Letter Sequence Other |
|---|
|
Results
Other: ML19290F175, ML19309E293, ML19309F675, ML19309G820, ML19312D649, ML19320C939, ML19322E558, ML19322E568, ML19323B469, ML19345B402, ML19347D269, ML19347E607, ML20008F619, ML20054F303, ML20126D163
|
MONTHYEARML19241C2491979-07-0202 July 1979 Safety Evaluation Rept Re Licensee Compliance W/Nrc 790516 Order.Requirements of Order Were Fulfilled.Plant May Resume operations.Long-term Mod Must Be Completed Project stage: Approval ML19241C2481979-07-0606 July 1979 Draft Ltr Re NRC 790516 Order Requiring Increase in Capability & Reliability of Plant to Respond to Various Transient Events.Plant May Resume Operations.Schedule for long-term Mod Will Be Forwarded within 30 Days Project stage: Draft Other ML19290E4671980-02-27027 February 1980 Transcript of 800227 Morning Briefing in Washington,Dc Re Event at Crystal River.Pp 1-74 Project stage: Request ML19312D0651980-02-29029 February 1980 Notification of 800304 Meeting W/B&W Licensees & Util in Bethesda,Md to Hear Presentation by Util Re 800226 Incident Project stage: Meeting ML19312D6491980-02-29029 February 1980 Responds to IE Bulletin 79-27, Loss of Non-Class IE Instrumentation & Control Power Sys Bus During Operation. Addl Time Is Required to Complete Review & Evaluation of non-class IE Instrumentation & Control Power Sys Project stage: Other ML19322E5681980-03-0606 March 1980 Ltr to All B&W Reactor Licensees Requesting Responses to IE Bulletin 79-27,Items 1-7.Responses to Items 1-5 Should Be Submitted by 800312.Responses to Items 6 & 7 Should Be Submitted by 800317 Project stage: Other ML19322E5581980-03-0606 March 1980 Forwards NRC Sent to B&W-designed Reactor Licensees,Requesting Info Re 800226 Transient Project stage: Other ML19290E8971980-03-12012 March 1980 Forwards Responses to NRC 800306 Request for Info Re Recent Transient.Util Will Perform Tests to Verify Remaining Info Following Nni/Ics Power Upsets.Will Verify That Operator Has Available Major Plant Parameters Identified in Response 4 Project stage: Request ML20126C6521980-03-13013 March 1980 Summary of 800304 Meeting W/Util,B&W Licensees Re Facility 800226 Nonnuclear Instrumentation Power Supply Failure Resulting in 43,000 Gallons of Coolant Escaping Primary Coolant Sys Into Reactor Bldg.Supporting Documentation Encl Project stage: Meeting ML19290F1751980-03-17017 March 1980 Forwards Response to Items 6 & 7 of Re Crystal River Unit 3 Incident.Corrective Action Plan Submitted 800312.Restart Projected for May 1980 Project stage: Other ML19312D4261980-03-24024 March 1980 Forwards Commitments Re Loss of Instrumentation Discussed During 800318 Meeting W/Nrc.Commits to Take Action to Allow Operator to Control Various Combinations of Loss of Instrumentation & Control Functions Prior to Restart Project stage: Meeting ML19309D4391980-03-24024 March 1980 Forwards Proposed Changes to Tech Specs,App a Project stage: Request ML19309E2931980-03-26026 March 1980 Updates 800229 Response to IE Bulletin 79-27.Util Will Complete Review & Evaluation of Non-Class IE Instrumentation & Control Sys as Required by Bulletin.Rept Will Be Submitted by 800426 Project stage: Other ML20126D1631980-04-0101 April 1980 Forwards Annotated Sequence of 800226 Events & Simplified Electrical Circuitry Schematics Per 800227 Request Project stage: Other ML19309G8201980-04-14014 April 1980 Confirmatory Order Re Util 800324 & 26 Commitments to Implement Actions Prior to Restart & to Respond to IE Bulletin 79-27 by 800426 Project stage: Other ML19309F6751980-04-25025 April 1980 Forwards Response to IE Bulletin 79-27, Loss of Non-Class IE Instrumentation & Control Power Sys Bus During Operation. Equipment Necessary for Cold Shutdown Available Project stage: Other ML19323C1221980-05-0202 May 1980 Forwards Request