ML17056B794
| ML17056B794 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 04/08/1992 |
| From: | Beall J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML17056B793 | List: |
| References | |
| 50-410-92-81, NUDOCS 9204200057 | |
| Download: ML17056B794 (60) | |
See also: IR 05000410/1992081
Text
U. S. NUCLEAR REGULATORY COMMISSION
REGION I
50-410/92-81
Qg~k~N
50-410
i
n
N
~ie~n~
acilit
Name
In
eci nAt:
~nducted;
Niagara Mohawk Power Corporation
301 Plainfield Road
Syracuse,
13212
Nine Mile Point Nuclear Power Station, Unit 2
Scriba, New York
March 24-28, 1992
I~us ectors:
S. Hansell, Operations Engineer, DRS
J. Ibarra, Senior Instrument and Controls Engineer, AEOD
D. Brinkman, Senior Project Manager, NRR
ther
on ri
NR
Personnel:
bserver
Approved by:
W. Schmidt, Senior Resident Inspector, DRP
R. Laura, Resident Inspector, DRP
P. Eddy, State of New York
'8
J.
Beall, Team Leader, DRS
pl
r
r
E
'
date
9204200057
920410
- DOCK 05000410
8
0
f
TABLE
F
NTENT
~Pa e
EXECUTIVE SUMMARY ......................................
2
1 e0
INTRODUCTION
~
~
~
~
~
~
~
a
~
~
~
~
~
~
~
~
~ '
t
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
3
1.1
1.2
The AIT Scope and Objectives ...........................
3
AIT Process
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
'
~
~
~
~
~
~
o
3
2.0 'OSS OF OFFSITE POWER AND CONTROL ROOM ANNUNCIATORS
~
~
~
4
2.1
2.2
2.3
2.4
Overview of Offsite and Onsite Power Systems ......... ~...
History and Design of Control Room Annunciation Power Supplies
.
Chronology ofEvents.........................-....
Highlights of the Event....
~ .,.................
~,
~
~
~
~
~
~
4
~
~
~
~
4
~
~
~
5
~
~
~
~
5
2.4.1
Loss of Control Room Annunciators
2.4.2
Loss of Offsite Power ..............-.....
~ ..
~
~
~
5
~ ~,o'
3.0
PERSONNEL AND NUCLEAR PL'ANT SYSTEMS PERFORMANCE
~
~
~
~
~
~
8
3.1
Equipment Performance
~
~
~
~
9
3.1.1
Power Supplies to Control'Room Annunciators......
3.1.2
Instrument AirSystem........;........
~ ..
~
3.1.3
Division IIIEDG Trip".......,...........
'..
~
~
~
9
9
10
3.2
Procedure Adequacy
3.3
Personnel Performance ..... ~...............
~
~
~
~
~
~
~
11
12
3.3.1
Auxiliary Boilers Relay Calibration Work Package
3.3.2
Meter and Test Technicians..............
3.3.3
Control Room Operators
12
13
13
4.0
GENERIC IMPLICATIONSOF THIS EVENT ....................
14
5.0
LICENSEE CORRECTIVE ACTIONS .........................
14
5.1
Immediate Corrective Actions.................
5.2
Short Term and Long Term Corrective Actions...'..'.
14
15
1
Table of Contents
6@0
CONCLUSIONS
o
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
o
1 5
7.0 'ANAGEMENTMEETINGS...............................
16
TABLE 1 - Chronology of Events
APPENDIX A - NRC Augmented Inspection Team Charter
APPENDIX B - Persons
Contacted
APPENDIX C - Documents Reviewed
FIGURE 1 - Nine Mile Point Unit'2, Simplified Electrical Distribution
EXE
TIVE
MMARY
On March 23, 1992, at about 10:00 a.m., licensee personnel inadvertently tripped one of the
two lines supplying offsite power to Nine Mile Point Nuclear Power Plant Unit 2, which was
shutdown with about one-third of the core offioaded.
