ML20062L284

From kanterella
Jump to navigation Jump to search
Rev 0 to Speakout Program Instruction SPI-13, Verification of Concerns
ML20062L284
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 02/24/1992
From:
HOUSTON LIGHTING & POWER CO.
To:
Shared Package
ML20062K985 List:
References
SPI-13, NUDOCS 9312290272
Download: ML20062L284 (2)


Text

.

.y STP 724 (02/90) s

"" U'"

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION 7

SPEAK 0UT PROGRAM INSTURCTION SPI-13 SPI-13 0

PAGE 1

& 2 Verification of Concerns EFFECTIVE DATE 02/24/92 1.O PURPOSE This instruction establish'is how SPEAKOUT will perform documented follow-up verifications on response actions to concern recommendations and how SPEAKOUT will disseminate information to Quality Assurance regarding actions taken for concerns for follow-up and effectiveness evaluation during quality verification activities.

2.0 SCOPE 1

This instruction applies to response actions to concern recommendations which are not related to individual disciplinary actions.

Items which could cause a

perception that the integrity of the SPEAKOUT program has not been maintained will not be disseminated to Quality Assurance.

3.0 DEFINITIONS Refer to Section IV, Appendix C, Definitions.

4.O REFERENCES Quality Assurance Department Memo of December 1,

1992,

" Quality Assurance Review of Maintenance Journeyman Basic Qualification Records and Work Definitions Problems".

4 5.o RESPONSIBILITIES 5.1 The

Manager, Quality Performance /SPEAKOUT is responsible for the maintenance and implementation of this instruction.

5.2 The Manager, Quality Performance /SPEAKOUT is responsible for ensuring that follow-up verifications on response actions to concern recommendations are performed and documented.

6.0 REQUIREMENTS 6.1 The

Manager, Quality Performance /SPEAKOUT will assign an individual to verify that a response action has been completed.

i 9312290272 900921 PDR ADDCK 05000498 J

P PDR

]

1 4

I i

STP 724 (02/90)

""8" SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION E-SPEAKOUT PROGRAM INSTRUCTION SPI-13 SPI-13 0

Verification of Concerns 2

2 EFFECTIVE DATE 02/24/92 6.2 The assigned individual will verify that objective evidence of the completion of the action exists.

6.3 The individual Will provide docusentation of the verification for the

Manager, Quality Performance /SPEAKOUT's review.

6.4 The documentated verification will be filed with 1

the originating SPEAKOUT concern.

6.5 The

Manager, Quality Performance /SPEAKOUT will review investigation reports and disseminate appropriate information to Quality Assurance regarding actions taken for concerns for follow-up and effectiveness evaluation during quality verification activities.

b Approvekw

,