NRC Integrated Inspection Report 05000498/2018004; 05000499/2018004, and Independent Spent Fuel Storage Installation Inspection Report 07201041/2018002
ML19032A079
Person / Time
Site: South Texas, 07201041  STP Nuclear Operating Company icon.png
Issue date: 02/01/2019
From: Nick Taylor
NRC/RGN-IV/DRP
To: Gerry Powell
South Texas
References
IR 2018002, IR 2018004
Download: ML19032A079 (36)


Text

February 1, 2019

SUBJECT:

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION - NRC INTEGRATED INSPECTION REPORT 05000498/2018004; 05000499/2018004, AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION INSPECTION REPORT 07201041/2018002

Dear Mr. Powell:

On December 31, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your South Texas Project Electric Generating Station, Units 1 and 2. On January 10, 2019, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any findings or violations of more than minor significance. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Nicholas H. Taylor, Branch Chief Project Branch B Division of Reactor Projects

Docket Nos. 50-498; 50-499, and 07201041 License Nos. NPF-76 and NPF-80

Enclosure:

Inspection Report 05000498/2018004, 05000499/2018004 and 0720104/2018002 w/attachments:

1. Documents Reviewed 2. NRC Request for Information

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers:

05000498, 05000499 and 07201041

License Numbers:

NPF-76 and NPF-80

Report Numbers:

05000498/2018004; 05000499/2018004 and 07201041/2018002

Enterprise Identifier: I-2018-004-0004 and I-2018-002-0096

Licensee:

STP Nuclear Operating Company

Facility:

South Texas Project Electric Generating Station, Units 1, 2, and ISFSI

Location:

Wadsworth, Texas

Inspection Dates:

October 1, 2018 to December 31, 2018

Inspectors:

A. Sanchez, Senior Resident Inspector

J. Choate, Resident Inspector

R. Kopriva, Senior Reactor Inspector

L. Brookhart, Senior ISFSI Inspection, FCDB

E. Simpson, CHP, Health Physicist, FCDB

O. Masnyk Bailey, Health Physicist, RI

A. Bolger, Health Physicist, MLIB

E. Love, Spent Fuel Transportation and Storage Inspector, DSFM

J. Woodfield, Spent Fuel Transportation and Storage Inspector, DSFM

N. Hernandez, Operations Engineer

Approved By:

Nicholas H. Taylor

Chief, Project Branch B

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at South Texas Project, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC-identified and self-revealed findings, violations, and additional items are summarized in the table below.

Licensee-identified non-cited violations are documented in the Inspection Results at the end of this report.

List of Findings and Violations

No findings or violations of more than minor significance were identified during the inspection.

PLANT STATUS

Unit 1 began the inspection period at 93 percent rated thermal power as part of coast down operations for refueling outage 1RE21, which began on October 5, 2018, and ended on November 11, 2018. The unit was returned to rated thermal power on November 14, 2018, and remained there for the rest of the inspection period.

Unit 2 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515 Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01Adverse Weather Protection External Flooding

The inspectors evaluated readiness to cope with external flooding on December 14, 2018.

71111.04Equipment Alignment Partial Walkdown

The inspectors evaluated system configuration during partial walkdown of the Unit 1, train B residual heat removal system during refueling outage on November 1, 2018.

Complete Walkdown (1 Sample)

The inspectors evaluated system configurations during a complete walkdown of the Units 1 and 2 essential chilled water system on December 10, 2018.

71111.05AQFire Protection Annual/Quarterly Quarterly Inspection

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Unit 1, containment building, Fire Area 63, Fire Zones 211 through 214, on October 9, 2018
(2) Unit 1, train C safety related switchgear and battery rooms, Fire Area 4, Fire Zones 52 and 53, on October 16, 2018
(3) Unit 2, train B emergency diesel generator room, Fire Area 37, Fire Zone 501, on November 1, 2018
(4) Unit 2, train A, B, C, and D auxiliary feedwater pump rooms, Fire Areas 48 through 51, on December 26, 2018

71111.08Inservice Inspection Activities (Unit 1)

The inspectors evaluated nondestructive examination activities by observing the following activities:

(1) Magnetic Particle Examinations

a) Feedwater System: Pipe Lugs 18-FW-1032-AA2 / 1PL1-LPL8, Work Order 86000011, Work Authorization 526051, and Report MT-2018-116

(2) Dye Penetrant Examinations

a) Residual Heat Removal System: Welded Attachment RHAHRS-1A-SK Support Skirt, Work Order 86000011, and Report PT-2018-196

b) Chemical and Volume Control System: Seal Water Injection Filter 1B Outlet Valve, Weld HFW0120, Pipe-to-Valve CV-0250B, Work Order 96013951, Work Authorization 598944, and Report PT-2018-190

(3) Ultrasonic Examinations

a) Reactor Coolant System: Pipe-To-Elbow 4-RC-1422-BB1 Weld 4, Scanning Angle of 450, Work Order 86000011, and Report UT-2018-104

b) Reactor Coolant System: Pipe-To-Elbow 4-RC-1422-BB1 Weld 2, Scanning Angle of 450, Work Order 86000011, and Report UT-2018-102

c) Reactor Coolant System: Pipe-To-Elbow 4-RC-1422-BB1 Weld 3, Scanning Angle of 450, Work Order 86000011, and Report UT-2018-103

d) Reactor Coolant System: Pressurizer Surge Line Weld Overlay, Safe End-To-Bent Pipe (PRZ Surge Noz-N1) / Pressurizer Surge Nozzle-To-Safe End PRZ-1-N1-SE-WOL /1 - WOL (N1), Scanning Angle of 450, Work Order 86000011, and Report UT-2018-105

e) Reactor Coolant System: Pressurizer Surge Line, PRZ-1-Nl-IR/ Surge Nozzle Inner Radius, Work Order 86000011, and Report UT-2018-100 f) Replacement Steam Generator: Tube Plate to Lower Shell Barrel A / RSG-1A-T1, Work Order 86000011, and Report UT-2018-097

(4) Visual Examinations

a) Reactor Coolant System: Bottom Mounted Instrumentation Penetrations 1-58, Work Order 753, and Report VE-2018-008

b) Reactor Coolant System: Reactor Vessel Closure Head Bare Metal Visual Examination of Penetration Nozzles 1-9, 14-23, 25-27, 29-61, 66-68, 70, 72, 75-78 (including vent pipe and general head area), Work Order 753, and Report VE-2018-009

c) Containment: Snubber SI-1208-HL5005, Work Order 86000011, and Report VTC-2018-060

The inspectors evaluated welding activities by observing the following welding activity:

(1) Gas Tungsten Arc Weld - Manual

a) Chemical and Volume Control System: Seal Water Injection Filter 1B Outlet Valve Replacement CV-0250B, Pipe-to-Valve CV-0250B, Weld HFW0120, Work Order 96013951, and Work Authorization 598944

The inspectors evaluated the licensees boric acid control program performance.

The inspectors evaluated the results of the licensees bare metal visual inspection of the reactor vessel upper head penetrations. The inspectors reviewed whether the required inspection coverage was achieved and whether limitations were properly recorded. The inspectors also reviewed whether the personnel performing the inspection were certified examiners to their respective nondestructive examination method.