The line loss led to a loss of control
room annunciators
and the declaration of an alert.
The second offsite power line also was
inadvertently tripped causing a total loss of offsite power.
Several minutes later, one of the
two running emergency diesel generators
(EDGs) tripped, due to loss of cooling water.
An augmented
inspection team (AIT) was dispatched by the NRC to determine the
circumstances
that led to this event, its causes,
safety significance and generic implications,
and the adequacy of the licensee's
response
to the event.
The AITbegan its assessments
on
March 24, 1992, completed its onsite reviews on March 28, 1992, and presented
its
preliminary findings in a public exit meeting on April 1, 1992.
A technician initiated the event by bumping contacts closed while replacing a glass relay
cover.
Human factors problems contributed to the inadvertent performance error.
One of the two sources of power to the control room annunciators
(UPS 1A) lost power and
was unable to transfer to another source due to an internal fault. The fault had been
identified 14 days before the event, had been assigned
a "C" priority (less than seven days),
and had been scheduled for work 2 days after the event.
This work delay indicates a need
for review of oversight of work prioritization and scheduling.
The remaining annunciator power source (UPS 1B) was not able to sustain the load, tripped
on overload within 30 seconds,
and control room annunciators
were lost.
The current design
represents
a continued vulnerability to a loss of control room annunciators during shutdown
or plant transients (high alarm and annunciator loads) ifcoincident with the loss of the non-
safety UPS 1A,
The internal UPS 1A fault was found to be a failed internal logic battery.
These batteries
were replaced following the IITwith a planned replacement cycle of about 15 months.
The
bad battery was sent to the vendor by the licensee for a failure analysis.
The earlier than
expected failure (seven months vice planned fifteen months'eplacement
interval) requires
followup.
Operator performance was acceptable.
The total loss of offsite power was caused by a
combination 'of inadequate work package plant impact assessment
and inaccurate technician
information.
Weaknesses
in management
support to operations also contributed.
The Division IIIEDG tripped during the event due to the loss of service water cooling.
This
trip disclosed a previously unrecognized
design vulnerability to a sequential loss of offsite
power sources.
That is, the offsite lines are lost not simultaneously, but separated
by
15 seconds or more.
In this scenario,
should the first EDG fail or be out of service (as on
March 23), then the Division IIIEDG willtrip unless it is followed by rapid operator action.
This represents
a potential generic issue for plants with EDGs that don't supply their own
auxiliary and support systems.
The consequences
of this event were minimal. The facility was in refueling with the reactor:
cavity flooded.
The reactor core and the reactor coolant system were unaffected, no
equipment was damaged
and no radioactivity was released.
D
Upon being informed of the loss of offsite power and control room annunciators
at
Nine Mile Unit 2 on March 23, 1992, the NRC Region I Regional Administrator and
senior management
from the Office of Nuclear Reactor Regulation (NRR) and the
Office for Analysis and Evaluation of Operational Data (AEOD) determined that an
Augmented Inspection Team (AIT) should be formed to review and evaluate the
circumstances
and significance of this occurrence.
The basis of the NRC concern was
the apparent inadequacies of management
controls of maintenance activities that
.
allowed the event to occur.
Accordingly, an AITwas selected, briefed, and the AIT
leader dispatched to the site on March 24, 1992.
~ 1.1
Th
AIT c
nd
ectiv
The charter for the AIT (Appendix A) was finalized on March 24, 1992.
The
charter directed the team to conduct an inspection and accomplish the
following objectives:
Conduct a timely, thorough and systematic review of the circumstances
surrounding the event, including the sequence of events that led to and
followed the March 23, 1992 loss of offsite power and control room
2.
Collect, analyze and document relevant data and factual information to
determine the causes,
conditions and circumstances
pertaining to the
event, including the response
to the event by the licensee's operating
staff;
3.
