ML17298A843

From kanterella
Jump to navigation Jump to search
Revision 27 to Updated Final Safety Analysis Report, Chapter 1, Introduction and General Description of Plant
ML17298A843
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 09/25/2017
From:
Duke Energy Progress
To:
Office of Nuclear Reactor Regulation
Shared Package
ML17298A847 List:
References
RNP-RA/17-0063
Download: ML17298A843 (72)


Text

HBR 2 UPDATED FSAR CHAPTER 1 INTRODUCTION AND GENERAL DESCRIPTION OF PLANT

HBR 2 UPDATED FSAR 1-i Amendment No. 11 CHAPTER 1 INTRODUCTION AND GENERAL DESCRIPTION OF PLANT TABLE OF CONTENTS

SECTION TITLE PAGE

1.0 INTRODUCTION

AND GENERAL DESCRIPTION OF PLANT 1.1.0-1

1.1 INTRODUCTION

1.1.0-1

1.2 GENERAL

PLANT DESCRIPTION 1.2.1-1 1.2.1 SITE AND ENVIRONMENT 1.2.1-1 1.2.2

SUMMARY

PLANT DESCRIPTION 1.2.2-1 1.2.2.1 STRUCTURES 1.2.2-1 1.2.2.2 NUCLEAR STEAM SUPPLY SYSTEM (NSSS) 1.2.2-1a 1.2.2.3 REACTOR AND PLANT CONTROL 1.2.2-2 1.2.2.4 WASTE DISPOSAL SYSTEM 1.2.2-2 1.2.2.5 FUEL HANDLING SYSTEM 1.2.2-3 1.2.2.6 TURBINE AND AUXILIARIES 1.2.2-3 1.2.2.7 ELECTRICAL SYSTEM 1.2.2-3 1.2.2.8 ENGINEERED SAFETY FEATURES PROTECTION SYSTEMS 1.2.2-3

1.2.2.9 INDEPENDENT SPENT FUEL STORAGE INSTALLATION 1.2.2-4

HBR 2 UPDATED FSAR 1-ii Revision No. 20 CHAPTER 1 INTRODUCTION AND GENERAL DESCRIPTION OF PLANT TABLE OF CONTENTS (continued)

SECTION TITLE PAGE

1.3 COMPARISON

TABLES 1.3.1-1 This Section was deleted in Revision 20.

1.4 IDENTIFICATION

OF CONTRACTORS 1.4.0-1

1.5 REQUIREMENTS

FOR FURTHER TECHNICAL INFORMATION 1.5.1-1

1.5.1 DELETED

BY AMENDMENT NO. 11

1.5.2 SAFETY

INJECTION SYSTEM DESIGN 1.5.2-1

1.5.3 SYSTEMS

FOR REACTOR CONTROL DURING XENON INSTABILITIES 1.5.3-1

1.5.4 CONTAINMENT

SPRAY ADDITIVE FOR IODINE REMOVAL 1.5.4-1

1.5.5 BLOWDOWN

CAPABILITY OF REACTOR INTERNALS 1.5.5-1

1.5.6 PROGRAMS

CONDUCTED DURING OPERATION 1.5.6-1

1.6 MATERIAL

INCORPORATED BY REFERENCE 1.6.0-1

1.7 DRAWINGS

AND OTHER DETAILED INFORMATION 1.7.0-1

1.8 CONFORMANCE

TO NRC REGULATORY GUIDES 1.8.0-1

HBR 2 UPDATED FSAR 1-iii Revision No. 20 CHAPTER 1 INTRODUCTION AND GENERAL DESCRIPTION OF PLANT LIST OF TABLES

TABLE TITLE PAGE 1.1.0-1 ACRONYMS 1.1.0-2 1.1.0-2 UNITS 1.1.0-10

HBR 2 UPDATED FSAR 1-iv Revision No. 20 CHAPTER 1 INTRODUCTION AND GENERAL DESCRIPTION OF PLANT LIST OF FIGURES

FIGURE TITLE 1.2.2-1 PLOT PLAN 1.2.2-2 GENERAL ARRANGEMENT REACTOR BUILDING PLANS - SHEET 1

1.2.2-3 GENERAL ARRANGEMENT REACTOR BUILDING PLANS - SHEET 2

1.2.2-4 GENERAL ARRANGEMENT REACTOR BUILDING - SECTIONS

1.2.2-5 GENERAL ARRANGEMENT REACTOR AUXILIARY BUILDING PLANS

1.2.2-6 GENERAL ARRANGEMENT REACTOR AUXILIARY BUILDING -

SECTIONS

1.2.2-7 GENERAL ARRANGEMENT FUEL HANDLING BUILDING AND MACHINE SHOP PLANS

1.2.2-8 GENERAL ARRANGEMENT FUEL HANDLING BUILDING AND MACHINE SHOP SECTIONS

1.2.2-9 GENERAL ARRANGEMENT TURBINE BUILDING GROUND FLOOR PLAN

1.2.2-10 GENERAL ARRANGEMENT TURBINE BUILDING MEZZANINE FLOOR

PLAN

1.2.2-11 GENERAL ARRANGEMENT TURBINE BUILDING OPERATING FLOOR

PLAN

1.2.2-12 GENERAL ARRANGEMENT TURBINE BUILDING SECTIONS

HBR 2 UPDATED FSAR 1.1.0-1 Revision No. 27

1.0 INTRODUCTION

AND GENERAL DESCRIPTION OF PLANT

1.1 INTRODUCTION

This updated Final Safety Analysis Report (FSAR) is for the H. B. Robinson Steam Electric

Plant Unit 2 (HBR 2). It is submitted to fulfill the requirements of 10CFR 50.71(e), as published

in the Federal Register on May 9, 1980. The Atomic Energy Commission (AEC) issued Facility

Operating License No. DPR-23 for HBR 2, dated July 31, 1970, specifying maximum power

level of 2200 MWt upon completion of preliminary testing and certain other prerequisites. These

prerequisites were satisfactorily met in the following months. The Docket No. is 50-261, and the

Construction Permit for the unit was No. CPPR-26. The Nuclear Regulatory Commission (NRC)

issued a license amendment on June 29, 1979, which authorized operation at a maximum

power level of 2300 MWt. A subsequent license amendment was issued on November 5, 2002, authorizing operation at a maximum power level of 2339 MWt. The FSAR for the unit was

submitted in November, 1968, and was amended a number of times prior to the issuance of the

licenses. This updated FSAR has been organized in accordance with the guidelines contained

in Regulatory Guide 1.70, Revision 3.

