ML18151A515

From kanterella
Jump to navigation Jump to search
Insp Repts 50-280/90-09 & 50-281/90-09 on 900402-12.No Violations Noted.Major Areas Inspected:Accuracy of Plant Eops,To Verify That Specified Actions Could Be Accomplished Using Existing Equipment,Controls & Instrumentation
ML18151A515
Person / Time
Site: Surry  Dominion icon.png
Issue date: 05/09/1990
From: Peebles T, Schin R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18151A516 List:
References
50-280-90-09, 50-280-90-9, 50-281-90-09, 50-281-90-9, NUDOCS 9005220376
Download: ML18151A515 (93)


See also: IR 05000280/1990009

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W.

ATLANTA, GEORGIA 30323

Report Nos.:

50-280/90-09 and 50-281/90-09

Licensee:

Virginia Electric and Power Company*

Glen Allen, VA

23060

Docket Nos.:

50-280 and 50-281

Facility Name:

Surry 1 and 2

License Nos.: DPR-32 and DPR-37

Inspection Conducted:

April 2 - 12, 1990

Inspector: ~

-f-

. _ *-

R. Schi n, Team Leader

Approved

Scope:

NRC learn Members:

J. Arildsen

NRC Contractors:

L. Mellen

M. Shannon

J. York

Haney,

Meeker, C_

~rt. T .. A. Peebles., Chief

Operations Brarich

Division *of Reactor Saf

SUMMARY

s-r-7o

Date Signed

Date Signed

This was

a

special

announced Emergency Operating Procedure (EOP) team

inspection.

Its purpose was to verify that the Surry EOPs were technically

accurate, and that their specified actions coulc! be accomplished using

existing equipment, controls and instrumentation.

The inspection evaluated

the adequacy of the licensee's EOPs [includi.ng Abnormal Procedures (APs) and

Fire Contingency Actions (FCAs)], conformance of these procedures to the

Westinghduse

Owners'

Group

Emergency

Response

Guidelines

(ERGs),

and

conformance to the approved writer's guide.

The inspection included a

comparison of the EOPs to the ERGs, a technical adequacy review of the

procedures, control room and in-plant walkthroughs, simulator eva*luation of

selected procedures, a review of on-going control of these: procedures, and

inte.rviews of operators who use the procedures .

\\

90051:5

0!50002:3()

FDC

2

Results:

The overall assessment concluded that the EOPs adequately covered the broad

range of accidents and equipment failures necessary for safe shutdown of the

plant, and were capable of safely shutting down the plant and placing it in

a stable condition.

The team identified as licensee strengths:

use of the

same writer

1 s guide for EOPs and APs, paragraph 3; and simulator support for

EOP inspection, paragraph 5.

The team identified weaknesses in procedures,

inc.luding.:

important operator actions missing

from

EOPs,

paragraph 3;

incorrect or incomplete directions to operators, paragraph 3; and inaccurate

or inconsistent use of key words and symbols, paragraph 3.

Violations or

deviations were not identified in this report .

REPORT DETAILS

1~

Persons Contacted

Licensee _Employees

  • 0.
  • W.
  • R.

T.

  • M.

A.

  • D.

M.

L.

D.

  • E.

G_.

  • B.
  • E.
  • 0.

H.

R.

I.

  • M.

w.

T.

  • P.
  • J.

J.

w.

  • R.

G. s.

R.

  • E.

D.

A.

E.

N.

A.

R.

R.

Beith, Procedures Group Human Factors Specialist

Benthall II, Licensing Supervisor

Blount II, Procedures Grau~ Supervisor

Bowden, Control Room Operator

Bowling, Assistant Station Manager, North Anna

Brown, Nuclear Training Supervisor

Christian, Assistant Station Manager, O&M -

French, Reactor Operator

Gardner, Senior Nuclear Training Instructor

Glover, Reactor Operator

Grechek, Assistant Station Manager, NS&L

Griffin, Control Room Operator

Gros~, Shift Operations Supervisdr

Harrell, Vice President, Nuclear Operations

Hart, Quality Assurance Supervisor

Johnson, Coritrol Room Operator

Johnson, Assistant Shift Supervisor

Jones III, Control Room Operator

Kansler, Station Manag~r

Kreheley, Senior Training Instructor

Kunkle, R~actor Operator

Linn, Contractor, Volian Enterprises Inc.*

Logan, Senior Staff Engineer

McCarthy, Operations Superintendent

Moore, Senior Nuclear Training Instructor

Mushenheim, Procedures Group Lead Writer

Prescott, Assistant Shift Supervisor

Ross, Reactor Operatpr

Scherer, Reactor Operator

Smith, Quality Assurance Manager

Souza, Assistant Shift Supervisor

Swander, Procedures Group

Turko, Testing Supervisor

Turner, Reactor Operator

Wheeler, Jr., Shift Supervisor

Yzzi, Assistant Shift Supervisor

Zoldork, Reactor Operator

Other licensee employees contacted included engineers, technicians,

operators, and office personnel .

\\

2

NRC Personnel

  • W. Holland, Senior Resident Inspector
  • C. Julian, Engineering Branch Chief, DRS
  • P. Kellogg, Operational Programs Section Chief, DRS
  • Attended exit interview on April 12, 199.0
  • Procedures reviewed during. this inspection are listed in Appendix A.

A list of abbreviations used in this report is contained in Appendix E.

2.

EDP comparison with ERGs and Regulatory Guide 1.33

The tea.m compared the index of Surry EOPs with the index of NRC approved

ERGs and found that the licensee had an EDP corresponding to each ERG with

the exception of ES-0.4, Natural circulation cooldown with steam void in

vessel without RVLIS.

The licensee had an operabl~ RVLI5.and had an EDP

ES~0.3, Natural circulation cooldown with steam void in vessel with RVLIS

(Appendix B, ES-0.3, comment h).

The team compared the 1 i censee I s index of EOPs and APs with the NRC

Regulatory Gui de 1. 33 1 i st of procedures for addressing emergencies and

other significant events.

This comparison determined that the licensee

had deve 1 oped sufficient procedures to cover the broad spectrum of

accidents and equipment failures.

.

.

The teal!) compared the Surry EOPs to the ERGs and found that they followed *

.the accident mitigatirin strategy and action sequence of the ERGs, except

as properly justified in the Surry EDP SOD or as noted in Appendix B to

this report.

In addition, the team evaluated EOP step deviation~ from the

ERGs incident to . the EDP wa l kthroughs and found them to be properly

justified and documented, except as noted in Appendix B.

The licensee's

EDP procedure entry and transition conditions closely followed the ERGs.

The licensee had made many changes to individual EOP steps from the way

they were written in the ERGs; to adapt them to the Surry uni ts, imp rove

the human factors, and comply with the writer's guide.

In addition, the

licensee's EOP steps contained some technical improvements over the ERG

steps.

In most cases, these EDP step deviations from the ERG were

adequately justified in the EOP

SOD.

The. licensee's plant specific

technical guidelines (PSTG) included the EDP

SOD, the EDP Setpoint

Document, and the Westinghouse Owners* Group ERGs.

The team identified a

few cases where the resulting EOPs deviated from the ERGs without adequate

justification in the EDP SOD.

These EDP deficiencies are described in

Appendix 8; where they are identified by

11 PSTG DEV 11 *

The team concluded

that none of these EOP deficiencies precluded the ability of the EOPs to

safely shut down the units.

There were no violations or deviations noted in this area.

3

3.

Independent technical adequacy review of EOPs

The team reviewed the licensee 1*s EOPs and selected samples of the APs and

FCAs, as listed in Appendix A,

for technical adequacy.

During this

review, the NRC identified numerous examples of technical or human factors

deficiencies as described below and in Appendix B.

The team found that the 1 i censees I

procedures did not fully address

important operator actions that were identified by an engineering study

on loss of intake canal.

(The elevated intake canal was the licensee's

ultimate heat sink).

For example, procedures did not address required

times for performing certain operator actions to preserve intake canal

inventory (Appendix B, AP 12.01, Steps 1 and 10a).

Procedures also did not

address local operation of condenser waterbox SW valves to preserve intake

canal inventory (Appendix B, ECA 0.0, Step 7b).

Manual valves required for

quickly cross connecting charging between units to protect RCP seals were

not clearly labeled or readily accessible (Appendix B, ECA 0.0, Step 10).

Also, during a loss of all _AC po~er, the operators had no ?ffective means

of communication with personnel outside the control room.

This lack of

communication severely hampered the ability of op~rators to implement the

EOPs and APs.

In response to these concerns, the 1 i censee * stated that they would

immediately revise AP-12.01, Loss of intake canal, with the revision to be

issued within one week.

Affected steps in that procedure are indicated in

Appendix 8.

The licensee also stated that they would initiate operator

use of sound powered phones for certain emergency conditions within one

month, pending availability of required equipment.

In addition, the licensee stated that they would make a design change to

the operations radio repeaters, to provide emergency power from batteries.

These three corrective actions are identified as IFis 280,281/90-09-01,

02., and 03.

Licensee design calculations for intake canal level showed that, in an

accident situation, the condenser waterbox valves must be closed within

70 seconds to preserve s~fficient water in the intake canal to handle a

LOCA.

A plant vulnerability was noted in that a loss of all AC power

to a unit for 30 minutes could cause a LOCA due to RCP seal failures

(Appendix B, ECA 0.0, Step 10) and without AC power to either unit, which

is beyond the design basis, the operators could not close the condenser

waterbox valves in time to prevent the intake canal from draining well

  • below the required level (Appendix 8, ECA 0.0, Steps 7a RNO and 7b).

Once

the canal level was down, it could not readily be regained.

The three

diesel powered emergency service water pumps could be started within two

hours, and then could pump water into the canal at a rate that could be

sufficient for both units to remain at hot standby, but less than the flow

rate of cooling water needed for a unit during a LOCA.

With a low intake

canal level, the eight large circulating water pumps that normally

supplied the large flo~ rate of water into the intake canal for both units

could not be started ev~n if their offsite power was restored ..

4

These pumps required a vacuum assist in their discharge p1p1ng, and with

the end of the discharge piping above the canal level, the required vacuum

could not be obtained.

In essence, once the canal level was lost, it

would be very difficult to be regained during a LOCA.

The licensee is

conducting an IPE.

The plant vulnerability to this beyond the design

basis event will be addressed in that analysis.

This is identified as

IFI 280,281/90-09-04.

Technical deficiencies identified by the team included incorrect direction

for operators.

One EOP step failed to recognize that the instrument used

to verify RCP s~al return temperature would have been isolated from the

flow path during an SI condition.

One EDP step incorrectly directed the

operator to transition past an important action (Appendix B, ECA-1.1,

step 22b RNO).

Another type of technical deficiency was the existence of

some incorrect setpoints in EOPs.

For example, one EOP included a natural

ci rcul at ion cool down rate of 100 *degrees per hour, when the setpoi nt

document number was 50 degrees per hour (Appendix B, ES-0.2, step 3a).

In

addition, the team observed some mathematical errors in the EOP setpoint

document.

There was an apparent weakness in the VP review and receipt

inspection of the setpoint document, which had been prepared by contractors.

The team concluded that none of the technical deficiencies precluded the

ability of the operators to use the EOPs to safely shut down th~ units .

The team found the technical adequacy of the APs and FCAs to be less than

that of the EOPs.

They were less complete, provided 1 ess guidance and

detail to the operators, and contained many more technical errors.

For

example, one FCA step directed operators to initiate the cold overpressure

protection system with the PORVs disabled (Appendix B, FCA-1.01, step 54).

Another FCA step directed operators to establish conditions for starting

an RCP when they could not do so (Appendix B, FCA-1.01, step 33).

Entry

conditions for one AP depended on an alarm whose setpoint had not been

changed to reflect current plant conditions.

(Appendix B, AP-24, entry

condition 2).

The APs and FCAs also had less well defined entry conditions.

In addition, these procedures were not written to the standards of the EDP

WG.

However, the new EOP dual column WG applied also to APs, and the

licensee was upgrading the APs to meet the standards of this WG.

Having

the EOPs and APs written to the same standards will aid the operators by

removing some potential confusion when using EOPs and APs together.

In response to the NRC identified technical deficiency concerns, the

licensee stated that they had changed the alarm setpoints of the steam

generator blowdown radiation monitors to be correct prior _to the exit

interview.

The licensee also stated that they would promptly revise 18

steps in 15 procedures.

These procedure revi.si ans were to be issued

within about 12 weeks, with Rev. 2 to the EOPs.

In addition, the licensee

stated that one procedure step would be revised. before the next refueling

outage.

These procedures and steps are identified in Appendix B.

4.

5

The licensee also stated that the remaining technica*l and human factors

items in Appendix B would be addressed with Rev. 3 to the EOPs as

appropriate.

These three scheduled corrective actions are identified as

IFis 280,281/90-09-05, 06, and 07.

The team found the EOPs to be unnecessarily complicated by many instances

of inaccurate and inconsistent use of key words and symbols.

Examples

included the words verify and should, transition terms, bullets, and

asterisks.

In addition, the use of cautions or notes often conflicted

with WG direction.

The inconsistent application of the writer 1 s guide

made the EOPs not amenable to verbatim operator compliance.

In general

the operators during interviews and simulator scenarios were able to

properly use the EOPs in spite of the writing deficiencies.

Operators did

not follow the key words and symbols when they appeared to conflict with

a procedure 1 s intent; however, these conflicts did lead operators to

interpret the intent of some steps differently.

Human factors comments

are addressed in Appendix Band writer 1 s guide comments are addressed

in Appendi,x C.

The licensee stated that they would address Appendix C

items* with Rev. 3 to the EOPs.

Appendix C items are identified as

IFI 280,281/90-09-08.

The team found the licensee 1 s EOP development, revision, and maintenance

procedure to be well organized and comprehensive. It included a verifi-

cation of EOPs by a station engineer and a human factors specialist as

well as a licensed operator and a procedure writer.

In addition, it

required in plant walkthroughs to determine if local actions could be

conducted as required.

These were in addition to the simulator

validation.

The. licensee

1 s writer

1 s guide for dual-column procedures was generally

well organized and complete, but was lacking in some important specifics.

Deficiencies identified with the writer 1 s guide are described in Appendix C.

The team found the EDP step deviation documents to be typically well

organized and cross referenced.

The EDP set point document was also well

organized; however, it had some inconsistencies in the quality of the

documentation.

In general, the information required to verify the set

points was referenced and was available.

There were no violations or deviations noted in this area.

Review of the EDPs by control room and plant walk-throughs

The NRC conducted control room and in plant walkthroughs of the EOP, AP,

and FCA procedures listed in Appendix A.

Transfers and branching were

checked and found to be proper, except as noted in the Appendix B.

The

team found the relationship between EOP. procedure nomenclature and

equipment labeling to be generally consistent and capable of being easily

understood without confusion, except as noted in Appendix 0.

This was

also the case with APs and FCAs; although more instances of inconsistent

procedure nomenclatur\\ and equipment labeling were found.

The team

noted an improving trend in equipment labeling and pl ant housekeeping.

Appendix D items are identified as IF! 280,281/90-09-09.

6.

Excepi;. as noted in Appendix B, the team found that i ndi ca tors, contro 1 s,

annunciators, and other equipment required by the EOPs, APs, and FCAs were

a~ailable.

The team noted during a limited number of walkthroughs that

some operator~ had difficulty in locating all controls and equipment used

in thete procedures~

The team also noted that ARPs have not received as

much licensee attention as other procedures -

some had not been revised

since 1975 or 1976.

In the control room, one complete set of controlled

EOPs, APs, and FCAs for each unit was located on the apprdpriate side of

the dual unit control room - these procedures were current and readily

available to the operators.

While the results of *the walkthroughs were generally satisfactory, .

many discrepancies in the areas of technical accuracy, writer 1s guide

adherence, and human factors were noted.

.Techni ca 1 and human factors

discrepancies are noted in Appendix B, writers guide discrepancies* in

Appendix C, and nomenclature discrepancies in Appendix D.

There were no violations ~r deviations noted in this area.

5_

Simulator observation

The team. observed two crews I performance* on the Surry Power Station

simulator. The following six scenarios were performed over a two-day

period:

CSF status tree red.path during transfer to cold leg recirculation

Loss of all AC (pre.ceded by fire. and loss of offs'ite p'ower)

Large break LOCA from RHR conditions

Loss of offsite power

Main control room evacuation

Steam generator tube rupture and LOCA

The operators performed the EOP exercise scenarios in r.eal time on the

simulator with the exception of the last half .of the main control room

evacuation scenario.

When the crew evacuated the main control room in

that scenario, the simulator was frozen, and a walkthrough discussion of

the crew* s follow-up actions was conducted. The team noted no significant

deficiencies with accident mitigation strategy or recovery action *in any

scenario. The crews were able to successfully incorporate their training

and experience with the procedures to mitigate the accidents. . The

procedures did not unnecessarily dup 1 i cate operator actions, and the

procedures did not cause the operators to physically interfere with each

other while performing the EOPs.

Ih g~neral, the procedures ~nsured the

operators addressed all the required prerequisite actions for their

.transitions from one EOP to another.

After one scenario, the operators stated that there was no pre-planned

procedure in p 1 ace for a fire in the switchyard.

They exhibited a need

and expressed a desire for such guidance.

\\

7

EOP place kee~ing aids; which included a location for a check mark by each

high level action step in an EDP to indicate completion of the* step, were

not consistently used by the operators.

The operators stated that they

had not been trained o~ the use of these place keeping aids.

Prior to

these EDP *exercise scenarios, the training staff had directed that the

check marks not be u~ed in simulator training. Operators also indicated a

need for ~lace keeping aids to be used to mark pages when transitioning

amo~g a number of procedures.

Sound powered phone jacks were not available in the simulator, but wete

in the main

control

room.

Operators stated that such means of

communications may be useful in a loss of all AC power.

Operators further

stated that they had not been trained on sound powered phone communications.

The controlled keys in the. simulator differed from those in the main

control room in location and labeling.

Although prebriefed on this

matter, one crew .exhibited confusion in obtaining certain EDP required

keys.

In the performance of the evacuation of the main control room scenario,

the NRC team verified that steps 33 and 54 in procedure FCA-1.01, Limiting

  • MCR fire,. failed to provide adequate -guidance to the operator.

Step 33

required operators to establish conditions for starting an

RCP from

outside the main control room:.

The operators indicated .that this could*

not be accomplithed in accordance ~ith existing procedures~

They further

stated that, without the ability to establish proper conditions, they

would not start an RCP.

Step 54 required operators to place the overpressure mitigation system

(OMS) in service.

Due to the complexity of FCA-1.01, the operators* did

not realize that the PORVs had been isolated in step 10a.

The operators

indicated that by the time. that st~p 54 was performed it would probably

be performed by the relief shift and that it was unlikely they would have

~ecogniied that the PORVs were blocked.

Furthermore, the operators stated

th.at all indications they would receive. would support that the OMS was i-n

service, when in fact it wa~ not.

The two crew.s exhibited significant concern for the time required for the

initiation of step 18c in procedure E-1, Loss of r'eactor. .or secondary.

coolant.

Operators stated that the actions in -that step might better be

accomplished through the use of an attachment.

One crew stated that they were unclear in their understanding of step~ 1n

FR-C.l, Response t6 inadequate core cooling. In particular, checking the

availability of seal leakoff flow to be greater than 0.3 GPM appeared

inconsistent with the RNO action to establish the support condition.

The NRC team noted that the simulator maintained subcooling for approxi-

mately 15 minut~s without PRZR level during a simulated LOCA/SGTR.

8

The Surry Training Department's simulator support personnel were a

valuable assistance to the team in every aspect of the simulator portion

of the inspection. The joint NRC-Surry thorough scenario development and

validation efforts resulted in the simulation of well defined events which

afforded significant support to the EOP inspection process.

There were no violations or deviations noted in this area.

6.

Management control of EOPs and interfacing documents (APs, FCAs, ARPs,

OPs, etc.)

NUREG-0899,

Guidelines for the preparation of emergency operating

procedures, paragraph 6.2.3, recommends licensees establish a program for

the on-going evaluation of EOPs.

Also, paragraph 6.2.4, updating EOPs,

recommends that when changes occur that will affect the EOPs, the changes

should be reviewed to ensure consistency with the technical guidelines

and the writer's guide.

The team reviewed the licensee I s procedure VPAP-506,

EOP deve 1 opment,

revision, and maintenance, dated October 24, 1989, for comp 1 i ance with

these recommendati ans.

This procedure addressed the EOP maintenance

program, which incorporated the fo 11 owing attributes:

  • Writer's Guide
  • V&V Guidelines
  • EOP Revision Process
  • Maintenance of Related Documents (basis, setpoints, etc.)
  • Plant Modifications
  • WOG ERG Revisions
  • Feedback from Training, Operating Experience, etc
  • Training on Revisions
  • Safety-Evaluations/Engineering Evaluations
  • Human Factors Involvement
  • Management Involvement

The licensee had been using an informal process for recommended changes to

EOPs, but had a procedure revision in progress that included an EOP

specific change recommendation form.

This form required a formal feedback

to the originator. The recommended change form would be processed using

station procedure VPAP-502, Procedure Process Control, dated February 5,

1990.

The licensee was revising APs to conform with the guidelines in

procedure VPAP-50.5,

Writers guide for . dua 1-co 1 umn procedures, dated

March 12, 1990.

  • The licensee had performed an EOP assessment during February 5 through 23,

1990. This assessment was performed by the Corporate Nuclear Safety (CNS)

group and identified approximately 300 items for review.

Each of these

items were to be addressed by the Surry Nuclear Station and changes were

to be made to the EOPs where appropriate.

The licensee stated that none

of the identified itB{!ls required any immediate action.

