Response Opposing Rockford League of Women Voters Proposed Findings of Fact & Conclusions of Law Re Liquid Pathway. Proposed Findings Misstate Record.Certificate of Svc EnclML20024C962 |
Person / Time |
---|
Site: |
Byron ![Constellation icon.png](/w/images/b/be/Constellation_icon.png) |
---|
Issue date: |
07/18/1983 |
---|
From: |
Furse M, Gallo J COMMONWEALTH EDISON CO., ISHAM, LINCOLN & BEALE |
---|
To: |
|
---|
References |
---|
ISSUANCES-OL, NUDOCS 8307210236 |
Download: ML20024C962 (8) |
|
Similar Documents at Byron |
---|
Category:FINDINGS OF FACT/CONCLUSIONS OF LAW
MONTHYEARML20078L1601983-10-17017 October 1983 Reply to Util Supplemental Findings of Fact & Conclusions of Law on Qa/Qc.Certificate of Svc Encl ML20080S1741983-10-14014 October 1983 Reply to Joint Intervenors Partial Proposed Findings of Fact & Conclusions of Law on Contention 1A.Intervenors Findings Misleading & Inaccurate & Should Not Be Adopted.Certificate of Svc Encl ML20080P1491983-09-30030 September 1983 Addl Proposed Findings of Fact & Conclusions of Law Re QA & Qc.Certificate of Svc Encl ML20080M5681983-09-30030 September 1983 Partial Proposed Findings of Fact & Conclusions of Law on Contention 1A.Certificate of Svc Encl ML20080G5651983-09-16016 September 1983 Reply to Applicant Proposed Findings of Fact & Conclusions of Law on Qa/Qc,Served on 830809.Applicant Has Not Borne Burden of Proof on Contention 1A.OL Must Be Denied. Certificate of Svc Encl ML20077S7201983-09-16016 September 1983 Reply to NRC Proposed Findings of Fact & Conclusions of Law on Qa/Qc Issues.Certificate of Svc Encl ML20077S7091983-09-16016 September 1983 Reply to Intervenor Proposed Findings of Fact & Conclusions of Law on Qa/Qc.Certificate of Svc Encl ML20080D3651983-08-25025 August 1983 Errata Suppl to Applicant 830809 Proposed Findings of Fact & Conclusions of Law Re QA & Qc.Certificate of Svc Encl ML20080D2241983-08-24024 August 1983 Reply to Revised Rockford League of Women Voters & Dekalb Area Alliance for Responsible Energy/Sinnissippi Alliance for Environ Findings of Fact & Opinion.Certificate of Svc Encl ML20077H9891983-08-0909 August 1983 Proposed Findings of Fact & Conclusions of Law on Qa/Qc. Certificate of Svc Encl ML20077J0971983-08-0909 August 1983 Proposed Findings of Fact & Conclusions of Law Re QA & Qc. Certificate of Svc Encl ML20085D7771983-07-26026 July 1983 Reply Opposing Rockford League of Women Voters Proposed Findings of Fact & Conclusions of Law Re Steam Generator Tube Integrity.Certificate of Svc Encl ML20077C8181983-07-20020 July 1983 Revised Findings of Fact & Opinion on Rockford League of Women Voters Contention 22 & Dekalb Area Alliance for Responsible Energy/Sinnissippi Alliance for Environ Contention 9(c).Certificate of Svc Encl ML20024C9621983-07-18018 July 1983 Response Opposing Rockford League of Women Voters Proposed Findings of Fact & Conclusions of Law Re Liquid Pathway. Proposed Findings Misstate Record.Certificate of Svc Encl ML20076L3271983-07-15015 July 1983 Reply to Dekalb Area Alliance for Responsible Energy/ Sinnissippi Alliance for Environ & Rockford League of Women Voters Findings of Fact & Conclusions of Law Re Emergency Planning.Certificate of Svc Encl ML20076K0001983-07-0101 July 1983 Proposed Findings of Fact & Conclusions of Law Re Class 9 Accidents.Certificate of Svc Encl ML20024B6361983-07-0101 July 1983 Proposed Findings of Fact & Conclusions of Law Re Steam Generator Tube Integrity ML20076K0021983-07-0101 July 1983 Proposed Findings of Fact & Conclusions of Law Re Liquid Pathway & Class 9 Accidents.Certificate of Svc Encl ML20072K6251983-06-30030 June 1983 Reply to Rockford League of Women Voters Proposed Findings of Fact & Conclusions of Law