Table 1.1.0-1 lists the acronyms and Table 1.1.0-2 gives the abbreviations used throughout this

updated FSAR.

HBR 2 is situated on Lake Robinson, a man-made 2250 acre lake, about 4.5 miles from

Hartsville, South Carolina.

The HBR 2 reactor is a pressurized light water moderated and cooled system. The unit is

designed to produce 2339 MWt. All steam and power conversion equipment, including the

turbine generator, was designed to permit generation of 787 MWe (gross).

The nuclear power plant incorporates a closed-cycle pressurized water Nuclear Steam Supply

System (NSSS) and a Turbine-Generator System utilizing dry and saturated steam. Equipment

includes systems for the processing of radioactive wastes, handling of fuel, electrical

distribution, cooling, power generation structures, and all other onsite facilities required to

provide a complete and operable nuclear power plant.

HBR 2 UPDATED FSAR 1.1.0-2 Revision No. 18 TABLE 1.1.0-1 ACRONYMS AC air conditioning; also, alternating current

ACI American Concrete Institute

ACS Auxiliary Coolant System

AEC Atomic Energy Commission

AFW Auxiliary Feedwater

AISC American Institute of Steel Construction

AISI American Iron and Steel Institute

ALARA as low as is reasonably achievable

AMSAC ATWS Mitigation System Actuation Circuitry

ANS American Nuclear Society

ANSI American National Standards Institute

APCSB Auxiliary and Power Conversion Systems Branch

API American Petroleum Institute

ARC Automatic Rod Control

ASA American Standards Association

ASCE American Society of Civil Engineers

ASME American Society of Mechanical Engineers

ASTM American Society for Testing and Materials

ATWS Anticipated Transient Without Scram

AVT All Volatile Treatment

AWS American Welding Society

AWWA American Water Works Association

BAT boron acid tank

B&PV boiler and pressure vessel

BIT boron injection tank HBR 2 UPDATED FSAR 1.1.0-3 Amendment No.3 TABLE 1.1.0-1 (Cont'd)

BOC beginning of cycle

BOL beginning of life

BTP branch technical position

BWR boiling water reactor

CCW component cooling water

CES Critical Experiment Station

CFPP Containment Fire Protection Status Panel

CFR Code of Federal Regulations

CIS Containment Isolation System

CMAA Crane Manufacturers Association of America, Inc.

CNS Corporate Nuclear Safety

CP&L Carolina Power & Light Company

CRD control rod drive

CRDM control rod drive mechanism

CRDS Control Rod Drive System

CS carbon steel CSS Containment Spray System

CV containment vessel CVCS Chemical and Volume Control System

CVTR Carolina-Virginia Tube Reactor

DBA design basis accident

DBE design basis earthquake

DC direct current DECLG double-ended, cold leg guillotine

DF decontamination factor HBR 2 UPDATED FSAR 1.1.0-4 Amendment No.7 TABLE 1.1.0-1 (Cont'd)

DG diesel generator

DMIMS Digital Metal Impact Monitoring System

DNB departure from nucleate boiling

DNBR departure from nucleate boiling ratio

DOT Department of Transportation

DS dedicated shutdown DTT Design Transition Temperature

Ebasco Electric Bond and Share Company

ECCS Emergency Core Cooling System

EFPH effective full-power hours

EFPY effective full-power years

ENC Exxon Nuclear Corporation

EOC end of cycle

EOL end of life

EPRI Electric Power Research Institute

ESF Engineered Safety Features

FAP Fire Alarm Status Panel

FDAP Fire Detection Actuation Panel

FDAS Fire Detection Actuation System

FHB Fuel Handling Building

FI Fully Integral Ruggedized Rotor

FIRL Franklin Institute Research Laboratory

FM Factory Mutual Research; also, frequency modulated

FSAR Final Safety Analysis Report

FW feedwater

GDC General Design Criteria

HBR 2 UPDATED FSAR 1.1.0-5 Amendment No.3 TABLE 1.1.0-1 (Cont'd)

GM Geiger - Mueller

GWPS Gaseous Waste Processing System

HBR H. B. Robinson

HEPA high-efficiency particulate air filters

HIS Hydraulic Institute Standards

HP high pressure HPSI high pressure safety injection

HVAC heating, ventilating, and air conditioning

IAEA International Atomic Energy Agency

I&C instrumentation and control

IC internal combustion

ID inside diameter IEEE Institute of Electrical and Electronic Engineers

INPO Institute of Nuclear Power Operations

IPBS Integrated Planning, Budgeting, and Scheduling

IPCEA Insulated Power Cable Engineers Association

ISI in-service inspection

IVSW isolation valve seal water

IVSWS Isolation Valve Seal Water System

LED light emitting device; also, light-emitting diode

LHGR linear heat generation rate

LMFBR liquid metal fast breeder reactor

LOCA loss-of-coolant accident LP low pressure LPSI low pressure safety injection

LVDT linear variable differential transducers HBR 2 UPDATED FSAR 1.1.0-6 Amendment No.3 TABLE 1.1.0-1 (Cont'd)

LWR light water reactor

MCA maximum credible accident

MCC motor control center

MDNBR minimum departure from nucleate boiling ratio

MG motor generator

MM Modified Mercalli MOV motor operated valve

MPC maximum permissible concentration

MSIV main steam isolation valve

MSL mean sea level

MTC moderator temperature coefficient

MWT makup water tank

NBS National Bureau of Standards

NDE nondestructive examination

NDTT nil-ductility transition temperature

NEMA National Electrical Manufacturer's Association

NFPA National Fire Protection Association

NIS Nuclear Instrumentation System

NML Nuclear Mutual Limited

NPSH net positive suction head

NRC Nuclear Regulatory Commission

NSAC Nuclear Safety Analysis Center (EPRI)