The licensee's

EOP assessment was no't issued prior to the end of this NRC

EOP

inspection .. However, the executive summary was discussed with the team

leader during the inspection.

7 .

9

Follo~ing the inspection, the NRC was provided with a copy of the licensee 1 s

assessment.

A ~eview of this document indicated the scope and depth of

the licensee 1s review was slightly different from the NRC 1 s inspection in

that it placed more emphasis on the verification and validation aspects

of EOP preparation.

The NRC inspection was broader in that it 16oked at

AP 1 s, FCA 1 s and ARP 1 s.

In.the areas where the two audits overlapped many of the general concerns

identified were similar ~n nature, although specific individual items were

for the most part different. The licensee 1 s assessment was an aggres~ive

in depth examination of the EOP 1 s, supporting procedures and documenta-

tion .. Th-is-assessment and the NRC 1 s inspection both indicate that a

large- effort is necessary to upgrade and maintain the EOP 1 s and related

procedures at the facility.

The QA group performed an EOP audit on April 19, 1989, thrbugh May 31,

1989, before the new Revision lA EOPs were complete.

The licensee

expressed plans to audit the EOP procedures on an.annual basis.

There were no violations or deviations noted in this area.

EOP user interviews

The team conducted intervie~s with seven licensed operators.

Two of the

operators were on the training staff and one of the operators was ori the

engineering staff.

One of the opera.tors was a shift supervisor.

All operators held active

licenses except one who had just gone to inactive status. The interviews

were conducted to sample the operators* opinions on the quality, usability,

and adequacy of the EOPs., to collect information on the approach to

training, and to augment the identification of specific deficiencies in

the EOPs.

.

Generally the operators were confident that the EOPs would work and could

be used in an actual emergency.

Specific comments identified in the

  • interviews* are discussed below.

One operator commented that the Rev ... lA EOPs were relatively .new and

the operators were not as familiar with them as they were with other

procedures.

He felt the operations staff had not been appropriately

  • involved in the preparation of the procedures.

He believed more simulator

time on the EOPs once they were finalized would be helpful.

He felt the

EOPs were workable in their present form for experienced operators but

that a less experienced operatof would have a more difficult time with

some of the more complicated EOPs.

One operator noted that the new Rev. lA EOPs contained fewer notes and

cautions than the old EOPs and felt that some of the excluded information

had been useful. Another operator commented that in some places the EOPs

were very detailed and in other places did not contain enough detail. One

interviewee felt that there were isolated areas in EOPs where more back-

ground information was needed.

10

Operators stated that division* of responsibility in the control room

during an emergency was understood and, although not formally covered in

an administrative procedure, was well covered and practiced in training.

When asked if there were any circumstances where additional staffing would

be helpful for implementing the EOPs, operators indicated the following

instances:

Station blackout, Control room fire, Intake canal loss, and

Dual unit events.

When asked if they felt they had enough time to .execute

the. EOPs, one operator said yes for most EOPs - but that for SG tube

rupture, and preventing the pressurizer from going solid upon spurious SI,

it would be close.

One operator indicated he felt the EOPs were too wordy

thus increasing performance time. Another operator indicated IA steps as

an example where the rules of usage (i.e., reading) made performance of

the procedures unnecessarily slow. Another operator interviewed also felt

reading procedures word for word slowed the process and that more training

to enhance EOP familiarity would speed procedure execution.

When asked about place keeping (i.e., transitions, branching, parallel

performance of procedures, continuous actions), operators indicated that

some method such as physical place markers in addition to currently used

check offs and shared responsibility (i.e., procedure reader and procedure

performer) would be very helpful .

Six of the operators were asked a specific example question (ECA-1.1

Step 22b RNO) involving an incorrectly written transition step to assess

operator use of procedures in terms *of step performance.

All performed

the same steps in the same order and explained consistent rationale.

While. the procedure incorrectly transitioned past step 22d, all operators

stated that they would have performed step 22d because they knew that

it was needed.

Operators indicated that communications between personnel was generally

good in the control room and between the control roam and locations

outside the control roam.

Operators indicated closed loop communication

(complete answer back) was emphasized during training.

Operators indicated that communication equipment was considered adequate

for most situations.

A concern for communications was expressed for

station blackout events.

During SB, radios would be limited to line of

sight and other communication would be limited to sound powered phone and

word of mouth.

One operator indicated that the radi as di dn I t work

well in some plant areas under normal conditions.

An interviewee felt

that for 1 ass of all AC someone from every department to serve as runner

was needed and perhaps this should be the case for every EOP. *

Most interviewees believed mare training was needed for the EOPs.

This

included more time and more specialized training for EOPs.

Operators

felt NLOs should be included in EDP training and drills.

One operator

indicated there was an ambiguous time between training on a revision and

its implementation (i.e., operator was trained on new procedure but

required to operate on previous version).

Operators indicated there was

no training on PRA or on important operator actions identified by PRA.

11

Some specific technical and human factors defi ci enci es in the EOPs were

identified by the interviews and are included in Appendix B.

There were no violations or deviations noted in this area.

8.

Follow-up on previous inspection findings

a.

(Closed)

DEV 280,281/87-32-02, Failure to meet procedure generation

package commitments in generating emergency operating procedure for

natural circulation cooldown

This deviation stated that the licensee had not provided adequate

written justification in the step deviation document for the reduc-

tion in subcooling margin as a result of the RCS depressurization

to establish RHR flow.

The team reviewed the current procedure,

ES-0.2, Natural circulation cooldown, Rev. lA, and the related SOD,

and determined that they adequately addressed the concern about

subcaoling margin.

9.

Exit interview

The inspection scope and findings were summarized on April 12, 1990, with

those persons indicated in paragraph 1.

The NRC described the areas

inspected and discussed in detail the inspection findings listed below.

IFI-04 below was discussed by telephone between R. Schin and W. Benthall

during April 18-26, 1990.

No proprietary information is contained in this

report.

No dissenting comments were received from the licensee.

Item Number

IFI 280,281/90-09-01

IFI 280,281/90-09-02

IFI 280,281/90-09-03

IFI 280,281/90-09-04

IFI 280,281/90-09-05

IFI 280,281/90-09-06

\\

Description, Paragraph

Revise AP-12.01,

Loss of intake canal,

within one week, paragraph 3 and Appendix B

Initiate operator use of sound powered

phones within one month, paragraph 3

Provide

emergency

battery

power

to

operations radio repeaters, paragraph 3

Conduct IPE analysis of loss of intake canal

resulting from loss of all AC power to a

unit, paragraph 3

Revise 18 steps in 15 procedures to address

technical deficiencies within 12 weeks,

paragraph 3 and Appendix B

Revise

one

step in AP-22.01,

Loss of

refueling cavity level, prior to refueling

outage, paragraph 3 and Appendix B

12

IFI 280,281/90-09-07

Corrective actions for all technical and

human factors comments,

paragraph 3 and

Appendix 8

IFI 280,281/90-09-08

Corrective actions for all writer's guide

comments, paragraph 3 and Appendix C

IFI 280,281/90-09-09

Corrective actions for all nomenclature and

labeling items, paragraph 4 and Appendix D

1-E-O

l-E-1

l-E-2

l-E::*-3

l-ES-0.0

l-ES-0.1

l-ES-0.2

l-ES-0.3

l-ES-1.1

l-ES-1.2

l-ES-1. 3

l-ES-1.4

l-ES-1.5

l-ES-3.1

l-ES-3.2

l-ES-3.3

l-ECA-0.0

l-ECA-0.1

1-ECA-0.2

l-ECA-1.1

l-ECA-1.2

l-ECA-2.1

l-ECA-3.1

l-ECA-3.2

  • 1-ECA-3.3

F-:-0

F-1

F-2

F-3

F-4

F-5

F-6

1-FR-C.l

1-FR-C.2

1-FR-C.3

1-FR-H.l

1-FR-H.2

1-FR-H.3

1-FR-H.4

APPENDIX A

PROCEDURES REVIEWED

Reactor Tri~ or Safety Injection

Loss of Reactor or Secondary Coolant

Faulted Steam Generator Isolation

Steam Generator Tube Rupture

Rediagnosis

Reactor Trip Response

Natural Circulation Cooldown

Natural Circulation Cooldown with Steam Votd *in

Vessel (With RVLIS)

SI Termination

Post LOCA Cooldown and Depressurization

Transfer to Cold Leg Recirculation

Transfer to Hot Leg Recirculation

Transfer to Cold Leg Recirculation from Hot Leg

Recirculation

Post-SGTR Cooldown Using Backfill

Post-SGTR Cooldown Usin,g Slowdown

Post-SGTR Cooldown Using Steam Dump

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

Loss of All AC Power

. REV. lA

Loss of All AC Power Recovery without SI Required REV. lA

Loss of All AC Power Recovery with SI Required

REV. lA

Loss of Emergency Coolant Recirculation

REV. lA

LOCA Outside Containment

REV. lA

Uncontrolled Depressurization of All Steam

Generators

SGTR with Loss of Reactor Coolant - Subcooled

Recovery Desi red.

SGTR with Loss of Reactor Coolant - Saturated

Recovery Desired

SGTR without Pressurizer Pressure Control

Critical Safety Functton Status Trees

Subcriticality (Status Tree)

Core Cooling (Status Tree)

Heat Sink (Status Tree)

Integrity (Status Tree)

Containment (Status Tree)

Inventory (Status Tree)

Response to Inadequate Core Cooling

Response to Degraded Core Cooling

Response to Saturated Core Cooling

Response to Loss ~f Secondary Heat Sink

Response to Steam ~enerator Overpressure

Response to Steam Generator High Level

Response to Loss of Normal Steam Release

Capabilities

REV. lA.

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

  • REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

Appendix A

1-FR-H. 5

1-FR-I.1

1-FR-I.2

1-FR-I. 3

1-FR-P.1

1-FR-P.2

1-FR-S .L

1-FR-S.2

1-FR-Z.1

1-FR-Z.2

1-FR-Z.3

1-FR-Z.4

AP-1.00

AP-1. 01

AP-1.02

AP-.3. 00

AP-4.00

AP-5.01

AP-5.03

AP-5.04

AP-5.05

AP-5.06

AP-5.07

AP-5.08

AP-5.09

AP-5.10

AP-5.11

AP-5.12

AP-5 .13

AP-5.14

AP-5.15

AP-5.16

AP-9.02

AP-10.00

2

Steam Generator Low Level

High Pressurizer Level

Low Pressurizer Level

Voids in Reactor Vessel

Imminent Pressurized Thermal Shock

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

Response to

Response to

Response to

Response to

Response to

Condition

Response to

Condition

Response to

Response to

Response to

Response to

Response to

Response to

Anticipated Pressurized Thermal

Nuclear Power Generation/ATWS

Loss of Core Shutdown

Shock

High Containment Pressure

Containment Flooding

High Containment Radiation Level

Containment Positive Pressure

Rod Control System Malfunction

Control Rod Misalignment

Malfunctioning Individual Rod Position

Indicator (!RPI)

Conditions Requiring Emergency Boration

Nuclear Instrumentation Malfunction

Radiation Monitoring System Process Vent

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. lA

REV. 00.01

05-18-89

01-28-88

06-23-88

05-29-89

Monitors ALERT/ALARM

Radiation Monitoring

Radiation Monitoring

Monitor

01-12-89

System Liquid Waste Monitor 02-13-87

System CC HX Servic~ Water

02-12-87

Radiation Monitoring System CC Monitors A and B*

(RI-CC-105 & RI-CC-106)

02-13-87

Radiation Monitoring System Restricted Control

Area Monitors

Radiation Monitoring System Main Control Room

REV. 00.03

Area Monitor

02-07-89

Radiation Monitoring System Containment *Particulate

and Gas and Manipulator Crane

10-19-89

Radiation Monitoring System Condenser Air Ejector 02-13-87

Radiation Monitoring System SG Slowdown

02-18-88

Radiation Monitoring System Recirc Spray Coolerr

Service Water Outlet

REV. 00.01

Radiation Monitoring System Reactor Coolant

Letdown Monitors

Radiation Monitoring System Discharge Tunnel

Radiation Monitoring System Containment High

Range Area

Radiation Monitoring System Reactor Containment

Area Monitors and CHRRM

04-02-87

02-23-88

02-13-87

10-19-89

Radiation Monitoring System Process Vent

or Process Vent Flow Monitor Malfunction

Loss of RCP Seal Cooling

Monitor,

Station Blackout

08-04-88

REV. 1

REV. 00.03

Appendix A

AP-10.01

AP-10.02

AP-10. 03

AP-10.04

AP-10. 05

Loss of Vital Bus I

Loss of *Vital Bus II

Loss of Vital Bus III

Loss of Vital Bus IV

3

Loss of Semi-Vital Bus 1 and AC Distribution

Panel 1-1

Loss of D. C. Power

Loss of Auto Load Shed

Partial Loss of Reserve Station Service

Partial Loss of Station Service

,

Service Water System Abnormal Conditions

Loss of Intake Canal

Loss of Component Cooling Water

Excessive RCS Leakage

AP-10. 07

AP-10 .10

AP-10 .11

AP-10 .12

AP-12.00

AP-12.01

AP-15.00

AP-16.00

AP-17.00

AP-17.01

-Auto Start Failure of EOG

AP-20.00

AP-21. 00

AP-21.01

AP-22.00

AP-22.01

AP-22.02

AP-24.00

AP-27.00

AP-31. 00

AP-36.00

AP-37.00

AP-37.01

AP-39.00

AP-40.00

AP-43.00

AP-47.00

AP-48.00

AP-49.0

Emergency Diesel Generator Fails to Accept

Electrical Load

Main Control Room Inaccessibility

Loss of Main Feedwater Flow

Response to AFW Check Valve Backleakage

Fuel Handling Abnormal Conditions

Loss of Refueling Cavity Level

Loss of Spent Fuel Pit Level

Minor SG Tube Leakage

Loss of Decay Heat Removal Capability

Increasing or Dec~easing RCS/PRZR Pressure

Control Room Security

Seismic Event

Abnormal Environmental Conditions

Natural Circulation of RCS

Non-Recoverable Loss of Instrument Air

Loss of Reactor Coolant Flow

Personnel Injury - Operations Response

Fire Protection - Operations Response

Loss of Domestic Water

FCA-1.00

Safe Shutdown Area Fire

FCA-1.01

Limiting MCR Fire

\\

08-23-88

08-23-88

08-23-88

08-23-88

07-21-87

04-11-89

01-28-88

REV. 00.03

I 04-14-87

REV. 00.01

REV. 00.00

04-02-87

06-14-89

06-23-88

06-28-89

04-02-87

04-02-87

04-19-88

01-10-89

10-13-88

10-26-88

02-12-87

09-27-88

03-03-87

01-28-88

02-07-89

REV. 00.05

03-03-87

05-30-89

02-12-87

09-11-87

04-21-89

01-08-89

REV. 00.09

REV. 00.05

APPENDIX B

TECHNICAL AND HUMAN FACTORS COMMENTS

This Appendix contains technical and human factors comments and observations.

Unless specifically stated, these comments are not* regulatory requirements.

Howeveri the licensee acknowledged that the factual content of each of these

comments. was correc.t a.s stated.

The 1 i censee. further agreed to eva 1 uate each

comment, to take appropriate *action, and to document that action. These items

will be reviewed during a future NRC inspection.

I. General Comments:

The licensee state.d that they would take corrective actions for Appendix B

comments per the following schedule:

1.

Prior to the exit interview:

Set the steam generator blowdown

radiation monitor alarms at the correct setpoints; AP-24, entry

condition 2.

2 .

Within one week of the exi't interview:

Revise AP-12.01, Loss of

intake canal; step 1 first asterisk, step one second ast:erisk, step

10a, step 15 table left column, and step 17 table right column.

(IFI

280,281/90-09-01)

3.

Within 12 weeks of the exit interview, with Rev. 2 to the EOPs:

Revise 18 steps in 15 procedures, as follows:

ECA-3.2 step 15a,

step 18c, and setpoint k.1; ES-0.3 step 3a; FR-I.2 step 4bl;

FCA-1.01 step 6; AP-21.01 step 4c; E-1 step 6d2 RNO;

ES-3.2

step 10c; FR-H.1 step 28 RNO; ES-3.1 Attachment 2 step 16; ECA 0.0

Attachment 4 step 7; ECA-2 .1 step 8b; ES-1. 3 step 2a; ECA-0. 2

step 1 RNO and step 3 caution; E-0 step 4a RNO; AP-1.00 step 8 RNO.

(IFI 280,281/90-09-05).

4.

With Rev. 3 to the EOPs:

Complete corrective actions for all techni-

cal and human factors com"lents in Appendix B.

(IFI 280,281/90-09-07)

In this Appendix,

comments

on

individual procedures are arranged

numerically in the following order:

II. EOP comments:

E-, ES-, ECA-, F- , FR-

III.

AP comments:

AP-

IV. FCA comments:

FCA-

11. EDP comments:

1.

E-0

a.

Reactor trip or safety injection

Step 2c RNO:\\This step required the closure of MSR steam supply

valve, MOV-MS-.1000, which did not have local valve position

indication.

Appendix 8

b.

c.

d.

e.

f.

g.

2

Step 2c RNO:

This step directed the closure of MSR steam supply

valves.

Two of those valves, MOV-MS-lOOA and MOV-MS~lOOB, had

labels with only the valve numbers.

Step 2d:

This step directed the verification of the generator

output breakers in the open position. The corresponding local

indication was

11trip.

11

Step 3b RNO:

This step failed to address action to be taken if

the EOG did hot start 1 fol lowing step 3b2 R

1NO. i

PSTG DEV, Step 4a RNO:

This st~p failed to iist low PRZR level

as an i ndi cation which required SI.

This was not properly

addressed in the SOD,

Step 13b RNO:

This step failecj to direct that both SI reset

push buttons may be required to be pushed in order to reset SI.

Step 32b:

This step failed to specify the indications to be

addressed in order to check

11 radiatiori -

NORMAL.

11

h.

Step 34a: This step failed to specify which pressure was to be

checked .

. i.

Step 34b:

Same as step 34a above.

j.

Step 35a RNO:

This step directed the energizing of PRZR heaters

from the AC emergency buses.

PRZR heater groups 8, C, and D ~ere

not on the AC emergency buses.

k.

Step 35a RNO:

This step failed to direct that the energizing

of the semi-vital bus be conducted in accordance with AP-10.05 *

step 10.

1.

Continuqus action page:

Same as step 4a RNO above.

2.

E-1

Loss of reactor or secondary coolant

a.

Step 1 caution: This taution contained an action statement and

did not indicate the consequences of nqt complying with the

caution.

b.

Step 1 third note:

The note contained an action statement.

C.

d.

Step 3 caution: This caution did not indicate the consequences

of not complying wi~h the caution.

Step 3a RNO:

The adverse feed flow value of 492 GPM was too

detailed a value to use, since it was the total of up to three

flow indicators.

\\

Appendix B

3

e.

PSTG DEV, Step 6d2 RNO:

This step re qui red the operator to

11 Continue with Step 8.

WHEN PRZR level greater than 11 percent,

THEN close PRZR spray valves as necessary.

11

The corresponding

step in the ERG stated

11 00 NOT STOP SI PUMPS. Try to stabi 1 i ze

RCS pressure with norma 1 PRZR spray.

GO TO STEP 8.

11

The EDP

SOD did not address this deviation.

It was not clear to the

procedure writer if Step 7, which was SI Termination, would be

performed after the Step 6d2 RNO was completed.

f.

Step 10 caution~

Same as itep 1 caution above.

g.

Step 10a RNO:

This step required the operator to

11 GO TO Step

14.

WHEN pressure less than 14 psia, THEN do Steps 10 through

14.

11

It was not clear to the procedure writer why this step was

worded differently than step 6d2 RNO above.

h.

Steps 10d and e:

As written, these steps could have cawsed the

operator to isolate the A SW header in RNO 10d without insuring

that the B SW header was operational.

i.

Step 11:

The location of infrequently operated equipment was

not indicated.

j.

Step 13a RNO:

Same as Step 10a RNO above.

k.

Step 13b:

The previous step that reset CLS, step 10, could have

been bypassed as a result of step 9b, which stated "GO TO Step

13 .

11

There was no RNO step to "Reset CLS" if the response to

the action step to

11 Verify CLS reset

11 was negative.

1.

Step 14 caution:

Same as step 1 caution above.

m.

Step 16a RNO:

The CC pumps were not included on the list of

equipment that should be loaded on the AC emergency busses.

n.

Step 18a2:

The listed equipment was not organized to expedite

verification of power availability.

~

o.

Step 22cl:

There were no permanent position indicators on the

Key switches for the SI Accumulator isolation valves.

p.

Step 23 caution:

The consequences of not complying with the

caution were not included in the caution statement.

q.

Step 25:

The action column directed the verification of several

valve positions, but there were no RNO actions if the valves

were not in the desired positions .

Appendix B

4

3.

E-2

Faulted steam generator isolation

a.

Step 1:

This step did not identify bypass valve indication as

requiring local verification.

b.

Step 1 RNO:

This step identified steam generator bypass valves

as requiring manual

closure.

These valves required local

closure.

c.

Step 2:

This step was w~itten as a step with a single substep.

This was not consiste~t with the WG.

d.

Step 3a RNO:

This step indicated that there was no preferred

order for performance of the substeps, although it was clear

that an inspection of secondary lines would not be attempted

until the other items had been inspected.

e.

Step 3a RNO sixth bullet: This bullet required that decay heat

release lines be inspected to determine that an initiating break

had occurred.

Due to their location, it would not be possible

to inspect these lines after a break.

f.

Step 4a RNO:

This step *was actually the RNO for step 4al only.

g.