The steam generator tube inspections were not required to be performed in this outage.

The inspectors evaluated a sample of 26 condition reports associated with inservice inspection activities.

71111.11Licensed Operator Requalification Program and Licensed Operator Performance Operator Requalification

The inspectors observed and evaluated just-in-time training for Unit 1 shutdown and cool down activities on October 1-2, 2018.

Operator Performance (1 Sample)

The inspectors observed and evaluated Unit 1 brief and operations during startup and heat up activities on November 6, 2018.

Operator Exams (1 sample)

The inspectors reviewed and evaluated requalification examination results on December 27, 2018.

71111.12Maintenance Effectiveness Routine Maintenance Effectiveness

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety-significant functions:

(1) Units 1 and 2, residual heat removal systems on December 10, 2018
(2) Unit 1, main steam generator power-operated relief valves due to functional failures on December 21, 2018
(3) Units 1 and 2, electrical auxiliary building heating, ventilation, and air conditioning systems on December 21, 2018

Quality Control (1 Sample)

The inspectors evaluated maintenance and quality control activities associated with the following equipment performance issues:

(1) Unit 1, train D steam generator power-operated relief valve cracked bonnet on October 23, 2018

71111.13Maintenance Risk Assessments and Emergent Work Control

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Unit 1, elevated risk due to planned maintenance on train B 125 Vdc battery and inverter IV-1203, which required entry into the Configuration Risk Management Program on November 16, 2018
(2) Unit 1, elevated risk due to emergent maintenance to tighten a reactor coolant system instrument tube fitting on the loop A flow transmitter (FT-0419) on November 17, 2018
(3) Unit 1, elevated risk due to planned maintenance on train A 125 Vdc battery and inverter IV-1201 which required entry into the Configuration Risk Management Program on November 30, 2018

71111.15Operability Determinations and Functionality Assessments

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Unit 1, containment equipment hatch closure within required time limit on November 15, 2018
(2) Unit 1, secondary containment normal level sump pump level transmitter level indication output on November 15, 2018
(3) Unit 2, loop 3 reactor coolant system delta temperature channel spiking down to 87 percent then back to 100 percent on November 16, 2018
(4) Unit 1, loop A flow transmitter (FT-0419) instrument line leak on November 19, 2018
(5) Unit 1, train C emergency diesel generator jacket water leak on November 20, 2018
(6) Unit 1, loop D flow transmitters (FT-0447, 0448, and 0449) following a bias shift during a leak repair on an instrument tubing union on November 24, 2018
(7) Unit 2, train C emergency diesel generator following local voltage unbalance alarms received during a surveillance test which required shutting down the generator on November 26, 2018

71111.19Post Maintenance Testing

The inspectors evaluated the following post-maintenance tests:

(1) Unit 1, train B residual heat removal pump following motor replacement on September 26, 2018
(2) Unit 2, train A spent fuel pool cooling pump following a failure to run on October 4, 2018
(3) Unit 1, extended range nuclear instrument NI-46 following power spiking on October 31, 2018
(4) Unit 1, train C main steam isolation valve following overhaul maintenance on November 2, 2018

71111.20Refueling and Other Outage Activities

The inspectors evaluated refueling outage 1RE21 activities from October 1 to November 11, 2018.

===71111.22Surveillance Testing The inspectors evaluated the following surveillance tests:

Routine===

(1) Unit 1, train B emergency safeguards function actuation test during a simulated loss of offsite power on October 12, 2018

Inservice (1 Sample)

(1) Unit 2, train A residual heat removal inservice test on November 16, 2018

Reactor Coolant System Leak Detection (1 Sample)

(1) Unit 1, reactor coolant inventory on November 15,

OTHER ACTIVITIES - BASELINE

71151Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below for South Texas Project, Units 1 and 2:

(1) MS09: Residual Heat Removal Systems (10/01/2017 through 09/30/18)
(2) MS10: Cooling Water Support Systems (10/01/2017 through 09/30/18)

71152Problem Identification and Resolution Semiannual Trend Review

The inspectors reviewed the licensees corrective action program for trends that might be indicative of a more significant safety issue.

Annual Follow-up of Selected Issues (4 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) The failure of a Unit 1 circuit board in the main steam pegging valve control circuitry on June 25, 2018. This caused an excessive steam demand transient and an increase in thermal reactor power to 103 percent before operators reduced power down to 48 percent.
(2) The failure of Units 1 and 2 diesel driven fire pumps to meet acceptance criteria for discharge pressure between June 14 and September 25, 2018.
(3) The failure of a Unit 2, train A electrical auxiliary building main air handling unit supply fan motor due to a fault inside the motor windings on June 5, 2017. This issues was documented in Condition Report (CR) 17-17075.
(4) The discovery of Sago pond weed in the Units 1 and 2 essential cooling pond ultimate heat sink and the introduction of grass eating carp (triploids) to resolve the issue. This issue was documented in CR 17-21846.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

60854 - Preoperational Testing of an Independent Spent Fuel Storage Inspection (ISFSI)60856 - Review of 10 CFR 72.212(b) Evaluations 60857 - Review of 10 CFR 72.48 Evaluations

Inspections of dry cask storage operations were conducted at STP on September 24-27 and November 26-29, 2018, by inspectors from NRC Regions I, IV, and the NRC Division of Spent Fuel Management. The purpose of the inspections was to observe and evaluate the licensees pre-operational demonstrations required by the Holtec HI-STORM FW Certificate of Compliance (COC), which STP had selected to use under its general 10 CFR Part 72 license.

STP conducted the demonstrations in accordance with the conditions and requirements specified in the Holtec HI-STORM FW Storage System COC 1032 Amendment 2 and HI-STORM FW Final Safety Analysis Report (FSAR), Revision 5.

License Condition No. 9 of the COC lists the pre-operational testing and training exercises required to be completed by a general licensee. During the September through November 2018 inspection dates, NRC inspectors observed STP perform the following operations: transfer of the multi-purpose canister (MPC) from the transfer cask to the HI-STORM FW overpack, MPC unloading operations from the storage overpack back into the transfer cask, and movement of the loaded HI-STORM FW overpack onto the STP ISFSI pad. STP had successfully completed the above listed pre-operations activities and fully demonstrated that the procedures, programs, and training related to those dry cask storage operations had been successfully integrated into its site operations. In addition, NRC inspectors reviewed the licensee's programs for heavy loads, emergency planning, fire protection, quality assurance, radiation protection, and record retention for inclusion of the 10 CFR Part 72 requirements of their generally licensed ISFSI into existing 10 CFR Part 50 programs. The licensee still has a number of demonstrations that are required to be completed before utilization of the HI-STORM FW system. Those demonstrations are projected to be performed in early 2019.