Re Alara.Certificate of Svc Encl ML20072G5311983-06-24024 June 1983 Proposed Findings of Fact & Conclusions of Law Re Liquid Pathway.Certificate of Svc Encl ML20072E5471983-06-21021 June 1983 Reply to Dekalb Area Alliance for Responsible Energy/ Sinnissippi Alliance for Environ Proposed Findings of Fact & Conclusions of Law Re Water Hammer.Certificate of Svc Encl ML20072E5681983-06-20020 June 1983 Proposed Findings of Fact & Conclusions of Law Re Emergency Planning.Certificate of Svc Encl ML20072E5611983-06-20020 June 1983 Findings of Fact & Conclusions of Law Re Emergency Planning ML20076J0791983-06-14014 June 1983 Proposed Findings of Fact & Conclusions of Law Re ALARA & Steam Generator Tube Integrity ML20076J0481983-06-0909 June 1983 Reply Opposing Rockford League of Women Voters Proposed Findings of Fact & Conclusions of Law Re Seismology. Certificate of Svc Encl ML20072B4641983-06-0707 June 1983 Proposed Findings of Fact & Conclusions of Law Re Steam Generator Tube Integrity.Certificate of Svc Encl ML20023D9551983-05-31031 May 1983 Proposed Findings of Fact & Conclusions of Law Re Seismology,Water Hammer & ALARA ML20071P7311983-05-31031 May 1983 Proposed Findings of Fact & Conclusions of Law on Contention 9a Re Water Hammer 1983-09-30
[Table view] Category:LEGAL TRANSCRIPTS & ORDERS & PLEADINGS
MONTHYEARML20207E0051999-03-0202 March 1999 Transcript of 990302 Public Meeting with Commonwealth Edison in Rockville,Md.Pp 1-104.Supporting Documentation Encl ML20236H9381998-06-30030 June 1998 Transcript of 980630 Meeting W/Commonwealth Edison in Rockville,Md.Pp 1-123.Supporting Documentation Encl ML20198P3001997-11-0404 November 1997 Transcript of 971104 Public Meeting W/Ceco in Rockville,Md Re Measures Established by Ceco to Track Plant Performance & to Gain Understanding of CAs Put Into Place to Improve Safety.Pp 1-105.W/Certificate & Viewgraphs ML20149M2951996-11-29029 November 1996 Exemption from Requirements of 10CFR50.60 Re Safety Margins Recommended in ASME Boiler & Pressure Vessel Code Case N-514 TXX-9522, Comment Opposing Proposed GL on Testing of safety-related Logic Circuits.Believes That Complete Technical Review of All Surveillance Procedures Would Be Expensive & Unnecessary Expenditure of Licensee Resources1995-08-26026 August 1995 Comment Opposing Proposed GL on Testing of safety-related Logic Circuits.Believes That Complete Technical Review of All Surveillance Procedures Would Be Expensive & Unnecessary Expenditure of Licensee Resources ML20059C2351993-12-17017 December 1993 Comment Supporting Petition for Rulemaking PRM-21-2 Re Commercial Grade Item Dedication ML20044A8111990-06-27027 June 1990 Comment Opposing Closure of Lpdr of Rockford Public Library ML20245J0191989-04-14014 April 1989 Comment Re Proposed Rule 10CFR50 Re Ensuring Effectiveness of Maint Programs for Nuclear Power Plants ML20214X1871987-06-11011 June 1987 Order Imposing Civil Monetary Penalty in Amount of $25,000 Based on Four Severity Level III Violations Noted During 860721-0808 Insp ML20205Q1711987-04-0202 April 1987 Order Imposing Civil Monetary Penalty in Amount of $25,000. App Re Evaluations & Conclusions Encl IR 05000812/20100311987-02-26026 February 1987 Order Imposing Civil Monetary Penalty in Amount of $100,000 Based on Violations Noted During Insps on 850812-1031 ML20210T7321987-02-11011 February 1987 Unexecuted Amend 6 to Indemnity Agreement B-97 Substituting Item 3 of Attachment to Indemnity Agreement in Entirety W/ Listed License Numbers,Effective 870130 ML20209J3251987-01-30030 January 1987 Transcript of 870130 Commission Discussion/Possible Vote on Full Power OL for Facility.Pp 1-72.Supporting Viewgraphs Encl ML20213G4381986-10-24024 October 1986 