Step 4d:

The verb

11 veri fy

11 was used to indicate that this step

should be accomplished, if possible.

This was not consistent

w i th the de f i n i t i o n o f II v e r if y II i n the WG .

' h.

Step 5 RNO:

ThE step required the operator to transfer to

alternate AFW water supply without specifying the alternate

water supplies or the preferred sequence for the selection of

the source.

i.

Step 6a:

This step required a consultation with the TSC.

It was unlikely that the TSC would be manned at this point in

the procedure.

j.

Attachment 1 step 3a first and second bullets:

These actions

were preceded by an asterisk instead of a bullet, which was

inconsistent with the WG.

k.

Attachment 1 step 3b first and second bullets:

These actions

were preceded by an asterisk instead of a bullet, which was-

inconsistent with the WG.

1.

Attachment 1 step 3b

RNO first and second bul 1 ets:

These

actions were preceded by an asterisk instead of a bullet, which

was inconsistent with the WG.

Appendix B

4.

m.

n.

0.

p.

q.

r.

5

Attachment 1 step 4a first through sixth bullets: These actions

were preceded by an asterisk in stead of a bull et, which was

inconsistent with the WG.

Attachment 1 step 4b:

Keys 66, 67, and 68 were required by this

step, but were not identified.

Attachment 1 step 4d first through sixth bullets: These actions

were preceded by an asterisk and a place keeping mark instead of

a bullet, which was inconsistent with the WG.

Attachment.I step 4d first through third bullets: These actions

were preceded by an asterisk instead of a bullet, which was

inconsistent with the WG.

Attachment 1 step 5 RNO:

This step was not preceded by an

asterisk, although it was a step that would be performed at a

later time when conditions permitted.

Attachment 1 step 7 first and second bullets:

These actions

were preceded by an asterisk instead of a bullet, which was

inconsistent with the WG .

E-3

Steam generator tube rupture

a.

Entry conditions:

Asterisks were used in a manner inconsistent

with the WG.

b.

Step 3 caution:

The two items in this caution were written

indicating actions of a continuous nature.

Consequence was not

included as part of the caution.

c.

Step 4 caution:

This caution did not contain a statement of

consequences.

The

item was written implying a continuous

action.

d.

Step 4:

This step was written as a continuous action as denoted

by an asterisk. There was no formal method to aid operators in

remembering all of the open continuous action steps.

e.

Step 5 Caution:

This caution was written as an action with

conditional logic.

Also no consequence was stated in the

caution.

f.

Step 5:

Same as Step 4 above .

\\

Appendix B

g.

h.

6

Step Sa* RNO:

The breakers were i dent ifi ed with labels that

appeared to be pink rather than purple as was designated for the

proper color coding.

The operator on the walkdown agreed there

was an inconsistency in the color coding.

Access to one breaker

fequired entering a restri~tively narrow space* between a

contaminated area and the breaker boxes.

Due to the lighting

conditions, a flashlight was required to read the label on this

breaker.

Ste~ 7 caution:

This caution did not contain a statement of

~onsequence as per the WG.

i.

Step 7:

Same as Step 4 above.

j.

Step 9b:

In this step an action step was imbedded as a substep

under a check. This may increase the potential for the operator

to overlook the action.

k.

Step lOal RNO:

Performan~e of this action required o~eration of

controls approximately 15 to 20 feet above the floor.

The

operator on the walkdown indicated they would be accessed by

climbing pipes.

No ladder was evident in the area.

1.

Step 12 caution:

A continuous action and a conditional action

were contained in this caution .. This caution did not contain a

statement of consequence as per the WG.

m.

Step 15 note:

The first two items in this caution contained

conditional actions.

This caution did not contain a statement

of consequence as per the WG.

n.

Step 15a:

This step used the phrase ONE TIME which was not

sufficiently explained in the step and which was not defined in

the WG.

o.

Step 15b

RNO first and . second bull et:

This step provided

the operator with two options for action but did not provide

direction regarding preferred action.

The operator on the

walkdown indicated he believed there was a preferred action.

p.

Step 15b3 RNO:

This step required the operator *to stand on a

pipe to operate a large valve.

The valve was reverse seated.*

The operator on the wal kdown said he was trained on wh*ich

direction to turn the valve hand wheel for the desired result

but the valve was not labeled as such locally or referred to as

such in the procedure.

q.

Step 15b RNO third and forth bullets:

Same as Step 15b RNO

first and second bullets .

Appendix B

7

r.

Step 16 caution:

This caution did not contain a statement of

consequence as per the WG.

s.

Step 20a RNO:

This step required the operator to monitor four

parameters but provided no specific direction as to what changes

to look for or expect.

t.

Step 27: Same as Step 4 above.

u.

Step 28c2:

This step required the operator to locally throttle

a valve to 25 percent open.

No formal indication of valve

position was provided locally requ,_r,ng operator judgment to

determine an intermediate valve position.

v.

Step 30b7:

This step required the operator to verify that a

control valve was controlling temperature but did not ~rovide a

specific description of what indications to use to make this

verification.

w.

Step 31a RNO:

This step used IAW as a referencing term but IAW

is not defined as a referencing term in the WG.

x.

Step 33 caution: This caution implied a continuous action.

The

caution did not contain a statement of consequence as per the

WG.

y.

Step 33a:

This step contained a table in which some en.tries

were marked with asterisks indicating continuous action steps.

The operator on the walkdown indicated that he felt an asterisk

should be used with the step number.

z.

Step 33a:

This step contained items directing the operator to

raise flow, lower flow, depressurize,

and maintain pressure,

however provided no specific information concerning how to or

how much to change the parameters.

aa.

Step 34b:

This step contained two references but used no

referencing terms as ~escribed in the WG.

ab.

Step 35a RNO first and second bullets:

This step provided

the operator with two options for action but did not provide

specific direction regarding preferred or appropriate action.

The operator on the walkdown indicated that the appropriate

action was determined based on the operating status of the other

unit.

Appendix 8

8

ac.

Step 35a RNO first bullet:

This step directed the performance

of a relatively complicated local action requiring several steps

and communication between the two units outside the control

room.

No specific direction or reference was provided for

performance of the action.

The needed continuous communication

between NLOs on units one and two required radios, but that was

not specified in the procedure.

A gaitronics phone was located

in the area of the locally operated component on unit one but

was well out of reach from the component.

ad.

Step 35a RNO second bullet:

Same as Step 31a RNO.

ae.

Step 37a RNO:

This step required an operator to adjust a flow

controller but did not provide a specific value as per the WG.

af.

Step 38a2a RNO:

Same as step 31a RNO.

ag.

Step 39 RNO:

This step directed the operator to "Dump more

steam" but provided no specific direction on by what means or

how much.

ah.

Step 39:

The operator on the walkdown indicated that this step

would probably involve trending several parameters by hand.

The

procedure provided no space, attachment, or blank page for this.

ai.

Step 39 fifth bullet: This step used "based on" as a referenc-

ing term but this term was not specified for referencing in the

WG.

aj.

Step 41 seventh bullet:

This step used the acronym RSST which was

not listed in the WG acronym attachment.

ak.

Step 42:

This step provided the operator with three options for

branching to another procedure but provided no guidance on

preferred procedure or how to decide.

The operator on the

walkdown indicated that the TCS or SS would make the decision.

The procedure provided no reference to the TSC.

al.

Attachment 1 step 3, 4, and 7:

These steps used asterisks in a

manner inconsistent with the WG.

am.

Attachment 1 step 8: Same as Step 31a RNO.

an.

Attachment 2 step 6:

This step required local operation of two

valves in .the turbine deck dog house.

The label tag for one of

the valves was inaccessible under recently installed insulation

or was missing.

Hot pipes and limited space caused apparent

difficulty for operator access and operation of the valves .

Appendix B

9

ao.

Attachment 2 step 7:

This step required local operation of

three valves located high above walkways, piping and openings

  • to the level below.

There was very limited room for ladder

placement and no apparent ladders in the area.

The operator on

the walkdown indicated he would climb nearby pipes and jump

across to piping near the valves.

A second operator on a

walkdown indicated he would obtain a safety belt to operate the

valves but only if he had time.

  • ap.

Step 5 continuous action page:

This step directed the operator

to transfer to alternate AFW water supply but provided no

specific steps or reference for performing the action.

The

operator on the walkdown indicated the action could involve

local operation of a valve and operation of a valve from the

control room or as a last resort the use of FW.

aq.

Continuous actions page:

The

heading for this page was

not underlined and asterisks were used, in violation of \\'.JG

direction.

5,

ES-0.0

Rediagnosis

a ..

Step 1:

This step was not written in the *form of a single step,

and was not consistent with the WG.

b.

Step 1 RNO first and second sub-bullets:

These steps indicated

that there was no preferred order for performance of the sub-

steps, although it was clear that the steps were dependent upon

the status of main steam line isolation.

c.

Step 3 second bullet:

The annunciator window for this step read

11Unit 1 AUX STM RAD ALERT /HI

11 *

This annunciator window was for

steam generator high radiation level although the annunciator

window did not refer to steam generator radiation level in the

engraving.

6.

ES-0.1

Reactor trip response

a.

Step 6a RNO:

This step directed action which required that

BC-227

be

verified

closed per OP-50.1,

REMOVAL

OF

THE

BEARING COOLING WATER SYSTEM FROM SERVICE.

The operator stated

that he would reach valve BC-227 by climbing on various

equipment and piping.

The valve was located approximately 20

feet above the fl oar, and no appropriate 1 adder was readily

accessible.

b.

Step 6a RNO:

This step directed action which required that the

11 fire water to air compressor

11

valve be opened per OP-50.1,

REMOVAL OF THE BEARING COOLING WATER SYSTEM FROM SERVICE.

The

step did not, specify FP-170 but incorrectly stated BC-170.

'

.

Appendix 8

10

c.

Step 7a

RNO:

This step required verification of letdown

isolation.

No specific direction was provided for performance

of this step. This was inconsistent with the list of applicable

valves provided in step 7c.

d.

Step 8b RNO:

This step directed the

11defeat

11 of TAVG and

delta T control for the affected loop.

This terminology was

inconsistent with the switches used to perform the action (TAVE

CH SEL and delta T CH SEL).

e.

Step 8b RNO:

This step directed the use of auxiliary spray.

No

specific information was provided for performance of the step

(Open HCV-1311).

f .. Step 9c: This step was not properly identified as a continuous

action step.

g.

Step 17: This step directed the local closure of the 1st point

extraction steam. bre~ker, 181-343. * The normal position of

181-343 was

11 closed. 11

h.

Step 19b: This step directed the opening of AOV-CP-122 and the

closing of MOV-CP-100 in the condensate polishing system.* Prior

to this step in the procedure, the position of these valves was

dependent on the initial plant conditions. This step failed to

adequatel~ address the required action~ for all possible initial

valve positions.

i.

Step 21a2 RNO:

This step failed to clearly define communica-

tions in that it required consultation with

11 plant staff 11 *

7.

ES-0.2

Natural tirculation Cooldown

a.

Cov_er Page Head~r:

The company name on the procedure did not

comply with the WG Section 6.2.1.a.l.

b.

~ntry Conditions:

Transition procedures were denoted with

asterisks instead of bullets as required by the WG.

c.

Step 1 Caut.ion:

There was inappropriate use of

11 should

11 instead*

of

11 shall,

11 i.e., if there was SI actuation, it would be

mandatory to implement procedure E-0.

d.

Step 6a RNO:

This step required that a tota 1 AFW fl ow of 492

gpm be read from a combination of gages that had small scale

units of 7 gpm.

These aw~ward scale units made the determina-

tion of feed flow to this precision impractical.

e.

Step 68 RNO:

The grouping of bullets below this step did not

have the word

11 or

11 between them.

Appendix B

11

f.

Step 14:

Attachment 3 was referenced when attachments 1 and.2

had not yet appeared in the procedure.

g.

Step 23c:

The overpressure mitigation key switches did not have

a label for

11enable

11 or

11disable

11 positions.

8.

ES-0.3

Natural circulation cooldown with steam void in RX vessel

a.

Step 1 first caution:

The verb

11 implemented

11 was used in the*

caution statement but'it did not appear in the WG.

b.

Step 1 second caution:

The first 14 steps of ES-0.2 must be

performed prior to th~ beginning of this procedure in order for

this procedure to work.

The note did not identify these actions

as mandatory.

c.

Step 1 first note:

This note indicated that it- was not

mandatory to monitor the continuous action page.

This was not*

in accordance with the intent of the WOG guidelines.

d.

Step 2: This step was not preceded by an asterisk, although it

was a step that would be performed continuously throughout the

procedure.

e.

Step 3a: This step had an incorrectly referenced cooldown rate.

The procedure used the value of 100 degrees per hour, but the

setpoint docum~nt required a 50 degree per hour cool down rate.

For this step, the ERG used a cooldown rate of 100 degrees per

hour.

e.

Step 4b2 RNO first and second bullets: These steps were _listed

as having no preferred sequence,

This was inconsistent with

operator training.

f.

Step 6c RNO:

This step indicated that IA should be available.

The step did not specify containment IA.

g.

Step 6cl:

This step required keys to accomplish the step, but

did not identify the required keys (Keys 11, 12 and 13).

h.

PSTG DEV, General:

The licensee had no procedure ES-0.. 4,

Natural circulation cooldown with steam void in vessel without

RVLIS.

The SOD justification for this was incomplete, in that

it did not consider RVLIS failure during or as a result of a

casualty to the plant that required a natural circµlation

cool down.

\\

Appendix B

12

9.

ES-1.1

SI Termination

a.

PSTG DEV, Step 7: This step stated II ISOLATE HHSI TO COLD LEGS.

11

The corresponding step in the ERG stated II Isolate BIT.

11

The EOP

SOD did not address this deviation.

b.

PSTG DEV, Step 8b RNO:

This stp stated

11 IF PRZR level can

NOT be maintained greater than llJ.;, THEN do the following:

1.

Align SI fl ow path

2.

GO TO ES-1. 2 POST LOCA COOLDOWN

AND DEPRESSURIZA TION, STEP 1

11 *

The corresponding step in the

ERG, which was Step llb RNO, stated

11 If PRZR

level can not be

maintained THEN manually operate SI pumps as necessary.

GO TO

E-1,

LOSS

OF

REACTOR

OR

SECONDARY

COOLANT,

Step

1.

11

The EOP SOD did not address this deviation.

c.

Step llcl RNO:

The indicator for RCP seal leakoff temperature

was not in this step, but was needed to insure that the

operators use the correct indicator.

d.

PSTG DEV, Step 12:

The sequence of steps in the EOP had been

changed and as written allowed the performance of ERG step 17

prior to the completion of ERG steps 13 through 15.

This was

contrary to the ERG required step sequence and the EOP SOD did

not address this deviation.

e.

Step 19a RNO:

Same as Step llcl RNO above.

f.

Step 20

RNO:

The

CC pumps were missing from the list of

equipment to be started when offsite power was restored, because

Step 19b directed the operator to this step if CC pumps were not

running.

g.

Step 21 caution:

This caution contained an implied action

statement and did not indicate the consequence of not complying

~ith the caution.

h.

Step 26:

The location of infrequently operated equipment was

not indicated in the EOP.

i.

Step 34: The same as step 26 above.

10.

ES-1.2

Post LOCA cooldown and depressurization

a.

Entry conditions: Asterisks were used in a manner incon~istent

with the WG.

b.

Step 1 caution:

This caution contained a conditional logic

action and a transition and contained

no

statement of

consequences and was thus inconsistent with the WG .

Appendix B

13

c.

Step 2a

RNO:

This step indicated a continuous action but

was not identified by an asterisk, nor did it appear on the

continuous action page.

The word continue was used to indicate

transition and continuous action but was not defined as such in

the WG.

d.

Step 3:

The operator on the walkdown indicated that items in

this step were performed in parallel.

There was no indication

of this in the procedure.

e.

Step 3b RNO:

This step used IAW as a referencing term but IAW

was not defined as a referencing term in the WG.

f.

Step 5:

This step was indicated as a continuous action by an

asterisk.

There was no formal method to aid the operator in

remembering all of the open continuous action steps.

g.

Step 5 RNO:

This step used the condit i ona 1 statement IF

necessary, THEN ... but provided no specific guidance on-how to

determine if necessary.

h.

Step 6 caution:

This caution contained a conditional logic

action and contained no statement of consequences and was thus

inconsistent with the WG.

i.

Step 6:

Same as step 5.

j.

Step 7 caution:

This caution contained no statement of

consequence as per the WG.

k.

Step 7.

This step was indicated as a continuous action by an

asterisk.

There was no forma 1 method to aid the operator in

remembering all of the open continuous action steps.

1.

Step 7 items a and b:

The SG narrow range level indicators

required for this step had red and yellow lines scribed

horizontally across the face of the i ndi ca tor.

These 1 i nes

were not referred to in the procedure and the operator on the

walkdown did not know of any purpose for them.

m.

Step 8 note:

This note contained a continuous action and two

conditional logic actions and was thus inconsistent with the WG.

n.

Step 13d: Same as Step 3b RNO:

o.

Step 16e:

This step required the operator to read 25 gpm or

greater on a charging flow indicator.

The scale at the bottom

of the indicator was compressed and did not have a mark or clear

indication for 25.

The operator on the walkdown indicated he

controlled flow to the'\\?ext mark up which he believed was

40 gpm.

.

Appendix B

-

14

p.

Step 17 note: This note required the operator to determine when

RCS pressure stabilized but provided no direction on how to

determine this. The operator on the walkdown indicated he would

use judgment based on watching it for four or five minutes.

Stabilize was not defined in the WG.

q.

Step 19a RNO: Same as Step 3b RNO.

s.

Step 20:

Same as Step 7.

t.

Step 22a:

Same as Step 3b RNO.

u.

Step 22c RNO:

This step required the operator to

11Borate

11 but

provided ho specific information on how much or how.

v.

Step 24c RNO:

Same as Step 3b RNO.

w.

Step 25b:

This step referenced procedures but did not use

referencing terms as directed by the WG.

x.

Step 29 last bullet:

The operator on the walkdown indicated

this was a local action. It was not indicated as such in the

procedure.

y.

Step 33 RNO:

This step required* the operator to return to

Step 7.

An operator in an interview indicated he believed it

would be more technically correct to return to Step 6.

11.

ES-1.3 Transfer to Cold Leg Recirculation

a.

PSTG DEV, Step 1 Caution:

The ERG caution for loss of offsite

power following SI re.set was not included.

This was not

adequately justified in the SOD.

b.

Step 1 Note:

The ERG note to remind the operator that the

foldout page for the E-1 series should be open was not included.

This was not adequately justified i~ the SOD.

c.

Step 2a:

This st~p established fl ow to the RSHX s but did not

give the opera.tor a value for minimum or maximum acceptable

flows.

The minimum flow was identified as 2400 GPM in the

setpoint document.

d.

Step 4 Caution:

This caution did not list the value for the

RWST empty alarm.

e.

Step 4:

This step did not verify that the charging pump

mini fl ow valves were shut.

The consequences of these valves

being open could be injection of radioactive recirculation water

into sections of the let~own system, VCT, etc.

Appendix B

12 .

15

f.

Step 4c4:

This step did not include a caution for the operator

to monitor charging pump discharge flows when isolating the CHG

pump RWST suction valves.

g.

Step 4 RNO:

This step did not direct operators to operate

valves locally and there was no caution for potential highly

radioactive fluids being present during local operations.

h.

Step 3 RNO:

This step did not require the operator to start a

LHSI pump if at least one LHSI pump was not running.

i.

Step 4b RNO:

These steps were listed as having no preferred

sequence.

This was inconsistent with operator training.

j.

Step 5d and Se:

There was no RNO column directing the operator

to locally close the valves if they failed to close from the

control room.

k.

General:

This procedure did not identify the m1n1mum contain-

ment sump level for running pumps on the reci rcul at ion sump.

This value was identified as 2.5 ft. in the setpoint document.

ES-1.4 Transfer to hot leg recirculation

a.

Entry cond.itions:

Asterisks were used in a manner inconsistent

with the WG.

b.

Step 2 caution:

This caution contained no statement of

consequences and thus was inconsistent with the WG.

c.

Step 5:

This step directed the operator to RETURN TO procedure

and step in effect".

In the WG

11 RETURN

11 TO is specified for use

in transitions but not for branching.

13.

ES-1.5 Transfer to cold leg recirculation from hot leg recirculation

a.

Cover page header:

The company name of the procedure did not

comply with the WG Section 6.2.1.a.l

b.

(NQ) was not in the WG list of abbreviations.

14. ES-3.l

Post-SGTR cooldown using backfill

a.

Cover page header:

The company name on the procedure did not

comply with the WG Section 6.2.1.a.l.

b.

Entry conditions:

Transition procedures were denoted with

asterisks instead of bullets as required by the WG.

c.

Step 1 Note:

There was inappropriate use of

11 should

11 instead of

"shall"; it was mandatory to use continuous action pages.

Appendix B

d.

e.

f.

g.

h.

i .

j.

k.

16

Step 2cl:

The key numbers were not designated for working the

SI accumulator key switches.

Step 4a RNO:

This step required that a tota 1 AFW fl ow of 492

gpm be read from a combination of gages that had

sma 11 seal e

units of 7 gpm.

These awkward scale units made the determina- *

tion of feed flow to this precision impractical.

Step 4b RNO:

The grouping of bullets below this step did not

have the wording

11 or

11 between theni.

Step 10a:

This step did not have an adverse containment

pressure value.

Step lOc:

The overpressure mitigation key switches did not have

a label for

11 enable

11 or

11disable

11 positions.

Step 13a Second Bullet:

The recorders for RCP leakoff flow Hi

and Lo Range, recorders FR-1-154A and FR-1-154B, referred to

reactor coolant pumps as 1, 2, and 3, instead of A, B, and C.