NSSS Nuclear Steam Supply System

NWRC National Weather Records Center

OBE operational basis earthquake

OD outside diameter HBR 2 UPDATED FSAR 1.1.0-7 Amendment No.3 TABLE 1.1.0-1 (Cont'd)

ORNL Oak Ridge National Laboratory

OSHA Occupational Safety and Health Administration

PA Public Address PACV Post-Accident Containment Venting

PBX private branch exchange

PCI pellet-cladding interaction

PCT peak clad temperature

PDC II power distribution control II

PF power factor PFI Pipe Fabrication Institute

pH Concentration of Hydrogen ions

PLA Pickard, Lowe & Associates

PLSA Part Length Shield Assembly

PMF probable maximum flood

PORV power-operated relief valve(s)

PPS Penetration Pressurization System

PRCF Plutonium Recycle Facility

PRT pressurizer relief tank

PSAR Preliminary Safety Analysis Report

PTS Pressurized Thermal Shock

PVC polyvinyl chloride PWR pressurized water reactor

QA quality assurance

QAC Quality Assurance Committee

QC Quality Control QCS Quality Control Systems HBR 2 UPDATED FSAR 1.1.0-8 Amendment No.3 TABLE 1.1.0-1 (Cont'd)

RAB Reactor Auxiliary Building

RC radiation control RCC rod cluster control

RCCA rod cluster control assembly

RCDT reactor coolant drain tank

RCGVS Reactor Coolant Gas Vent System

RCP reactor coolant pump

RCPB reactor coolant pressure boundary

RCPS Reactor Coolant Pump System

RCS Reactor Coolant System

RG Regulatory Guide RG&E Rochester Gas and Electric

RH relative humidity RHR residual heat removal

RHRS Residual Heat Removal System

RMS Radiation Monitoring System

RPS Reactor Protection System

RPV reactor pressure vessel

RTD resistance temperature detectors

RTG reactor and turbine-generator

RTGB reactor and turbine-generator board

RT NDT Reference Temperature, Nil-Ductility Transition

RTS Reactor Trip System

RWP radiation work permits

RWST refueling water storage tank

SAFDL specified acceptable fuel design limit

HBR 2 UPDATED FSAR 1.1.0-8a Revision No. 15 TABLE 1.1.0-1 (Continued)

SAR Safety Analysis Report SBOStation Blackout

SCR Silicon Control Rectifier

SFP Spent Fuel Pit

SHNPP Shearon Harris Nuclear Power Plant

SG Steam Generator

SI Safety Injection

SIS Safety Injection System

SOR Senior Operator License

SPCSiemens Power Corporation

SRO Senior Reactor Operator

SRWP Standing Radiation Work Permit

SS Stainless Steel SSE Safe Shutdown Earthquake

SSPC Steel Structure Painting Council

STP Standard Temperature and Pressure

SWP Service Water Pump

SWPS Solid Waste Processing System

HBR 2 UPDATED FSAR 1.1.0-9 Amendment No.10 TABLE 1.1.0-1 (Cont'd)

SWRI Southwest Research Institute

SWS Service Water System

TD theoretical density TDH total developed head

TEMA Tubular Exchanger Manufacturers' Association

TLD thermoluminescent dosimeters

TSC Technical Support Center

USAEC United States Atomic Energy Commission

USAS United States of America Standards

USGS United States Geological Survey

UHF ultra high frequency

UL Underwriter's Laboratories, Inc.

UPS uninterruptible power supply

UT ultrasonic test UTM Universal Transverse Mercator

VCT volume control tank

VHF very high frequency

WAPD Westinghouse Atomic Power Division

WDS Waste Disposal System

Westinghouse Westinghouse Electric Corporation

WOL wedge opening loading

WREC Westinghouse Reactor Evaluation Center

HBR2UPDATEDFSAR 1.1.0-10TABLE1.1.0-2 UNITS acre ac acre-foot ac-ft ampere amp atmosphere per cubic centimeter atm/cc average temperature T avg brake horsepower bhp British thermal units per hour Btu/hr British thermal units per hour/foot Btu/hr/ft British thermal units per hour/square foot Btu/hr-ft 2 calorie cal centimeter cm centipoise cp Chi/Q /Q cubic centimeter cm 3 or cc cubic centimeters per hour cc/hr cubic centimeters per minute cc/min cubic feet per minute cfm or ft 3/min cubic feet per second ft 3/sec or cfs cubic foot ft 3 cubic meter m 3 cubic yard yd 3 curie Ci curie per cubic centimeter Ci/cc curie per second Ci/sec HBR2UPDATEDFSAR 1.1.0-11 TABLE 1.1.0-2 (Cont'd) curie per year Ci/yr cycles per second cps or Hz degrees centigrade

°C degrees Farenheit

°F degrees Kelvin

°K direct current DC disintegrations per second per milligram DPS/mg electron volt ev feet (foot) ft feet per second fps foot-inch ft-in.foot-pound ft-lb gallon gal gallons per day gal/day or gpd gallons per hour gal/hr gallons per minute gal/min or gpm gram g gram mole per degree Rankine g mole/°R gram per cubic centimeter g/cc or g/cm 3 Hertz hz horsepower HP hour hr inch (inches) in. inch water gage in. wg or wg inside diameter ID kiloelectron volt Kev HBR2UPDATEDFSAR 1.1.0-12 TABLE 1.1.0-2 (Cont'd) kilogram kg kilovolt kV kilovolt-ampere kVa kilowatt kW kilowatt per foot kW/ft megawatt MW megawatt days per metric ton of uranium MWD/MTU megawatt (electric)

Mwe megawatt (thermal)

Mwt mercury Hg meter m micro curie per cubic centimeter Ci/cc micro mho per centimeter (conductivity) mho/cm micron, micro mile per hour mph mile per second mps millicurie mCi milligram per square decimeter mg/dm 2 milliliter ml million electron volts Mev millirem per hour mrem/hr milliroentgen per hour mR/hr millivolt mv minute or minimum min HBR 2 UPDATED FSAR