The ISFSI activities specifically reviewed during the on-site inspections and during in-office review included:

(1) Evaluated and observed dry run operations, listed above, associated with License Condition No. 9 of the COC
(2) Reviewed the licensees implementation of STPs Heavy Load Program to encompass dry cask storage operations
(3) Reviewed analyses to determine maximum weights placed on the cask handling crane during loading operations and procedures for manual operation of the hoisting system and the bridge and trolley transfer mechanisms in emergent conditions
(4) Reviewed evaluations that verify the cask handling crane meets the single-failure proof criteria as described in NUREG-0554
(5) Reviewed load testing documentation for the cask handling crane for compliance with ASME B30.2 and ASME B30.10 criteria
(6) Reviewed cask handling crane daily, periodic, and annual inspection procedures for compliance with ASME B30.2 criteria
(7) Reviewed STPs wire and synthetic rope periodic and annual testing procedures for compliance with ASME B30.9 criteria
(8) Reviewed design specifications, load testing documentation, and maintenance procedures for all special lifting devices, including the HI-TRAC VW Lift Blocks, HI-TRAC VW Lift Yoke, MPC Lift-Lock, and HI-STORM Lift Brackets for compliance with ANSI N14.6
(9) Reviewed design specifications, purchase specifications, and load testing for the vertical cask transporter
(10) Reviewed fuel selection procedures for compliance with license requirements with regard to cooling time, decay heat, burn-up, enrichment, etc.
(11) Reviewed the licensees implementation of 10 CFR Part 72 emergency planning requirements into the existing 10 CFR Part 50 Emergency Plan
(12) Reviewed the licensees fire and explosion hazards analysis for the ISFSI and conducted a walk-down of the heavy haul path and ISFSI to ensure all hazards had been identified and evaluated
(13) Reviewed the licensees 10 CFR 72.212 report to verify all site-specific evaluations had been completed to ensure conformance with the terms, conditions, and specifications of the HI-STORM FW COC in accordance with Inspection Procedure 60856
(14) Reviewed radiological dose calculations to verify that the annual levels from ISFSI operations would be less than the limits specified in 10 CFR 72.104
(15) Reviewed licensees ISFSI maintenance and surveillance procedures to verify compliance with requirements from the FW FSAR and license Technical Specifications
(16) Reviewed STPs quality assurance program, corrective action program, and implementing procedures for incorporation of ISFSI related activities
(17) Reviewed STPs radiation protection program for implementation of ISFSI activities, which included ALARA planning, neutron dosimetry, radiation work plans, and calibration of radiological instrumentation
(18) Verified the licensee had established procedures to ensure record retention requirements of 10 CFR 72.212 and verified the licensee had submitted its ISFSI Decommissioning Funding Plan per 10 CFR 72.30(b)
(19) Reviewed the licensees program and procedures to implement changes in accordance with 10 CFR 72.48 requirements. Additionally, inspectors reviewed 10 CFR 72.48 safety evaluations/screenings performed by the licensee for ISFSI operations at STP in accordance with Inspection Procedure 60857
(20) Evaluated and observed the licensees radiation protection implementation during the dry run observations
(21) Evaluated and observed the licensees implementation of foreign material exclusion process during MPC transfer operations

The inspectors did not identify any issues of concerns requiring documentation.

INSPECTION RESULTS

Observation

71152 - Semi-Annual

Trend Review

The inspectors reviewed the licensees corrective action program entries, NRC generated condition reports, maintenance activities deferred from outage scope, maintenance re-work performance indicator, foreign material exclusion (FME) performance indicator and corrective action documents, and recent equipment issues discovered following refueling outages.

The inspectors noted and documented the following issues and trends:

  • There have been several issues associated leaking reactor coolant system (RCS) loop flow transmitter tubing connections. One instance in Unit 2 on RCS loop B resulted in a temporary modification that installed an enclosure around the tubing connection and injected it with sealant. The leak was discovered on August 29, 2018, and documented in Condition Report (CR) 18-10183. There were two tubing leaks discovered in Unit 1. One leak on RCS loop A was discovered on November 14, 2018, and is being monitored with contingency actions if the leak increases in size and is also on the Unit 1 forced outage list for repair. This issue was documented in CR 18-13993. The second leak on RCS loop D was discovered during Mode 3 normal operating pressure and temperature walkdowns. During the repair, the three transmitters in loop D were over-ranged and experienced a zero-bias shift. The transmitter discrepancy was discovered during a channel check on November 24, 2018, and documented in CR 18-14266. Operations continues to monitor these channels for any changes. The licensee captured the trend and is performing a common cause evaluation under CR 18-14369.

The inspectors verified that all issues concerning the leaking RCS flow transmitter tubing connections were addressed within the scope of the corrective action program.

As of the date of this inspection report, the cause evaluation and corrective action development had not been completed and could not be assessed. The inspectors did not identify any trends or concerns that might be indicative of a more significant safety issue.

  • The FME program performance has been placed on departmental elevation notice for continued poor performance despite the station having performed 10 cause evaluations for significant FME issues since 2011. This was concluded on July 23, 2018, and documented in CR 18-5434. The licensees root cause evaluation determined the root cause to be that the program oversight had not identified and corrected declines in behavioral performance. Part of the failure to recognize declines in performance was the incorrect categorization of more significant events as lower safety significant events and not associating FME events with human performance errors. The licensee is in the process of implementing corrective actions.

The inspectors verified that all issues concerning the FME program were addressed within the scope of the corrective action program and that the completed and planned corrective actions appeared to be appropriate to correct the identified causes. The inspectors did not identify any trends or concerns that might be indicative of a more significant safety issue as most issues were identified prior to closing up systems and being placed in service.

EXIT MEETINGS AND DEBRIEFS

On October 26, 2018, the inspectors presented the inservice inspection results to Mr. J. Connolly, Chief Nuclear Officer, and other members of the licensee staff.

On December 31, 2018, the inspector presented the annual requalification inspection results to Mr. A. Culver, Training Supervisor, and other members of the licensee staff.

On January 8, 2019, the inspectors presented the results from the pre-operational ISFSI inspections to Mr. G. T. Powell, President and Chief Executive Officer, and other members of the licensee staff during a telephonic exit conference. Licensee personnel acknowledged the information presented.

On January 10, 2019, the inspector presented the quarterly resident inspection results to Mr. G. T. Powell, President and CEO, and other members of the licensee staff.

The inspectors verified no proprietary information was retained or documented in this report.