Attachment 2:

Asterisks were used in place of bullets, which

did not conform to the WG .

Attachment 2 Step lb:

There were no numbers provided for the

keys to be used in the SG blowdown permissive key switches, and

the switches did not have any labeling to indicate position.

15.

ES-3.2

Post-STGR cooldown using blowdown

a.

Step 4a RNO:

The adverse feed fl ow va 1 ue of 492 GPM was too

detailed a value to use, since it was the total of up to three

flow indications.

b.

Step 4:

The location of infrequently operated equipment was not

specified.

c.

Step 10c:

This step directed the operator to Operating

Procedure 1-0P-32.1,

PLACING

SLOWDOWN

COOLING

IN

SERVICE.

This procedure ca 11 ed for several system lineups/checkoffs as

prerequisites for entering it.

The procedure, as written,

didn't support rapid implementation during a casualty.

d.

Step 14c:

There were no permanent position indicators on the

Overpressure Mitigation system key switches and the key number

was not included in the procedure.

Appendix B

17

16.

ES-3.3

Post-SGTR Cooldown Using Steam Dump

a.

Step 2b:

The values for minimum RCS subcooling based on CETCs

did not include the natural circulation values.

b.

Step Sa:

The values for maximum cooldown rate in the RCS cold

legs did not include natural circulation values.

c.

Step Sa:

Cooldown .of the RCS must also be maintained in

accordance with p 1 ant TS pressure/temperature curves but no

reference was made for their use.

d.

PSTG DEV, Step 7:

This step required the operator to initiate

steps in Attachment 7.

These steps were plant specific and not

in the ERG.

They included taking the loop isolation valves off

their backseats, which operators estimated would take a licensed

operator at least 30 minutes and possibly over an hour to

comp 1 ete.

The performance of these steps would de 1 ay the

cooldown.

This potential delay was no~ adequately justified in

the SOD.

  • e.

Step 9:

The -SG narrow range 1 eve 1 was 1 i sted as 25 percent

(32 percent) and was listed as 97 percent (32 percent) in other

parts of this procedure.

f.

PSTG DEV, Step 10:

This step required the operator to reduce

the ruptured SGs pressure by 100 psig. This was contrary to the

ERG which stated that steam should be released slowly from the

ruptured SG_to avoid a rapid decrease in pressure and sub5equent

reinitiation of break flow.

This was not justified in the SOD.

g.

Step* 12d:

Same as Step 2b.

h.

Step 14a:

The

RCS pressure for p 1 acing the overp_ressure

.mitigation system in service did not list the adverse contain-

ment value.

i.

Step 14c:

The overpressure mitigation key switches did not have

a label for the

11 enable

11 or "disable." positions.

j.

PSTG DEV, Step 14: This step placed the overpressure mitigation

system in service and was contrary to ERG steps.

The

SOD

justification for adding this step was inadequate.

It did not

address the potential actuation of the OPM system and subsequent

flow of unborated water from the SG into the RCS.

k.

Step 16a:

Same as Step Sa.

1.

Step 16c RNO:

This step required the operator to dump steam at

the "maximum rate

11 from *,he intact SGs.

The intent of this ERG

step was to dump steam at. a controlled rate. This step devia-

tion from the ERG was not justified in the SOD.

Appendix B

18

m.

Step 17:

This step incorrectly indicated that there was no

preferred order for performance.

n .. Cover page header:

The company name on this procedure did not

comply with the WG section 6.2.1.a.l.

o.

PSTG DEV, Step 1 Note:

This note indicated that it was not

mandatory to monitor the continuous action page.

This was not

in accordance with the intent of the ERG.

p.

Step 2c:

This step re qui red keys to accomplish the step, but

did not identify the required keys.

q.

Step 4a RNO:

This step required that a total feed flow of 492

GPM be read from a combination of gauges that had sma 11 seal e

units of 7 GPM.

The awkward scale units of FI-FW-200 A, B,

and C, made the determination of feed flow to this precision

impractical.

r.

Step 4b RNO:

The groupings of bullets below this step did not

have the wording

11 or

11 between them.

s.

Step Sb RNO:

These steps were listed as having no preferred

sequence.

This was inconsistent with operator training.

t.

Step Sb RNO:

There was no method for locally opening the PORVs

although the step required this action.

u.

Step Sb RNO third and fourth bullets: These steps were listed

as having no preferred sequence.

This was inconsistent with

operator training.

v.

Step 10:

Consideration of potential radiological

release

wa.s not reevaluated prior to initiation of this step, and

appropriate precautions were not identified in this step.

w.

Step 10 RNO:

The step did not direct the operator to manually

operate the ruptured SG PORV to decrease SG pressures.

x.

Step 14c:

The step did not identify the keys required to enable

the overpressure mitigation system.

y.

Step 16c RNO:

Same as Step Sb RNO.

z.

Step 16c RNO Thi rd and Fourth Bullets: Same as Step Sb RNO,

Third and Fourth Bullets.

aa.

Attachment 2 Steps la, le and ld:

These items were preceded by

asterisks instead of bullets.

\\,

Appendix B

19

ab.

Attachment 2 Step la, le, and ld:

The appropriate SFs were not

identified with the listed valves.

ac.

Step 13 Second Bull et:

The recorders for RCP lea koff fl ow HI

and LO range, recorders FR-1-154 and FR-1-154B, referred to

reactor coolant pumps as 1, 2, and 3, instead of a, b, and c.

ad.

Attachment 1 Step la:

This step called for using one of the

P-250 Analog trend recorders and the vertical board had a label

process computer trend recorder.

ae.

Attachment 2 Step lb:

Steam generator blowdown permissive key

switches did not have a position indication label.

They were

marked with a magic marker.

af.

Entry condition: These items were preceded by an asterisk

instead of bullets.

17.

ECA-0.0

Loss of all AC power

a.

Cover page header:

The company name on the procedure did not

comply with the WG Section 6.2.1.a.1.

b.

Step

read

gpm.

flow

4:

This step required that a total AFW flow of 492 gpm be

from a combination of gages that had small scale units of 7

These awkward scale units made the determination of feed

to this precision impractical.

c.

Step 5 Caution: There was inappropriate use of II shoul d

11 in stead

of

11 shal1

11 , i.e. an evaluation had to be made prior to taking

any action affecting no. 3 EOG.

d.

Step 6 Caution: There was inappropriate use of

11 should

11 instead

of

11 shall

11 , i.e. if an SI signal existed, it must be reset.

e.

Step 7a RNO:

In this step, if the other unit had AC power from

its diesel, operators were directed to cross tie power from

that unit's H bus to its J bus to close the condenser waterbox

valves on the affected unit.

This would take much longer than

70 seconds, thus per design calculation ME-0166, canal level

would be lost to below that needed to handle a LOCA.

The

licensee stated that the design for power to the condenser

waterbox va 1 ves was as fo 11 ows:

There were a total of eight

large eight foot diameter pipes supplying water by gravity flow

from the intake canal to the condenser waterboxes, four on unit

1 and four on unit 2.

Each pipe had two motor operated flow

i so 1 at ion valves, one on the condenser in 1 et and one on the

condenser out 1 et.

Eight of these va 1 ves ( four on unit 1 and

four on unit 2) were powered from either the unit 1 J bus or

the unit 2 J bus through an ABT.

Thus if either unit's J bus

had power, all eight valves would close automatically (when

intake canal level went below 23.5 feet) and this large flow of

water from the intake canal

could be

stopped within 70

seconds.

-

.

Appendix B

f.

g.

h.

i.

j.

20

The number three diesel supplied power to the J bus of either

unit, seeking the first one with no voltage. However, the power

supply arrangement for the other eight valves was substantially

different. The number 1 diesel supplied power to the unit 1 H

bus, and number 2 diesel supplied unit 2 H bus.

Four unit 1

waterbox valves were powered from the unit 1 H bus, and four

unit 2 waterbox valves were powered from the unit 2 H bus.

Thus; if only one unit's H bus had power, the waterbox valves

on the other unit wou.ld remain open .until they were closed in

this step.

There was no ABT from the two units 1 H buses to

close all eight waterbox valves within 70 seconds:

Step 7b:

This step did not include locally closing the

c;:irc water isolation valves.

If electrical power was not

obtained to close these valves, operators stated that they would

have difficulty in closing the circ water isolation valves locally

within one hour and intake canal level would likely be lost.

These were eight foot diameter valves.

Local closing required

an operator to manally turn a handwheel 3600 times for each valve.

The valves were not equipped with mechanical aids to assist the

operators in closing them quickly.

Step 10:

This step directed operators to cross tie charging

from the other unit to the affected unit to supply seal water

to the *RcPs.

However, the licensee was not well prepared to

cross tie charging in a timely manner; due to poor labeling and

accessibility of some valves (see FCA-1.00 Attachment 78). The

licensee would take substantially longer than 30 minutes to

establish RCP seal cooling.

Attachment 1 part 1 Step 2:

This step i dent ifi ed that pumps

2-CS-P-lA (breaker no 24J-5) and 2-RS-P-lA (breaker no. 24J-4)

were the A pumps but labels showed that these were the B pumps.

There was incorrect identification in this step.

Attachment 4:

Asterisks were used in place of bullets which ~as

inconsistent with the WG.

Attachment 4 Step 7:

This step required the unlocking of valves

  • 1-CH-728 and 2~cH-447.

During the walkthrough the valves were

found to be neither locked nor chained.

The administrative lock

log did not require these valves to be locked.

18.

ECA-0.1

Loss of all AC power recovery without SI required

a.

Step 1 caution: This caution contained an action statemerit and

did not indicate the consequences of not complying with the

caution.

b.

Step 1 note:

This note contained an implied action statement.

c.

Step 1: The location of infrequently operated equipment was not

indicated.

Appendix B

d ..

e.

f.

21

Step 2 first caution:

The meter indication that provided the

correct indication of this value was missing in this step~

Step 2 second caution:

The referenced indicator scale was in

megawatts, but the value in the caution was given in KW.

Step 4e:

The action specified in this step would be difficult

to perform, because the meter had only three graduation marks

below 40 GPM.

g.

Step 6:

Same as step 1 above.

h .. Step 8 first caution:

This caution contained an action state-

ment and did not indicate the consequences of not complying with

the caution.

i .

j.

k.

1.

m.

n.

0.

p.

q.

r.

s.

Step 8 note:

This note contained an action statement.

Step 8:

Same.as step 1 above.

Step 11:

Same as step 1 above.

Step 12 first caJtion: This caution contained an action state-

ment and used the term

11 slowly

11 which was ambiguous and not in

accordance with the WG.

Step 12 s~cond caution:

Same as step 12 first caution above.

Step 12 third caution: This caution contained an implied action

statement.

Step 14bl:

Same as step 4e above.

Attachment 1 Part 1 Step 2:

The pump breakers were l-CS-P-18

and l-RS-P-18 vice 1-CS-P-lA and 1-RS-P-lA and the MCC lJl-1

Supply breaker was 14Jl-6 vice 14J-16.

Attachment 1 Part 2 Step 3:

The trip fuses were not normally

r~moved and that part of the acti~n step was not applicable.

Attachment 1 Part 2 Steps 5 and 7:

The Sync switch in

these steps did not exist and the steps were, therefore, not

applicable.

Attachment 1 Part 3:

This part contained action to restore

power to some equipment when the lJ Bus was returned to normal,

but there was no direction about what to do with the breakers

placed in PTL in Part 1, Step 1 .

\\

Appendix B

22

19.

ECA-0.2

Loss of all AC power recovery with SI required

a.

Step 1 RNO:

This step directed establishing cold leg recirc

valve alignment for LHSI and HHSI suction from the sump when

RWST level was less than or equal to 22 percent. This was prior

to.the automatic shift of suction.

The operator stated that he

would defer performance of this step to the automatic shift of

suction, and he would perform the step if the automatic shift of

suction did not occur at its proper RWST level setpoint.

b.

Step 1 RNO:

This step used paragraph designations

11 a

11 and

11b

11

in the RNO column without the corresponding paragraphs in the

ACTION/EXPECTED

RESPONSE column.

c.

Step 1 RNO:

This step directed the closing of LHSI recirc

valves. The LHSI recirc valves 1 switches were not arranged in an

orderly fashion on the MCR 1 s control board.

d.

Step 3 caution:

This step stated that energized emergency bus

load should not exceed 1200 amps. The MCR emergency bus current*

meter indications read 0-800 amperes with the aforementioned

limit off-scale.

e.

Step 3b RNO:

This step fa i 1 ed to address the performance of

step 3d.

f.

Step 6a:

This step failed to specify the relevance of

11 any

11

intact narrow range SG level.

g.

Step 6b

RNO:

This step failed to state the conditional

direction in accordance with the WG.

h.

Step 6c:

This step failed to identify which

SGs were

applicable.

i.

Step 8a RNO:

This step fa i 1 ed to address the performance of

step 8e.

j.

Step 11 caution: This step failed to specify what was meant by

11 excessive seal leakage

11 of an RCP. The operator stated that he

considered.

11 excess i ve 1 eakage

11 to be greater than 6 gpm which

was off-scale on the associated recorder, FR-l-154A.

20.

ECA-1.1

Loss of emergency coolant recirculation

a.

Entry conditions:

Asterisks were used; which was inconsistent

with the WG.

b .

Step 2 RNO:

This step failed to identify the components in

a particular train.

Appendix B

23

c.

Step 4a RNO:

This step fa i 1 ed to reference the procedure for

locally establishing fire water cooling to IA compressors,

OP-50.1, Removal

of the bearing cooling water system from

service.

d.

Step 4a RNO:

This step directed action which required that the

IA compressor local controller, 1-IA-C-l, be placed in auto per

OP-50.1.

Auto indication was obscured by the switch when auto

was selected.

e.

Step 4a RNO:

This step directed action which required that

BC-227 be verified closed per OP-50.1.

The

operator stated that

he would reach the valve by climbing on various equipment and

piping.

The valve was located approximately 20 feet above the

floor and no appropriate ladder was readily accessible.

f.

Step 4a RNO:

This step directed action whic~ required that the

11 fire water to air compressor

11 valve be opened per OP-50.1.

The

step did not specify FP-170 but incorrectly stated BC-170.

g.

Step 5a:

This step required maintaining cooldown rate prior to

step 5b initiating RCS cooldown .

h.

Step 5b RNO:

This step and local indication failed to address

the unconventional direction (counter clockwise to close) of

local steam dump handwheel operation.

Convenient means of local

communications to .the MCR during the high noise steam dumping

was not available.

i.

Step 6 RNO:

This step failed to direct CTMT fan operation if

desired by the TSC.

j.

Step 14 RNO:

This step failed to state the method

to be

used to thrott 1 e the SI valves which were not designed for

throttling.

k.

Step 21a:

This step failed to direct the warming of RHR if

desired by the TSC.

l.

Step 21c:

This step failed to direct the placing of RHR in

service if desired by the TSC.

m.

Step 22b RNO:

This step transitioned so as to omit step 22d.

Step 22d opened the SI accumulator isolation valve breakers, and

was important for operators to perform.

n.

Step 28b RNO:

Same as step 5b RNO above.

o.

Step 29a RNO:

Same as step 5b RNO above.

p.

Step 30b RNO:

This step transitioned so as to omit step 30d.

Appendix B

21.

24

q.

Step 31b RNO:

Same as step Sb RNO above.

r.

Step 33a:

Same as step 21a above.

s.

Step 33c:

Same as step 21c above.

t.

Step 34b RNO:

Same as step Sb RNO above.

u.

Attachment 2:

Same as entry conditions above.

v.

Attachment 2 Step 6:

This step required unlocking valves CH-728

and CH-447 which are not 1 ock.ed.

ECA-1.2

LOCA outside containment

a.

Entry conditions:

Asterisks were used in a manner inconsistent

with the WG.

b.

Step la:

This step re qui red the local operation of three

breakers. The NLO on the walk.down indicate-d that a control room

operator would have provided him the keys needed for the area.

The step did not indicate the need for keys .

c.

Step le:

A colon was used in a manner inconsistent with WG.

d.

Step 2a, d, and g:

Same as Step le.

e.

Step 2 continued:

Same as Step le.

22.

ECA-2.1

Uncontrolled Depressurization of All Steam Generators

a.

Cover page header:

The company name on the procedure did not

comply with the WG Section 6.2.1.a.l.

b.

Step

1

Note:

This

note

indicated that it was

not

mandatory

to monitor the

continuous action

page.

This

was not in accordance with the intent of the ERG.

c.

PSTG DEV Step 2c:

This step had the operator check for RCS hot

leg temperatures decreasing.

The intent of the ERG was to have

the operator check. for RCS hot leg temperatures stabilized.

This EOP step deviation from the ERG was not justified in the

SOD.

.

d.

Step 2b:

This step required the operator to maintain SG level

less than 50 percent but did not identify an adverse containment

value.

e .

Step 29:

No caution was listed to warn the operator of the

minimum PZR level for reenergizing PZR heaters, 24 percent

(55 percent), and the operator indicated that PZR heaters could

be reenergized if PZR level was .greater than 17 percent.

Appendix B

25

f.

Step 2a:

The values for maximum cooldown rate in the RCS cold

legs did not include natural circulation values.

g.

Step 28:

The required VCT levels in the action statement and

RNO were not the same value. 27 percent versus 34 percent.

h.

Step 3a:

This step did not list a minimum HHSI flow required

for continuation or exiting from this step. The operator could

not provide a specific value.

i.

Step 3 Note:

The recorders for RCP l eakoff fl ow Hi and Lo

range, recorders FR-1-154 and FR-1-1548, Referred to reactor

coolant pumps as 1, 2, and 3 instead of A, B, and C.

j.

Step 3e RNO:

No direction was given to the operator to locally

close the Chg. pump miniflow valves.

k.

Step 3 Note:

The instruments for RCP seal injection fl.ow

referred to reactor coolant pumps as 1, 2, and 3 instead of A,

B, and C.

l.

Step 4 RNO: Alternate AFW supply sources were not listed.

m.

PSTG DEV, Attachment 1 Step 6a:

This step did not caution the

operator that if offsite power was lost after SI was reset,

manual action may be required to start safeguards equipment.

This was not in accordance with the ERG.

n.

Attachment 1 Step 2a:

This step directed the operator to

11 Do

Not Continue" if containment pressure is greater than 14 Psia.

This statement would stop operator actions in this procedure.

o.

Attachment 1:

Various steps in this attachment used asterisks

instead of bullets.

p.

Attachment 1 Step 4b:

The steam generator blowdown permission

key switches did not have a position indication label.

They

were marked with a magic marker.

q.

Attachment 1 Steps 4a, c, and d:

The appropriate SG(s) were

not identified with the.listed valves.

r.

Step 6b:

The operator stated that he would initially verify

the alarm windows to satisfy this step.

The main steamline

radiation monitor alarms were identified as Unit 2 MSTM. ABC.

RAD. MON., and were physically located on the Unit 2 side of the

alarm panel.

s.

Step 6b:

The operator stated that he would initially verify the

alarm windows to satisfX this step.

The TD AFW pump exhaust

radiation monitor alarm was identified as Unit 1 Aux. Stm. Rad.

and was physically located on the Unit 2 side of the alarm

panel.

.

Appendix B

26

t.

Step 7 Caution:

This caution contained a conditional logic

action and contained no statement of consequences and was thus

inconsistent with WG direction.

u.

Step 7b:

This step directed the operator to reset SI if

necessary.

The operator was unable to specify what would

ful fi 11 the term

11 necessary

11 *

v.

Step 8g:

There was no

RNO step to direct the operator to

locally close the CS discharge valves.

w.

Step 8h:

There was no RNO step to direct the operator to

locally close the caustic supply valves.

x.

Step 9:

This step checked the RWST 1 eve l greater than the 22

percent recirculation switchover setpoint and did not have an

asterisk to identify the -step as a continuous action item.

y.

Step 8b:

This step had a less than 12 psia containment pressure

setpoint .for resetting CLS and Step 13a had a less than 14 Psi a

containment pressure setpoint for resetting CLS. It was also

noted that neither step documented the minimum pressure for

operation of the spray system which was i dent ifi ed in the

setpoint document as 10 psia.

z.

Step lOC:

This step required keys to accomplish the step, but.

did not identify the required keys.

aa.

Step lla RNO:

SI may have been terminated in Step 78 or attach-

ment 1 Step 1.

The action statement was an SI reinitiation

criteria which made the RNO statement inadequate~

ab.

Steps 11 band c RNO:

The band c RNO steps were reversed.

ac.

Step* llc: SI may have been terminated in Step 7b or attachment

Step 1.

The action statement was an SI reinitiation criteria

which made the RNO statement inadequate.

ad.

Step 12:

Same as Step 6a Attachment 1.

ae.

Step 14a RNO:

This step did not direct the operator to restore

intake canal level by going to AP 12.01, loss of intake canal

level. It also did not specify the minimum canal level which was

identified as 24 ft. in the setpoint document.

af.

Step 14cl RNO:

The seal leakoff line had been isolated by the

SI signal and seal leakoff would flow through the letdown relief

in containment.

The temperature instrument used by the operator

was located downsteam of the relief valve and would not see

leakoff temperature.

As a result, the operator may not close

TV-CC-107 as required by this step and after starting the CC

pump, the RCP seals could be cooled at greater than 1 degree per

minute, which could result in seal failure.

Appendix B

27

ag.

Step 18 RNO:

This step did not direct the operator to locally

operate various valves.

ah.

Step 19 RNO:

This step did not direct the operator to locally

operate various valves.

ai.

Step 14c5 RNO:

This step failed to reopen TV-CC-107 after

returning the CC system to operation. This could result in

failure to provide adequate cooling to the RCP seals.

aj.