1.1.0-13 TABLE 1.1.0-2 (Cont'd)

neutron multiplication factor, effective K eff neutron multiplication factor, infinity K neutrons per square centimeter-second (nv) n/cm 2-sec ohm-centimeter (Resistivity) ohm-cm

parts per billion ppb

parts per million ppm

per second sec

-1 pound lb

pound mass lbm

pounds per cubic foot lb/ft 3 or pcf pounds per hour lb/hr

pounds per square foot lb/ft 2 or psf pounds per square inch psi

pounds per square inch (absolute) psia

pounds per square inch (differential) psid

pounds per square inch (gage) psig

radiation absorption dose rad

radius r

reactivity k/k reactivity change rate k/sec revolutions per minute rpm

revolutions per second rps

roentgen R

roentgen equivalent man rem

roentgens per hour R/hr

root mean square rms HBR 2 UPDATED FSAR 1.1.0-14 TABLE 1.1.0-2 (Cont'd) second sec

specific gravity sp gr square ( )2 or sq square centimeter cm 2 square foot ft 2 or sq ft

square inch in.2 or sq in.

square mile mi 2 or sq mi

standard cubic feet scf or stdft

standard cubic feet per minute scfm or stdft 3/min standard cubic feet per second scfs temperature of the cold leg T cold temperature of the hot leg T hot thickness T

thousand pounds kip thousand pounds per linear foot k/lf thousand pounds per square inch ksi thousandth of an inch mil ton (short ton) ton, st tonne (metric ton, 2,204.62 lb) te, mt volt V

volt alternating current V AC volt ampere Va volt direct current V DC volume percent vol %

water column wc watt W HBR 2 UPDATED FSAR 1.1.0-15 TABLE 1.1.0-2 (Cont'd) watt per cubic centimeter W/cc week wk

weight percent wt %

yard yd

year yr

HBR 2 UPDATED FSAR 1.3.1-1 Revision No. 20

1.3 COMPARISON

TABLES Section 1.3 information was deleted in Revision 20.

HBR 2 UPDATED FSAR 1.4.0-1 1.4 IDENTIFICATION OF CONTRACTORS The Carolina Power & Light Company (CP&L), as owner, engaged or approved the engagement

of, the contractors and consultants identified below in connection with the design and

construction of HBR Unit 2. However, irrespective of the explanation of contractual

arrangements offered below, CP&L was the sole applicant for the construction permit and is the

operating licensee, and as owner and licensee is responsible for the design, construction, and

operation of the Unit.

HBR 2 was designed and built by the Westinghouse Electric Corporation as prime contractor for

CP&L. Westinghouse undertook to provide a complete, safe, and operable nuclear power plant

ready for commercial service. The project was directed by Westinghouse from the offices of its

Atomic Power Division in Pittsburgh, Pennsylvania, and by Westinghouse representatives at the

plant site during construction and plant startup. Westinghouse engaged the engineering firm of

Electric Bond and Share Company (Ebasco) Services Incorporated of New York City, New York, to provide the design of the structures and non-nuclear portions of the plant to prepare

specifications for the purchase and construction thereof. CP&L reviewed the designs and

specifications prepared by Westinghouse and Ebasco Services to assure that the general plant arrangements, equipment, and operating provisions were satisfactory to them. CP&L inspected

the construction work to assure that the plant was built in accordance with the approved plans

and specifications.

The plant was constructed under the general direction of Westinghouse through a general

contractor who was responsible for the management of all site construction activities and who

either performed or subcontracted the work of construction and equipment erection.

Preoperational testing of equipment and systems and initial plant operation was performed by

CP&L personnel under the technical direction of Westinghouse.

As consultants on studies of plant site geology, hydrology, and seismology, the firm of Dames

and Moore of New York, New York, was engaged by CP&L to work in conjunction with Ebasco

Services.

As additional consultants on seismology and geology, Dr. G. W. Housner of the California

Institute of Technology; Dr. J. L. Stuckey and Dr. L. L. Smith, Consultants, Raleigh, North

Carolina; and Dr. P. Byerly, Consultant, Oakland, California, were engaged by CP&L.

As consultants on reactor and plant engineering, site meteorology, and general site studies, the

firm of Pickard, Lowe, and Associates of Washington, D. C. was engaged by CP&L.

HBR 2 UPDATED FSAR 1.5.1-1 Amendment No. 11 1.5 REQUIREMENTS FOR FURTHER TECHNICAL INFORMATION Research and development (as defined in Section 50.2 of the commission's regulations) was

conducted regarding final core design details and parameters (no longer applicable due to

refueling changes), analytical methods for kinetics calculation, safety injection (emergency core

cooling) system, xenon stability and related control systems, containment spray additive

effectiveness, and capability of reactor internals to resist blowdown forces. The information

submitted in Supplement No. 1, Tab 11 Item 1 of the original FSAR clarified the status of

Westinghouse safety-related research and development programs as they related to the HBR 2.

That information is now obsolete and not included in the updated FSAR.

1.5.1 DELETED

BY AMENDMENT NO. 11.

1.5.2-1 1.5.2 SAFETY INJECTION SYSTEM DESIGN

The design of the safety injection system is essentially that proposed at the time the

construction permit was issued; that is, it includesnitrogen-pressurized accumulators to inject

borated water into the RCS to rapidly and reliably reflood the core following a loss-of-coolant

accident (LOCA). Additional analyses have been performed to demonstrate that the

accumulators in conjunction with other components of the emergency core cooling system can

adequately cool the core for any pipe rupture.

Research and development work has also been performed on the integrity of Zircaloy-clad fuel

under conditions simulating those during a LOCA. Under the conservatively evaluated

temperature predicted for the fuel rods during LOCA, the clad may burst due to a combination of

fuel rod internal gas pressure and the reduction of clad strength with temperature. Burst

cladding could block flow channels in the core, so that core cooling by the safety injection

system would be insufficient to prevent fuel rod melting.