for Addl Info for Safety Evaluation Re 800226 Incident at Facility.Includes Info Re Mods Which Validate Info Provided by Indicators During Power Loss Situation Project stage: Approval ML19312D8521980-05-0202 May 1980 Forwards Response to Part I of NRC 800502 Request for Addl Info Re Restart After 800226 Accident.Util Is Installing Redundant Indicators Above Intercommunication Sys Section of Control Board.Part II Responses Will Follow Project stage: Request ML19323B4691980-05-0606 May 1980 Summarizes Background,Status & Future Plans Re Changes in Main Steam Line Rupture Matrix Sys,Safety Task Force Priority Item 51.Includes Description & Justification of short-term Change & Conclusions Project stage: Other ML19320A8541980-06-25025 June 1980 Responds to NRC 800502 Request for Info Re Pressurizer Safety Valves.Includes Data Taken During 800226 Incident to Assist in Determining Flow Rates & Conditioners in RCV-8 Relief Train.Test Results Will Be Sent When Available Project stage: Request ML19320C9391980-07-16016 July 1980 Advises That Restart W/O Completion of Item 51 Is Justified,As Original FSAR Is Still Valid for Present Design.All Items Will Be Completed Prior to Mode 2 Operation.Affidavit Encl Project stage: Other ML19330A9791980-07-18018 July 1980 Forwards Safety Evaluation Re 800226 Incident.Corrective Actions Taken Are Sufficient to Permit Restart & to Ensure Safe Operation Project stage: Approval ML19330A9821980-07-18018 July 1980 Safety Evaluation of Corrective Action Following 800226 Incident.Actions Taken Are Sufficient to Permit Restart Project stage: Approval ML19345B4021980-11-26026 November 1980 Forwards Nonproprietary Version of Nuclear Safety Review Task Force, Final Rept.Nuclear Safety Task Force Was Established to Identify Areas That Indicate Potential for Improvement in Safety of Facility Project stage: Other ML19347D2691981-03-0606 March 1981 Submits Nuclear Safety Task Force Recommendations Which Will Be Resolved in 1981.Schedule & Resources Estimate 1981 for Resolution of Recommendations in Category 7 Will Be Submitted by 810417 Project stage: Other ML20008F6191981-04-16016 April 1981 Forwards Schedule & Resources Estimate for Nuclear Safety Task Force Recommendations.Detailed Schedule Provided Re Completion of Engineering Studies Identified in Util Project stage: Other ML19347E6071981-04-30030 April 1981 Evaluation of Crystal River Nuclear Power Station Project stage: Other ML20054F3031982-06-11011 June 1982 Submits Status of Engineering Studies Resulting from Nuclear Safety Task Force Recommendations Re 800226 Transient Project stage: Other 1980-04-01
[Table View] |
Text
.
8005120 %
i Florida l
Power May 6, 1980 File:
3-0-1-a Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Contaission Washington, D.C. 20555 S ubj ect :
Crystal River Unit 3 Docket No. 50-302 Operating License No. DPR-72 Nuclear Safety Task Force Priority Items and Confirmatory Order for Crystal River Unit 3, April 14,1980
Dear Sir:
This letter provides a suninary of the background, status, and future plans related to changes in the Main Steam Line Rupture Matrix System, Safety Task Force Priority Item No. 51.
Background
One of the principal objectives of the CR-3 Nuclear Safety Task Force was to identify design or operational features which could lead to loss of all secondary cooling, thus requi ring operator action and increasing the potential for water relief through the pressurizer relief or safety valves.
A number of simplified event tree analyses were performed by the Task Force.
Several of these event tree analyses, including those for steam line break, loss of main feedwater, cxcessive main feedwater, loss of AC power, and loss of ICS power, include sequences which lead to initiation of the steam line rupture matrix.