PSTG DEV, Step 22:

Both subset steps in the action statement

are SI reinitiation steps.

The RNO steps did not direct the

operator to manually initiate SI.

During the walkthrough, the

operator walked through manually aligning valves.

This step was

not in accordance with the ERG, and was not justified in the

SOD.

ak.

Step 26:

While reviewing the letdown piping diagrams, the NRC

noted that RV 1203 on print 11448-FM-088C did not have a relief

setpoint. The operators were unable to readily provide the

relief setpoint.

aj.

Step 26 RNO:

This step did not direct the operator to locally

operate various valves.

al.

Step 28 RNO:

This step did not direct the operator to locally

operate various valves.

am.

Step 30 RNO:

This step could result in RCP seal failure because

CC may not have been restored and the seal leakoff temperature

instrument used by the operator was not in the flowpath with

MOV-1381 closed.

an.

Steps 30 c and d:

These steps did not list normal CC flows.

ao.

Step 31:

This step directed the ope.rator to verify all AC buses

energized by offsite power.

The operator had some difficulty

determining which instruments to review for verification of th1s

step.

ap.

Step 37 RNO:

This step did not direct the operator to locally

operate various valves as necessary.

aq.

Step 37:

11 Reset Auto-Start Inhibit

11 was not i dent ifi ed as a

1 oca 1 action.

ar.

Step 39:

Same as Step 22.

as.

Step 40b:

Same as Step 22.

at.

Step 40c:

Same as Step ')oc.

au.

St~p 40d:

Same as Step 100.

Appendix B

28

23.

ECA-3;1

SGTR with loss of rea~tor coolant - subcooled recovery

a.

. Cover page header:

The company name on the procedure did not

comply with the WG Section 6.2.1.a.l.

b.

Entry Conditions:

Transition procedures were denoted with

asterisks instead of bullets as required by the WG.

c.

Step 1 caution:

This caution inappropriately used

11 should

11

instead of

11 shal1

11 *

It was necessary to align the SI system for

cold leg recirculation.

d.

Step Sc:

This step required the operator to 11veri fy

11 CLS set,

and the operator stated that if the CLS had not been set that

action would be taken to change this condition.

Verify as

defined in the WG required the operator to observe that* a

condition existed but did not direct the

operator to take

action to change the condition.

The misuse of

11 verify

11

was

generic to all of the EOP procedures.

e.

Step 10a RNO:

This step required that a tota 1 AFW fl ow of 492

gpm be read from a combination of gages that had sma 11 sea 1 e

units of 7 gpm.

These awkward scale units made the determina-

tion of feed flow to this precision impractical.

f.

Step 10b RNO:

The grouping of bullets below this step did not

have the wording

11or

11 between them.

g.

Step 17 Caution:

This step contained inappropriate use of

llshould

11 instead of

11 shall

11 ; RCPs must not be started without

prtor status evaluation.

h. *

Step 28dl:

Key numbers were not designated for working SI

accumulator key switches.

i".

Step 36a second bullet:

The recorders for RCP leakoff flow Hi

and Lo range, recorders FR-l-154A and FR-1-1548, referred to

reactor coolant.pumps as 1, 2, ~nd 3 instead of A, B, and C.

24.

ECA-3.2

SGTR with loss of reactor coolant - saturated recovery

a.

b.

C.

Cover page header:

The company name on the procedure did not

co~~ly with the WG sectio~ 6.2.1.a.l.

Step 1 first note:

The fir.st 13 steps of ECA-3.1 must be

performed prior to the beginning of this procedure in order for

this procedure to work.

The note did not identify these actions

as mandatory.

Step 1 second note:

This note indicated that it was . not

mandatory to monitor the continuous action page.

This was not

in accordance with the intent cif the ERG.

...

Appendix B

29

d.

Step la:

LIC-CS-200A and LI-CS-2008 did not have the appropri-

ate power supply designations on the meter scale.

e.

Step lb:

The steps that were used to make up to the RWST were

incorrectly identified as not having a* preferred method of

performance.

f.

Step lb first and secontj bullets: These bullets required local

actions, but were not identified as requiring local actions.

g.

Step 2 caution:

Actions were contained in this caution, which

was inconsistent with WG section 6.4.4.a.S.

h.

Step 4a RNO:

This step required that a total feed flow of 492

gpm be read from a combination of three gauges that had small

scale units of *7 gpm.

The awkward scale units of FI-FW-200-A,

B, and C made the determination of feed flow to this precision

impractical.

i.

Step 4b RNO:

The groupings of bullets below this ste*p were not

divided into groups of three with the statement

11or

11 between

them .

j.

Step S second and third notes: Actions were contained in these

cautions, which.was inconsistent with WG section 6.4.4.a.S.

k.

Step Sc RNO first and second bullets: These- steps were listed

as having no preferred sequence.

This was inconsistent with

operator training and normal engineering practice of opening the

steam dumps before' using the PORVs.

l.

Step Sc RNO first bullet:

There was no metho~ for locally

opening the PORVs although the step required this action.

m.

Step Sc RNO third and fourth bullets: These steps were listed

as having no preferred sequence.

This was inconsistent with

operator training.

n.

0.

Step 8:

This step required a switch position of

11off

11 *

pressurizer heater group C did not have an off position.

switch did have a position "pull to lock

11 *

The

The

Step 13b RNO:

This step required the operators to manually open

the charging line isolation valve.

The operators interviewed

indicated that this valve actually had to be opened locally.

T~ere was no local method for accomplishing this step .

\\

Appendix B

- - - - - - - - - -

30

p.

Step 13e:

This step required the use of FI-2-122A.

The scale

on the instrument was compressed _on the lower end of the scale.

This made a flow reading of very close to 25 gpm difficult to

distinguish.

q.

Step 15a:

This step used the verb

II secured

11 *

This statement

was inconsistent with the operators* action of placing the

system in

11 auto

11 *

r.

Step 17:

This step required the verification that five

parameters were decreasing or stable.

No

indication was

available to indicate this information.

This information

required trending to determine the appropriate status.

s.

Step 18c:

This step required the pressurizer heaters to be

turned on without determining if they were actually needed.

t.

Step 21d RNO:

This step indicated that IA should be available.

The step did not specify containment IA.

u.

Step 2ldl: This step required keys to accomplish the step, but

did not identify the required keys (Keys 11, 12 and 13) .

. v.

Step 22b second bullet:

The procedure title was inconsistent

with the preceding bullet, in that it did not identify that

actions were required .to be performed from the MCR.

w.

Step 24b:

The~ verb

11 veri fy

11 was used to indicate that this step

should be accomplished, if possible.

This was not consistent

with the definition of

11 verify

11 in the WG.

x.

Step 25:

This step was not written in the form of a single

step, which was not consistent with the WG. *

y.

Step 27:

This step indicated that the substeps could be

performed in any order.

Under some conditions it would be

necessary to perform the first bullet before the second bullet.

z.

Step 27 seventh bullet:

The abbreviation RSST did not appear on

the approved WG abbreviation list.

aa.

SOD step 5 forth note:

The reference to set point E .13 was

incorfect.

The set point was applicable to the third note.

ab.

Setpoint B.8:

This calculation concerned the RCS

pressure

correspcindi ng to the* shutoff pressure of the 1 ow head SI pumps

plus allowance for normal channel accuracy.

The setpoint was

based upon the SI pump shutoff head for an RWST level of zero.

The calculation failed to include the additional head for an

Appendix B

31

RWST level of 100 percent.

As a result, the calculated shutoff

head setpoint was 366 ft instead of approximately 408.5 ft.

The equivalent RCS pressure setpoint was 250 psig instead of

approximately 270 psig.

The licensee 1 s setpoint contractor

stated that this setpoint error would be corrected in the next

EOP setpoint document revision, scheduled to be completed by

the contractor in about four months.

Additionally, the portion

concerning dPelev was written incorrectly.

The calculation as

written gave the result -711.7 psi. The mathematically correct

answer was 7.3 psi. This setpoint was used in eighteen steps in

the EOPs.

ac.

Setpoint B.9:

This calculation concerned the RCS pressure

corresponding to the shutoff pressure of the low head SI pumps

plus allowance for normal channel accuracy and post-accident

transmitter errors.

The setpoi nt was based upon the SI pump

shutoff head for an RWST level of zero. The calculation failed

to include the additional head for an RWST level of 100 percent.

As a result, the calculated shutoff head setpoint was 366 ft

instead of approximately 408.5 ft.

The equivalent RCS. pressure

setpoint was 525 psig instead of approximately 545 psig.

The

licensee 1 s setpoint contractor stated that this setpoint error

  • would be corrected in the next EDP setpoint document revision,

scheduled to be completed by the contractor in about four

months.

Additionally,The portion concerning dPelev was written

incorrectly.

The calculation as written gave the result 23.7

psi.

The mathematically correct answer was 7.3 psi.

This

setpoint was used in eighteen steps in the EOPs.

ad.

Setpoint K.1:

This calculation concerned RCS subcooling margin

and used a combination of RCS temperature measurement and

pressure measurement uncertainty converted into a temperature

based on saturated conditions.

Under certain conditions, at

lower RCS pressures (below 400 psi) the RCS subcooling value of

30 degrees would indicate that the operator was operating in

the subcooled region; however, based on the uncertainties of the

calculation the operator may have been operating at saturated

conditions.

This phenomenon would increase the probability of

operation in the saturated region as RCS pressure decreased and

increase the probability of vessel voiding.

This calculation

was based upon a three standard deviation uncertainty range

for the subcooling margin at .a reactor coolant system pressure

of 400 psi.

However the subcooling margin calculation was

assumed to be valid at lower pressures by maintaining the

calculated subcool ing margin and increasing the uncertainty

in the value of subcoo 1 i ng and subsequently increased the

probability of operation in the saturated condition.

As RCS

pressure decreased to 100 psig the probability of operating

in the saturated region would have increased to a l eve 1 of

Appendix B

32

approximately one standard deviation and the uncertainty in the

subcool ing margin value would have correspondingly decreased.

This exceeded the minimum acceptable probability limit for

errors of 95 percent (2 standard deviations) per NRC Reg.

Guide 1.105.

This setpoint was used in 16 steps in the EOPs.

25.

ECA-3.3

SGTR without pressurizer pressure control

a.

PSTG DEV, Step 4:

The ERG step was deleted with the justifica-

tion that establishing auxiliary spray flow would terminate SI.

However, the ERG step included other actions and it was possible

that SI may not be required. The EDP SOD did not address these

aspects of the deviation.

b.

PSTG DEV, Step 4:

The corresponding step in the ERG stated

11 IF

narrow range level in any intact SG continues* to increase.

11 The

word

11 intact

11 was not included in the procedure and the EDP SOD

did not address this deviation.

c.

Step llc RNO:

The indicator for RCP seal leakoff temperature

was not in the step, but was needed to insure that the operators

use the correct indicator .

d.

e.

Steps 19a and d RNO:

Same as step llc RNO above.

Step 21:

The location of infrequently operated equipment was

not indicated.

f.

Step 22cl:

There were no permanent position indicators on the

SI Accumulator switch keys and the key numbers were not included

in the EOP.

g.

Step 26 caution:

This caution contained an implied action

statement.

h.

PSTG DEV, Step 30 note:

This ERG note which stated

11The upper

head region may void during RCS depressurization if RCPs are not

running.

This may result in a rapidly increasing PRZR l~vel

11 ,

was deleted from the EOP.

The justification failed to consider

the fact that PRZR heaters had been secured since step 13 and

that the note only stated that a rapid rise in pressurizer level

may occur.

i .

PSTG DEV, Step 31a:

The corresponding step in the ERG was

divided into two separate steps with different RNO actions.

The

justification for this deviation in the EDP SOD stated that it

simplified the logic without unnecessary delay.

Since the EOP

RNO step could send the operator to procedure steps that mtght

not be applicable, the deviation could introduce delays .

\\

Appendix B

33

26.

F-0

Critical safety function status trees

a.

General comment:

The ERF computer simulation could not display

the correct path if an erroneous instrument reading was input to

the system. There was no method for bypassing incorrect inputs

and displaying the correct path.

The status or path color or

alternate paths were not displayed.

The operators interviewed

stated that they would use the F-0 procedure and would not use

or rely on the E~F computer output when using the EOPs.

27.

FR-C.l

Response to inadequate core cooling

a.

PSTG DEV, Step 8b:

This step stated

11 H2 concentration -

LESS

THAN 4~~

11 *

The corresponding step in the ERG stated "Hydrogen

concentration -' LESS THAN 6.0~~ in DRY AIR.

11 The EOP SOD did not

address this deviation.

b.

PSTG DEV, Step 9a RNO:

This step stated "Maintain total feed

flow* greater than 350 gpm until narrow range level greater

than ...

11 *

The corresponding step in the ERG stated

11 Increase

total feed flow to restore narrow range level greater than ...

11

The EOP SOD did not address this deviation .

C.

PSTG DEV, Step 20:

The EOP step added the extra words "USING

STEAM DUMPS" at the end of the high level step. This statement

was not included in the ERG.

This step deviation was not

justified in the EOP SOD.

d.

Step 21b:

There were no permanent position indicators on the SI

Accumulator isolation key switches and the key numbers were not

included.

28.

FR-C.2

Response to degraded core cooling

a.

Step 1 caution:

This caution contained no statement of

consequences as per the WG.

The caution contained a continuous

monitoring action and a reference to another procedure.

b.

Step 2a

RNO:

This step provided five alternative actions

(bullets one through five) to the operator but provided no

guidance on necessary or sufficient conditions.* No specific

direction was provided on how to perform the alternatives. The

operator on the walkdown indicated either of the first two

alternatives as sufficient, the third and forth alternatives

together as probably sufficient, and required referencing part

of attachment 7b to FCA-1.00 to perform the fifth alternative.

FCA-1.00 was not referenced in this step and the operator took

considerable thinking and time to find it .

    • ':.**:: ., . ~. *, ..... .

'

.* **-* -.

'

... *.

. .*, .~ . -. : .

Appendix B

34

c.

Step 4 note:

This note inappropriately included a caution

statement.

d.

Step 10b RNO:

This step required the operator to locally

crosstie to turbine bldg air but provided no specific direction

or reference for performing the action .

. e.

Step llb~ This step requjred the operator to dump steam to the

main condenser but provided no direction on how to perform this.

The operator on the walkdown indicated this was a relatively

complicated action.

f.

Step llb RNO:

This step provided the operator with two

alternatives for action but provided no direction as to

preferred action.

The operator on the wa lkdown indicated he

believed there was a preierred action.

g.

Step 13b RNO:

This step used IAW as a referencing term but IAW

was not defined as a referencing term in the WG.

h.

Step 14 caution:

This caution was located near the bottom of

the page while most of the related steps were on the following

page.

i.

Step 15b RNO:

Same as Step llb RNO.

j.

Step 16 RNO:

Same as Step 2a RNO.

k.

Step 17 RNO:

Same as Step 13b RNO.

l.

Genera 1 comment

on

FR-C. 2:

This procedure contained many

transitions (eight transitions on pages five and six alone).

This could increase the probabi 1 i ty of operator errors and

place keeping problems, especially when the operator is under

psychological stress during an emergency.

29.

FR-C.3

Response to saturated core cooling

~

a.

No comments.

30.

FR-H.1

Response to loss of secondary heat sink

a.

PSTG DEV, Entry Conditions: The EDP stated that this procedure

could be entered when an ORANGE path existed.

The ERG did not

contatn that provision and the F-0.3 Heat Sink CSF Status Tree

did not contain the provision.

b.

Step 1 second caution:

The caution contained an action state-

ment and did not indicate the consequences of not complying

with the caution.

.. - ,., .. - '

Appendix B

35

c.

PSTG DEV, Step 4e RNO:

This step stated

11 GO TO Step 10.

11

The corresponding step in the ERG stated

11GO TO Step 7.

11

The EDP SOD did not address this deviation.

d.

Step 11 caution: This caution did not indicate the consequences

of not complying with the caution .

. e.

Step 11 first and second notes:

These notes contained action

statements.

f.

PSTG DEV, Step 14a RNO:

The EDP directed the operator to

continue to step 16.

This deviated from the ERG required step i

sequence, but the EDP SOD did not address this deviation.

This

was a 1 so an examp 1 e of the use of the phrase

11Cont i nue wi th

11

that required the operator to do all of the steps that were

initially by passed in order to comply with the ERGs.

If the

operator had only done the steps specified in the EDP, then step

15, which established IA to containment, would not have been

done.

See comments in E-1 step 6d2 RNO and step 10a RNO above

for additional information.

g.

PSTG DEV, Step 18:

The corresponding step

11Maintain PRZR PORVs - AT LEAST TWO OPEN.

11

not included in the EDP. The EDP SOD did

deviation.

in the ERG stated

This statement was

not address this

h.

PSTG DEV, Step 23b RNO:

The corresponding step in the ERG

stated

11THEN start one LHSI pump if none running.

11

The EDP just

stated

11THEN verify one LHSI pump running.

11

The EDP SOD did not

address this deviation.

i.

PSTG DEV, Steps 25a and b RNO:

The corresponding step in the

ERG stated

11 BIT

11 and the EDP stated

11SI

11 *

The EDP SOD did not

address this deviation.

j.

Step 28 RNO:

The step did not include the action to "leave one

in AUT0

11 after PRZR PORVs which was included in step 25.

This

step would improperly leave all PRZR PORVs isolated.

32.

FR-H.3 * Response to steam generator high level

a.

No. comments.

33.

FR-H.4

Response to loss of normal steam release capabilities

a.

Note 1:

The intent of Note 1 was to insure pressure was main-

tained low enough to prevent steam rel ease through a safety

valve.

The 1085 psig limit may have been too high to prevent

weapage or subsequent actuation following an initial actuation,

since subsequent safety valve actuation has been found to

typically occur at lower pressures.

Appendix B

36

b.

Step 2 RNO:

The operator was told to manually or locally dump

steam.

Under this step the SG PORVs were listed. The SG PORVs

could not be locally operated.

34.

FR-H.5

Response to steam generator low level

a.

Step 2:

The verb

11 verify

11 was used to indicate that this step

should be accomplished, if possible.

This was not consistent

with the definition of

11 v,erify 11 in the WG.

b.

Step 2 RNO:

This step indicated that an action should be

accomplished manually.

The step actually had to be accomplished

locally.

c.

Step 4:

This step required that a feed flow of 168 gpm be read

from a gauge that had small scale units of 7 gpm.

The awkward

scale units of FI-FW-200-A, B, and C made the determination of

feed flow to this precision difficult.

35.

FR-I.1

Response to pressurizer high level

a.

b.

C.

d.

e.

f.

Step 1:

This step was not written in the form of a single step,

and was not consistent with the WG.

Step 2a2 RNO:

This step used the verb verify.

This use of

verify in this step was inconsistent with the WG definition. If

the pump miniflow valve was not opened the GHG/SI pump could not

be started.

Step 2b RNO:

This step indicated that there was no preferred

order for performance of the substeps, although it was clear

that establishing CTMT IA was the preferred method.

Step 2b RNO first bull et:

This substep contained no action

verb.

11 CTMT "IA system

11 did not clearly indicate the required

action.

Step 2c2 RNO:

'This step used the verb verify.

This use of

verify in this step was inconsistent with the WG definition. If

the pump miniflow valve was not opened the GHG/SI pump could not

be started.

Step 4bl:

This step used the verb verify. This use of verify

in this step was inconsistent with the WG definition. There was

no previous step that would have established a charging flow of

greater than 25 gpm.

Charging flow was established at 25 gpm in

step 2.4.c .

\\

Appendix B

37:

g.

Step 4b3:

This step used the verb verify. This use of verify

in this step was inconsistent with the WG definition.

This

step did not have an RNO which directed the operator to close

the letdown orifice isolation valves.

36.

FR-I.2

Response to pressurizer low level

No comments.

37.

FR-I.3 Response to voids in reactor vessel

a.

Step 2b second bullet RNO:

This step required the cross tying

of containment IA and turbine building instrument air.

This

step was performed by locally manipulating two locked valves.

These two valves and key numbers were not denoted in the step.

b.

Step 3b:

This step did n.ot have an RNO to locally open the

valve.

c.

Step 17 a, b, and c: This step required starting of fans.

Fans

in Step a could be started manually but those in Steps band c

must be started locally. The Step did not indicate manually or

locally.

38.

FR-P.1

Response to imminent pressurized thermal shock condition

a.

Step 8c RNO:

This step failed to reference the computer point

required to access the RCP seal leakoff temperature.

b.

Step 15c:

This step and its associated RNO were split between

two pages.

39.

FR-P.2

Response to anticipated pressurized thermal shock condition

a.

Step lel RNO:

This step was a local action but was not

identified as such in the step.

b.

Step le2 RNO:

This step was a local action but was not

identified as such in the step.

c.

Step le4 RNO:

This step directed the operator to isolate

feedwater to faulted SG(s) unless necessary for RCS temperature

control but provided no specific information on how to determine

if necessary for temperature contra l.

The operator on the

wa l kdown indicated this was determined by operator judgment

based on knowledge of plant conditions .

Appendix B

38

40.

FR-S.1

Response to nuclear power generation/ATWS

a.

Step 5b RNO:

This step failed to indicate the direction of

operation of the trip lever when the local indication was

obscured.

The operator stated the incorrect direction for

operation.

b.

Step 11:

This step failed to specify the requirements for the

isolation of AFW line(s).

c.

Step

12b:

This step failed to reference OP-lF for SOM

calculation.

d.

Step

13 caution:

The continuation of boration to obtain

adequate shutdown margin was incorrectly stated as a caution

statement.

41.

FR-S.2

Response to Loss of Core Shutdown

a.