Rod burst experiments have therefore been conducted on Zircaloy rods to evaluate the

mechanism and effects of this potential channel blockage. Single rod tests are presented in

detail in Reference 1.5.2-1.

1.5.3-1 Revision No. 18 1.5.3 SYSTEMS FOR REACTOR CONTROL DURING XENON INSTABILITIES

In the transition to large Zircaloy-clad-fuel cores, the potential of power spatial redistribution

caused by instabilities in local xenon concentration was created.

Extensive analytical work has been performed on reactor core stability (References 1.5.3-1, 1.5.3-2, and 1.5.3-3). These references indicate that a core of this size may be unstable against axial power redistribution, but is nominally stable against transverse (denoted X-Y)

power oscillations. The plant is therefore provided with instrumentation which will allow the

operator to detect the axial power oscillations, and procedures exist for suppressing these

oscillations (Section 7.7.1).

Control information for suppression of power oscillation is obtained from four long ion chambers, each divided into an upper and lower section, mounted vertically outside the core. Both

calculation and experimental measurements at SENA, San Onofre and Haddam Neck have

shown that this out-of-core instrumentation represents in core power distribution, which is

adequate for power distribution control (Reference 1.5.3-3).

The control strategy is based on the difference in output between the top and bottom sections of

the long ion chambers. If the operator allows axial power imbalance to exceed operating limits, various levels of protection are invoked automatically. These include generation of alarms, turbine power cutback and blocking of control rod withdrawal.

1.5.5-1 Revision No. 15 1.5.5 BLOWDOWN CAPABILITY OF REACTOR INTERNALS

As documented in the response to AEC Questions dated 3/24/69, the computer code BLODWN-

2 was used to evaluate the blowdown capability of the reactor internals. In the response to AEC

Questions dated 8/22/69, it was indicated that the BLODWN-2 analysis performed for Indian

Point was applicable to Robinson. Detailed data from that evaluation was included in the

response to AEC Questions which indicates that the "Blowdown Capability of Reactor Internals" was evaluated with BLODWN-2.

Furthermore, in June 1980, the response of the reactor vessel (including the internals) to a

guillotine break at the reactor vessel inlet nozzle was evaluated by a different set of computer

codes in WCAP-9748 (Westinghouse Owners Group Asymmetric LOCA Loads Evaluation).

Subsequent review by the NRC determined that the probability of failure in the primary system

is low enough that a double ended guillotine break need not be postulated as a design basis

event for defining structural loads (reference Generic Letter 84-04).

The response of Siemens fuel assemblies to LOCA blowdown forces was evaluated in XN-NF-

76-47 (Combined Seismic-LOCA Mechanical Evaluation for Exxon Nuclear 15x15 Reload Fuel).

This evaluation is cited in UFSAR Section 4.0.

1.5.6-1 1.5.6 PROGRAMS CONDUCTED DURING OPERATION

There are no ongoing programs specific to HBR 2 to demonstrate the acceptability of

contemplated future changes in design or modes of operation.

1.5R-1 Amendment No. 11 HBR 2 UPDATED FSAR

REFERENCES:

SECTION 1.5

1.5.2-1 WCAP-7379-L, Performance of Zircaloy Clad Fuel Rods During a Single Rod Test, October 6, 1969. (Westinghouse Proprietary).

1.5.3-1 Poncelet, C. G. and Christie, A. M., "Xenon Induced Spatial Instabilities in Large Pressurized Water Reactors," WCAP-3680-20, March 1968.

1.5.3-2 McGough, J. D., "The Effect of Xenon Spatial Variations and the Moderator Coefficient Core Stability," WCAP-2983, August 1966.

1.5.3-3 Westinghouse Proprietary Report, "Power Distribution Control in Westinghouse PWR," WCAP-720. OCTOBER 1968.

1.5.4-1 Westinghouse Confidential Report, "Investigation of Chemical Additives for Reactor Containment Sprays," WCAP-7153, March 1968.

HBR 2 UPDATED FSAR 1.6.0-1 1.6 MATERIAL INCORPORATED BY REFERENCE Topical Reports and other material incorporated by reference are called out in individual

subsections and listed in the section reference lists.

HBR 2 UPDATED FSAR 1.7.0-1 1.7 DRAWINGS AND OTHER DETAILED INFORMATION The "drawing package" is not part of the original FSAR. This section is not applicable to the

Updated FSAR.

HBR 2 UPDATED FSAR 1.8.0-1 Revision No. 27 1.8 CONFORMANCE TO NRC REGULATORY GUIDES Regulatory Guides (originally called Safety Guides) have been published beginning in late 1970.

Since H. B. Robinson (HBR) was licensed for operation prior to that time, they were not

addressed. Those Regulatory Guides which have been addressed during the operating phase

are discussed below.

HBR 2 UPDATED FSAR 1.8.0-2 Revision No. 27 Regulatory Guide 1.8 PERSONNEL SELECTION AND TRAINING (SEPTEMBER 1975)

ANSI Standard N18.1-1971 PERSONNEL SELECTION AND TRAINING

The criteria for selection and training of personnel for operation of Robinson 2 are addressed in

the Robinson Technical Specifications.

HBR 2 UPDATED FSAR 1.8.0-3 Revision No. 27 Regulatory Guide 1.13 FUEL STORAGE FACILITY DESIGN BASIS Conform to Regulatory Guide 1.13 only as it relates to the new high-density spent fuel storage

racks design for preventing damage resulting from the safe shutdown earthquake (SSE), and

protecting the fuel from mechanical damage.

HBR 2 UPDATED FSAR 1.8.0-4 Revision No. 27 Regulatory Guide 1.28 QUALITY ASSURANCE PROGRAM REQUIREMENTS (DESIGN AND CONSTRUCTION)

Conformance with Regulatory Guide 1.28 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-5 Revision No. 27 Regulatory Guide 1.29 SEISMIC DESIGN CLASSIFICATION Comply with Regulatory Guide 1.29, Revision 3, only as it relates to the new high-density spent

fuel storage racks designated Seismic Category I as defined and outlined in the regulatory

guide.