DOCUMENTS REVIEWED

71111.01 - Adverse Weather

Condition Reports

18-1565

18-2147

18-6407

18-10622

18-9383

18-9384

Procedures

Number

Title

Revision

0PGP03-ZV-0001 Severe Weather Plan

0PEP07-ZG-0024 Exterior Flood Barrier Penetration Seal Visual Examination

0PEP01-ZE-0001

Structures Monitoring

0PSP11-ZE-0001

Check Valve Inspection

71111.04 - Partial Equipment Alignment

Condition Reports (CRs)

18-11066

18-11194

18-12135

18-11792

18-15228

Procedures

Number

Title

Revision

0POP02-CH-0001 Essential Chilled Water System

Drawings

Number

Title

Revision

5R209F05018#1

Piping and Instrumentation Diagram Component Cooling Water

System

5R169F20000#1

Piping and Instrumentation Diagram Residual Heat Removal

System

5V119V10001#2

Piping and Instrumentation Diagram HVAC Essential Chilled

Water System

3V119V10002#2

Piping and Instrumentation Diagram HVAC Essential Chilled

Water System

3V119V10003#2

Piping and Instrumentation Diagram HVAC Essential Chilled

Water System

71111.05AQ - Fire Protection Annual/Quarterly

Procedures

Number

Title

Revision

0RCB63-FP-0211 Fire Preplan Reactor Containment Building SW Peripheral Area

0RCB63-FP-0212 Fire Preplan Reactor Containment Building NW Peripheral Area

0RCB63-FP-0213 Fire Preplan Reactor Containment Building NE Peripheral Area

0RCB63-FP-0214 Fire Preplan Reactor Containment Building SE Peripheral Area

0EAB04-FP-0052

Fire Preplan Electrical Auxiliary Building ESF Switchgear Room,

Train C

0EAB04-FP-0053

Fire Preplan Electrical Auxiliary Building, Channel IV Battery and

Distribution Room

0DGB37-FP-0501 Fire Preplan Diesel Generator Building, Train B

0DGB37-FP-0513 Fire Preplan Diesel Air Intake/Exhaust, Train B

0IVC50-FP-0401

Fire Preplan Isolation Valve Cubicle, Pump Room Train A

0IVC49-FP-0402

Fire Preplan Isolation Valve Cubicle, Pump Room Train B

0IVC48-FP-0403

Fire Preplan Isolation Valve Cubicle, Pump Room Train C

0IVC51-FP-0400

Fire Preplan Isolation Valve Cubicle, Pump Room Train D

71111.08 - Inservice Inspection Activities

Condition Reports

17-12995

17-15763

17-17970

18-1146

17-12997

17-15859

17-18419

18-3055

17-13007

17-16094

17-19487

18-4215

17-13011

17-16125

17-19831

18-4536

17-13083

17-16270

17-19835

18-12050

17-13360

17-16285

17-20667

18-12531

17-14067

17-16604

17-20673

18-12532

17-15032

17-16990

Work Authorization Numbers (WAN)

24603

96013951

Procedures

Number

Title

Revision

0PEP01-ZA-0305

Testing/Programs Engineering Program Requirements

0PEP10-ZA-0001

Nondestructive Examination Written Practice

0PEP10-ZA-0002

Inservice Inspection Ultrasonic Nondestructive Examination

Written Practice

0PEP10-ZA-0004

General Ultrasonic Examination

0PEP10-ZA-0009

Recording Data from Direct Visual, Liquid Penetrant, and

Magnetic Particle Examinations

0PEP10-ZA-0010

Liquid Penetrant Examination (Color Contrast Solvent

Removable)

0PEP10-ZA-0017

Magnetic Particle Examination (Dry Powder Yoke Method)

0PEP10-ZA-0023

Visual Examination of Component Supports for American

Society of Mechanical Engineers (ASME)Section XI Inservice

Inspection

0PEP10-ZA-0024

ASME XI Examination for VT-1 and VT-3

0PEP10-ZA-0025

ASME Section XI Visual Examination for Containment Metal

Liner Inspections

0PEP10-ZA-0032

Visual VT-2 Examinations

0PEP10-ZA-0054

ASME Section XI VE Visual Examinations

0PGP03-ZE-0033 RCS Pressure Boundary Inspection for Boric Acid Leaks

0PGP03-ZE-0133 Boric Acid Corrosion Control Program

0PGP04-ZE-0304 Inservice Inspection Program for Welds and Component

Supports

0PSP11-RC-0015 ASME Section XI Inservice Inspection

OPSP11-SN-0004 Hydraulic Snubbers Functional Test

PDI-UT-1

Performance Demonstration Initiative (PDI) Generic Procedure

for the Ultrasonic Examination of Ferritic Pipe Welds

G

PDI-UT-2

PDI Generic Procedure for the Ultrasonic Examination of

Austenitic Pipe Welds

H

PDI-UT-5

PDI Generic Procedure for the Straight Beam Ultrasonic

Examination of Bolts and Studs

F

PDI-UT-8

PDI Generic Procedure for the Ultrasonic Examination of Weld

Overlaid Similar and Dissimilar Metal Welds

H

Procedures

Number

Title

Revision

PQR-003

Procedure Qualification Record for Welding Procedure

Specification (WPS) No. P1-T.

PQR-0126

Procedure Qualification Record for WPS No. P1-T (CVN).

PQR-0127

Procedure Qualification Record for WPS No. P1-T (CVN).

PQR-016

Procedure Qualification Record for WPS No. P8-T-Ag-1.

PQR-0197

Procedure Qualification Record for WPS No. P8-T-Ag.

PQR-0199

Procedure Qualification Record for WPS No. P1-A-Lh.

PQR-0205

Procedure Qualification Record for WPS No. P1-A-Lh.

PQR-035

Procedure Qualification Record for WPS No. P8-T-Ag.

PQR-037

Procedure Qualification Record for WPS No. P8-T-Ag, P8-A

and P8-AT-Ag.

PQR-040

Procedure Qualification Record for WPS No. P1-A/P1-A-

Lh/P1AT-Lh.

PQR-046

Procedure Qualification Record for WPS No. P8-T-Ag and

P8-AT-Ag.

PQR-087A

Procedure Qualification Record for WPS No. P1-AT-Lh (CVN).

PQR-087B

Procedure Qualification Record for WPS No. P1-AT-Lh (CVN).

UTI-004

Ultrasonic Technical Instruction

UTI-016

Ultrasonic Technical Instruction

UTI-065

Ultrasonic Technical Instruction

WPS No. P1-A-Lh QW-482 ASME WPS

WPS No. P1-T

QW-482 ASME WPS

WPS No. R8-T-Ag QW-482 ASME WPS

Drawings

Number

Title

Revision

10025E58

South Texas Project Electric Generating Station, Units 1 and 2,

Closure Head General Assembly Interface Inf. for RRVCH

2M369PCV0217

Chemical and Volume Control "CV"

5R179F05007#1

Piping and Instrumentation Diagram Chemical and Volume

Control System

Figure: B-RHX-1

South Texas Project Electric Generating Station, Units 1 and 2,

Residual Heat Removal Hxs 1A, 1B, 1C

W9324055

Anchor/Darling Valve Company, 2"-1888 Socket Ends Stainless

Steel Double Disc Gate Valve with Non-Cobalt Trim and 10" Tee

Handle

A

Miscellaneous

Documents

Number

Title

Revision

or Date

Boric Acid Corrosion Control Program Health

Scorecard, 4th Quarter 2017

January 25,

2018

Examination Plan for 1RE21, ASME Section XI

Inservice Inspection Programs of South Texas

Project Electric Generating Station, Unit 1

October 3, 2018

Letter - Markley to

Halpin

South Texas Project Electric Generating Station,

Units 1 and 2 - Request for Relief RR-ENG-3-02

from ASME Code Requirements for Reactor

Pressure Vessel Flange Insert Nondestructive

Examination (TAC Nos. ME4764 and ME4765)