Step 1:

This step required the operator to verify intermediate

range flux decreasing but did not identify an acceptable rate.

The ERG background information 1 isted an acceptable value as

greater than -.2DPM.

b.

Step 2 RNO: This step required the operator to emergency borate

which w.as inconsistent with Step la RNO which required the

operator to borate.

The ERG required a preferred method of

borating the RCS.

42.

FR-Z.1

Response to containment high pressure

a.

Step 1 caution:

This caution did not contain a statement of

consequences as per the WG.

b.

Step 6 RNO:

This step directed the operator to manually or

locally close the MSTVs and bypass valves._ The MSTVs could not

be closed locally.

c.

Step 7 caution:

This caution suggested action based on a

conditional statement and did not contain a statement of

consequences.

d.

Step 8 note:

This note contained an action.

e.

Step 8a and c RNO: This step used IAW as a referencing term but

IAW was not defined as a referencing term in the WG.

f.

Step 9b:

procedure

specified

This step directed the operator to "RETURN

TO

and step in effect".

In the WG,

11 RETURN T0 11

was

for use in tra:\\!,s it ions but not for branching.

  • Appendix B

39

g.

Step 10a RNO items 1 and 2:

Item 1 presented a conditional

action to perform steps 10 through 12 when CTMT pressure was

less than 14 psig.

Item 2 directed the operator to

11 RETURN TO

procedure and step in effect.

11

The way the procedure was

written, the operator may have some confusion over whether to

wait for the pressure to be less than 14 psig before taking any

further action or continuing with the steps in effect.

Also

there was no formal place keeping method to remind the operator

of item 2 and which procedure would be in effect in response

to item 2.

This step appeared to be a continuo~s actio~

requiring an asterisk as per the WG.

h.

Step 10a RNO item 2:

Same as step 9b.

i.

Step 10d and e:

The operator on the walkdown made the observa-

tion that the procedure had the operator verify A SW header

components operating before isolating the A SW header, but did

not have the operator verify B SW components before isolating

the B SW header.

j.

Step 12 RNO:

This step required the operator to perform one of

three options within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> from the initiating event.

No

specific guidance was provided regarding preferred action and

there was no method of place keeping to avoid overlooking these

actions.

k.

Step 13:

Same as step 9b.

43.

FR-Z.2

Response to Containment Flooding

a.

General Comment:

The concern with flooding in containment was

that critical plant components needed for plant recovery could

be damaged and rendered inoperable.

The procedure did not

identify a maximum level, the flood level, or what equipment

would be lost at what levels.

b.

Step 1:

The intent of this step was to identify sources of

water to the containment sump, and to isolate them if possible:

1)

The sources listed in Step 1 were not complete.

2)

Instrumentation

used

to

identify unexpected

sources

of water were not listed.

3)

Isolation valves were not listed.

c.

Step ld: This step had the control room consult with the TSC to

determine required actions:

1)

The TSC may not be *~anned.

Appendix B

44.

40

2) , The step did not include options to isolate leakage.

d.

Step 2:

This step requested chemistry to sample the containment

sump:

1)

The chemistry procedure (l-COP-168) only covered sampling

for activity.

2)

Following a loss of offsite power CC would not be readily

available and as a result, chemistry would not be able to

sample the containment sump.

Consequently, this procedure

could not be completed.

.

e.

Step 3:

This step referenced TSC personnel for exchange of

information and subsequent actions, and the TSC may not be

manned.

f.

Steps 2 and 3:

The containment sump pumps may not be available,

following

containment flooding,

for sampling purposes or

transfer of sump water.

The containment sump

pump

upper

temperature limit for pumped liquid was 115 degrees F, per the

manufacturer's technical manual, PG8.

Also the pump electrical

connections may be under water .

FR-Z.3

Response to containment high radiation level

No comments.

45

FR-Z.4

Response to containment positive pressure

a.

b.

C.

d.

Step 2bl:

This step had no direct method of determining the

required RCP sea 1 * return temperature.

The

RCP

seal return

temperature instrument was not in a flow path with seal return

isolated.

Specific guidance was

required to prevent the

operator from reading an incorrect temperature and as a result

chill shocking the RCP seal.

Step 3 RNO al:

This step used the verb verify.

This use of

verify in this step was inconsistent with the WG definition.

Step 14a RNO:

This step used the verb verify.

This use of

verify in this step was inconsistent with the WG definition.

If the valve MOV-CS-lOOA was not opened 1-CS-P-lB could not be

started.

Step !Sa:

This step used the verb verify. This use of verify

in this step was inconsistent with the WG definition.

If the

valve MOV-CS-lOOA was not opened 1-CS-P-lB could not be started .

\\

'

Appendix B

41

III. AP comments

1.

AP-1.00

Rod control system malfunction

a.

Step 2b RNO:

This step incorrectly referenced the Reactor

trip/safety injection procedure as EP-1.00 vice l-E-0.

This

error was consistent throughout the procedure.

b.

Step 8 RNO:

This step directed that reactor be matched and

stabilized at less than 75 percent powe~. Previously, in step 7

the procedure directed that th'e turbine power be less than : or

equal to 70 percent.

2.

AP-1.01

Control rod misalignment

a.

Step 1 note:

This step failed to specify whether reactor or

turbine power was assumed to be 70 percent or less~

b.

Step 5 caution:

This step failed to specify the 75 percent

power limit as reactor or turbine power.

C.

d.

Step 7:

This step directed the placement of

11all

11 disconnect

switches to open vice the affected bank 1 s disconnect switches ..

Step 10:

This step failed to specify the actions required to

reset affected bank P/A converter.

3.

AP-1.02 Malfunctioning individual rod ~osition indicator (IRPI)

'

a.

Step 1 caution:

This step incorrectly directed verification of

rod to band vice rod to bank position.

b.

Step 4 RNO:

This step failed to specify from when the 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

time limit was to be commenced.

c.

Step 5:

This step failed to indicate which of the actions were

to be performed by the instrument shop.

4.

AP-3.00

Conditions requiring emergency boration

a.

Attachment 1:

This attachment was not referenced in the

procedure and appeared to serve no useful purpose.

5.

AP-4.00 Nuclear instrument malfunction

a.

General:

Asterisks were used throughout the procedure instead

of bullets .

\\

. , .. * ~ -*-*. ***** ..

,

Appendix B

42

6.

AP-5.01

Radiation

monitoring

system

process

vent monitor(s)

alert/alarm

a.

Step 1:

This step was not numbered.

b.

Step 3b:

This step failed to specify to whom the information

was to be provided.

c.

Step 3b:

This step required the reading of flow rate indica-

tion.

The

associated.

indication,

FI-GW-100,

was

not

referenced in th~ step and was poorly incremented in divisions

of 7 CFM.

d.

Step 3b:

This step required the reading of the Kaman effluent

monitors,

RI-GW-130-1

and

RI-GW-130-2.

The

indicator's

parameters were displayed numerically (i.e., 47 corresponds to

micro-curies/second).

There were no procedures in place to

state the parameter associated with a particular number.

7.

AP-5.03

Radiation monitoring system liquid waste monitor

a.

Step 9:

This step directed checking the flow monitor vice the

flow rate monitor.

The entry conditions described it as the

flow rate mon,toring device.

8.

AP-5.04

Probable causes and references

a.

Step 3 RNO:

This step had improper lettering of substeps.

9.

AP-5.05

Radiation mon~toring system CC monitors A & B

a.

Entry conditions: The information was incomplete. The equipment

that would alarm was not listed.

b.

Attachment 1:

This attachment was not referenced in the

procedure and appeared to serve no useful purpose.

10.

AP-5.06

Radiation monitoring system restricted control area monitors

a.

General: Asterisks were used throughout the procedure instead of

bullets.

b.

General:

The procedural steps did not address all of the

monitors listed in the entry conditions.

c.

Step 3:

This step had the operator dump the control room

bottled air without verification of radiation levels .

'

Appendix B

  • 43

11.

AP-5.07

Radiation monitoring system main control room air monitor

a.

Attachment 1:

This attachment was not referenced in the

pro~edure and appeared to serve no useful purpose.

12.

AP-5.08

Radiation monitoring system containment particulate and gas

and manipulator crane

a.

Step 10:

The step directed the checking of three valves, but

did not indicate w~at position the valves should be in.

Since

the positions would vary depending on the tause of the alarm,

more information was required in this step.

b.

Step 13:

No guidance was provided to the operator if the

radiation level was high, but had not increased by a factor of

1000.

c.

Attachment 1:

This attachment was not referenced in the

procedure and appeared to serve no useful purpose.

13.

AP-5.09

Radiation monitoring system condenser air ejector

a.

General: Asterisks were used throughout the procedure instead of

bullets.

14.

AP-5.10

Radiation monitoring system SG blowdown

a.

Entry conditions:

The alarm meters that this procedure applied

to were not inaicated.

b.

Attachment 1:

This attachment was not referenced in the

procedure and appeared to serve no useful purpose.

15.

AP-5.11

Radiation monitoring system recirc spray cooler service

water outlet

a.

b.

C.

d.

e .

Entry condition 1: This entry condition was not written in the

same format as other AP entry conditions.

Step 6:

These actions were preceded by an asterisk instead of a

bullet, which was inconsistent with the WG.

Step 7:

These actions were preceded by an asterisk instead of a

bullet, which was inconsistent with the WG.

Attachment 1 step 1:

These actions were preceded by an asterisk

instead of a bullet, which was inconsistent with the WG.

Attachment 1 step 2:

This reference was preceded by an asterisk

instead of a bullet, wht~~ was inconsistent with the WG.

r

Appendix B

44

16.

AP-5.12

Radiation monitoring system reactor coolant letdown monitors

a.

General:

Asterisks were used throughout the procedure instead

of bullets.

17.

AP-5.13

Radiation monitoring system discharge tunnel

a.

Step 1 RNO:

This step referred to step 5 which re qui red the

monitor to be verified operable.

When the transition to step 5

was accomplished from the RNO column a PT was required to verify

the monitor operable.

When the same step was transitioned to in

the AER column a PT was not required.

b.

Step 2:

This step referred to closing valve HCV-LW-104A and B.

The method did not direct the operator to set the pot to zero.

There was no closed position on the pot.

c.

Step 2:

This action was preceded by an asterisk instead of a

bullet, which was inconsistent with the WG.

d.

Step 4:

These actions were preceded by an asterisk instead of a

bullet, which was inconsistent with the WG.

e.

Step 5:

Refer to comment for step 1 RNO.

f.

Step 6:

These actions were preceded by an asterisk instead of a

bullet, which was inconsistent with the WG.

g.

Attachment 1 step 1:

This reference was preceded by an asterisk

instead of a bullet, which was inconsistent with the WG.

h.

Attachment 1 step 2:

This reference was preceded by an asterisk

instead of a bullet, which was inconsistent with the WG.

18.

AP-5.14

Radiation monitoring system containment high alarm range

area

a.

User block:

The nomenclature in this block was inconsistent

with other APs.

b.

Step 6:

These actions were preceded by an asterisk instead of a

bullet, which was inconsistent with the WG.

c.

Step 7a:

These actions were preceded by an asterisk instead of

a bullet, which was inconsistent with the WG.

d.

Attachment 1 step 1: These actions were preceded by an asterisk

instead of a bullet, which was inconsistent with the WG.

e.

Attachment 1 step 2:

This reference was preceded by an asterisk

instead of a bullet, which was inconsistent with the WG.

Appendix 8

19.

'

45

AP-5.15

Radiation monitoring. system reactor containment area

monitors and CHRRM

a.

General: Asterisks were used throughout the procedure instead of

bullets.

20.

AP-5.16

RM system process vent monitor or process vent flow monitor

malfunction

a.

Step 2b RNO third and jforth bullets: These actions could only

be preformed locally. This was not specified.

b.

Step 4a RNO:

This step identified a transition to AP-5.24;

however, AP-5.24 did not list AP-5.16 as an entry condition.

c.

Attachme~t 1 step 1:

The substeps were preceded by asterisks,

which was inconsistent with the WG.

d.

Attachment 1 step 2:

The substeps were preceded by asterisks,

which was inco~sistent with the WG.

21.

AP-9.02

Loss of RCP seal cooling

a.

Entry Condition:

This

section did not list all entry

conditions.

b.

Step 8:

Prior to entry into this step there was no caution

about the maximum allowable cooldown rate of 1 degree F/minute.

c.

Step 12:

This step did not caution the operator to check seal

1 eakoff temperatures 1 ess than 235 degrees F and if not to

es tab 1 i sh a coo 1 down rate of 1 ess than or equa 1 to 1 degree

F/minute.

22.

AP-10.00 Station ~lackout

a.

Entry conditions: This section lacked specifics as to when this

procedure, instead of the EOPs, would be the proper procedure to

use in a loss of power casualty.

b. . Genera 1 comment:

The procedure did riot inc 1 ude any actions to

restore communications capabilities.

The procedure did not

mention the time sensitivity of some recovery actions and the

cross connect capabilities that could be used to mitigate the

adverse affects of this casualty.

Appendix B

46

c.

Step 4c:

The fact that the operation of the stub bus tie was a

local operation was not indicated in the procedure step.

d.

Step 9:

This step lacked the detail necessary to insure that

none of the actions necessary to carry out the step would be

overl ook.ed.

e.

f.

g.

h.

Step 11:

Step 15:

Step 16:

Step 18:

numbers.

remember

Same as step 9 above.

Same as step 9 above.

The undefined abbreviation

11TS

11 was used in this step.

This step referred to two Attachments by their

Their titles were not included to help the operators

how the attachments were used.

i.

Step 20:

The specific indication lights, that must be checked

on the mimic bus, were not included in the step to insure the

correct bus status was obtained.

j.

Step 21:

Same as step 20 above .

k..

Step 21 RNO:

The undefined abbreviation

11 RSSP was used in this

step.

1.

Step 23:

Same as step 20 above.

m.

Step 25:

Same as step 20 above.

n.

Steps 26a and c RNO:

The verb

11 verify

11 was used in these steps,

but no action statement was included to cover the situation when

the break.er was not found in the desired position.

o.

Step 26 RNO:

The local operations were not indicated in the

step as required.

p.

Step 28:

Same as step 20 above.

q.

Step 29:

Same as step 20 above.

r.

Step 31:

Same as step 20 above.

s.

Step 32 RNO:

Same as steps 26a and c RNO and step 26 RNO above.

t.

Step 33:

Same as step 26 RNO above.

u.

Step 36 RNO:

Same as steps 26a and c RNO and step 26 RNO above .

\\

Appendix B

47

v.

Attachment 3 Steps lA and B, Steps 2A and Band Steps 3A and B:

Same as step 20 above.

w.

Attachments 3 and 4:

Same as steps 26a and c RNO above.

x.

Attachment 4 Steps lA and B ~nd Steps 2A and B:

Same as step 20

above.

y.

Attachment 5:

This attachment was not referenced in the

p1ocedure and appeared to serve no useful purpose.

23.

AP 10.01

Loss of vital bus I

24.

25.

26.

27.

a.

General:

Asterisks were used in the procedure instead of

bullets.

b.

Step 3 RNO:

The old numbering scheme was used for the reactor

trip procedure.

c.

Step 21 Note:

The note was misleading in that it stated that

flow was lost, instead of flow

11 indication

11 was lost.

AP 10.-02

Loss of vital bus II

a.

General:

Same as AP 10.01 general comment.

b.

Step 3 RNO:

Same as AP 10.01 Step 3 RNO.

AP 10. 03

Loss of vital bus I II

a.

General:

Same as AP 10.01 general comment.

b.

Step 3 RNO:

Same as AP 10.01 Step 3 RNO.

AP 10.04

Loss of vi ta l bus IV

a.

General:

Same as AP 10. 01 general comment.

b.

Step 3 RNO:

Same as AP 10.01 Step 3 RNO.

AP-10.05

Loss of a semi-vital bus and AC distribution panel

a.

Entry conditions:

This section did not list the busses that

this procedure applied to and did not include the specific

conditions when this procedure, instead of the EOPs, should be

used to respond to the situation.

b.'

Step 8:

The local operation was not indicated in the step as

required.

Appendix 8

c.

48

Step 9:

The step lacked the detail necessary to insure that

none of the actions required to carry out the step would be

overlooked.

ct.

Step 10a:

Same as step 8 above.

e.

Step 10a:

The undefined abbreviation

11 SV8

11 was used.

f.

Step 11:

The title of the attachment was not included to help

the operators remember how the attachment was used.

g.

Attachment 1:

The SVBs were incorrectly indicated as SVBI and

SVB2 vice lSVBl and 2SV81.

h.

Attachment 4:

This a.ttachment was not referenced in the

procedure and appeared to serve no useful purpose.

28.

AP-10.07

Loss of DC power

a.

General :

Asterisks were used in the procedure in stead of

bullets.

b.

Step 1:

The operator indicated that he would be checking for

reactor trip breaker indication lights not lit, but the step

called for the reactor trip breaker to be open.

c.

Step 1:

The operator stated he would observe the valve indica-

tion not lit and the TDAFW pump running.

The step required the

operator to check the TDAFW pump steam supply valve open, but

the indicating light may not have power.

ct.

Step 2:

This step required the operator to verify the generator

output breaker open, but the indicating lights may not have

power.

Breaker position would have to be checked locally.

e.

Step 6d:

The procedure identified valve SOV-()-113A power

available and this valve designation did not exist on the

control board.

29.

AP-10.10

Loss of auto load shed

a.

General :

Asterisks were used in the procedure in stead of

bullets.

b.

Step 1: The instrumentation necessary to verify that two station

service buses were energized from one RSS transformer was

unclear to the operator.

\\

Appendix B

49

30.

AP-10.11

Partial loss of reserve station service

a.

Step 4:

This step required the verification of

11 RCS circula-

tion -

forced

11 *

The

RNO for this step did not involve the

attempt to start or restart a RCP,

but went directly to

AP-39.00, Natural Circulation of RCS or AP-27.00, Loss of Decay

Heat Removal.

b.

Step 6:

This step required the operator to

11 verify unit condi-

tions - stable

11 , without defining the normal parameters for loss

of reserve station service.

c.

Step 8:

This step required the operator to

11 check radiation

monitors -

normal

11 without specifying the specific monitors to

check.

d.

Step 8

RNO first through third asterisks:

These actions

were preceded by an asterisk instead of a bullet, which was

inconsistent with the WG.

e.

e.

Step 9 first through third asterisks:

preceded by

an

asterisk instead of a

inconsistent with the WG .

Step 10 first through third asterisks:

preceded by

an

asterisk instead of a

inconsistent with the WG.

These actions were

bull et, which was

These actions were

bull et, which was

f.

Attachment 2 step 2 first through forth asterisks:

These

statements were preceded by an asterisk, which was inconsistent

with the WG.

31.

AP-10.12

Partial loss of station service

a.

Step 2:

The verb

11verify

11 was used to* indicate that this step

should be accomplished, if possible.

This was not consistent

with the definition of

11 verify

11 in the WG.

b.

Step 6:

These actions were preceded by an *asterisk which was

inconsistent with the WG.

c.

Step 7:

Due to non-vi ta l nature of this step it was not

appropriate for inclusion in this AP.

ct.

St~p 7 first and second asterisks:

These actions were preceded

by an asterisk instead of a bullet, which was inconsistent with

the WG.

e .

Step 8:

Due to the non-vital nature of this step, it was not

appropriate for inclusio~, in this AP.

Appendix B

f.

50

Step 7 first through third asterisks:

preceded by an asterisk instead of a

inconsistent with the WG.

These actions were

bullet, which was

g.

Attachment 2. step 1:

This action was preceded by an asterisk,

which was inconsistent with the WG.

h.

Attachment 2 step 5:

This action was preceded by an asterisk,

which was inconsistent with the WG.

i.

Attachment 3 step l:

This action was preceded by an asterisk,

which was inconsistent with the WG.

j.

Attachment 3 step 2:

This action was preceded by an asterisk,

which was inconsistent with the WG.

32.

AP-12.00

Service water system abnormal conditions

a.

b.

C.

d.

e.

f.

Step 3a first and second hollow bullets:

This symbol was not

defined in the WG.

Step 3a

RNO:

This step was a local action, but was not

identified as such .

Step 3a first and second hollow bullets:

This symbol was not

defined in the WG.

Step 3a

RNO:

This step was a local action, but was not

identified as such.

Step 4 note first and second hollow bullets:

This symbol was

not defined in the WG.

Step 5a5 RNO:

This step required the operator to cross tie to

the unaffected units CHG pump SW system if both of the affected

units CHG pump SW pumps were air bound after only attempting to

vent the affected system one time.

Depending on the volume of

air in the system this could compound the problem by allowing

air to enter the unaffected units CHG pump SW system, poten-

tially air binding the CHG pump SW pumps on the unaffected unit.

g.

Step 6:

This step to read certain values on the ERF computer

did not have an RNO, although some set points were occasionally

not available, including the point selected by the team.

h.

Step 6 first and second asterisks: These actions were preceded

by an asterisk instead of a bullet, which was inconsistent with

the WG .

i .

Step 6 second asterisk first and second hollow bullets:

This

symbol was not defined in the WG.

Appendix 8

51

j.

Step 9 second asterisk:

The minimum required service water

inlet temperature for the co~trol room chiller, 85 degrees, did

not appear to be realistic.

The inlet temperature at the time

of the inspection was 58 degrees.

k.

Step 9 forth . asterisk:

This step addressed the IA system

without specifying the turbine building IA system.

1.

Step 11:

This step required that the operator check

II strainer

delta-P - normal

11 without identifying the appropriate parameters

to check.

m.

Step 12:

This step required that the operator check .suction

pressure -

normal" and

11discharge pressure -

normal" without

identifying the appropriate parameters to check.

n.