Assess
the safety significance of the event and communicate to
Regional and Headquarters
management
the facts and safety concerns
related to the problems identified; and
4.
Evaluate the licensee's review of and response
to the event and
implemented corrective actions.
t.2
A TP
During the period March 24-28, 1992, the AIT conducted an independent
inspection, review, and evaluation of the conditions and cir'cumstances
associated
with this event.
The team inspected the event-initiating relays, the
offsite power supply breakers,
control room annunciators'ower
supplier, and
related indications in the control room;
held discussions
and formal interviews
with personnel involved in this event; reviewed relevant records including
computer printouts before, during, and after the event, and trends of pertinent
4
plant parameters;
and evaluated the adequacy of established
procedures,
management
oversight, and personnel training.
Appendix B is the list of
personnel contacted by the AITand Appendix C is the list of documents
reviewed by the AIT members.
This inspection was conducted in accordance with NRC Manual Chapter 0513,
Part III, Inspection Procedure 93800, Regional Instruction 1010.1 and
additional instructions provided in the AITcharter.
2.0
F
FF ITEP WERAND
NTR LR
M
IAT R
2.1
rview f ffi
n
ni
P wr
m
Nine Mile Point Unit 2 receives power from two offsite 115 kV lines, called
line 5 and line 6.
The breakers for these lines are located in the Scriba
.
switchyard approximately one-half mile from the site.
Figure
1 is a simplified
one-line diagram of the portion of the electrical distribution involved in the
,March 23, 1992 event.
At the time of the event, line 5 was supplying power to the Division I and III
buses through transformer RSST-A with R-50, motor-operated
disconnect
switch MDS-3 an'd the Division I and IIIbreakers all shut.
The auxiliary
boilers were also being powered from line 5 with MDS-10, MDS-5, and the
auxiliary boilers breaker shut,
The Division II bus was being supplied by
line 6 through R-60, MDS-4, transformer RSST-B and the Division II breaker.
Open were MDS-20, the Division IIIbreaker from transformer RSST-B and
all the EDG breakers to their respective buses.
The Division I EDG was out
of service for planned maintenance
and the Division II and IIIEDGs were
aligned for automatic start on loss of power to their respective buses.
The Division IIIEDG is dedicated to supply power to the High Pressure
Core
Spray (HPCS) system.
The remaining safety-related equipment is divided
between Divisions I and II. The HPCS system was not required to be
operable at the time of the event, but was available as a backup for adding
water to the reactor coolant system and the flooded reactor cavity.
2.2
Hi t
D in f
nr]R
m
nni inPwr
lier
The Nine Mile Point Unit 2 control room annunciators
are powered jointly
from two uninterruptible power supplies (UPS), UPS-1A and UPS-1B.
Upon
loss of one UPS, the annunciator power supply circuit of the other continues to
supply all the loads alone. Ifan overload condition results, the remaining
power supply would trip, as it did on March 23, 1992, and all control room
annunciators would become deenergized.
I
Each UPS can supply the annunciators by using an ac or a dc (station
batteries) input. A separate
maintenance
ac source also can be used to supply
the annunciator circuit directly in case of UPS failure or planned UPS
maintenance.
Each UPS unit has a control logic module which monitors
voltage and which initiates automatic transfers to maintain power to the
Each UPS control logic module also contains internal battery
packs (three "D" cells per pack) for certain functions.
Proper voltage from
these internal batteries was necessary for annunciator power to be transferred
from the maintenance
supply and back to the UPS.
For additional details on UPS design,
see NUREG-1455, "Transformer Failure
and Common-Mode Loss of Instrument Power at Nine Mile Point Unit 2'on
August 13, 1991."
2.3
Chr nol
of Event
The AITcompiled independently a detailed chronology of events by
interviewing cognizant personnel, reviewing relevant records including
computer printouts before, during, and after the event, and trends of pertinent
plant parameters.