Unexecuted Amend 5 to Indemnity Agreement B-97,substituting Item 3 of Attachment to Agreement in Entirety W/Listed License Numbers,Effective on 861106 ML20211B0841986-08-0505 August 1986 Transcript of 860805 Meeting Between Region Iii,Computer Interference Elimination & Util in Redmond,Wa Re Plant as-built Drawing Review.Pp 1-200 IR 05000506/20070221986-05-0202 May 1986 Order Imposing Civil Monetary Penalty in Amount of $25,000 for Violations Noted During Insp on 850506-0722.Violations Noted:Failure to Establish Radiological Safety Procedures & to Adequately Train Personnel ML20138C7301985-12-0909 December 1985 Order Imposing Civil Penalty in Amount of $25,000 Per 850606 Notice of Violation & Proposed Imposition of Civil Penalty.Licensee May Request Hearing within 30 Days of Date of Order ML20205E8741985-10-28028 October 1985 Exemption from GDC 4 of 10CFR50,App a Requirement to Install Protective Devices Associated W/Postulated Pipe Breaks Primary Coolant Sys.Topical Rept Evaluation Encl ML20102A2981985-01-0707 January 1985 Petition Requesting Aslab Grant Intervenor Appeal & Order Further Hearings on Safety of Plant ML20099L2581984-11-27027 November 1984 Notice of Withdrawal of Appearance in Proceeding.Certificate of Svc Encl ML20099G5381984-11-23023 November 1984 Supplemental Appeal Brief in Response to Intervenor 841106 Supplemental Brief on Appeal & in Support of ASLB 841016 Supplemental Initial Decision Authorizing Issuance of Ol. Certificate of Svc Encl ML20100K0411984-11-22022 November 1984 Submits Concerns Re Safety of Local Residents in Event of Accident & Excessively High Cost of Projected Operation of Facility ML20107H7841984-11-0606 November 1984 Supplemental Brief on Appeal of ASLB 841016 Supplemental Initial Decision Granting Authority for Issuance of Ol. Decision Should Be Reversed.Certificate of Svc Encl ML20140E4081984-10-31031 October 1984 Executed Amend 1 to Indemnity Agreement B-97,deleting Items 2A & 3 in Entirety ML20098G8841984-10-0202 October 1984 Joint Statement of RW Manz & W Faires Re Findings 3-11 Through 3-17 of NRC 830930 Integrated Design Insp Rept. Certificate of Svc Encl ML20098G8681984-10-0202 October 1984 Answer to Intervenor Motion to Reopen Record Re Bechtel Independent Design Review.Motion Should Be Denied ML20098G8901984-10-0202 October 1984 Joint Statement of Kj Green & RW Hooks Re Integrated Design Insp ML20098G8911984-10-0202 October 1984 Joint Statement of Cw Dick & EM Hughes Re Independent Design Insp ML20098G8821984-10-0101 October 1984 Affidavit of Kj Green Re Integrated Design Insp Concerning Mechanical Engineering Work ML20098G8741984-10-0101 October 1984 Affidavit of Br Shelton Re Integrated Design Insp ML20098G8881984-09-29029 September 1984 Affidavit of RW Hooks Re Integrated Design Insp Concerning Structural Design ML20098G8831984-09-28028 September 1984 Affidavit of W Faires Re Findings 3-15 & 3-16 of NRC 830930 Integrated Design Insp Rept ML20098G8811984-09-28028 September 1984 Affidavit of Cw Dick Re Independent Design Review ML20098G8791984-09-28028 September 1984 Affidavit of RP Tuetken Re Readiness for Fuel Loading ML20098G8781984-09-28028 September 1984 Affidavit of RW Manz Concerning Findings 3-11 Through 3-14 & 3-17 of NRC 830930 Integrated Design Insp Re Westinghouse ML20098G8871984-09-28028 September 1984 Affidavit of EM Hughes Re Idvp ML20098G8851984-09-27027 September 1984 Affidavit of Rl Heumann Re Costs of Delay in Startup & Operation of Unit 1 ML20098E2371984-09-24024 September 1984 Reply to Intervenor 840918 Proposed Supplemental Initial Decision.Certificate of Svc Encl ML20097E7221984-09-13013 September 1984 Agreed Motion for Time Extension Until 841101 to File Petition for Hearing