Creek Nuclear Generating Station Pump & Valve Inservice Testing Program ML20070E3411994-07-0808 July 1994 Proposed Tech Specs Re Improved Protection to Safety Related Electrical Equipment from Loss of Capability 1999-09-05
[Table view] |
Text
.
not to exceed 7 days in any 30 day period if a startup transformer is out of service. None of the I
engineered safety feature equipment fed by the remaining transformer may be out of service.
- 2. The reactor may remain in operation for a period not to exceed 7 days if 125 VDC Motor control Center DO-2 is out of service, provided the requirements of specification 3.8 are met.
C. Standby Diesel Generators 1
- 1. The reactor shall not be made critical unless both diesel generators are operable and capable of feeding their designt.ted 4160 volt buses.
- 2. If one diesel generator becomes inoperable during power operation, repairs shall be initiated immediately and the other diesel shall be operated at least one hour every 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> at greater than 20%
rated power until repairs are completed. -The reactor may remain in operation for a period not to exceed 7 days in any 30-day period if a diesel generator is out of service. During the repair period none of the engineered safety features normally fed by the operational diesel generator may be out of service or the reactor shall be placed in the celd shutdown condition.
- 3. If both ditsel generators become inoperable during power operation, the reactor shall be placed in the cold shutdosn condition.
- 4. For the diesel generators to be considered operable:
A) There atall be a minimum of 14,000 gallons of diesel fuel in the standby diesel generator fuel tank, OR B) To facilitate inspection, repair, or replacement of equipment which would require full or partial draining of the standby diesel generator fuel tank, the following conditions must be met:
- 1) There shall be a minimum of 14,000 gallons of fuel oil contained in temporary tanker trucks, connected and aligned to the diesel generator fill station.
OYSTER CREEK 3.7-2 l-l 9012170168 901207 PDR ADOCK 05000219 p PDR L. . ._ . _ . . _ _ _ _ . , - _ _ . _ _ . . . . ___ _._ - _ , - ~ _ _ _ _ . _ _ . . . . , _
-AND-
- 2) The reactor cavity shall be flooded above elevation 117 feet with the spent fuel pool gates removed, or all reactor fuel shall be contained in the spent fuel pool with spent fuel pool gates installed.
AND
- 3) The plant shall be placed in a configuration in wh.tch the core spray system is not required to be operable.
Baees: The general objective is to assure an adequate supply of power with at least one active and one standby source of power available for operation of equipment required for a safe plant
]
shutdown, to maintain the plant in a safe shutdown condition j and to operate the required engineered safety feature equipment following an accident.
AC power for shutdown and operation of engineered safety feature ,
equipment can be provided by any of four active (two 230 KV and two '
34.5 KV lines) and either of two standby (two diesel generators) sources of powor. Normally all six sources are available. However, to provide for maintenance and repair of equipment and still have redundancy of power sour:es the requirement of one active and one standby source of power was established. The plant's main generator is not given credit as a source since it is not available during shutdown.
The plant IPSV DC syatem consists of three batteries and associated distribution synten. Batteries B and C are designated as the safety related subsystems while battery A is designated as a non-safety related subsystem. Safety related loads are supplied by batteries B and C, each with two associated full capacity chhrgers. One charger on each battery is in service at all tires with the second charger available in the event of charger failure. These chargers are active sources and supply the normal 12iv DC requiraments with the batteries and standby sources. (1)
In applying the minimum requirement of one active and one standby
! source of AC power, since both 230 KV lines are on the same set of towers, either one or both 230 KV lines are considered as a single l active source.
The probability analyals in Appendix "L" of the FDSAR was based on one diesel and shows that even with only one diesel the probability of requiring engineered safety features at the same time as the second diesel fails is quite small. The analysis.used information en peaking diesels when synchronisation was required which is not the case for Oyster Creek. Also the daily test of the second diesel when one is temporarily out of service tends to improve the reliability as does the fact that synchronization is not required.
OYSTER CREEK 3.7-3
,a indicated in Amendment 18 to the Licensing Application, there are numerous sources of diesel fuel which can be obtained within 5 to 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and the heating boiler fuel in a 75,000 gallon tank on the
! site could also be used. As indicated in Amendment 32 of the Licensing Application and including the Security System loads, the load requirement for the loss of of f site power would require 12,410 gallone for a three day supply. For the case of loss of offsite power plus loss-of-coolant plus bus failure 9790 gallone would be
, required for a three day supply, i
In the case of loss of offsite power plus loss-of-coolant with both diesel generators starting the load requirements (all equipment i operating) shown there would not be three days' supply. Howev .,
not all of this load is required for three days and, after evaluation of the conditions, loads not required on the diesel will be curtailed. It is reasonable to expect that within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> conditions can be evaluated and the following loads curtailed
- 1. One Core Spray Pump
- 2. One Core Spray Booster Pump
- 3. One Control Rod Drive Pump
- 4. One Containment Spray Pump
- 5. One Emergency Service Water Pump With these pieces of equipment taken off at 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> after the incident it would require a total consumption of 12,840 gallons for a three day supply. Therefore, a minimum technical specification requirement of 14,000 gallons of diesel fuel in the standby diesel generator fuel tank will exceed the engineered safety features operational requiremont after an accident by approximately 9%.
During plant cold shutdown or refueling, it may be necessary to inspect, repair and replace the 15,000 gallon standby diesel <
generator furi storage tank. This would require tank partial or full drain dosn. An alternate fuel supply configuration may be established which consists of temporary tanter trucks capable of containing 14,000 gallons. This configuration is capable of supporting continuous operation of both diesels for at least 3 days.
The temporary configuration is acceptable since a minimal power load would be required during and following a design basis condition of a loss of offsite power while the plant is in cold shutdown or refueling. Analysis shows that in the event of a tornado or seismic event which may cause a loss of offsite power and a temporary loss of the temporary EDG fuel oil supply, power can be restored before the ceneequen:es of previously analyzed conditions are exceeded.
Referencess (1) Letter, Ivan R. Finfrock, Jr. to the Director of Nuclear Reactor l
Regulation dated April 14, 1978.
OYSTER CREEK 3.7-4