Step 121

RNO:

This step addressed the IA system with out

specifying the turbine building IA system.

o.

Step 16:

This step required the operator to "check vacuum

priming pump seal recirc temperature - normal

11 , but there was no

clear method for accomplishing this step .

p.

Step 17 first and second asterisks:

These actions were preceded

by an asterisk, which was inconsistent with the WG.

q.

Step 18 first and second asterisks: These actions were preceded

by an asterisk, which was inconsistent with the WG.

r.

Step 19 first through third asterisks:

These actions we.re

preceded by an asterisk, which was inconsistent with the WG.

s.

Attachment 1 step 1 first through fifth asterisks:

These

actions were prec~ded by an asterisk, which was inconsistent

with the WG.

t.

Attachment 1 step 2 first asterisk: This action was preceded by

an asterisk, which was inconsistent with the WG.

33.

AP-12.01

Loss of intake canal

a.

Step one first asterisk:

According to design calculation

ME-166,

the condenser waterboxes must be isolated within a

specific time (70 seconds) to prevent loss of the intake canal

level (ultimate heat sink) to less that that required to handle

a LOCA.

ME-166 also required other actions to be completed

within certain times, such as isolation of many service water

flowpaths within one hour.

These times were not specified in

this procedure.

Also, operators were not aware of these time

requirements.

\\

Appendix B

52

b.

Step 1 second asteri sl<.:

This step required the CW pumps to be

started from the MRC.

With the normal equipment line up, the CW

pump mode switches were in local. With the switches in local it

was only possible to start the pumps locally.

This procedure

step and the associated RNO both required normal power to be

available to start the circ pumps.

If this procedure was

entered as a transition from AP-10.00, neither the AER nor the

RNO could be performed.

c.

Step 3:

This step directed the operator to go to step 22 if the

canal level was stable or increasing.

When directed to step 22,

the operator would proceed to step 23 which directed him to

verify canal level was increasing. If canal level was stable,

step 23 RNO was then applicable. This directed the operator to

continue efforts to restore level.

These efforts were not

applicable since any efforts to restore level were bypassed in

the transition from step 3 to step 22.

Additionally, there were

no procedural steps that would have caused the canal at stable

level to increase.

d.

Step 5:

These actions were preceded by an asterisk instead of a

bullet, which was inconsistent with the WG.

e.

Step 6:

This action contained one. substep instead of being

written as a single step, which was inconsistent with the WG.

f.

Step 10a: This step required the operators to start

able ESW pumps.

Design calculation ME-166 required

pumps be started within a certain time (two hours).

was not specified in the procedure.

all avail-

that these

This time

g.

Step 10b first and second ho 11 ow bull et:

This action was

required to .be performed within a specific time by design

calculation ME-166.

This time was

not specified in the

procedure.

h.

Step 10 first and second hollow bullet:

This symbol was

undefined in the WG.

i.

Step 11 first through eighth hollow bullets: These symbols were

undefined in the WG.

Additionally, the place keeping markers

following each hollow bullet were not in accordance with the WG.

j.

Step 13:

These actions were preceded by an asterisk instead of

a bullet, which was inconsistent with the WG.

k.

Step 15 table left column first entry:

This column was not

clear to the interviewed operators in that the definition of at

power was different than the definition giving during general

training and the definit{?n used in other procedures .

Appendix B

53

1.

Step 17 table left column first entry:

This column was not

clear to the interviewed operators in that the definition of at

power was different than the definition giving during general

training and the definition used in other procedures.

m.

Step 17 table right column case 1 second entry:

This step was

not identified as a continuous action step and had no method of

place keeping to remind the operator of required actions 24

hours later.

This step required that the CCW Hxs with service

water be throttled to a SW dP of between 0.75 and 1.00 inches

per heat exchanger.

This action was required to be performed

within this time by design calculation ME-166.

This step did

not have a method to advise the operator to perform it at the

required time.

n.

Step 22:

These actions were preceded by an asterisk instead of

a bullet, which was inconsistent with the WG.

o.

Step 24

RNO:

This step was not necessary based upon the

accepted operator definition of the verb

11verify

11 as used in

step 24.

p .

q.

Step 26i These actions were preceded by an asterisk instead of

a bullet, which was inconsistent with the WG.

Attachment 2 step 3d5:

level intake structure.

The step referred to a G bus in the low

There was no bus with this designation.

r.

Attachment 2 step 4b:

The equipment required to perform this

step was not available at the low level intake structure, nor

was it transported to the low level intake structure when the

operator went to the structure.

s.

Attachment 2 step 5b:

This step required local river water

level to be checked without a quantitative method of accom-

plishing the task.

34.

AP-15.00

Loss of component cooling

a.

Entry conditions:

There were very few conditions leading up to

the loss of component cooling in th~s section of the procedure.

It did not include the related alarm response procedures.

b.

Step 1:

This appeared to be an immediate action step, but it

was not designated as such in the procedure.

c.

Step 3:

This step lacked the detail necessary to insure that

none of the actions necessary to carry out the step would be

overlooked .

Appendix B

54

d.

Step 7:

Same as step 3 above.

e

Step 8:

Same as step 3 above.

f.

Step 12:

Same as step 3 above.

g.

Attachment 3:

This attachment was not referenced in the

procedure and appeared to serve no useful purpose.

35.

AP-16.00

Excessive RCS leakage

a.

b:

C.

d.

e.

f.

Entry conditions:

There was no transit.ion step from ARP-B-A-3,

CTMT SUMP HI LVL, to AP-16.00.

Step 4:

This step had a misplaced continuous action step

asterisk.

Step 6 RNO:

This step failed to direct a reactor trip prior to

SI.

Step 10:

This step directed the notification of chemistry that

all primary sampling was secured. The operator stated that he

would dispatch an operator to verify a 11 sarnp 1 i ng va 1 ves were

closed. This step did not direct this action.

Step 18b:

This step described HCV-1137 as the excess letdown

HCV, while step 18f described HCV-1137 as the flow control valve

Step 22

RNO:

This step failed to underline WHEN/THEN and

IF/THEN in accordance with the WG.

g.

Step 23:

This step incorrectly directed checking PDT influent

vice PDT influent level.

36.

AP-17.00

Auto start failure of EOG

a.

b.

C.

d.

General:

Asterisks were used throughout the procedure instead

of bullets.

Step 1:

The operators had difficulty in finding the a 1 arms

which were located on Alarm Panels BA2, CG6, and VSP-C5.

Step 14:

This step directed the operator to place the selector

switch in remote but it was labelled

11 auto.

11

Step 10 RNO:

A hose was not readily available to connect the

wall drain tank and the base tank .

\\

Appendix B

55

37.

AP-17.01

Emergency diesel generator fails to accept electrical load

a.

General:

Asterisks were used throughout the procedure instead

of bullets.

b.

Step 2: This step did not identify that local verification was

required.

38.

AP-20.00

Main control room inaccessibility

a.

Step 4:

This step required the evacuation of the control room;

however, it failed to require the operators to bring APP R key

ring, FCA procedures, and steam tables which were required for

the successful completion of subsequent procedure steps.

39.

AP-21.00

Loss of main feed flow

a.

Step 1 RNO:

After a reactor trip, the operator was transitioned

to EP-1, and not to E-0.

b.

Step 9:

This step required the operator to verify SG levels

trending to

11 NOL

11 *

An operator stated that NOL meant normal

operating level.

This was inconsistent with the WG, which

defined NOL as normal operating limit.

c.

Attachment 1 step 1 fifth bullet:

The word across was spelled

11cross

11

Also, asterisks were used in place of bullets.

40.

AP-21.01

Response to AFW check valve backleakage

a.

Step 1:

The use of verify in this step was inconsistent wi-th

operator training.

b.

Step 2:

This action was preceded by an asterisk, which was

inconsistent with the WG.

c.

Step 3:

These actions were preceded by an asterisk, which was

inconsistent with the WG.

d.

Step 4c:

This step was not clear on how many valves could be

shut without SNSOC approval.

The operators interviewed answered

zero, one, and three when asked to interpret the number of

valves that could be closed before SNSOC approval was required.

e.

Step 5:

These actions were preceded by an asterisk, which was

inconsistent with the WG.

f.

Step 5 second asterisk: This step was not preceded by a caution

to describe the personnel danger involved in opening this vent -

exposure to steam.

Appendix B

56

g.

Step 6:

These actions were preceded by an asterisk, which was

inconsistent with the WG.

h.

Step 6 second asterisk: This step was not preceded by a caution

to describe the personnel danger involved in opening this vent

exposure to steam.

i.

Step 9:

This step required the AFW pump to be returned to

operable status; however, it had not been declared inoperable.

j.

Step 10 first through third asterisks:

These actions were

preceded by

an asterisk instead of a bullet, which was

inconsistent with the WG.

k.

Attachment 1 AFW header temperature:

This step did not clearly

define the expected operator actions at 165, 185 and 200

degrees.

l.

Attachment 1 required surveillance forth unnumbered step:

m *

The operators gave conflicting interpretations of the statement

11 No additional logging requirements 11 *

Attachment 2 step 6:

This step required that the AFW pump be

cooled, but did not specify the required final temperature of

the AFW pump.

41.

AP-22.00

Fuel handling abnormal conditions

a.

Step 3:

These actions were preceded by an asterisk instead of a

bullet, which was inconsistent with the WG.

b.

Step Sb:

This procedure step required that valves VS-103-A and

VS-103-B be placed in the closed position.

The valves had no

indicated closed position.

c.

Steps 10 and 11:

These steps would have to be performed in the

reverse order if t~e affected equipment was needed to put fuel

in the safe condition.

d.

Step 13:

These actions were preceded by an asterisk instead of

a bullet, which was inconsistent with the WG.

42.

AP-22.01

Loss of refueling cavity level

a.

Step 3a RNO first and second bul 1 ets:

These bul 1 ets aligned

alternate suction. If the first bullet "LHSI suction from CNTMT

sump

11 was aligned then only step 3b applied and not the step 3b

RNO.

If the second bullet "RWST x-tie from unaffected Unit.

to CHG/SI pump suction" was aligned only step 3b

RNO was

applicable.

These ste~ were written as equally acceptable

steps, but could not be u'sed that way in the AER and RNO format

as they were written.

Appendix 8

57

b.

Step 3c and step 3c RNO:

These steps required the operator to

perform the same step in the AER and RNO column.

c.

Step 7: This step required the evacuation of containment, which

based on current operator training involved sealing of the

containment. However, steps 8, 9, and 11 required some opera-

tions to be accomplished in containment.

d.

Step 10:

These actions were preceded by an asterisk instead of

a bullet, which was inconsistent with the WG.

e.

Step 11:

This step required the determination that cavity

1 eve 1 was restored; however, there was no direct method for

determining the required level.

f.

Step 12:

These actions were preceded by an asterisk instead of

a bullet, which was inconsistent with the WG.

g.

Attachment 1 step 1:

This reference was preceded by an asterisk

instead of a bullet, which was inconsistent with the WG.

h.

Attachment 1 step 2:

This refer~nce was preceded by an asterisk

instead of a bullet, which was inconsistent with the WG.

43.

AP-22.02

Loss of spent fuel pit level

a.

Genera 1:

Asterisks were used in the procedure instead of

bullets.

44.

AP-24.00

Minor SG tube leakage

a.

Entry condition 1:

This entry condition was an increase in the

activity on the condenser air ejector radiation monitor.

However, the re 1 ated annunciator response procedure did not

direct the operator to AP-24.00.

b.

Entry condition 2:

This entry condition was an increase in the

activity on the steam generator blowdown radiation monitor.

However, control room records indicated that the alert and alarm

setpoints on the blowdown radiation monitors were set at more

that two decades above the current meter readings~

Meter

RI-SS112

RI-SS113

Reading

8.0xlOE2

l.lxl0E2

Alert

1. 2xlOE5

1. 2xlOE5

Al arm

2.4xlOES

2. 4xlOES

Appendix B

58

The licensee's procedures stated that, for process monitors, the

alert setpoint should be two to five times the background

reading, and the alarm setpoint should be 10 to 15 times the

background reading.

The control room records stated that these

alert

and

alarm

setpoints

had

last been

adjusted

on

July 11, 1978, over 11 years ago.

Since 1978, the steam

generators had been replaced and other events had caused the

background reading of these blowdown radiation monitors to vary.

The licensee stated that process radiation monitor setpoints were

not included in a periodic maintenance program.

Operators looked

at the blowdown radiation monitor setpoints daily, but did not

check that they were set at the appropriate levels.

With the

setpoints set so far above background, the alarms would not

function to alert the operator in support the APs or EOPs.

Prior to the end of this fnspection, the licensee stated that the

blowdown radiation monitor setpoints had been corrected and they

were reviewing the initiation of a periodic maintenance program.

c.

Step 1 RNO:

After a reactor trip, this step directed the

operator to go to EP-1.00, and not E-0.

d.

e.

Step 3:

The list of instruments to be used to identify the

affected SG did not include the steam line radiation monitors .

Step 4 fourth bullet:

The applicable valve numbers were not

included for locally isolating the affected SG supply to the

turbine driven AFW pump.

Also, asterisks were used in place of

bullets.

45.

AP-27.00

Loss of decay heat removal capability

a.

Step 3 RNO:

The verb

11 verify

11 was used in the step, but no

action statement was included to cover the situation when the

valve was not found in the desired position.

b.

Attachment 2:

This attachment was not referenced in the

procedure and appeared to serve no useful purpose.

46.

AP-31.00

Increasing or decreasing RCS/PRZR pressure

a.

Steps 4 and 5:

The location of these steps in the middle of the

procedure caused unnecessary transitions.

b.

Step Sb:

This step required the operator to return all controls

to

11 NORMAL

11 *

However, none of the related contra ls had a

position labeled NORMAL.

\\.

..

Appendix B

59

C.

Step 7 RNO:

After a reactor trip, this step directed the

operator to EP-1.00, and not E-0.

47.

AP-36.00

Control room security

a.

Step 1:

This step failed to address obtaining the padlocks

required to lock the doors.

b.

Step 6: * This step contained an improperly placed comment in the

RNO column.

c.

Step 6 RNO:

This step fa i 1 ed to direct

11Use Base Radi 0

11 as done

in the step 3 RNO.

d.

Step 4:

This step failed to address the conduct of* a search of

the MCR.

48.

AP-37.00

Seismic event

a.

General:

Asterisks were used in the procedure instead of

bullets.

49.

AP-37.01

Abnormal environmental conditions

a.

Step 2:

This step lacked the detail necessary to insure that

all of the areas containing components necessary for safe

operation were listed and placed under appropriate scrutiny to

provide for early detection of potential flooding conditions.

Contingency actions were not developed, in advance, to combat

the most likely flooding situations that could occur.

b.

Step 3 note: The word

11 note

11 was not underlined as required in

the WG.

c.

Step 4 caution:

The word

11 caut i on

11

was not underlined as

required in the WG.

d.

Step 4 note:

Same as step 3 note above.

e.

Step 8 note:

Same as step 3 note above.

f.

Step 9:

This step also covered the situation of either unit on

RHR and did not reflect that fact.

g.

Step 11 caution:

Same as step 4 caution.

h.

Step 12a:

This step referred to an area as *

11 1ow level ,

11 but it

was not clearly indicated as a location at the Intake Structure .

.,

Appendix B

60

i.

Step 17:

This step appeared to be a simple step, but it was in

fact a very involved task. Detailed information to help the

operators perform the step was not included.

j.

Step 21:

The undefined abbreviation "ISO" was used in this

step.

k.

Attachment 1 Step 2:

The step lacked the detail necessary to

insure that none of the actions necessary to carry out the step

would be overlooked.

1.

Attachment 1 Step 3:

The step 1 acked the addi ti ona 1 guidance

necessary to properly carry out the intent of the step.

m.

Attachment 1 Steps 4 and 5:

Same as Attachment 1 step 3 above.

n.

Attachment 1 Step 8: The undefined abbreviation

11 RSD

11 was used

in this step.

o.

Attachment 3 Step 12:

The seventh and ninth door on this list

had the same title. Apparently one of the titles was incorrect

or one of the doors was incorrectly listed twice.

p.

Attachment 4 Step 1:

The verb

11 veri fy" was used in the step,

but no action statement was included to cover the situation when

the equipment/valve was not found in the desired position.

q.

Attachment 4 Steps 2, 3 and 4:

Same as Attachment 4 step 1

above.

r.

Attachment 5 Step 10:

Same as step 21 above.

s.

Attachment 7:

This Attachment was not referenced in the

procedure and appeared to serve no useful purpose.

50.

AP-39.00

Natural circulation

a.

Entry conditions:

The one condition listed was very general ih

nature and did not clearly define the conditions when this

procedure vice an EOP would be used.

Two Abnormal Procedures,

AP-37.01 Step 16 and AP 27.00 Step 19, directed the operator to

this procedure, but were not listed as entry conditions.

b.

Step 5:

The words "NARROW RANGE" were missing after the word

"ALL".

C.

Attachment 1 Second bullet after IMPENDING:

The delta

11 P

11 at

the end of the sentence was incorrect -

delta: "T" was needed .

\\

Appendix B

61

d.

Attachment 2:

This Attachment was not referenced in the

procedure and appeared to serve no useful purpose.

51.

AP-43.00

Loss of reactor coolant flow

a.

Step 3:

This step was inconsistent with the ES-0.1 step 8b RNO.

b.

Step 5:

This step failed to reference the procedure( s) to be

used for performance of unit shutdown.

52.

AP-48.00

Fire protection - operations response

a.

Step 1:

Performance of this step re qui red the ga i-tron i cs

system to be operable.

An RNO step to call out the fire brigade

without gai-tronics available was not included.

b.

Step le:

To be consistent with operator training this step

would have been repeated.

c.

Step 6:

The use of

11 check

11 was not appropriate in this step in

that all non-affected areas would be checked for certain area

fires.

d.

Step 6:

These actions were preceded by an asterisk instead of a

bullet, which was inconsistent with.the WG.

e.

Step 10:

This step only applied. when the RNOs in steps 4 or 5

were applicable.

f.

Step 14:

These actions were preceded by an asterisk instead of

a bullet, which was inconsistent with the WG.

53.

AP-49.00

Loss of domestic water

a.

Entry conditions:

Alarms or other system conditions that would

indicate a possible loss of domestic water were not listed in

this section of the procedure.

IV. FCA comments

1.

FCA-1.00 Attachment 2 Local operation of EOG 1 and 2. *

a.

General: Asterisks were used in the procedure instead of

bullets.

b.

Caution:

The use of a scribe mark for a control setting

appeared to be inappropriate.

2.

FCA-1. 00 Attachment 3 #3

EOG alternate fast start

No comments.

Appendix 8

62

3.

FCA-1.00 Attachment 4 Individual transfer of components to auxiliary

shutdown panels

a.

Parts A and B:

These parts incorrectly identified the transfer

switch position AUX PNL.

All 34 local switches were labeled

AUX P.

4.

FCA-1.00 Attachment 6 Communications

a.

Part 8:

There was no step at the *top of this part of the

procedure to direct the operator, who would man the J8 COMM 7

panel, to bring a list of Beeper assignments.

The operator

would need the list to page people from the J8 COMM 7 panel.

b.

General comment:

The security department had an emergency

diesel generator that automati~ally started on loss of AC power

and energized the security portable radio repeaters.

However,

the licensee had no provision for. operators to take advantage of

the security portable radios *to en.able them to have communica-

tions needed to implement EOPs.

C.

General comment:

A sound powered telephone system existed in

the plant and was used by the Instrumentation and Co.ntrol

Department.

No plans or provisions had been implemented for

operators to use this system during pl ant casualties such as

loss of AC power, when communication problems were known to

exist.

5.

FCA-1.00 Attachment 78

Establishing charging pump cross connect

a.

Genera 1 :

Asterisks were used in the procedure instead of

bullets.

b.

C.

d.

e.

Step 4:

This step was no longer necessary because *the valves

were no longer locked.

Step 3:

Valves 21168 and 21150 were not clearly labelled to

assist the operator in quickly locating them.

Step 6:

Valve l-CH-729 was not clearly labelled and the

operator had difficulty finding it. Also it was in a contami-

nation overhead area; the operator needed to find a ladder, and

then it was still hard to reach the valve for operation.

Steps 5 and 7:

Valve l-CH-728 was difficult to operate because

of piping interfe.rence .

\\

Appendix B

63

6.

FCA-1.00 Attachment 8 Alternate steam release

No comments.

7.

FCA-1.00 Attachment 12A

Establishing RCS letdown

a.

Notes Page 1:

All the provisions of these notes were not

incorporated into the body of the two parts of this procedure~

unlike the notes in the EOPs.

8.

FCA-1.00 Attachment 18

Cross connecting emergency busses

No comments.

9.

FCA-1.01

Limiting MCR fire

a.

Step 6:

This step required the evacuation of the control room;

however, it failed to require the operators to bring the steam

t.ables. Additionally, the procedure required only one APP R Key

ring, when two key rings were required to accomplish thi*s

procedure if both units* remote shutdown panels were manned.

b.

Step 10b:

This step required that the MSTVs be pl aced in the

disable position. The switch did not have a disable position -

the appropriate switch position was labeled 11 FIRE EMERG. CLOSE"

c.

Step 10c: This step required that key switches be placed in the

disable position. The switch did not have a disable position -

the.appropriate switch position was labeled 11 EMERG CLOSE 11

d.

Step 16a:

A non-permanent adhesive label was used to indicate

valve position on the HSP.

e.

Step 19:

A non-permanent adhesive label was used to indicate

valve position for the PRZR heater group A and B transfer

switches on the HSP.

f.

