ML20212B5745 September 1999Rev 11 to 2000-ADM-4532.04, Oyster Creek Emergency Offsite Dose Calculation ManualGrab sample
Offsite Dose Calculation Manual
Annual Radioactive Effluent Release Report
ML20209H50514 July 1999Proposed Tech Specs Pages 3.1-15 & 3.1-17 of Table 3.1.1
ML20209E0957 July 1999Proposed Tech Specs,Changing Component Surveillance Frequencies to Indicate Frequency of Once Per Three Months
ML20212H54418 June 1999Proposed Tech Specs Reflecting Installation of Addl SFP Storage Racks That Will Accommodate Increase in Spent Fuel Assemblies Beyond Existing Storage Capacity of SFP as Described in Licensing ReptHydrostatic
ML20195D0763 June 1999Proposed Tech Specs,Permitting Plant Operation with Three Operable Recirculation LoopsShutdown Margin
Anticipated operational occurrence
Hydrostatic
Fuel cladding
ML20205P85315 April 1999Proposed Tech Specs,Modifying Number of Items in Sections 2 & 3 of Tss,Expanding Two Definitions in Section 1 & Modifying Bases Statements in Sections 2,3 & 4Shutdown Margin
Earthquake
Fuel cladding
ML20198K06723 December 1998Proposed Tech Specs Pages 3.8-2 & 4.8-1,changed to Specify Surveillance Frequency of Once Per Three Months
ML20195C65610 November 1998Proposed Tech Specs Section 5.1.A,removing Restriction on Sale or Lease of Property within Exclusion AreaShutdown Margin
Offsite Dose Calculation Manual
Hydrostatic
Annual Radiological Environmental Operating Report
ML20155J7505 November 1998Proposed Tech Specs,Modifying Safety Limits & Surveillances of LPRM & APRM Sys & Related Bases to Ensure APRM Channels Respond within Necessary Range & Accuracy & to Verify Channel OperabilityScram Discharge Volume
Fuel cladding
ML20151V5093 September 1998Proposed Tech Specs 3.4.A.10.e & 3.5.A.2.e Re Condensate Storage Tank Level
ML20237D95921 August 1998Proposed Tech Specs Removing Requirement for ADS Function of EMRV to Be Operable During Rv Pressure Testing & Correcting Note H of Table 3.1.1
ML20237B2226 August 1998Proposed Revised Tech Specs Pages for Change Request 205,dtd 961031,correcting Minor & Inadvertent Editorial Changes in Locations Where Changes Have Not Been ProposedEarthquake
ML20236T12123 July 1998Proposed Tech Specs Pages for Amend to License DPR-16,to Establish That Existing SLMCPR Contained in TS 2.1.A Is Applicable for Next Operating Cycle (Cycle 17)Fuel cladding
ML20236T48121 July 1998Proposed Tech Specs Re Changes to Administrative ControlsHydrostatic
Fuel cladding
ML20236T49821 July 1998Proposed Tech Specs Re Reactivity Control
ML20236J14330 June 1998Proposed Tech Specs,Consisting of Revised Page 3-5 Re RPV Pressure/Temp Limits
ML20236H21829 June 1998Proposed Tech Specs,Modifying EDG Insp Requirement Previously Submitted in Entirety
ML20248K28528 May 1998Proposed Tech Specs Re That Such First Type a Test Required by Primary Containment Leakage Rate Testing Program Be Performed During Refueling Outage 18RFire Barrier
Probabilistic Risk Assessment
Large early release frequency
ML20197G27723 December 1997Proposed Tech Specs Reflecting Change in Trade Name of Owner & Operator of Oyster Creek Nuclear Generating StationOffsite Dose Calculation Manual
Annual Radioactive Effluent Release Report
Process Control Program
Fire Protection Program
ML20197J25610 December 1997Proposed Tech Specs Changing Pages 2.3-6,2.3-7,3.1-11, 3.1-14,3.1-16,3.4-8,3.8-2,3.8-3,4.3-1,4.5-13 & 6-1Ultimate heat sink
Fuel cladding
ML20210L33115 August 1997Proposed Tech Specs,Incorporating Note Which Indicates That Proposed Change to SL Mcrp Applicable for Current Operating Cycle (Cycle 16) OnlyFuel cladding
ML20135C20027 November 1996Proposed Tech Specs Pages 4.7-1,4.7-2,4.7-3 & 4.7-4 Re Surveillances for Station Batteries
ML20129K34012 November 1996Proposed Tech Specs,Consisting of Change Request 224, Implementing Revised 10CFR20, Stds for Protection Against Radiation Effective 910620Shutdown Margin
High Radiation Area
Offsite Dose Calculation Manual
Hydrostatic
Annual Radiological Environmental Operating Report
Deep Dose Equivalent
Power change