April 5, 2011

Letter - Markley to

Richards

South Texas Project Electric Generating Station,

Units 1 and 2 - Request for Relief RR-ENG-3-04 to

Apply Alternative to the ASME Boiler and Pressure

Vessel Code Section XI Requirements for

Examination of Class 1 and Class 2 Piping Welds

(TAC Nos. ME70SS and ME70S6)

September 10,

2012

Letter - Pascarelli to

Powell

South Texas Project Electric Generating Station,

Unit 2 - Request for Relief No. RR-ENG-3-20 for

Extension of the Inspection Frequency of the

Reactor Vessel Cold-Leg Nozzle to Safe-End Welds

with Flaw Analysis (CAC NO. MF7428)

June 30, 2016

Letter - Pascarelli to

Powell

South Texas Project Electric Generating Station,

Units 1 and 2 - Relief Request RR-ENG-3-22 for the

use of Encoded Phased Array Ultrasonic

Examination Techniques In Lieu of Radiography

(EPID L-2017-LLR-0154}

July 24, 2018

Miscellaneous

Documents

Number

Title

Revision

or Date

Model No:

16-1000001 Assmnt

No: 73 Cnd Seq No:

16-9146

South Texas Project Nuclear Operating Company

Assessment Report. (Snapshot Assessment)

Leakage trending associated with the 12 Boric Acid

Corrosion Control Program PM's.

August 4, 2016

PM MM-2-90002098

BACC Preventative Maintenance. Reactor

Containment Fan Cooler Cooling Coil (10 Coils).

Cleaning/Inspection.

April 11, 2018

PM MM-2-90002097

BACC Preventative Maintenance. RCFC Fan 22B

RCFC Cooling Coil (10 Coils). Cleaning/Inspection.

April 11, 2018

PM MM-2-90002096

BACC Preventative Maintenance. RCFC Fan 22A

RCFC Cooling Coil (10 Coils). Cleaning/Inspection.

April 11, 2018

PM MM-2-90002095

BACC Preventative Maintenance. Reactor

Containment Fan Cooler Cooling Coil (10 Coils).

Cleaning/Inspection.

October 14,

2016

PM MM-2-90002094

BACC Preventative Maintenance. RCFC Fan 21B

RCFC Cooling Coil (10 Coils). Cleaning/Inspection.

October 14,

2016

PM MM-2-90002093

BACC Preventative Maintenance. Reactor

Containment Fan Cooler Cooling Coil (10 Coils).

Cleaning/Inspection.

October 14,

2016

PM MM-1-90002092

BACC Preventative Maintenance. RCFC Fan 11B

RCFC Cooling Coil (10 Coils). Cleaning/Inspection.

October 29,

2015

PM MM-1-90002091

BACC Preventative Maintenance. RCFC 11C

Cooling Coil (10 Coils). Cleaning/Inspection.

October 29,

2015

PM MM-1-90002090

BACC Preventative Maintenance. Reactor

Containment Fan Cooler Cooling Coil (10 Coils).

Cleaning/Inspection.

October 29,

2015

PM MM-1-90002089

BACC Preventative Maintenance. Reactor

Containment Fan Cooler Cooling Coil (10 Coils).

Cleaning/Inspection.

March 30, 2017

PM MM-1-90002088

BACC Preventative Maintenance. RCFC 12B

Cooling Coil (10 Coils). Cleaning/Inspection.

March 30, 2017

PM MM-1-90002087

BACC Preventative Maintenance. RCFC 12A

Cooling Coil (10 Coils). Cleaning/Inspection.

March 30, 2017

Miscellaneous

Documents

Number

Title

Revision

or Date

NOC-AE-17003532

South Texas Project Electric Generating Station,

Units 1 and 2, Docket No. STN 50-498, STN 50-499,

Proposed Alternative for the use of Encoded Phased

Array Ultrasonic Examination Techniques in Lieu of

Radiography (Relief Request RR-ENG-3-22)

December 12,

2017

STP8053 (7/13)

Station Self-Assessment Program, Snapshot Self-

Assessment Plan. Risk-Informed ISI Periodic

Evaluation for South Texas Project Electric

Generating Station, Units 1 and 2, in Conjunction

with End of the Third Interval, First Period. Condition

Report CR-14-10410

June 24, 2014

1000975

Electric Power Research Institute (EPRI) Boric Acid

Corrosion Guidebook. Managing Boric Acid

Corrosion Issues at PWR Power Stations

PM 05000175

WAN 560570

Pressurizer Power Operated Relief Valves. Monitor

Reactor Coolant System Trends and Develop

Corrective Actions, as Necessary.

September 19,

2018

PM 05000175

WAN 559644

Pressurizer Power Operated Relief Valves. Monitor

Reactor Coolant System Trends and Develop

Corrective Actions, as Necessary.

September 5,

2018

PM 05000175

WAN 558683

Pressurizer Power Operated Relief Valves. Monitor

Reactor Coolant System Trends and Develop

Corrective Actions, as Necessary.

August 22, 2018

PM 06000556

Chemical and Volume Control System. Perform

System Walkdowns in Valve Pits and Areas not

Routinely Accessed to Properly Identify Outage

Scope.

October 22,

2018

PM 06000556

Chemical and Volume Control System, Inspect Valve

Pits and other Difficult to Access Areas

October 22,

2018

Boric Acid

Evaluations

Number

Title

Date

16-06764-5

N1CVFCV0111A, Reactor Make-Up to Chemical and

Volume Control System Blending Tee Flow Control Valve

October 2,2017

17-15948

2N121NPA102C, Low Head Safety Injection Pump 1C

June 7, 2017

17-16232-2

Residual Heat Removal System Heat Exchanger 1B

November 16,

2017

Boric Acid

Evaluations

Number

Title

Date

17-16255-1

7R171TCV0505, CVCS Blended Flow to Reactor Water

Storage Tank Vent Valve

June 7, 2017

17-17970-2

Residual Heat Removal System Heat Exchanger 1A

September 20,

2017

17-18058-2

2N121TSI0206B, High Head Safety Injection Pump 1B

Discharge Valve

July 17, 2017

17-18419-2

B1RCFT0419, Active Leakage on RC-FT-0419 High

Pressure T to Drain Valve Outlet Fitting

November 2,

2017

17-20067

2N121TSI0132, Low Head Safety Injection Pump 1A

Discharge Test/Vent Valve

September 13,

2017

17-20624-3

2N121TSI0126 High Head Safety Injection Pump 1A

Discharge Sample Valve, Downstream Isolation Valve

September 14,

2017

18-00390-3

Residual Heat Removal (RHR) System Heat

Exchanger (HX) 1C

March 14, 2018

18-01250

2N121NPA102B, Low Head Safety Injection Pump 1B

Boric Acid Deposits

February 26,

2018

71111.11Q - Licensed Operator Requalification Training

Procedures

Number

Title

Revision

or Date

0POP03-ZG-0007

Plant Cooldown

Miscellaneous

Documents

Number

Title

Date

Annual Requalification Results Summary

December 21, 2018

71111.12 - Maintenance Effectiveness

Condition Reports (CRs)

