MONTHYEARIR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) ML23243A9272023-09-19019 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) IR 05000334/20230022023-08-0909 August 2023 Integrated Inspection Report 05000334/2023002 and 05000412/2023002 ML23157A1072023-06-0707 June 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000334/2023011 and 05000412/2023011 IR 05000334/20230012023-05-0808 May 2023 Integrated Inspection Report 05000334/2023001 and 05000412/2023001 L-23-058, 180-Day Steam Generator Tube Inspection Report2023-03-27027 March 2023 180-Day Steam Generator Tube Inspection Report IR 05000334/20230102023-03-0808 March 2023 Biennial Problem Identification and Resolution Inspection Report 05000334/2023010 05000412/2023010 IR 05000334/20220062023-03-0101 March 2023 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2022006 and 05000412/2022006) IR 05000334/20220042023-02-0909 February 2023 Integrated Inspection Report 05000334/2022004 and 05000412/2022004 IR 05000334/20224012023-01-0909 January 2023 Security Baseline Inspection Report 05000334/2022401 and 05000412/2022401 (Cover Letter Only) ML22314A2682022-12-16016 December 2022 Review of the Fall 2021 2R22 Steam Generator Tube Inspection 180 Day Report IR 05000334/20220032022-11-10010 November 2022 Integrated Inspection Report 05000334/2022003 and 05000412/2022003 and Independent Spent Fuel Storage Installation Inspection Report 07201043/2022001 IR 05000334/20220052022-08-31031 August 2022 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2022005 and 05000412/2022005) IR 05000334/20220022022-08-12012 August 2022 Integrated Inspection Report 05000334/2022002 and 05000412/2022002 IR 05000334/20224022022-08-12012 August 2022 Cyber Security Problem Identification and Resolution Inspection Report 05000334/2022402 and 05000412/2022402 (Cover Letter Only) IR 05000334/20220112022-06-29029 June 2022 Temporary Instruction 2515/194 Inspection Report 05000334/2022011 and 05000412/2022011 IR 05000334/20225012022-06-29029 June 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2022501 and 05000412/2022501 IR 05000412/20223012022-06-14014 June 2022 Initial Operator Licensing Examination Report 05000412/2022301 IR 05000334/20220102022-05-12012 May 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000334/2022010 and 05000412/2022010 IR 05000334/20224202022-05-11011 May 2022 Security Baseline Inspection Report 05000334/2022420 and 05000412/2022420 - Cover Letter IR 05000334/20220012022-05-10010 May 2022 Integrated Inspection Report 05000334/2022001 and 05000412/2022001 IR 05000334/20210062022-03-0202 March 2022 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2021006 and 05000412/2021006) IR 05000334/20210042022-02-14014 February 2022 Integrated Inspection Report 05000334/2021004 and 05000412/2021004 L-22-054, Steam Generator Inspection Report- Fall 2021 Refueling Outage2022-02-10010 February 2022 Steam Generator Inspection Report- Fall 2021 Refueling Outage IR 05000334/20210032021-11-0909 November 2021 Integrated Inspection Report 05000334/2021003 and 05000412/2021003 IR 05000334/20210112021-10-19019 October 2021 Temporary Instruction 2515/194 Inspection Report 05000334/2021011 and 05000412/2021011 IR 05000334/20210102021-09-29029 September 2021 Triennial Fire Protection Inspection Report 05000334/2021010 and 05000412/2021010 IR 05000334/20210052021-09-0101 September 2021 Updated Inspection Plan for the Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2021005 and 05000412/2021005) IR 05000334/20214022021-08-18018 August 2021 Security Baseline Inspection Report 05000334/2021402 and 05000412/2021402 IR 05000334/20214012021-08-12012 August 2021 Material Control and Accounting Program Inspection Report 05000334/2021401 and 05000412/2021401 (Cover Letter Only) IR 05000334/20210022021-08-11011 August 2021 Integrated Inspection Report 05000334/2021002 and 05000412/2021002 IR 05000334/20210012021-05-13013 May 2021 Integrated Inspection Report 05000334/2021001 and 05000412/2021001 IR 05000334/20214032021-05-13013 May 2021 Cyber Security Problem Identification and Resolution Inspection Report 05000334/2021403 and 05000412/2021403 (Cover Letter Only) ML21097A1142021-04-19019 April 2021 Review of Steam Generator Tube Inspection Report for the Spring 2020 Refueling Outage IR 05000334/20213012021-04-0101 April 2021 Initial Operator Licensing Examination Report 05000334/2021301 IR 05000334/20210122021-03-24024 March 2021 Biennial Problem Identification and Resolution Inspection Report 05000334/2021012 and 05000412/2021012 IR 05000334/20210132021-03-0404 March 2021 Nuclear Regulatory Commission Investigation Report No. 1-2019-010 and Inspection Report 05000334/2021013 and 05000412/2021013 IR 05000334/20200062021-03-0303 March 2021 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2020006 and 05000412/2020006) IR 05000334/20200042021-02-12012 February 2021 Integrated Inspection Report 05000334/2020004 and 05000412/2020004 IR 05000334/20205012020-11-23023 November 2020 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2020501 and 05000412/2020501 IR 05000334/20200032020-11-13013 November 2020 Integrated Inspection Report 05000334/2020003 and 05000412/2020003 IR 05000334/20200112020-10-26026 October 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000334/2020011 and 05000412/2020011 IR 05000334/20204012020-10-0505 October 2020 Security Baseline Inspection Report 05000334/2020401 and 05000412/2020401 (Cover Letter Only) IR 05000334/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000334/2020005 and 05000412/2020005) IR 05000334/20200022020-08-13013 August 2020 Integrated Inspection Report 05000334/2020002 and 05000412/2020002 2023-09-29