This detailed chronology is provided in Table 1,
2.4
Hi hli hs f h
Ev nt
f
n r I R
m Annuncia
r
On March 9, 1992, UPS-1A automatically transferred power, as
designed,
to the annunciators
to the maintenance
source,
This transfer
occurred due to a voltage fluctuation caused by testing on another
circuit. The UPS-1A control logic sensed
the voltage drop and
properly initiated the transfer.
Licensee personnel were unable to return the annunciators
to their
normal source.
The cause of this problem was not known and a Work
Request (WR 201538) was initiated with a "C" priority (less than seven
days) to troubleshoot the failure'o transfer.
The loss of line 5 (see Section 2.4.2) on March 23, 1992, deenergized
the annunciator circuits powered from UPS-1A.
Power remained
available from the large station batteries but, as had been identified two
weeks previously, UPS-1A was not able to transfer to another supply.
For a short period of time (less than 30 seconds),
UPS-1B maintained
the control room annunciators.
Because the plant was shutdown, many
alarms and annunciators were energized causing a high load on the
circuit. UPS-1B was unable to continue to supply the demand alone,
and the annunciator circuit tripped on overload.
Power was restored to the control room annunciators after about
80 minutes.
2.4.2 ~ffff
P
On March 20, 1992, meter and test technicians began calibrating relays
using an electrical preventive maintenance procedure (No. S-EPM-
GEN-2Y070).
The work package had been prepared
a month earlier,
but had been postponed
as part of the work package review activities
which were corrective actions following the Nine Mile Point Unit
1
loss of ultimate heat sink (see NRC Inspection Report 50-220/92-80).
The plant impact assessment
in the work package did not address
effects should any of the relays actuate during the job.
On March 23, 1992, a technician inadvertently bumped contacts of the
backup overcurrent protection relay on the "B" phase of the auxiliary
boilers supply breaker.
At the time, the technician had completed
calibration of the relay and was replacing the glass cover.
The meter
and test personnel
noted that a relay trip had occurred, notified the
control room, and were directed to come to the c'ontrol room to
explain.
~
The auxiliary boiler relay trip (type 86) had also tripped the next
breaker up the circuit (see Figure 1), R-50.
The relay logic included
two sets of contacts which effectively mimicked the power circuit up to
MDS-5.
Since R-50 and MDS-10 were closed, a current path existed
which picked up another relay (type 94), which tripped R-50. At the,
time of the event, MDS-20 was open so no current path existed to
actuate the type 94 relay for the line 6 breaker, R-60.
The trip of R-50 deenergized all equipment being supplied from line 5.
This equipment included UPS-1A, two of the three air compressors,
the
Division I bus and the Division IIIbus.
After about 10 seconds,
the
Division IIIEDG successfully completed an automatic start and
restored power to the Division IIIbus.
After about 20 seconds,
control
e
room annunciators were lost due to the inability of the remaining power
supply (UPS-1B) to sustain the load.
The Division I bus, which had
included one of the two running service water pumps, remained
deenergized
since its dedicated EDG was out of service for planned
maintenance.
Control room operators took a number of initial actions in response to
the event.
These actions included dispatching an operator to the refuel
floor to continuously monitor water level, debriefing the meter and test
personnel on the cause of the event, and declaring an Alert in
accordance with the licensee's Emergency Plan.
About 10 minutes after the event began, the last running air compressor
tripped due to loss of cooling water caused by the loss of line 5. Air
pressure,
already dropping, began to fall more rapidly.
Operators were
concerned
as to the continued leak tightness of the air bladder seals
around the outside of the reactor vessel and in the submerged
main
steam lines.
About 18 minutes after line 5 tripped, control room operators attempted
to restore power to the deenergized
equipment (including the
annunciators) by closing MDS-20 and using power from line 6.
Control room operators
had called the utility's offsite power control
center in Syracuse
and had been told that the travelling switchyard
operator (based about 20 miles south of the plant in Fulton) would be
radioed to go to the Scriba switchyard and close the offsite breakers.