Re Emergency Planning Commitment W ML20097C5311984-09-12012 September 1984 Motion to Reopen Record to Include Plant Design as Issue. Supporting Documentation & Certificate of Svc Encl ML20097B7791984-09-10010 September 1984 Proposed Supplemental Initial Decision Re Reinsp Program. Certificate of Svc Encl ML20096A6391984-08-30030 August 1984 Rebuttal Testimony of RW Hooks Re Validity of Info in Attachment 7 to Stokes Testimony Concerning Design Assumption for Plant.Stokes Info Inapplicable to Plant. Related Correspondence ML20096A6191984-08-30030 August 1984 Rebuttal Testimony of B Erler Re Stokes Allegations Concerning Evaluations of Discrepancies in Calculated Actual Stress Performed by Sargent & Lundy.Related Correspondence ML20096A6261984-08-30030 August 1984 Summary of Rebuttal Testimony & Testimony of ML Somsag, Eb Branch,D Demoss,Mr Frankel,Bf Maurer & Jk Buchanan Re Plant QC Inspector Reinsp Program & C Stokes Allegations Re Welds.Related Correspondence ML20096A6441984-08-28028 August 1984 Notice of Withdrawal of Appearance in Proceeding.Related Correspondence ML20112D5271984-08-24024 August 1984 Applicant Exhibit A-R-4,consisting of Feb 1984 Rept on Bryon QC Inspector Reinsp Program ML20112D5031984-08-24024 August 1984 Applicant Exhibit A-R-5,consisting of June 1984 Suppl to Rept on Bryon QC Inspector Reinsp Program ML20112D7441984-08-23023 August 1984 Intervenor Exhibit I-R-1,consisting of Undated List of Teutken Safety Category Insp Types ML20112D7511984-08-21021 August 1984 Staff Exhibit S-R-1,consisting of 840813 Instruction for Walkdown of Cable Tray Hanger Connection Welds ML20112D4641984-08-21021 August 1984 Intervenor Exhibit I-R-11,consisting of Undated Chronological Date Listing of Util Responses to Interrogatory 12.VA Judson to Mi Miller Re Interrogatory 12 & Supplemental Responses Encl 1999-03-02
[Table view] |
Text
-.
~
'b,
' Dated 7/18/83 -
'/
-UNITED STATES OF AMERICA '
i El NUCLEAR REGULATORY COMMISSION JUL 2 0 983 > 21 !
l 7-BEFORE THE ATOMIC SAFETY AND LICENSING BOARD " 'j.'($.I (+?-
/f l
. M
- (p In The Matter of )
)
COMMONWEALTH EDISON COMPANY ) Docket Nos. 50-454 OL
) 50-455 OL
)
(Byron Nuclear Power Station, )
Units 1 & 2) )
APPLICANT'S REPLY TO THE LEAGUE'S PROPOSED FINDINGS OF FACT AND CONCLUSIONS
> OF LAW REGARDING LIQUID PATHWAY As authorized by the Stipulation between all parties to this proceeding dated August 18, 1982, Commonwealth Edison Company (" Applicant") files this reply to the Rockford League of Women Voters' ("Intervenor") Proposed Findings of Fact and Conclusions of Law Regarding Liquid Pathway.
- 1. Intervenor's Site Characterization Intervenor's Proposed Findings 4 through 11 misstate the record with respect to the proper characterization of.
the Byron site geology and hydrogeology. Many of the " facts" proposed by the Intervenor are misleading-to various degrees.
In'Intervenor Proposed Findings _5 and 6, Intervenor
. states =that the bedrock underlying the Byron' site is extremely fractured near the surface ~and that the top of the ground-water table is in this' area of the bedrock.- These findings when read together with findings 7-11 suggest that contaminant
~
8307210236 830718 b PDR ADOCK 05000454 A - .-. _
PDR- .
a travel times will be influenced by these characteristics.
However, the uncontradicted testimony establishes that at the Byron site the most highly fractured portion of the bedrock has been excavated, and, more importantly, that radioactive contamination under the postulated acc idents would enter the acquifer at approximately 62 to 70 feet from (Applicant the surface, well below the groundwater table.
Proposed Finding 328; Lahti, Applicant's Prepared Testimony at 4, ff. Tr. 6750.)