Steps 21a, b, and c:

The verb

11 verify

11 was used to indicate

that the first two steps should be accomplished, if possible.

The third step required the operator to verify the same actions

that had been accomplished in the previous steps.

The. use of

the verb verify in these steps was inconsistent.

g.

Step 22:

The controls of the AFW pumps on the remote shutdown

panel were not in consistent order.

The upper level had the

controls arranged

11C11 ,

11A

11 ,

118

11 ,

and

11C

11 *

The lower level

controls were arranged

118

11 and

11A

11 :

h ..

Step 25b first bullet: The procedure step required one SW pump

control switch in hand and one in auto.

The switches were

labeled CHG PP SW PP SW-P-lOA and CHG PP SW PP SW-P-108 .

. "*"* .. * .

--

. *'~

\\ ..... ;*-* ... .- .

Appendix B

64

i.

Step 27:

Steam tables were required to perform this step but

were not available.

j.

Step 33 note 1:

This note included a list of 10 action steps,

which was contrary to the. WG.

These steps were not properly

prioritized and also were not separately included in procedure

steps.

k.

Step 33 note 2:

The prioritized order for reactor coolant pumps

was inconsistent with the priority in other procedures.

1.

Step 33:

The OP referenced for establishing conditions to

start a RCP, OP-5, could not be accomplished by operators when

attempted from outside the control room.

There was no procedure

for accomplishing this function from outside the control room.

m.

n.

Step 54:

This step, which put the overpressure mitigation

system in service, appeared to be impractical since the PORVs

were di sab 1 ed in step 10a for RCS i nte"grity.

If operators

attempted to place the overpressure mitigation system in service

in the normal manner, they would receive indications that it was

in service, when in fact it was not because the PORVs were

disabled .

Various Steps:

The name plate was missing from steam generator

pressure channel Bon the remote shut down panel .

\\

APPENDIX C

WRITER'S GUIDE COMMENTS

This appendix contains writer's guide (WG) comments and observations. Unless

specifically stated, these comments were not regulatory requirements.

However,*

the licensee acknowledged that the factual content of each of these comments

was correct as st_ated.

The 1 i censee agreed to eva 1 uate each comment, to take

the appropriate action, and to document that action.

These items will be

reviewed during a future NRC inspection.

L Inadequacies in the Writer's Guide

The writer's guide did not thoroughly address each aspect of the

procedures nor did it define restrictively the methods designated for use

in order to assure consistency within and between procedures and to *retain

that consistency over time and through personnel changes.

The following

weaknesses led to problems and inconsistencies in the EOPs or allowed for

future inconsistencies in the revision or development process:

1.

Section 6.4.8(a), Transitions,. did not define the use "Do" and

"Continue 11 as used in transitions, however, these terms were used

in numerous cases to direct transitions.

These terms were also

used inconsistently, and consequently they were used both when a

restricted set of steps or substeps were to be completed and also

when the procedure was correctly performed without such restrictions.

2.

Section 6.4.8(c), Referencing, failed to clearly restrict the terms

which were acceptab 1 e for use in referencing other procedures.

Consequently several referencing terms (e.g., IAW) were identified

in the procedures which were not identified* in the guidance on

referencing.

3.

Section 6.4.8 of the writer's guide failed to state if the procedure

name was required in addition to procedure number when procedures

were identified in branching or referencing.

4.

Section 6.4.8(c), Referencing, stated that specific steps of supple-

ment,al procedures should be considered for incorporation into the

original procedure instead of referencing. The writer's guide failed

to provide restrictive criteria for consideration.

5.

Section 6.4.8(a), Transitions, stated:

"If steps that are to be

repeated are not lengthy, then consider repeating the information and

not using the transition." The writer's guide did not establish the

criteria for this decision and therefore was nci~restrictive.

6.

Section 6.4.4 stated:

"Do not include actions within cautions.i' In

practice this guidance was. not fo 11 owed and numerous in stances of

action statements within caut i ans were i dent ifi ed.

Operators were

trained to expect action steps to be numbered and located in sequence

in the AER and RNO columns of the procedure.

Actions that were

located in a caut{on or note were likely to be missed due to operator

expectations about'how the procedures worked.

" ..... ,

.*.**.***

Appendix C

2

7.

The writer 1 s guide stated:

11A step identified in the Westinghouse

ERG background as a Continuous Action Step should be identified by an

asterisk to the left of the step number, unless the procedure text

clearly indicates that it is a continuous action by using continuous

action verbs (e.g., Maintain, Monitor), or is specified in a Note or

a Caution.

11

The team had several concerns with this statement:

(1) The use of the term

11 should

11 was nonrestrictive.

(2) Use of

asterisks to identify Continuous Action Steps helped ensure that

these steps were not overlooked, but this advantage was lost when

steps with continuous action verbs were not marked with an asterisk.

(3) Insufficient guidance was provided as to whether placement of

asterisks was only allowed on high level steps, or was acceptable

for substeps and in the RNO column.

(4) The definition suggested

that the continuous action was impJied in notes and cautions. This

definition appeared to contradict section 6.4.4 of the writer 1 s

guide which* stated that notes and cautions shall not contain action

steps. (5) The use of WHEN THEN logic terms indicated a continuous

action and were not addressed as such in the writer 1 s guide.

8.

Continuous Action Steps were defined as

11 performed any time after

they are presented or are steps that require continuous monitoring

before an action can be accomplished

11 *

This definition included

non-sequential steps_ in the definition of Continuous Action Steps and

could result in confusion and difficulty in procedure control.

9.

Section 6.3.4 stated that equipment mark numbers should be included

as substeps when needed for clarification, the noun name and equip-

ment mark numbers should be used when i dent ifyi ng 1 oca 1 equipment,

and a reference to a piece of equipment should be used consistently

throughout the procedures. The use of the term

11 should

11 rather than

11 shall

11 implied that there were criteria for noncompliance with this

guidance.

The writer 1 s guide failed to state that criteria.

10.

Section 6.4 provided direction for writing action steps.

No guidance

was provided for acceptabi 1 i ty and/or format for action substeps

under high level CHECK steps.

11.

Section 6.4.2 of th~ writer 1 s guide failed to address a method for

i dent ifyi ng an order of preference for alternative actions when

alternative actions were listed in a step.

12.

The writer I s guide stated, II_As a genera 1 rule, branching to other

procedures should take place from the RNO column.

The writer 1 s guide

failed to restrictively define the criteria for when branching to

other procedures would be acceptable in the AER column.

13.

The writer

1s guide stated that

11 an underline space shall bi provided

at the high-level step for a check mark to signify the action of the

step has been completed.

11

This guidance failed to consider place

keeping for portions of proce~ures which were repeated.

, .. -.*,

  • .**.**

Appendix C

3

14.

The writer 1 s guide failed to include, in the list of parentheses

usage, the use of parenthesis around the letter

11 s

11 at the end of a

word to indicate that the singular or plural from of the word may

apply.

15.

Section 6.4.4 stated that a caution may be repeated at any time

throughout the procedure but failed to define the criteria for

caution repetition.

16.

Section 6.2.2 stated that

11 the instruction pages shall have a border

on all sides of the page

11 but did not define the size of the border.

II. Deviations from the EDP writer 1 s guide.

A sample of the EOPs was evaluated for deviations from the Surry writer 1 s

guide. Types of deviations noted were characterized in this section and

accompanied by a list of examples of the specific deviations.

Note that

some steps contained more than one deviation.

1.

The following steps used terms for transitions between steps within

in a procedure, or terms for branching or references to other

procedures/references in a manner not specified by the WG.

E-3, Step 35a RNO

E-3, Step 38a2a RNO

E-3, Step 39 fifth bullet

E-3, Stop 8

E-3, Step 31a RNO

FR-C.2, Step 13b RNO

FR-C.2, Step 17 RNO

FR-Z.l, Step 5

FR-Z.l, Step 8a & c RNO

FR-Z.l, Step 9al RNO

FR-Z.l, Step 9b

FR-Z.l, Step 10a2 RNO

FR-Z.l, Step 13

ES-1.2, Step 3b RNO

ES-1.2, Step 13d

ES-1.2, Step 19al RNO

ES-1.2, Step 22a

ES-1.2, Step 24c RNO

ES-1.4, Step 5

2.

The fol lowing steps contained a reference to another procedure but

did not include a reference term.

E-3, Step 34b

ES-1.2, Step 25b

\\

.. ,

Appendix C

4

3.

The following step used words with a meaning important to the action

that were not defined in the WG.

E-3

Step 15a

4.

The following steps contained one or more of the following violations

of the WG: (1) conditional or continuous actions in cautions or

notes, (2) references or transitions in cautions or notes, (3) no

statement of consequences in a caution, (4) a caution in a note.

E-3, Step 3 caution

E-3, Step 4 caution

E-3, Step 5 caution

E-3, Step 12 caution

E-3, Step 15 note

E-3, Step 33 caution

FR-C.2, Step 1 caution

FR-Z.l, Step 1 caution

FR-Z.l, Step 7 caution

FR-Z.l, Step 8 note

ES-1. 2, Step 1 caution

ES-1.2, Step 6 caution

ES-1. 2, Step 8 note

ES-1.4, Step 2 caution

5.

The following steps used asterisks in a manner inconsistent with the

WG.

E-3, Entry conditions

E-3, Steps 3,4 & 7

ECA-1.2, Entry conditions

ES-1.2, Entry conditions

ES-1.4, Entry conditions

6.

The

following

steps used punctuation/underlining in a manner

inconsistent with the WG.

E-3, Continuous action page heading

ECA-1.2, Step lb & c

ECA-1.2, Step 2a,d, & g

ECA-1.2, Step 2 continued

7.

The following step used an acronym that did not appear in the WG

acronym list.

8.

E-3, Step 41 seventh bullet

The following caution used a caution at the bottom of a page when

most of the related steps were on the following page in violation of

WG direction.

\\

FR-C.2, Step 14 caution

. .,.. . . . ..

~ *. : - .. ,. .

APPENDIX D

NOMENCLATURE

This Appendix contains basic nomenclature weaknesses.

For example, instances

where writer's guide application to the EDP would cause the reader to expect an

exact nomenclature match with component labeling, yet there was no match.

It

also includes. instances where a complete match was neither required nor found

and the mismatch or lack of label was sufficient to cause concern.

In addi-

tion, inadequate labeling methods such a use of dymotape or hand written labels

was noted.

The licensee agreed to evaluate each item and make the appropriate.

changes.

These items will be reviewed during a future NRC inspection~

Procedure

FCA-1. 00

FCA-1.01

Step/pg.

part A

part B

10a

19

EDP nomenclature

1-FW-P-3A

1-FW-P-3B

1-CH-P-lA

1-CH-P-lC.

1-CH-P-lB

1-CH-P-lC

2-FW-P-3A

2-FW-P-3B

2-CH-P-lA

2-CH-P-lC

2-CH-P-lB

2-CH-P-lC

PCV-( )455C

LCV-()460A

PCV-()456

HCV-() 137

PRZR HTR

11A

11 BANK

-. :**. .

~ ..

Component nomenclature

STM GEN AUX FD PP3A

STM GEN AUX FD PP

11 3B

11

CHARGING pp

II iA"

CHARGING PP

11 lC

11

CHARGING PP

11 18

11

CHARGING PP lC

CUB. 25H4 AUX SiEAM

GEN. FD PUMP A

CUB. 25J4 AUX STEAM

GEN. FD PUMP B

  • CUB. 25HS CHARGING

pp A

CUB. 25H6 CHARGING

pp C

CUB. 25JS CHARGING PPB

CUB. 25J2 CHARGING PPC

P~ESS RELEIF VV 1455C

HI PRESS LETDOWN STOP

VV 1460A

PRESS RELEIF VV 1456C

EXCESS. LETDOWN HEAT

EXCHANGER FLOW 1137

PRZR HEATER GROUP A

.... * * .. **:** -*::;,, .,

  • -'

Appendix D

2

E-3

4

lbl-343

181-3-43

PRZR HTR 11811 BANK

PRZR HEATER GROUP E

FR-H.4

2c RNO

TCV-MS-205A

2MS-TCV-205A

TCV-MS-205B

2MS-TCV-205B

TCV-MS-105A

2MS-TCV-105A

TCV-MS-1058

lMS-TCV-1058

ECA-2.1

28b

MOV-11158

MOV-LCV-11158

MOV-1115C

MOV-LCV-1115C

MOV-11150

MOV-LCV-11150

MOV-1115E

MOV-LCV-1115E

37

MOV-MS-lOOA

MOV-SD-lOOA

MOV-MS-1008

MOV-S0-1008

MOV-MS-lOOC

MOV-SO-lOOC

MOV-MS-1000

MOV-SD-1000

ES-1. 3

4bl

Phase 1 Status

Status

4cl

Phase 2 Status

Status

ES-0.2

7b RNO

SG PORVs

Atmos Stm Dump VVs

Att. IA

P-250 analog

Process computer

trend recorders

trend recorders

ES-3 .1

Att. IA

P-250 analog

Process computer

trend recorders

trend recorders

ECA-3.1

5g

Caustic supply

refuel WTR chem add

valves

TK outlt VV a and b

E-1

la

HHsi to cold leg

Cold Leg HHSI line flow

Sa

PRZR PORV block

Relief Line

valves

isolation vvs

13c

caustic sup~,ly

Refuel WTR CHEM ADD

valves

TANK OUTLT vvs

. . .. ~ : *~ . . . . ., . . . ' .

-*

Appendix D

ES-1. l

ECA-0.l

ECA-3.3

FR-H.l

AP-5.08

. "*-. *< . ~*--:~ . ;

29b

la

2b

2c

13b

16b

16c

15d

21

1

1

7b

7e

3a

3b

3c

3c

9

3

FW isolation reset

RCP seal injection

isolation valve

Safeguards area

exhaust fan

CROM fans

RCP seal return

valve

CHG pump VCT

suction valves

CHG pump RWST

suction valves

RWST crosstie

1st PT Extraction

steam MOV

Turbine drain

valves

Reheater vents

Permissive Status

light C-21

Permissive Status

light F-1

Purge supply and

exhaust valves

Purge supply fans

Instrument Air

valves

AOV-IA-( )03

Air recirc fans

\\

STM GENS-BYP FW CONT

RCP seal water

injection line

isolation valve

l-VS-F-40A/408

CONT ROD CLG 480v

fans

RCP seal LK OFF

return OTSD Trip vv

CHG pump SUCT FROM

VCT !SOL vvs

CHG PUMP SUCT FROM

RWST ISOL vvs

RWST SI XTIE

1st PT Heater ES

ISOL vv

Turbine INLT & CROSS

UNDER ORN vvs

Reheater ORN vents

RCVR ISOL vvs

SI BLOCKED PRZ

LO PRESS

LOT AVE SI BLOCKED

STM FLOW & PRESS

RX CTMT valves

CTMT fans

CTMT IA COMP INSIDE

CTMT SUCT vvs

SOV-IA-( )03

CTMT AIR recirc fans

~. :a*,. -..... ," ...... .

  • '*,.
    ;
~ ~.... . .

..*** :* " .,

. : .* .. _ ...... -.

,. *.' '*'* ~--..

Appendix D

4

AP-10.00

AP-37.01

AP-16.00

AP-36.00

E-0

ES-0.1

Att. 1

12b

Att.5

step 6

step 8

18d

1

2b

5

9

19

35a RNO

120 RNO

Charging pump CCW

pump

Control room

chillers

Control room AHUs

ESGR AHUs

Shroud cooling

fans*

SW Supply MOVs

RCP Oil Cooler

Thermal Barrier

loop drain valve

MRC To Annex

Unit 1 exit to

Stairwell

Unit 2 exit to

Stai rwe 11

PERM

FEED REG valves

CHG pump CC pump

reactor banks

Shroud cooling fans

bypass interlock*

switch

BYP

Charging pump CLG

WTR pump

REL & CONT RM WTR

CLR

Control room CHILL

WTR A/C FDR

REL RM CHILL WTR A/C

FDR

CONT ROD cooling

fans

BC WTR.HX INLT vvs

RCP CLR CC OUTLT

FLOW OTSD TRIP vv

RCP Thermal Barrier

CC OUTLT FLOW OTSD

TRIP vv

LOOP ORN HOR ISOL VVS

CONTROL ROOM DOOR 1

. CONTROL ROOM DOOR 3

CONTROL ROOM. DOOR 4

N

STM GEN FW FLOW CONTR

CHRG PP CLG WTR PPS .

34.5 KV Rx CORR

CONT. ROD CLG FAN 480V

STM DUMP CONTR

BYP INTERLOCK

' ,, ' .* , ,**, *.

    • '
  • - '

,. *, '*. ;*~ -~.r r

      • ,* * *

~

'

_-* *. t

  • .. , \\ ;*;' ,**,.~ ** :** * * *I ,.

'** '.,',*,

~ * (' *

    • ,.
  • r' *
  • :

..

Appendix D

5

AP-16.00 *

17

CCW head tank

CC SURG TK LVL

level

18b

excess letdown HCV

EXCESS LETDOWN FLOW

HCV-1137

SETPT HCV-1137

AP-5.03

1

LW MONITOR

LIQ WASTE DISP

AP-1. 01

5

ROD DROP

DROPPED ROD

AP-1. 00

4

NIS DROPPED ROD

. NIS DROPPED ROD ROD

STOP AND TURB

STOP AND TURB RNBK

RNBK

\\

. . . *t~

. ,, .* '._ ... ;*"* .. , ..

. . : ,. *. '. -*** ** : ... ~-

. ** .I "'..... * .. \\' *:. ~. *****.' ...... *

.*

  • ~* *

. ;

, ... :* ... ~ *- -*- *-

...

AC

AER

AFW

AP

ARP

ATWX

AUX

BRK

cc

CETC

CHG

CLS

CNS

CST

cs

CROM

CSFST

CTMT

cw

DC

DEV

DP

DP ELEV

ECCS

EOG

EOP

ERF

ERG

FCA

FCV

GPM

HCV

HP

HX

IA

I&C

IF!

LHSI

LOCA

MCC

MCR

MON

MOV

MSTV

NLO

NI

NR

NRC

NQ

OMS

OP

APPENDIX E

ABBREVIATIONS

Alternating Current

Action Expected Response

Auxiliary Feedwater

Abnormal Procedures

Alarm Response Procedures

Anticipated Transient Without Scram

Auxiliary

Breaker

Component Cooling

Core Exit Thermocouple

Charging

Consequence Limiting Safeguards

Corporate Nuclear Safety

Condensate Storage Tank

Containment Spray

Control Rod Drive Mechanism

Critical Safety Function Status Tree

Containment

Circulating Water

Direct Current

Deviation

Differential Pressure

Differential Pressure Due to Elevation

Emergency Core Cooling System

Emergency Diesel Generator

Emergency Operating Procedure

Emergency Response Facility

Emergency Response Guidelines

Fire Contingency Action

Flow Control Valve

Gallons Per Minute

Hand Control Valve

Health Physics

Heat Exchaner

Instrument Air

Instrumentation and Control

Inspector Followup Item

Low Head Safety Injection

Loss of Coolant Accident

Motor Control Center

Main Control Room

Monitor

_

Motor Operated Valve

Main Steam Trip Valve

Non-licensed Operator

Nuclear Instrumentation

Narrow Range

Nuclear Regulatory Commission

Not Qualified

\\

Overpressure Mitigation System

Operating Procedure

._.. t *

  • **
  • ,

.**

,~ *** ,

  • * *

' *.' ****** .-*. *,*.

,

  • -.. _**.* .. *-*,:*-
    • ."7".:

II

/

)

.~

- .~

Appendix E

PGP

PORV

Pp

PRA

PSID

PSIG

PSTG

PSTG DEV

PRZR

QA

QC

RCP

RCS

RECIRC

RHR

R/hr

RM

RNO

RO

RSST

RTD

RVLIS

RWST

RX

SB

SOD

SER

SFP

SG

SGTR

SI

SNSOC

SPDS

SRO

ss

STM

SW

Tavg

Tc

TC

TD

Th

TR

Tref

TRANS

TS

TSC

TURB

V&V

VCT

VPAP

2

Procedures Generation Package

Power Operated Relief Valve

Pump

Probalistic Risk Assessment

Pressure Square Inch-differential

Pressure Square Inch-guage

Plant Specific Technical Guidelines

PSTG Deviation

Pressurizer

Quality Assurance

Quality Control

Reactor Coolant Pump

Reactor Coolant System

Recirculation

Residual Heat Removal

Roentgen/hour

Radiation Monitor

Response Not Obtained

Reactor Operator

Reserve Station Service Transformer

Resistance Temperature Device

Reactor Vessel Level Instrumentation System

Refueling Water Storage Tank

Reactor

Station Blackout

Step Dilation Document

Safety Evaluation Report

Spent Fuel Pit

Steam Generator

Steam Generator Tube Rupture

Safety Injection

Station Nuclear Safety and Operating

Committee

Safety Parameter Display System

Senior Reactor Operation

Shift Supervisor

Steam

Service Water

Temperature-average

Temperature-Cold

Thermocouple

Transition Driver

Temperature-Hot

Trend Recorder

Temperature-Reference

Transformer

Technical Specification

Technical Support Center

Turbine

Verification & Validation

Volume Control Tank

Virginia Power Administrative Procedure

--

. . . . .* .. ~ *. '.

, . . :-.

. ..~.

. .- ., .. *

. *. --- :'*'

  • -

Appendix E

WG

WOG

WR

X-Tie

3

Writer's Guide

Westinghouse Owner's Group

Writers Guide

Cross Tie

\\

  • -
, ... -:* .--
  • ,* *.** ,.,*-~ ***.* ': .
  • * !" ... *:-.
  • .:.*, .*,:-*.

.*, ...... _ *****.~