18-12135

18-1737

18-11194

18-11066

17-17075

17-15261

17-14667

18-12169

Purchase Order Number

29803

Work Authorization Numbers (WAN)

2819

2860

2104

565616

586343

Procedures

Number

Title

Revision

SEG-0009

Maintenance Rule Basis Document

SEG-0014

Maintenance Rule Program Users Guideline

0PGP04-ZE-0313

Maintenance Rule Program

Drawings

Number

Title

Date

16-11379-21

Life Cycle Management Plan for the Residual Heat

Removal System

November 2017

Miscellaneous

Documents

Number

Title

Date

Maintenance Rule Expert Panel Meeting Package

January 2018

Maintenance Rule Expert Panel Meeting Package

June 2018

Maintenance Rule Expert Panel Meeting Package

November 2018

71111.13 - Maintenance Risk Assessment and Emergent Work Control

Procedures

Number

Title

Revision

0POP11-DJ-0002

Online Class 1E125V DC Battery and Inverter Removal from

Service and Restoration

0POP01-ZO-0006

Risk Management Actions (RMAs)

0PGP03-ZG-RMTS

Risk-Managed Technical Specifications Program

0PGP03-ZA-0091

Configuration Risk Management Program

0POP04-DJ-0001

Loss of Class 1E 125 VDC Power

0PGP03-ZO-0055

Protected Components

Condition Reports (CR)

18-13993

18-14534

17-18164

Work Authorization Numbers (WAN)

601368

Work Activity Risk (WAR)

2796

RICTCAL Sequence Number

269

278

71111.15 - Operability Determinations and Functionality Assessments

Condition Reports (CRs)

18-12152

18-13993

06-3315

03-10610

11-4249

18-14343

18-14621

18-14266

18-14091

18-14038

18-2471

18-2395

Work Authorization Numbers (WAN)

601974

601591

Procedures

Number

Title

Revision

0PMP04-ZG-0012

Equipment Hatch Removal and Installation

0PGP03-ZO-0052

Containment Management

0POP03-RC-0100

RCS Vacuum Fill

0PGP03-ZO-0046

RCS Leakage Monitoring

0PSP03-RC-0006

Reactor Coolant Inventory

0PSP03-DG-0026

Standby Diesel Generator Common Mode Failure Test

0PSP03-ZQ-0028

Operator Logs

148

0PGP04-ZA-0002

Condition Report Engineering Evaluation

Drawings

Number

Title

Revision

or Date

5R149F05001#1

RCS Primary Coolant Loop

5Q159F22540#1

Piping and Instrumentation Diagram Standby Diesel Jacket

Water

G5-253-202

Control Schematic (Generator) Protective Relaying and

Metering

September

29, 1977

G5-253-202

Control Schematic (Generator) High Voltage and Regulator)

June 4,

2001

Calculations

Number

Title

Revision

or Date

11-RC-006

RCS Heatup Analysis for Units 1 and 2 Refueling Outages

09-RCS-004

RCS Time to Boil with Water in Reactor Cavity

MC-6477

Added Commodities Inside The RCB

AC05002#1

Quantification of Unqualified Coatings Inside The Reactor

Containment Building (RCB) For Unit 1

May 21,

2018

71111.19 - Post Maintenance Test

Condition Reports (CRs)

16-10971

17-23347

18-11496

18-11855

Work Authorization Numbers (WAN)

543666

569573

598473

598800

Procedures

Number

Title

Revisions

0PSP05-NI-0046

Extended Range Neutron Flux Channel IV Calibration

0PGP03-ZM-0021 Control of Configuration Changes

0PSP03-SP-0024

Steam Line Isolation Actuation and Response Time Test

0PSP03-MS-0002 Main Steam System Cold Shutdown Valve Operability

0PSP03-RH-0002 Residual Heat Removal Pump 1B(2B) Inservice Test

0PMP05-RH-0001 Residual Heat Removal Pump Motor Inspection

11, 12,

Vendor

Documents

Number

Title

Revision

VTD-G077-0001

Ex-core Neutron Flux Monitoring

Engineering

Reports Number

Title

Date

DCP 18-11855-12

Update design documents per vendor recommendation

October 26,

2018

71111.20 - Refueling and Other Outage Activities

Condition Reports (CRs)

18-1523

18-1804

18-2176

Work Authorization Number (WAN)

534670

564060

600430

Procedures

Number

Title

Revision

0POP03-ZG-0005

Plant Startup to100%

0POP03-ZG-0010

Refueling Operations

0PSP03-XC-0001

Refueling Containment Penetration Status

0POP03-ZG-0001

Plant Heatup

0POP03ZG-0007

Plant Cooldown

0POP03-ZG-0014

Mode Change Checklist

0POP03ZG-0004

Reactor Startup

71111.22 - Surveillance Testing

Condition Reports (CRs)

18-13993

Procedures

Number

Title

Revision

0PSP03-DG-0008 Standby Diesel 12(22) LOOP Test

0PSP03-DG-0014 Standby Diesel 12(22) LOOP - ESF Actuation Test

0PSP03-RH-0001 Residual Heat Removal Pump 1A(2A) Inservice Test

0POP02-RH-0001 Residual Heat Removal System Operation

0PGP03-ZO-0046 RCS Leakage Monitoring

0PSP03-RC-0006 Reactor Coolant Inventory

Drawings

Number

Title

Revision

5R169F20000#2

Residual Heat Removal System

5N129F05013#2

Safety Injection System

71152 - Problem Identification and Resolution

Condition Reports

18-7676

18-8940

18-9294

18-8098

18-11165

Condition Reports

18-9443

18-7925

14-16486

16-6495

18-5434

18-13113

18-11066

18-12213

18-12232

Procedures

Number

Title

Revision

0PGP03-ZF-0018

Fire Protection System Functionality Requirements

0PGP03-FP-0106

Fire Protection Water System Functional Test

SEG-0008

Printed Circuit Board Maintenance and Replacement Guideline

0PGP03-ZF-0001

Fire Protection Program

0PGP03-ZA-0014A Foreign Material Exclusion Program, Administrative Procedure

0PGP03-ZA-0014

Foreign Material Exclusion Program, Implementing Procedure

MG-0008

Station Rework Reduction Program

Drawings

Number

Title

Revision

7Q270F00006

Fire Protection Storage and Pumps

Engineering

Reports Number

Title

Date

SM-03566

Nonconformance Report, Fire Water Pump No 1

December 16, 1986

SM-03567

Nonconformance Report, Fire Water Pump No 2

December 16, 1986

SM-03568

Nonconformance Report, Fire Water Pump No 3

December 16, 1986

4OA5.1 Other Activities (IP 60854, IP 60856, IP 60857)

Condition Reports (CRs)