HBR 2 UPDATED FSAR 1.8.0-6 Revision No. 27 Regulatory Guide 1.30 QUALITY ASSURANCE REQUIREMENTS FOR THE INSTALLATION, INSPECTION, AND TESTING OF INSTRUMENTATION AND ELECTRICAL

EQUIPMENT

Conformance with Regulatory Guide 1.30 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-7 Revision No. 27 Regulatory Guide 1.33 QUALITY ASSURANCE PROGRAM REQUIREMENTS (OPERATION)

Conformance with Regulatory Guide 1.33 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-8 Revision No. 27 Regulatory Guide 1.37 QUALITY ASSURANCE REQUIREMENTS FOR CLEANING OF FLUID SYSTEMS AND ASSOCIATED COMPONENTS OF WATER-COOLED NUCLEAR POWER PLANTS

Conformance with Regulatory Guide 1.37 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-9 Revision No. 27 Regulatory Guide 1.38 QUALITY ASSURANCE REQUIREMENTS FOR PACKAGING, SHIPPING, RECEIVING, STORAGE, AND HANDLING OF ITEMS FOR WATER-COOLED NUCLEAR

POWER PLANTS

Conformance with Regulatory Guide 1.38 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17

HBR 2 UPDATED FSAR 1.8.0-10 Revision No. 27 Regulatory Guide 1.39 HOUSEKEEPING REQUIREMENTS FOR WATER-COOLED NUCLEAR POWER PLANTS Conformance with Regulatory Guide 1.39 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-11 Revision No. 27 Regulatory Guide 1.52 DESIGN, TESTING, AND MAINTENANCE CRITERIA FOR POST ACCIDENT ENGINEERED SAFETY - FEATURE ATMOSHPERE CLEANUP

SYSTEM AIR FILTRATION AND ADSORPTION

UNITS OF LIGHT-WATER-COOLED NUCLEAR

POWER PLANTS (MARCH 1978)

ANSI Standard N510-1975/1980 TESTING OF NUCLEAR AIR-CLEANING SYSTEMS The RNP Ventilation Filter Testing Program, as described in Section 5.5.11 of the Improved

Technical Specification, shall comply with the frequencies specified in Positions C.5 and C.6 of

Regulatory Guide 1.52 (March 1978) and conducted in general conformance with ANSI

Standard N510-1975 or N510-1980. Applicable portions of the Fuel Handling Building Ventilation System and Containment Purge System shall be tested in accordance with ANSI

Standard N510-1975. Applicable portions of the Control Room Emergency Filtration System

shall be tested in accordance with ANSI Standard N510-1980.

HBR 2 UPDATED FSAR 1.8.0-12 Revision No.27 Regulatory Guide 1.54 QUALITY ASSURANCE REQUIREMENTS FOR PROTECTIVE COATINGS APPLIED TO WATER-COOLED NUCLEAR POWER PLANTS (JUNE

1973)

ANSI Standard N101.4-1972 QUALITY ASSURANCE FOR PROTECTIVE COATINGS APPLIED TO NUCLEAR FACILITIES

HBR2 is not committed to compliance with RG 1.54 and ANSI 101.4.

The applicable surfaces at Robinson 2 are recoated with original type coating or approved equal

in accordance with original specification requirements, or equivalent engineering requirements

established for touch-up and repair.

HBR 2 UPDATED FSAR 1.8.0-13 Revision No.27 Regulatory Guide 1.58 QUALIFICATION OF NUCLEAR POWER PLANT INSPECTION, EXAMINATION, AND TESTING PERSONNEL

Conformance with Regulatory Guide 1.58 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-14 Revision No. 27 Regulatory Guide 1.60 DESIGN RESPONSE SPECTRA FOR SEISMIC DESIGN OF NUCLEAR POWER PLANTS Comply with Regulatory Guide 1.60 only as it relates to design spectra for the new high-density

spent fuel storage racks.

HBR 2 UPDATED FSAR 1.8.0-15 Revision No. 27 Regulatory Guide 1.61 DAMPING VALUES FOR SEISMIC DESIGN OF NUCLEAR POWER PLANTS Comply with Regulatory Guide 1.61 only as related to damping factors for the new high-density

spent fuel storage racks.

HBR 2 UPDATED FSAR 1.8.0-16 Revision No. 27 Regulatory Guide 1.64 QUALITY ASSURANCE REQUIREMENTS FOR THE DESIGN OF NUCLEAR POWER PLANTS Conformance with Regulatory Guide 1.64 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-17 Revision No. 27 Regulatory Guide 1.74 QUALITY ASSURANCE TERMS AND DEFINITIONS Conformance with Regulatory Guide 1.74 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-18 Revision No. 27 Regulatory Guide 1.75 PHYSICAL INDEPENDENCE OF ELECTRICAL SYSTEMS. See Section 7.4.2.1 for application of Regulatory Guide 1.75.

HBR 2 UPDATED FSAR 1.8.0-19 Revision No. 27 Regulatory Guide 1.88 REQUIREMENTS FOR COLLECTION, STORAGE, AND MAINTENANCE OF QUALITY ASSURANCE RECORDS FOR NUCLEAR POWER PLANTS Conformance with Regulatory Guide 1.88 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-20 Revision No. 27 Regulatory Guide 1.92 COMBINING MODAL RESPONSES AND SPATIAL COMPONENTS IN SEISMIC RESPONSE ANALYSIS Guidelines set forth in Regulatory Guide 1.92 were used only as they related to the new high-

density fuel storage rack seismic analysis.

HBR 2 UPDATED FSAR 1.8.0-21 Revision No. 27 Regulatory Guide 1.94 QUALITY ASSURANCE REQUIREMENTS FOR INSTALLATION, INSPECTION, AND TESTING OF STRUCTURAL CONCRETE AND STRUCTURAL

STEEL DURING THE CONSTRUCTION PHASE

OF NUCLEAR POWER PLANTS

Conformance with Regulatory Guide 1.94 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-22 Revision no. 27 Regulatory Guide 1.97 INSTRUMENTATION FOR LIGHT-WATER-COOLED NUCLEAR POWER PLANTS TO ASSESS PLANT CONDITIONS

DURING AND FOLLOWING AN ACCIDENT (REV 3)

The guidelines for selecting variables to be monitored were established in accordance with

Regulatory Guide 1.97 (Revision 3) and NUREG 0737

Supplement 1.