Syracuse personnel estimated a half hour response
time.
The decision to use line 6 followed discussions with the meter and test
personnel who stated that there were no problems with this approach.
This operation also received the concurrence of the senior control room
supervisor.
The Operations Manager and the Plant Manager were also
present at the time with the latter being briefed prior to assuming his
role as the Emergency Director at the Technical Support Center.
The closure of MDS-20 completed the controls logic associated
with the
still tripped type 86 relay for, the auxiliary boiler; this resulted in the
trip of R-60 and the loss of line 6. At this time, Unit 2 had lost all
offsite power (LOOP).
After about 10 seconds,
the Division II EDG successfully completed an
automatic start and reenergized
the Division II bus,
Shortly thereafter,
SWP-1B automatically restarted which restored service water to
Division II loads.
Operators also promptly restarted RHS-P1B to
restore shutdown cooling.
There was no apparent rise in reactor
coolant system temperature during the less than two minute interruption
in shutdown cooling flow.
Service water cooling remained interrupted to the running Division III
'DG due to a potential design deficiency (see Section 3.1.3).
The
Division IIIEDG tripped due to loss of cooling water after about seven
minutes.
Control room operators, in conjunction with meter and test personnel,
determined that failure to reset the initial tripped type 86 relay had
caused the opening of R-60 upon MDS-20 closure.
The type 86 relay
was reset and the Fulton-based operator arrived at the Scriba
switchyard and reclosed the R-50 and R-60 breakers.
The initial
attempt to restore power to the line 5 loads was not successful
because
MDS-3 would not close.
Operators initiated a work request to
troubleshoot MDS-3 but successfully
used a different lineup (from
line 6) to restore power.
No problems were found during
troubleshooting efforts and MDS-3 was later closed successfully.
Upon restoration of the control room annunciators,
operators noted high
reactor building sump level alarms.
The levels were found to be the
result of normal leakage which continued while the sump pumps were
deenergized.
After power w'as restored to the pumps, sump levels
"
returned to normal.
The licensee restored the plant to a normal shutdown lineup and, after
discussions with the NRC and offsite organizations,
terminated the
Alert.
30
PER
L AND
LEAR PL NT
Y TEM
PERF
RMAN E
The AIT assessed
the performance of the personnel and the plant systems before,
during, and after the event.
The findings of the AITare grouped into three broad
categories:
Equipment Performance;
Procedure Adequacy; and Personnel
Performance.
i mn Perfrm
The equipment performed as expected, with the exception of the power
supplies to the control room annunciators,
the instrument air system, and the
Division IIIEDG. Also, MDS-3 initiallyfailed to close, but it was inspected
by the licensee,
no problems were found, and it closed successfully on the next
attempt.
3.1.1
w r
i
R
m
As discus'sed in Section 2.4.1, control room annunciator power from
UPS-1A was from the maintenance supply at the time of the event.
Loss of line 5 deenergized
the maintenance
supply and the power
supplies from UPS-1B sustained the load for less than 30 seconds
before tripping and deenergizing the control room annunciators.
A WR
had been initiated on March 9, 1992, with a "C" priority (less than
7 days) to troubleshoot the inability of UPS-1A to transfer, but no work
had begun as of March 23, 1992.
Post-event investigation determined that one of the small internal
battery packs had failed and, after battery replacement,
UPS-1A was
able to transfer properly from the maintenance
supply.
The licensee
sent the failed battery to a vendor for a failure analysis.
The licensee
planned replacement interval for these batteries was 15 months.
The
failure of one battery after about seven months requires followup.
3.3.2
The loss of line 5 deenergized
two of the three air compressors
and air
pressure
began to drop.
Operators took various actions as valves began
to drift to their failed (on loss of air) positions causing, in some cases,
system transients.