[Table view] Category:Letter
MONTHYEARML24025A0922024-01-25025 January 2024 Requalification Program Inspection L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 IR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 L-23-229, Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports2023-11-29029 November 2023 Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 L-23-247, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-11-17017 November 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 L-23-227, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 20232023-10-20020 October 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 2023 ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) ML23263A0192023-09-20020 September 2023 Operator Licensing Examination Approval ML23243A9272023-09-19019 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 L-23-208, Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA00256152023-09-14014 September 2023 Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA0025615 L-23-167, Twenty-Third Refueling Outage Inservice Inspection Summary Report2023-09-13013 September 2023 Twenty-Third Refueling Outage Inservice Inspection Summary Report L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000334/20230022023-08-0909 August 2023 Integrated Inspection Report 05000334/2023002 and 05000412/2023002 ML23219A0592023-08-0707 August 2023 Steam Generator Inspection Reports - Spring 2023 Spring Refueling Outrage L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-179, Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-07-18018 July 2023 Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA0025615 ML23188A0982023-07-17017 July 2023 Correction to the Safety Evaluation Issued Related to Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23188A0672023-07-10010 July 2023 Project Manager Assignment L-23-165, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-06-26026 June 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-139, Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report2023-06-13013 June 2023 Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report ML23157A1072023-06-0707 June 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000334/2023011 and 05000412/2023011 ML23143A0272023-05-23023 May 2023 Licensed Operator Positive Fitness-For-Duty Test L-23-055, Submittal of the Updated Final Safety Analysis Report, Revision 342023-05-23023 May 2023 Submittal of the Updated Final Safety Analysis Report, Revision 34 ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23135A7872023-05-19019 May 2023 Summary of Conference Calls Regarding the Spring 2023 Steam Generator Tube Inspections L-23-137, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-05-18018 May 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 L-23-125, Cycle 24 Core Operating Limits Report2023-05-17017 May 2023 Cycle 24 Core Operating Limits Report ML23124A3882023-05-16016 May 2023 Summary of Regulatory Audit in Support of License Amendment Request to Revise Technical Specification 5.6.3, Core Operating Limits Reports (COLR) and TS 4.2.1 Fuel Assemblies ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) L-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000334/20230012023-05-0808 May 2023 Integrated Inspection Report 05000334/2023001 and 05000412/2023001 L-23-129, Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations2023-05-0505 May 2023 Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations ML23118A3812023-04-28028 April 2023 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations L-23-115, Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological2023-04-27027 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological L-23-126, Discharge Monitoring Report (Npdes), Permit No. PA00256152023-04-22022 April 2023 Discharge Monitoring Report (Npdes), Permit No. PA0025615 CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML23107A2502023-04-18018 April 2023 Requalification Program Inspection 2024-01-25
[Table view] |
See also: IR 05000334/2020010
Text
February 24, 2020
Mr. Rod L. Penfield
Site Vice President
FirstEnergy Nuclear Operating Company
Beaver Valley Power Station
P.O. Box 4
Shippingport, PA 15077
SUBJECT: BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - TEMPORARY
INSTRUCTION 2515/194 INSPECTION REPORT 05000334/2020010 AND
05000412/2020010
Dear Mr. Penfield:
On January 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection
at Beaver Valley Power Station, Units 1 and 2 and discussed the results of this inspection with
Mark Manoleras and other members of your staff. The results of this inspection are
documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public
Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Glenn T. Dentel, Chief
Engineering Branch 2
Division of Reactor Safety
Docket Nos. 05000334 and 05000412
License Nos. DPR-66 and NPF-73
Enclosure:
As stated
cc w/ encl: Distribution via LISTSERV
ML20058D181
Non-Sensitive Publicly Available
SUNSI Review
Sensitive Non-Publicly Available
OFFICE RI/DRS RI/DRP RI/DRS
NAME LDumont PFinney GDentel
DATE 2/24/20 2/24/20 2/24/20
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Numbers: 05000334 and 05000412
License Numbers: DPR-66 and NPF-73
Report Numbers: 05000334/2020010 and 05000412/2020010
Enterprise Identifier: I-2020-010-0010
Licensee: FirstEnergy Nuclear Operating Company
Facility: Beaver Valley Power Station
Location: Shippingport, PA
Inspection Dates: January 27, 2020 to January 31, 2020
Inspectors: L. Dumont, Reactor Inspector
C. Hobbs, Reactor Inspector
Approved By: Glenn T. Dentel, Chief
Engineering Branch 2
Division of Reactor Safety
Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees
performance by conducting Temporary Instruction 2515/194 at Beaver Valley Power Station,
Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight
Process is the NRCs program for overseeing the safe operation of commercial nuclear power
reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
2
INSPECTION SCOPES
The inspection was conducted using Temporary Instruction 2515/194 (ADAMS Accession
No. ML17137A416), effective November 1, 2017. The inspectors reviewed the licensees
implementation of the Nuclear Energy Institutes voluntary industry initiative in compliance with
Commission guidance. The inspectors discussed Beaver Valleys open phase condition system
design and ongoing implementation plans with plant staff. The inspectors reviewed licensee
and vendor documentation, and performed system walkdowns to verify that the installed
equipment was supported by the design documentation. Beaver Valley had recently completed
physical installation and the equipment was being operated in a monitoring mode with the trip
functions disabled.
OTHER ACTIVITIES - TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL
2515/194 - Inspection of the Licensees Implementation of Industry Initiative Associated With the
Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
The inspectors reviewed the licensees implementation of the Nuclear Energy Institute
Voluntary Industry Initiative, (ADAMS Accession No. ML15075A454) dated March 16,
2015. This included reviewing how the licensee updated their licensing basis to reflect the need
to protect against open phase conditions.
Inspection of the Licensees Implementation of Industry Initiative Associated With the Open
Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
(1 Sample)
(1) FirstEnergy selected the open phase detection system designed and manufactured
by Power System Sentinel Technologies, LLC, as the design vendor for the open
phase condition system at Beaver Valley Power Station. The open phase protection
system is designed to protect the offsite power sources from a loss of phase
condition.
The offsite electrical distribution system is functionally the same for both Beaver
Valley Unit 1 and Unit 2. Two general design criteria (GDC-17) offsite power sources
are credited for each unit. At each unit offsite power is provided by two independent
system station service transformers (SSSTs), each powered from a different bus of
the 138 kV switchyard to supply reliable power to two safety-related 4kV buses for
each Beaver Valley unit. The 138 kV connections between the switchyard buses and
the SSSTs are made with overhead lines having separate towers for each line. At the
time of the inspection the active trip feature of the open phase detection systems
installed at Beaver Valley was not enabled for either unit.
INSPECTION RESULTS
Temporary Instruction 2515/194-03.01 - Voluntary Industry Initiative 2515/194
Detection, Alarms, and General Criteria
1. 03.01(a)(1) OPC are detected and alarmed in the control room for Unit 1 and 2.
2. 03.01(a)(2) Detection circuits are sensitive enough to identify an OPC for credited
loading conditions (i.e., high and low loading).
3. 03.01(a)(3) OPC design and protective schemes minimize misoperation or spurious
action in the range of voltage unbalance normally expected in the transmission
3
system that could cause separation from an operable off-site power source. In the
design of the OPC system, multiple features have been added to prevent spurious
trips of the system. FirstEnergy solutions demonstrated that the actuation circuit
design does not result in lower overall plant operation reliability.
4. 03.01(a)(4) No class 1E circuits were replaced with non class 1E circuits during
installation of the open phase detection system.