The compliance with these documents is detailed in the following correspondence:

CP&L Letter NLS-84-509, E. E. Utley (CP&L) to S. A. Varga (NRC), "Response to

Order Confirming Commitments on Emergency Response Facility," dated December

31, 1984.

CP&L Letter NLS-85-198, S. R. Zimmerman (CP&L) to S. A. Varga (NRC), "Revision

to Compliance Report for Regulatory Guide 1.97, Revision 3," dated July 18, 1985.

CP&L Letter NLS-86-267, A. B. Cutter (CP&L) to S. A. Varga (NRC), "Revision 2 to

Regulatory Guide 1.97 Submittal," dated July 28, 1986.

CP&L Letter NLS-87-093, A. B. Cutter (CP&L) to S. A. Varga (NRC), "Change

Reactor Coolant Pump Seal Return Flow to Type D3 Variable," dated May 1, 1987.

CP&L Letter NLS-87-136, S. R. Zimmerman (CP&L) to S. A. Varga (NRC), "Revision

4 to Regulatory Guide 1.97 Submittal," dated October 9, 1987.

CP&L Letter NLS-87-065, A. B. Cutter to NRC, "CCW Temperature Instrumentation -

R.G. 1.97," dated March 27, 1987.

NRC Letter, G. Requa (NRC) to E. E. Utley (CP&L) "Request for Information - R.G.

1.97," March 5, 1987.

NRC Letter, K. T. Eccleston (NRC) to E. E. Utley (CP&L), "Regulatory Guide 1.97,"

April 29, 1987.

CP&L Letter RNP-RA/01-0164, B. L. Fletcher III to NRC, "Request for Technical

Specification Change to Eliminate Requirements for the Post-Accident Sampling

System," dated October 31, 2001.

NRC Letter, A. G. Hansen (NRC) to J. W. Moyer (CP&L), "H. B. Robinson Steam

Electric Plant, Unit No. 2 - Issuance of an Amendment RE: Elimination of

Requirements for the Post-Accident Sampling System (TAC No. MB3380)," dated

January 14, 2002

HBR 2 UPDATED FSAR 1.8.0-23 Revision No. 27 Regulatory Guide 1.116 QA REQUIREMENTS FOR INSTALLATION, INSPECTION, AND TESTING OF MECHANICAL EQUIPMENT AND SYSTEMS

Conformance with Regulatory Guide 1.116 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-24 Revision No. 27 Regulatory Guide 1.123 QUALITY ASSURANCE REQUIREMENTS FOR CONTROL OR PROCUREMENT OF ITEMS AND SERVICES FOR NUCLEAR POWER PLANTS

Conformance with Regulatory Guide 1.123 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-25 Revision No. 27 Regulatory Guide 1.124 DESIGN LIMITS AND LOADING COMBINATIONS FOR CLASS I LINEAR-TYPE COMPONENT SUPPORTS DEP complied with Regulatory Guide 1.124 only as it related to the design of the rack

component supports for the new high-density fuel storage racks.

HBR 2 UPDATED FSAR 1.8.0-26 Revision No. 27 Regulatory Guide 1.133 LOOSE PARTS DETECTION PROGRAM FOR THE PRIMARY SYSTEM OF LIGHT-WATER-COOLED REACTORS (REVISION 1)

RG 1.133 Revision 1 Section D states "In cases where licensees of operating reactors (licensed

prior to January 1, 1978) have not previously committed to install a loose-part detection system

or where the design of an existing system precludes upgrading to an effective functional

capability, the licensee should install a system in conformance with the programmatic aspects of

the guide, specifically Sections C.2 and C.3, or propose an acceptable alternative. In cases

where a loose part is known to be present or there exists a high probability that a part may

become loose based on experience with other reactors of similar design, a loose-part detection

system conforming to this guide should be installed."

The Loose Parts Detection System at HBR 2 is in compliance with the regulatory position C.2

and C.3 with the following exceptions:

Portions of the functional tests are performed every quarter instead of the recommended

monthly frequency of Section C.3.a.(2).(d). Portions of the background checks are performed

every six months instead of the recommended quarterly frequency of Section C.3.a.(2).(e).

Special reports to the NRC are not submitted to setpoint changes as recommended in Section

C.3.a.(2).(a).

HBR 2 UPDATED FSAR 1.8.0-27 Revision No. 27 Regulatory Guide 1.137 FUEL OIL SYSTEMS FOR STANDBY DIESEL GENERATORS (REVISION 1)

HBR 2 will comply with Regulatory Guide 1.137 with the following exceptions:

Regulatory Position C.1 is not applicable to HBR 2 per NRC's letter dated January 13, 1978 which

distributed Regulatory Guide 1.137 and provided additional guidance regarding NRC's implementation of this guide for all nuclear power plants. Position C.1 was to be evaluated on a

case by case basis for application to all construction permit cases under review whose Safety Evaluation Report had not been issued as of November 1, 1979. Since HBR 2 had an operating license as of this date, Position C.1 is not applicable.

Regulatory Position C.2 is applicable to HBR 2 per NRC's letter dated January 13, 1978 except as

follows:

A. The analyses performed will be limited to API or specific gravity, water and sediment, viscosity and cloud point. The specifications that will be met will be in accordance with the

Diesel Fuel Oil Testing Program (Improved Standard Technical Specifications Bases) which

also are in accordance with the emergency diesel generator manufacturer's

recommendations.

B. The Unit No. 2 diesel fuel oil storage tank is filled from site storage tanks, the sampling frequency will be as described below:

1. New fuel oil received for storage in the fuel oil storage tanks and subsequently transferred to the Unit 2 DG fuel oil storage tank is verified to meet the analysis limits of the Diesel Fuel Oil Testing Program prior to adding to the storage tanks. This is

accomplished either by verifying the integrity of the seal(s) on the tank truck against

the certificate of compliance or by testing of the fuel oil prior to transfer from the tank

truck.

