Text
STP 724 (02/90)
"8" SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION 7
SPEAK 0UT PROGRAM INSTRUCTION SPI-07 SPI-07 2
SPEAK 0UT REPORTS PAGE 1 OF 2 trrtenvr DAE 3/2/93 1.0 PURPOSE This instruction establishes SPEAKOUT Report requirements and defines the type, purpose and content of the SPEAKOUT Report.
2.0 SCOPE This instruction applies to the SPEAKOUT Monthly Report.
The SPEAKOUT Monthly Report is a manually produced report that provides a brief summary of the SPEAKOUT activities for the previous month.
3.0 DEFINITIONS Refer to Section IV, Appendix C, Definitions.
4.0 REFERENCES
4.1 SPEAKOUT Program Instruction
- Manual, SPI-02, Classificatioin of Concerns.
4.2 SPEAKOUT Program Instruction Manual, SPI-06, Filing and Tracking of Concerns.
5.0 RESPONSIBILITIES 5.1 The Manager, Quality Performance /SPEAKOUT, has the overall responsibility for the implementation, maintenance and updating of this instruction.
6.0 REQUIREMENTS 6.1. The
- Manager, Quality Performance /SPEAKOUT will assure accurate and updated information is obtained for the SPEAKOUT Monthly Report.
6.1.1 The SPEAKOUT Monthly Report is provided at a specified period of time.
9312290237 900921 PDR ADOCK 05000498 p
PDR i
STP 724 (02/90)
NUMBER EV.
SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION SPEAK 0UT PROGRAM INSTRUCTION SPI-07 SPI-07 2
PAGE OF SPEAKOUT REPORTS 2
2 UTECTIVE DATE 3/2/93 7.0 DOCUMENTATION SPEAKOUT Monthly Report 8.0 Attachments None i
l i
)