One such transient resulted in the loss of cooling
water to the remaining running air compressor which tripped and
increased
the rate of air pressure
loss.
Operators were also concerned about the possibility of leakage through
the seals around the reactor vessel and in the main steam lines.
The
seals are designed not to fail catastrophically on loss of air but do use
air pressure to enhance leak tightness.
An operator was immediately
dispatched
to continuously monitor water level in the flooded reactor
cavity.
10
Although there was no evidence of seal leakage during the event, the
operators were concerned about possible seal leakage or failure due to
loss of air pressure.
Operators were also required to take various other
actions to mitigate transients caused by loss of air pressure.
No backup
air supply, such as a diesel air compressor for the system or
pressurized
bottles for the seals was provided during the refueling
outage.
3.1.3
Divi i n III D
The Division IIIEDG started,
as designed,
due to undervoltage on the
Division IIIbus caused by the loss of line 5. The EDG supplied the
bus until it tripped on high jacket water temperature
caused by the loss
of service water flow following the loss of line 6.
At the time of the event, service water was available to the Division III
EDG from service water pumps (SWP) on the Division I bus (SWP-1A)
and the Division II bus (SWP-1B).
The loss of line 5 deenergized
the
Division I bus, tripping SWP-1A.
The Division I EDG was out of
service undergoing planned maintenance
so the Division I bus remained
deenergized
until power was restored to it"from an offsite source.
Service water continued to be supplied to the running Division IIIEDG
from SWP-1B, which was powered from the Division II bus being-
energized from line 6.
The service. water supply valves to the Division IIIEDG automatically
shut on low water pressure but require operator action to open.
This
automatic closure feature is blocked for the first minute of Division III
EDG operation.
The time delay is sufficient for the Division I and
Division II EDGs, ifstarted simultaneously with the Division IIIEDG,
to come up to speed and sequence
the service water pumps onto the
buses and restore system pressure.
The design, therefore, assumed
the
simultaneous
loss of offsite power (LOOP) and start of all EDGs.
'he
March 23, 1992 event, involved a sequential loss of offsite power
with 18 minutes between the loss of line 5 and line 6.
The trip of
line 6 deenergized
the Division II bus, tripping the remaining running
service water pump (SWP-1B).
The Division II EDG successfully
started automatically, reenergized
the Division II bus, and the safety-
related components (including SWP-1B) on the bus were reenergized
in
the proper sequen'ce.
The interruption in service water pressure
and
11
flow caused the closure of the Division II service water supply valve to
the running Division IIIEDG since the one minute duration closure
block on the valve had begun 18 minutes earlier when line 5 was lost.
The Division IIIEDG tripped due to loss of cooling'water about
seven minutes later.
The trip of the Division IIIEDG demonstrated
a previously not
recognized vulnerability to a sequential LOOP.
The interrelationship in
the controls logic of the three EDGs would lead to the loss of cooling
water to the Division IIIEDG in the following generalized
scenario:
~
Loss of the offsite line supplying Division IIIand Division I (or
Division II) buses, coincident with main generator trip (or bus
transfer not available);
~
The Division IIIEDG starts successfully but the other EDG fails
(or is not in service);
~
Loss of remaining offsite line 15 seconds or more later.
The possibility that a sequential LOOP may be more limiting than a
simultaneous LOOP is a potential generic issue.
The above scenario
also indicates the net to reassess
the NMP-2 emergency core cooling
system (ECCS) with respect to this previously not recognized
vulnerability.
3.2
Pr
edure Ad
ac
In general,
the licensee's
procedures
were adequate,
and they provided
direction to control the event,
However, the plant electrical procedures
were
cumbersome
and in some cases contained generic information in lieu of
specific details.
An example is, the system operating procedures for the
115 kV Switchyard, 13.8 kV/4.16 kV/600V, and Emergency A.C.
Distribution systems all contain the same generic information for a "Loss of
Bus" event.