18-1458

18-2283

18-2440

18-3341

18-3394

18-6595

18-7248

18-7519

18-7780

18-7975

18-8173

18-8234

18-8236

18-8387

18-8710

18-9258

18-9284

18-9306

18-9350

18-9398

18-9582

Procedures

Number

Title

Revision

0PEP02-ZM-0012

Fuel Selection for Dry Cask Storage

0PEP02-ZM-0004

Physical Inventory of Fuel Assemblies

Procedures

Number

Title

Revision

STP Reporting Manual

0PEP02-ZM-0001

Special Nuclear Material Item Control Areas

0ERP01-ZV-IN01

Emergency Classification

0DCS03-ZO-0008

DCS Abnormal Response

ZV-0006

Letters of Agreement

0ESB99-FP-0906

Fire Preplan for ESB and ISFSI Pad

0PGP04-ZA-0328

Engineering and Vendor Document Processing

0DCS03-ZO-0001

HI-STORM Transport Operations

NOC-AE-17003456

STP Fire Hazards Analysis Report

HI-2146056

ISFSI Dose Rate and HI-STORM FW CoC Radiation

Protection Program Dose Rate Limits

0PGP04-ZA-0307

Assessment of External Flooding Effects for STP 1 & 2

ISFSI

HI-21566473

Safety Analysis Summary of the Tornado Generated Missile

Analysis for HI-STORM FW Version XL

0PGP04-ZA-0328

Specification for Total Plant Numbering System

0DCS03-ZO-0002

HI-STORM and MPC Pre-Use Inspections

0PSP03-ZQ-0028

Operator Logs

146

0PGP03-ZX-0002

Condition Reporting Process

0PQP01-ZA-0003

Vendor Overview Activities (numerous)

0PRP07-ZR-0036

Radiological Controls or Dry Cask Storage

STP-005

Proposal for Neutron Dosimetry Evaluation for STP

N/A

ALARA Review Package

0DCS01-ZA-0001

Dry Cask Storage Program Implementation

0DCS02-ZN-0002

10CFR72.48 Screening and Evaluations

0DCS03-ZO-0003

MPC Loading Operations

0DCS03-ZO-0005

MPC Transfer Operations

0DCS03-ZO-0007

MPC Unloading Operations

Design Basis Documents

Number

Title

Revision

HI-2114830

Final Safety Analysis Report on the HI-STORM FW MPC

Storage System

N/A

Certificate of Compliance No. 1032

Miscellaneous

Documents Number

Title

Revision

or Date

N/A

HI-STORM Belly Band Certifications

August 24,

2018

TP-HOL-010

Dry Fuel Storage Training for Vertical Cask Transporter

N/A

N/A

Individual Training Certifications (numerous)

N/A

HI-2135940

HI-STORM FW Cask Handling Weights

0PGP03-ZI-0026

Lifting, Rigging, and Material Handling

PS-3107

Purchase Specification for the HI-STORM FW Lift Bracket

PS-3701

Purchase Specification for the HI-TRAC VW Lift Links

PS-3702

Purchase Specification for the HI-TRAV VW Lift Yoke

PS-3723

Purchase Specification for the HI-TRAV VW Lift Lugs

DOC-104-107-063R0

HI-STORM FW Lift Brackets for South Texas Project

Nuclear Plant

PS-1120

Purchase Specification for the Vertical Cask Transporter

PS-3734

Purchase Specification for FW Lift Lock

G. Powell

PAPERWORK REDUCTION ACT STATEMENT

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control

Number 31500011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Information Request

August 27, 2018

Notification of Inspection and Request for Information

South Texas Project Electric Generating Station Unit 1

NRC Inspection Report 05000498/2018004; 05000499/2018004

INSERVICE INSPECTION DOCUMENT REQUEST

Inspection Dates: October 12-26, 2018

Inspector: Ronald A. Kopriva

A. Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or electronic

format (ims.certrec.com preferred), in care of Ron Kopriva, by October 1, 2018, to facilitate

the selection of specific items that will be reviewed during the onsite inspection week. The

inspector will select specific items from the information requested below and then request

from your staff additional documents needed during the onsite inspection week (Section B of

this enclosure). We ask that the specific items selected from the lists be available and ready

for review on the first day of inspection. Please provide requested documentation

electronically if possible. If requested documents are large and only hard copy formats are

available, please inform the inspector(s), and provide subject documentation during the first

day of the onsite inspection.

If you have any questions regarding this information request, please call the inspector as

soon as possible.

On October 12, 2018, a reactor inspector from the Nuclear Regulatory Commissions (NRC)

Region IV office will perform the baseline inservice inspection at South Texas Project

Electric Generating Station, Unit 1, using NRC Inspection Procedure 71111.08, "Inservice

Inspection Activities. Experience has shown that this inspection is a resource intensive

inspection both for the NRC inspector and your staff. The date of this inspection may

change dependent on the outage schedule you provide. In order to minimize the impact to

your onsite resources and to ensure a productive inspection, we have enclosed a request

for documents needed for this inspection. These documents have been divided into two

groups. The first group (Section A of the enclosure) identified information to be provided

prior to the inspection to ensure that the inspector is adequately prepared. The second

G. Powell

group (Section B of the enclosure) identifies the information the inspector will need upon

arrival at the site. It is important that all of these documents are up to date and complete in

order to minimize the number of additional documents requested during the preparation

and/or the onsite portions of the inspection.

We have discussed the schedule for these inspection activities with your staff and

understand that our regulatory contact for this inspection will be Ms. Robyn Savage of your

licensing organization. The tentative inspection schedule is as follows:

Preparation week: October 8-11, 2018

Onsite dates: October 12-26, 2018

Our inspection dates are subject to change based on your updated schedule of outage

activities. If there are any questions about this inspection or the material requested, please

contact the lead inspector Ronald A. Kopriva at (817) 200-1104.

(e-mail to: ron.kopriva@nrc.gov).

A.1

ISI/Welding Programs and Schedule Information

1. A detailed schedule (including preliminary dates) of:

1.1. Nondestructive examinations planned for ASME Code Class Components

performed as part of your ASME Section XI, risk informed (if applicable), and

augmented inservice inspection programs during the upcoming outage.

1.2. Examinations planned for Alloy 82/182/600 components that are not included in

the Section XI scope (If applicable)

1.3. Examinations planned as part of your boric acid corrosion control program

(Mode 3 walkdowns, bolted connection walkdowns, etc.)

1.4. Welding activities that are scheduled to be completed during the upcoming

outage (ASME Class 1, 2, or 3 structures, systems, or components)

2. A copy of ASME Section XI Code Relief Requests and associated NRC safety

evaluations applicable to the examinations identified above.

2.1. A list of ASME Code Cases currently being used to include the system and/or

component the Code Case is being applied to.

3. A list of nondestructive examination reports which have identified recordable or

rejectable indications on any ASME Code Class components since the beginning of

the last refueling outage. This should include the previousSection XI pressure

test(s) conducted during start up and any evaluations associated with the results of

the pressure tests.

G. Powell

4. A list including a brief description (e.g., system, code class, weld category,

nondestructive examination performed) associated with the repair/replacement

activities of any ASME Code Class component since the beginning of the last outage

and/or planned this refueling outage.

5. If reactor vessel weld examinations required by the ASME Code are scheduled to

occur during the upcoming outage, provide a detailed description of the welds to be

examined and the extent of the planned examination. Please also provide reference

numbers for applicable procedures that will be used to conduct these examinations.