Intervenor Proposed Finding 7 states that the fracturing in the Galena-Platteville dolomites is regional l
in nature. The Applicant does not dispute this assertion.
however, that the l
Proposed Finding 7 goes on to state, regional fracturing raises a serious threat to the health j
and safety of the public, given the occurrence of a serious accident. Even given the regional nature of the fracturing, 1/ In fact, the l
' this assertion plainly does not follow.-
travel times calculated by the Applicant and the NRC Staff l
l l
assumed regional fracturing. (Holish, Applicant's Prepared Testimony at 7, 8, 16-18, ff. Tr. 6750; Codell, Staley, NRC Staff Prepared Testimony at 11, 12, ff. Tr. 6649.) In addition, the accidents postulated and analyzed by the Applicant (the BRH tank rupture and the core melt release) assumed regional fracturing. (Id. Lahti, Applicant's Pre-pared Testimony at 5, ff. Tr. 6750.) The consequences of
-1/
It should also be noted that this " fact" is proposed without. record support.
the BRH tank rupture were found not to endanger the health and safety of the public, and the environmental risks from a core melt release were found to be acceptably small. (Appli-cant Proposed Findings 341-344, 345-361.)
Intervenor Proposed Finding 9 is misleading. This Proposed Finding asserts, among other things, that at this time it is not possible to say that there is not a continuous joint running from the site to the Rock River. The testimony of both the Applicant and the NRC Staff is miscited in support.
The testimony of Applicant's witness, fairly read, is clearly to the contrary. At Tr. 6767, the page cited by Intervenor, Mr. Holish testified as follows:
O But you cannot say there is not a continuous joint running from this site to the river, can you?
A I cannot say that, on the basis of physically seeing the actual joint, but, however, my engineering judgment and the interpretation of the data that we have collected so far would lead me to believe that the joints are discontinuous, especially from the mapping that has been done.
The citation to the NRC Staff's testimony, Tr. 6711, con-
-tains no reference to continuous jointing. To the contrary, the NRC Staff elsewhere testified unambiguously that the results of Applicant's investigation show that continuous fractures or joints do not run from the site to the Rock River. (Staley, NRC Staff Prepared Testimony at 14, ff. tr.
6649; Staley, Tr. 6655.)
I -
Intervenor Proposed Findings 10 and 11, taken together, constitute a mischaracterization of the testimony of Dr. Bernard ~ Wood, who testified for the Intervenor.
2 Intervenors imply that Dr. Wood's method / for characterizing the bedrock underlying the Byron site assumes that the rock formation contains joints at irregular intervals. The record does not support this interpretation. Dr. Wood
- advocated the_use of tracer studies and fissure modeling because the fractures were in his opinion continuous, not because they were irregularly spaced. (Wood, Tr. 6893-6900, 6918-6919; Wood, Intervenors' Prepared Testimony at 5, ff.
Tr. 6879.)
In, conclusion, Intervenor Proposed Findings 4 through 11 are.not supported by the record.
- 2. Applicant's Site Characterization Intervenor Proposed Findings 13 through 17 consti-tute an attack on the Applicant's Byron site investigation.
These findings are not supported by the record.
In Finding 13 it is asserted that Applicant was
. unable to state.how many of the'154 core borings _ intersected joint: fractures. In-fact, Lawrence Holish testified that, on the basis of his examination of the drilling lobes and observation of theLcores, probably every single boring intersected a joint fracture. (Holish, Tr. 6751. )
l
-2/-
'Although not. described, this' method apparently involves
- a tracer' and modeling study,: proposed- by Dr. Wood. in
-his prepared testimony'and the: subject ofLextensive cross-examination. .-(Wood, Intervenors' Prepared Testi-mony'at-8, ff. Tr. 6879; Wood, Tr.16919-6922.')
I l
Intervenor Proposed Finding 15 correctly states that Applicant has not performed a tracer study of contaminant migration from the Byron site to the Rock River. A tracer study is lengthy, difficult, and not well known by many engineers. (Holish, Tr. 6768, 6842, 6920.) In view of the adequacy of the Byron site investigation, such a study is simply not warranted. (Applicant Proposed Findings 317, 318.)
Intervenor Proposed Finding 17 incorrectly implies that, due to a possible factor of ten difference between effective porosity as calculated using the approach of D. T. Snow and that determined from in situ water pressure test and geophysical data, Applicant's final conclusion as to contaminant velocity is ten times too slow. At Tr. 6775, the page following that cited by Intervenor, counsel for Intervenor asked Applicant's witness that very question, i.e., could contaminant velocities as finally determined by Applicant be ten times too slow. The answer was "no."