Protective Actions Criteria
1. 03.01(b)(1) Two SSSTs at both Unit 1 and Unit 2 were identified as susceptible to an
open phase condition and the licensee has implemented design changes on all four
transformers to mitigate the effects.
2. 03.01(b)(2) With an open phase condition present and no accident condition signal,
the open phase design would not adversely affect the function of important-to-safety
systems, structures, or components. The licensees OPC design solution added two
PSSTech systems on each SSST, TR-1A, TR-1B, TR-2A, and TR-2B. The credited
plant response was unaffected and would be the same regardless of the conditions
that generated the lockout of the transformer.
Detection, Alarms, and General Criteria Exceptions 2515/194
03.01(a)(5) The Beaver Valley Unit 1 UFSAR has been updated to discuss the design
features of the open phase condition detection system. However, the Unit 2 UFSAR was not
updated at the time of the inspection. This has been noted in CR-2020-00263 and as part of
the self-assessment conducted prior to the start of the inspection under SA-BN-2020-
1796. The licensee provided to the inspectors the proposed changes to the licensing basis
that discussed the system requirements related to the effects of, and protection for, any open
phase condition design vulnerability.
Protective Actions Exceptions 2515/194
03.01(b)(3) Inspectors determined that with an open phase condition and an accident
condition signal present, the open phase detection system would not adversely affect the
function of the load shedding and sequencing system to provide a means of disconnecting
and sequencing of loads on the safety related buses. The open phase protection trip circuit
was installed; however, this trip function will remain disabled until cessation of plant
operations. FirstEnergy issued a letter, dated November 19, 2018, to inform the NRC that
based on the previously announced near-term plant shut downs, Beaver Valleys OPC
detection equipment will remain in the monitor mode up until the respective shut down dates
for each site. As such, the OPC equipment on both units were not placed in the trip mode of
operation.
03.01(b)(4) The licensee had not established documentation for periodic tests, calibrations,
setpoint verifications, or inspection procedures associated with the PSS Tech equipment.
This action was being tracked in their corrective action program (CR-2020-00586) and was
identified as part of the self-assessment conducted prior to the start of the inspection under
SA-BN-2020-1796.
4
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
inspection results to Mark Manoleras and other members of the licensee staff.
5
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
2515/194 Corrective Action CR-2020-00263
Documents CR-2020-00585
CR-2020-00586
Corrective Action CR-2020-00708
Documents CR-2020-00732
Resulting from
Inspection
Drawings RE-0001C Beaver Valley Power Station Unit 2 Equipment One Line 15
Diagram
RE-0001C Beaver Valley Power Station Unit 1 Equipment One Line 32
Diagram
Engineering ECP 15-0060-000 Unit 2 Open Phase Detection System Reference Documents 5/31/2018
Changes ECP-15-0059- Unit 1 Open Phase Detection System Reference Documents 11/30/2015
000
ECP-18-0156- Unit 1 Main Transformer Leads Protection Replacement 4/18/2019
000
Miscellaneous Open Phase Protection (OPP) System Factory Acceptance 5/18/2016
Test (FAT) Plan for FENOC
Open Phase Protection (OPP) System Site Acceptance Test 8/3/2016
Procedure for Single Channel System
Open Phase Protection (OPP) System Procedure for OPP 12/5/2018
System Online Commissioning
PSSTech OPD System Enhanced Test Execution, Results 0
and Conclusions
Shiftly readings of SSST Secondary Phase Voltages 1/26/2020
and
1/27/2020
Daily SSST 1A High line Drop Inspection 1/26/2020
and
1/27/2020
PSSTech Open Phase Protection (OPP) System Preventive 0.0.1
Maintenance Guide
6
Inspection Type Designation Description or Title Revision or
Procedure Date
L-18-219 First Energy Solutions letter to NRC announcing intent to 11/19/2018
leave OPC systems in monitoring mode until plant closures
in 2021.
Procedures 1OM-36.4.AFY SS Service Transformer 1B Open Phase Alarm 1
1OM-36.4.AFZ SS Service Transformer 1A Open Phase Alarm 0
1OM-54.3.OUT1 Beaver Valley Unit 1 Outside Log Readings 71
2OM-36.4.AFK SS Service Transformer 2A Open Phase Alarm 0
2OM-36.4.AFK SS Serv Tfmr Open Phase Alarm 1
2OM-36.4.AFL SS Service Transformer 2B Open Phase Alarm 1
Self-Assessments SA-BN-2020- BVPS self assessment for TI-194 Open Phase Condition 1/24/2020
1796 inspection
7