ML20134H05431 October 1996Proposed Tech Spec,Requesting Deletion of Table 3.5.2
ML20129C06910 October 1996Proposed Tech Specs,Clarifying Functional Requirement to Provide Interlock Permissive Which Ensures Source of Cooling Water Available Via Core Spray Sys Prior to Depressurization
ML20129A57310 October 1996Proposed Tech Specs,Revising Addl Group of Surveillances Where Justification Completed Following Receipt of Amend 144Scram Discharge Volume
ML20134F4104 October 1996Proposed Tech Specs 2.1.A & 3.10.C to Reflect Change in SLMCPR & Revise Operating CPR Limit for Stability, RespectivelyAnticipated operational occurrence
Fuel cladding
ML20117E70623 August 1996Proposed Tech Specs,Proposing New pressure-temp Limits Up to 22,27 & 32 EFPY Based on Predicted Nilductility Adjusted Ref Temp for Corrresponding EFPY of OperationHydrostatic
ML20115G21017 July 1996Proposed Tech Specs,Allowing Implementation of 10CFR,App J, Option BHigh Radiation Area
Offsite Dose Calculation Manual
Fuel cladding
ML20113A86419 June 1996Proposed Tech Specs Table of Contents,1.24 Re Footnote to definition,1.25 Re Definition,Section 3.5.A.3b Re Containment,Section 4.5 Re Containment,Bases for Section 4.5 & Section 6.9.3.b Re Reporting RequirementsHigh Radiation Area
Offsite Dose Calculation Manual
Fuel cladding
ML20111A3847 May 1996Proposed Tech Specs,Adopting Provisions of STS NUREG-1433, Rev 1,dtd 950407,Sections SR 3.0.1,3.0.3 & Associated BasesTime of Discovery
ML20107E77515 April 1996Proposed Tech Specs 5.3.1 Re Handling Heavy Loads Over Irradiated FuelHydrostatic
ML20101P15631 March 1996Rev 9 to Oyster Creek Nuclear Generating Station Pump & Valve IST ProgramSafe Shutdown
High Radiation Area
Stroke time
ML20101J76828 March 1996Proposed Tech Specs,Modifying Statements in TS & Bases to Correctly Reflect Ref Parameter for Anticipatory Scram Signal BypassScram Discharge Volume
ML20101J60925 March 1996Proposed Tech Specs,Deleting Spec Which Requires Thorough Insp of EDG Every 24 Months During ShutdownSafe Shutdown
ML20100J91523 February 1996Proposed Tech Specs Re Implementation of 10CFR50,App J, Option B
ML20100H99722 February 1996Proposed Tech Specs 3.7-1,3.7-2,4.7-1 & 4.7-2 Re Deletion of TS Requirement to bi-annually Inspect EDG & Mod of Spec Re AOT
ML20095C1035 December 1995Proposed Tech Specs Re Rev of Submittal Date for Annual Exposure Data Rept Bringing Plant Into Conformance w/10CFR20.2206 & Relaxing Overly Restrictive Administrative Requirement
ML20086A71626 June 1995Proposed Tech Specs Re Performance of Reactor Shutdown & Drywell to Inspect Snubbers in Svc for Only 12 Months
ML20080P65028 February 1995Proposed Tech Specs Change Request 225 Re Change to Page 6-4 of Tech Spec Section 6.5.1.12.Change Consistent w/NUREG-1433,STSs General Electric Plants,BWR/4,Rev 0,dtd 920928
ML20078N3798 February 1995Proposed Tech Specs Re Oyster Creek Spent Fuel Pool ExpansionHydrostatic
ML20078Q64815 December 1994Revised TS & Bases Pages to Section 3.1 of TS Change Request 191Scram Discharge Volume
Power change
ML20078M14325 November 1994Proposed TS 5.3.1.E,allowing 2,645 Fuel Assemblies to Be Stored in Fuel PoolHydrostatic
ML20073F95026 September 1994Revised Plan for Long Range Planning Program for Oyster Creek Nuclear Generating Station
ML20073F94126 September 1994Revised Plan for Long Range Planning Program for TMI Nuclear Station Unit 1
ML20072S2922 September 1994Proposed Tech Specs Supporting Rev of APRM Channel Calibr Interval from Weekly to QuarterlyScram Discharge Volume
ML20072Q42520 August 1994Rev 0 to Oyster Creek Nuclear Generating Station Sea Turtle Surveillance,Handling & Reporting Instructions for Operations Personnel
ML20072L47419 August 1994Proposed Tech Specs Control Rod Exercising & Standby Liquid Control Pump Operability TestingShutdown Margin
ML20070J79731 July 1994Rev 8 to Oyster Creek Nuclear Generating Station Pump & Valve Inservice Testing ProgramSafe Shutdown
Stroke time
ML20070E3418 July 1994Proposed Tech Specs Re Improved Protection to Safety Related Electrical Equipment from Loss of CapabilityFuel cladding