Moreover, the Snow analysis was not used to evaluate design basis accident scenarios. It was one of two distinct methods employed to evaluate the hydrogeologic aspects of a postulated core melt release. Since the Snow analysis was designed for a kind of bedrock different than'that beneath the Byron l
site, the Snow analysis was used by Applicant only as a basis of comparison to determine the effects of aperture size and fracture size. (Holish, Tr. 6775; Holish, Applicant's Prepared Testimony at 25-26, ff. Tr. 6750.)
Intervenor's attempt in Findings 13 through 17 to
, cast doubt upon the credibility of the Byron site investi-gation performed by the Applicant is without merit.
In view of the foregoing discussion, Applicant respectfully requests that Intervenor's proposed findings and conclusions on this contention not be adopted by the Board.
Respectfully submitted,
.jp 3 po ,
^
' .j z ! aj - I j' ';'
Joseph Gallo
~~
- h. ,t M.
Mirk C. Furse Attorneys for Commonwealth Edison Company Joseph Gallo Mark C. Furse ISHAM, LINCOLN & BEALE Suite 5200 Three First National Plaza Chicago, Illinois 60602 (312) 558-7500
/
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In The Matter of )
)
COMMONWEALTH EDISON COMPANY ) Docket Nos. 50-454 OL
) 50-455 OL
)
(Byron Nuclear Power Station, )
Units 1 & 2) )
CERTIFICATE OF SERVICE The undersigned, one of the attorneys for Common-wealth Edison Company, certifies that he filed the original and two copies of the attached " Applicant's Reply to the League's Proposed Findings of Fact and Conclusions of Law Regarding Liquid Pathway" with the Secretary of the Nuclear Regulatory Commission and served a copy of the same on each of the persons at the addresses shown on the attached service ,
list. Service on the Secretary and all parties, unless otherwise indicated, was made by deposit in the U.S. Mail, first-class postage prepaid, this 18th day of July, 1983.
E'2 //f?
One of the Attorneys for Commonwealth Edison Company ISHAM, LINCOLN & BEALE Three First National Plaza Chicago,. Illinois 60602 (312) 558-7500 m
h p .--
e-SERVICE LIST COMMONWEALTH EDISON COMPANY -- Byron Station Docket Nos. 50-454 and 50-455 Mr. Ivan W. Smith Secretary Administrative Judge and Chairman ATTN: Chief, Docketing and Atomic Safety and Licensing Service Section Board Panel U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, D.C. 20555 washington, D.C. 20555 Ms. Betty Johnson Dr. Richard F'.' Cole 1907 Stratford Lane Atomic Safety and Licensing Rockford, Illinois 61107 Board Panel U.S. Nuclear Regulatory Commission Ms. Diane Chavez Washington, D.C. 20555 SAFE 326 North Avon Street Atomic Safety and Licensing' Rockford, Illinois 61103 Board Panel U.S. Nuclear Regulatory Commission Dr. Bruce von Zellen Washington, D.C. 20555 Department of Biological Sciences Northern Illinois University Chief Hearing Counsel' DeKalb, Illinois 60115 Office of the Executive Legal. Director Joseph Gallo, Esq.
U.S. Nuclear Regulatory Commission Isi.am, Lincoln & Beale Washington, D.C. 20555 Suite 840 1120 Connecticut Avenue, N.W.
Dr. A. Dixon Callihan Washington, D.C. 20036 Union Carbide Corporation P.O. Box Y Douglass W. Cassel, Jr.
Oak Ridge, Tennessee 37830 Jane Whicher BPI HMr. Steven C. Goldberg Suite 1300
-Ms. Mitzi A'. Young 109 N. Dearborn Office of the Executive Legal . Chicago, Illinois 60602 Director U.S. Nuclear Regulatory. Commission Ms. Patricia Morrison Washington, D.C.. 20555 5568 Thunderidge Drive Rockford, Illinois 61107 Atomic Safety and Licensing Appeal' Board Panel Mr. David Thomas U.S. Nuclear Regulatory Commission 77 South Wacker Drive-Washington, D.C. 20555 Chicago, Illinois 60621 Mr. Richard J. Rawson Office of the Executive-Legal Director-U.S. Nuclear Regulatory Commission Washington, D.C. 20555
_ l