6. Copy of any 10 CFR Part 21 reports applicable to structures, systems, or

components within the scope of Section XI of the ASME Code that have been

identified since the beginning of the last refueling outage.

7. A list of any temporary non-code repairs in service (e.g., pinhole leaks).

8. Please provide copies of the most recent self-assessments for the inservice

inspection, welding, and Alloy 600 programs.

9. Copy of the procedures for welding and NDE that will be used during the outage.

A.2

Reactor Pressure Vessel Head

1. Provide a detailed scope of the planned bare metal visual examinations (e.g., volume

coverage, limitations, etc.) of the vessel upper head penetrations and/or any

nonvisual nondestructive examination of the reactor vessel head including the

examination procedures to be used.

1.1. Provide the records recording the extent of inspection for each penetration

nozzle including documents which resolved interference or masking issues

that confirm that the extent of examination meets 10 CFR 50.55a(g)(6)(ii)(D).

1.2. Provide records that demonstrate that a volumetric or surface leakage path

examination assessment was performed.

2. Copy of current calculations for EDY, and RIY as defined in Code Case N-729-1

that establish the volumetric and visual inspection frequency for the reactor vessel

head and J-groove welds.

A.3

Boric Acid Corrosion Control Program

1. Copy of the procedures that govern the scope, equipment, and implementation of the

inspections required to identify boric acid leakage and the procedures for boric acid

leakage/corrosion evaluation.

G. Powell

2. Please provide a list of leaks (including code class of the components) that have

been identified since the last refueling outage and associated corrective action

documentation. If during the last cycle, the unit was shutdown, please provide

documentation of containment walkdown inspections performed as part of the boric

acid corrosion control program.

A.4

Additional Information Related to all Inservice Inspection Activities

1. A list with a brief description of inservice inspection, and boric acid corrosion control

program related issues (e.g., Condition Reports) entered into your corrective action

program since the beginning of the last refueling outage. For example, a list based

upon data base searches using key words related to piping such as: inservice

inspection, ASME Code,Section XI, NDE, cracks, wear, thinning, leakage, rust,

corrosion, boric acid, or errors in piping examinations.

2. Provide training (e.g. Scaffolding, Fall Protection, FME, Confined Space) if they are

required for the activities described in A.1 through A.3.

3. Please provide names and phone numbers for the following program leads:

Inservice inspection (examination, planning)

Containment exams

Reactor pressure vessel head exams

Snubbers and supports

Repair and replacement program

Licensing

Site welding engineer

Boric acid corrosion control program

B.

Information to be Provided Onsite to the Inspector(s) at the Entrance Meeting

(October 12, 2018):

B.1

Inservice Inspection / Welding Programs and Schedule Information

1. Updated schedules for inservice inspection/nondestructive examination activities,

including planned welding activities, and schedule showing contingency repair

plans, if available.

2. For ASME Code Class welds selected by the inspector from the lists provided from

section A of this enclosure, please provide copies of the following documentation for

each subject weld:

Weld data sheet (traveler).

Weld configuration and system location.

Applicable Code Edition and Addenda for weldment.

Applicable Code Edition and Addenda for welding procedures.

G. Powell

  • Applicable welding procedures used to fabricate the welds.

Copies of procedure qualification records (PQRs) supporting the weld

procedures from B.1.b.v.

Copies of welders performance qualification records (WPQ).

Copies of the nonconformance reports for the selected welds (If

applicable).

Radiographs of the selected welds and access to equipment to allow

viewing radiographs (if radiographic testing was performed).

Copies of the preservice examination records for the selected welds.

Readily accessible copies of nondestructive examination personnel

qualifications records for reviewing.

3. For the inservice inspection related corrective action issues selected by the inspector

from section A of this enclosure, provide a copy of the corrective actions and

supporting documentation.

4. For the nondestructive examination reports with relevant conditions on an ASME Code

Class components selected by the inspector from Section A above, provide a copy of

the examination records, examiner qualification records, and associated corrective

action documents.

5. A copy of (or ready access to) most current revision of the inservice inspection

program manual and plan for the current interval.

6. For the nondestructive examinations selected by the inspector from section A of this

enclosure, provide a copy of the nondestructive examination procedures used to

perform the examinations (including calibration and flaw characterization/sizing

procedures). For ultrasonic examination procedures qualified in accordance with

ASME Code,Section XI, Appendix VIII, provide documentation supporting the

procedure qualification (e.g. the EPRI performance demonstration qualification

summary sheets). Also, include qualification documentation of the specific equipment

to be used (e.g., ultrasonic unit, cables, and transducers including serial numbers) and

nondestructive examination personnel qualification records.

B.2

Reactor Pressure Vessel Head

1. Provide the nondestructive personnel qualification records for the examiners who will

perform examinations of the reactor pressure vessel head replacement (If applicable).

G. Powell

2. Provide drawings showing the following:

Reactor pressure vessel head and control rod drive mechanism nozzle

configurations

Reactor pressure vessel head insulation configuration

Note: The drawings listed above should include fabrication drawings for the nozzle

attachment welds as applicable.

B.3

Boric Acid Corrosion Control Program

1. Please provide boric acid walk down inspection results, an updated list of boric acid

leaks identified so far this outage, associated corrective action documentation, and

overall status of planned boric acid inspections.

2. Please provide any engineering evaluations completed for boric acid leaks identified

since the end of the last refueling outage. Please include a status of corrective actions

to repair and/or clean these boric acid leaks. Please identify specifically which known

leaks, if any, have remained in service or will remain in service as active leaks.

B.4

Codes and Standards

1. Ready access to (i.e., copies provided to the inspector(s) for use during the inspection

at the onsite inspection location, or room number and location where available):

Applicable Editions of the ASME Code (Sections V, IX, and XI) for the

inservice inspection program and the repair/replacement program.

2. Copy of the performance demonstration initiative (PDI) generic procedures with the

latest applicable revisions that support site qualified ultrasonic examinations of piping

welds and components (e.g., PDI-UT-1, PDI-UT-2, PDI-UT-3, PDI-UT-10, etc.).

3. Boric Acid Corrosion Guidebook Revision 1 - EPRI Technical Report 1000975.

ML19032A079

SUNSI Review

ADAMS:

Non-Publicly Available

Non-Sensitive

Keyword:

By: NTaylor

Yes No

Publicly Available

Sensitive

NRC-002

OFFICE

SRI:DRP/B

RI:DRP/B

C:DRS/PSB2

C:DRS/OB

C:DRS/IPAT

C:DRS/EB1

NAME

ASanchez

JChoate

HGepford

GWerner

RKellar

VGaddy

SIGNATURE

AAS

JMC

HJG

GEW

RLK

Vgg

DATE

1/29/19

01/25/19

01/19/19

01/20/19

01/17/19

1/17/19

OFFICE

C:DRS/EB2

C:DNMS/CHP

BC:DRP/B

NAME

JDrake

JKatanic

NTaylor

SIGNATURE

JFD

JFK

NHT

DATE

1/22/19

1/22/19

2/1/19