This, in turn, causes isolation of both main and auxiliary feedwater, and without subsequent operator action, prevents heat removal on the secondary system and leads to the HPI heat removal mode.
Because of the comparatively low prob-dbilities assigned to Correct operator action, the event trees thus show an undesirably high likelihood of ending up in this less desirable cooling code.
l l
General Office 3201 ininy-founn street scuin. P O Box 14o42, St Petersburg. Florda 33733 813 - 866 5151
Director Page Two May 6, 1980 Office of Nuclear Reactor Regulation In light of these conclusions and similar conclusions reached by the Task Force in reviewing the interaction of the Steam Line Rup-ture Matrix System and the EFW system, the Task Force recommended, subject to NRC staff approval, that the rupture matrix signals be deleted from emergency feedwater valves FWV-161 and FWV-162, in the short-term (as soon as possible), and that longer term changes be incorporated in the rupture matrix to preclude feeding the affected generator in the event of a steam line rupture without inhibiting EFW for all other events.
These conclusions are fully consistent with Staff's Reconnendation 4 of draft NUREG-0667 which states:
"4.
Steam Line Break Detection and Mitigation System A.
Eliminate Adverse Interaction with AFW System B.
Reevaluate and Modify Such That System is Capable of Differentiating Between Steam Line Break and Over-cooling and Undercooling Transients."
Elimination of rupture matrix signals to emergency feedwater valves FWV-161 and -162 satisfies the NRC Staff Recommendation 4.A.
The longer tenn changes contemplated are expected to satisfy Recommen-dation 4.B.
Description of Short-Term Change Valves FWV-161 and -162 are preset at 22% open to pass a minimum of 500 gpm.
The Steam Line Rupture Matrix System isolates valves FWV-161 and -162, FWV-33 through -36 as well as main feedwater and main steam if low pressure is sensed in both steam generators.
The sroposed short-term change would eliminate the rupture matrix sig-nals to FWV-161 and -162, thus allowing EFW to be delivered to both steam generators, even if the rupture matrix actuates on both steam generators.
Justification for Short-Term Change The adverse effect of the short-term change is the potential for increased mass and energy release to the containment and associated increase in peak building pressure for an SLB inside containment
(
when compared to the analysis described in Section 14.2.2.1.5 of the FSAR. Analysis is now being perfonned with the intent of show-l ing that adequate operator action time is available to preclude l
overpressurizing the containment in this event.
The results of l
this analysis and additional details including basis of the analy-l sis, risk assessment of short-term operation with the change, com-l parison with other operating plants, etc, will be completed by mid-l May and submitted to the NRC as soon as possible after that.
Cirector Page Three May 6,1980 Office of Nuclear Reactor Regulation Conclusions Significant improvement in the availability and reliability of the EFW system can be achieved by elimination of the Steam Line Rupture Matrix signals to emergency feedwater val ves FW V-161 and -162.
This is consistent with NRC Recommendation 4 of NUREG-0667.
How-ever, since this requires a deviation from the present FSAR Steam Line Break Analysis in Section 14.2.2.1.5, NRC Staff approval is requi red.
If you have any questions about this submittal, please contact this office.
Sincerely, FLOR DA POWER CORPORATION I
S f'/ ((
(
g' George /C. Moore Vice President Power Production GCMemhT0706 cc:
Director Of fice of Inspection and Enforcement U.S. Nuclear Regulatory Commission Suite 3100 101 Marietta Street Atlanta, GA 30303
(
STATE OF FLORIDA COUNTY OF PINELLAS G. C. Moore states that he is the Vice President, Power Production, of Florida Power Corporation; that he is authorized on the part of said company to sign and file with the Nuclear Regulatory Commission the information attached hereto; and that all such statements made and matters set forth therein are true and correct to the best of his knowledge, information and belief.
0 liM vGr. sCT Moore Subscribed and sworn to before me, a Notary Public in and for the State and County above named, this 6th day of May,1980.
% At Notary Public Notary Public, State of Florida at Large, My Commission Expires: August 8, 1983 CameronNotary 3(D12)