2. Stored fuel in the storage tanks and in the Unit 2 DG fuel oil storage tank is sampled every 31 days in accordance with the Diesel Fuel Oil Testing Program.

Diesel Generator (DG) fuel oil is controlled under the QA Program by virtue of the procedures for

testing of DG fuel oil being incorporated in the Plant Operating Manual which is part of the approved

QA Program.

Fuel Oil sampling from the discharge of the transfer pump was compared to the methodology in

ASTM D270-1975 and verified to be an equivalent sampling methodology.

The above position is based on the following references:

(1) NRC letter, Robert B. Minogue (NRC) to Regulatory Guide Distribution List (Division 1), regarding Regulatory Guide 1.137 dated January 13, 1978.

(2) NRC letter, D. G. Eisenhut (NRC) to All Power Reactor Licenses, January 7, 1980, Incoming Document No. NLU-80-48.

(3) CP&L letter, NO-80-725, M. A. McDuffie (CP&L) to D. A. Eisenhut (NRC), "Quality Assurance Requirements for Diesel Generator Fuel Oil", May 14, 1980.

HBR 2 UPDATED FSAR 1.8.0-28 Revision No. 27 Regulatory Guide 1.137 FUEL OIL SYSTEMS FOR STANDBY DIESEL GENERATORS (REVISION 1)

(4) NRC letter, Steven A. Varga (NRC) to J. A. Jones (CP&L), September 30, 1981, Incoming Document No. NLU-81-482.

(5) CP&L letter, NO-81-1914, November 20, 1981, S. R. Zimmerman (CP&L) to S. A.

Varga (NRC), "Quality Assurance Requirements Regarding Diesel Generator

Fuel Oil" (6) NRC letter, S. A. Varga (NRC) to J. A. Jones (CP&L), December 10, 1981, Incoming Document No. NLU-81-607.

(7) CP&L Letter, NO-92-1404, Charles R. Dietz (CP&L) to NRC, regarding Fuel Oil Sampling methodologies, May 15, 1992.

(8) NRC Inspection Report No. 50-261/92-32, December 28, 1992.

HBR 2 UPDATED FSAR 1.8.0-29 Revision No. 27 Regulatory Guide 1.144 AUDITING OF QUALITY ASSURANCE PROGRAMS FOR NUCLEAR POWER PLANTS Conformance with Regulatory Guide 1.144 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-30 Revision No. 27 Regulatory Guide 1.145 ATMOSPHERIC DISPERSION MODELS FOR POTENTIAL ACCIDENT CONSEQUENCE ASSESSMENTS OF NUCLEAR POWER PLANTS, (RE-ISSUE FEBRUARY, 1983 TO CORRECT

PAGE 1.145-7 IN REVISION 1, NOVEMBER 1982)

HBR-2 complies with the provisions of Regulatory Guide 1.145, February 1983, for the analysis of offsite meteorology conditions that support the Updated FSAR Chapter 15

Accident Analyses performed using the Alternative Source Term (AST) dose methodology

described in Regulatory Guide 1.183. Compliance with the specific details contained within this

Regulatory Guide is limited to the analyses as described in the applicable DEP licensing

submittals for AST implementation.

HBR 2 UPDATED FSAR 1.8.0-31 Revision No. 27 Regulatory Guide 1.146 QUALIFICATION OF QA PROGRAM AUDIT PERSONNEL FOR NUCLEAR POWER PLANTS Conformance with Regulatory Guide 1.146 is addressed in the description of the Quality

Assurance Program incorporated by reference in Chapter 17.

HBR 2 UPDATED FSAR 1.8.0-32 Revision No. 27 Regulatory Guide 1.155 STATION BLACKOUT

HBR2 complies with the intent of NRC Regulatory Guide 1.155. In developing the Station

Blackout (SBO) Coping Analysis (Document 8S19-P-101), the guidance of NUMARC 87-00

has been applied. The NUMARC 87-00 methodology has been utilized, with specific

exceptions in areas including: (1) evaluation of the effects of loss of ventilation, and (2)

evaluation of the containment isolation capability. The analytical method applied and the

results of these analyses are documented in SBO Coping Analysis 8S19-P-101.

HBR 2 UPDATED FSAR 1.8.0-33 Revision No. 27 Regulatory Guide 1.183 ALTERNATIVE RADIOLOGICAL SO URCE TERMS FOR EVALUATING DESIGN BASIS ACCIDENTS AT NUCLEAR POWER REACTORS, JULY 2000

HBR-2 complies with the provisions of Regulatory Guide 1.183, July 2000, for selected Updated

FSAR Chapter 15 Accident Analyses. Compliance with the specific details contained within this

Regulatory Guide is limited to the following bounding design basis accidents, as described in

the applicable DEP licensing submittals.

FSAR Section

References:

1. Common Dose Consequence Inputs for Alternative Source Term (AST) Analyses (UFSAR Section 15.0.12) 2. Main Steamline Break Event (UFSAR Section 15.1.5)
3. Reactor Coolant Pump Shaft Seizure (Locked Rotor) (UFSAR Section 15.3.2)
4. Withdrawal of a Single Full-Length RCCA (UFSAR Section 15.4.3.1)
5. Steam Generator Tube Rupture (UFSAR Section 15.6.3)
6. Design Basis Fuel Handling Accidents (UFSAR Section 15.7.4)

HBR 2 UPDATED FSAR 1.8.0-34 Revision No. 27 Regulatory Guide 4.15 QUALITY ASSURANCE FOR RADIOLOGICAL MONITORING PROGRAMS - EFFLUENT STREAMS AND THE ENVIRONMENT HBR 2 is not committed to Regulatory Guide 4.15. The guidance within Reg. Guide 4.15 was

used as a source of information to aid in developing and maintaining quality assurance for the

Radiological Environmental Monitoring Program. This program is implemented by procedures

as required by the Robinson Technical Specifications.