This type of procedure format does not ensure a consistent
operational practice between all operating crews.
The overhead alarm response procedure for the tripped backup overcurrent
relay No. 852426, "Aux Boiler Transformer BU LKO Relay Trip" did not
contain the relay impact on 115 kV line 5 or 6.
12
Procedure N2-OP-72, "Standby and Emergency A.C. Distribution," was the
only procedure that specifically stated to reset lockout relays (86 overcurrent
devices) prior to energization of the 4.16 kV 1E busses.
Operating procedures
N2-OP-70, "Station Electrical Feed and 115 kV Switchyard," and N2-OP-71,
"13.8 kV/4160V/600V A.C. Power Distribution," did not direct the operators
to reset tripped relays prior to energizing electrical busses or distribution lines.,
The operating procedure used to cross-tie 115 kV Line 6 to reserve station
service transformer 1A, N2-OP-70 section H.5.0, did not reference the
protective interlock trip from the auxiliary boiler transformer regular or
backup overcurrent relays (86 devices).
The procedure used to return 115 kV Line 5 to service is an example of a
cumbersome procedure.
Procedure N2-OP-70 section 7,0 provides direction to
first, go to procedure N2-OP-71 section H, and perform steps 1.0.a through
1.0.n or H.5.0 as applicable.
The operator returns back to procedure N2-OP-
70 for nine steps.
After completing the nine steps, procedure N2-OP-70
directs the operator back to procedure N2-OP-71 section H.6.0.
The first step
in N2-OP-71 section 6.0.a. refers the operator back into procedure N2-OP-70
section E,
N2-OP-70 section E.2.0 and 3.0 provide direction to energize
reserve station service transformer 1A. When the reserve station service
transformer 1A is energized,
the operator returns to procedure N2-OP-71
section 6.0.b. to complete the restoration of power to the 13.8 kV and
4.16 kV buses.
3.3
Per
nnel Perf rmance
3.3.1
Auxilia
iler
Rela
li
i n W rk Packa
e
The work package prepared for the calibration of the auxiliary boiler
backup overcurrent protection. relays was not adequate.
The package
did not contain all the drawings needed to understand
the effects should
any of the relays be actuated.
The plant impact assessment,
which was
part of the work package, did not address
the impact of inadvertent
relay actuation during the work. Work package review activities,
which were corrective actions following the Nine Mile Point Unit 1
loss of ultimate heat sink (see NRC Inspection Report 50-220/92-80),
did not identify and correct these deficiencies.
Similar problems were found in other relay work packages,
but a
review of a sample of non-relay work packages did not identify similar
deficiencies.
13
3.3.2
M
r
n
T
T
hni i
The performance of the meter and test personnel during the event was
weak.
The technician working at the relay and replacing the cover did not
know the effects of inadvertent relay actuation.
The technician
performance error during cover replacement was inadvertent and, due
in part, to human factor problems.
Only a small positioning error was
necessary
to bump the contacts closed and the technician had to lean
over in a kneeling position to replace the cover on the relay which was
just a few inches from floor level.
The prompt, forthright disclosure of the performance error helped
control room operators understand
the cause of the loss of line 5.
Due
to the concurrent loss of control room annunciators,
operators were not
able to identify immediately the cause of the event and thought initially
that it had originated offsite.
The ASSS asked the meter and test personnel, who had come to the
control room to explain the trip, ifthere was any problem in closing
MDS-20 preparatory to using power from line 6 to reenergize lost
buses,
The meter and test personnel inaccurately stated that there was
no problem in the proposed course of action.
Closure of MDS-20
caused
the trip of R-60 and the loss of line 6 (LOOP), since the initial
relay trip had not been reset.
3.3,3
n r l R
m
The licensed operators'esponse
to the loss of 115 kV offsite electrical
power was good.
The shift correctly classified the loss of control room
as an Alert. The operators
made a reasonable
decision to
restore electrical power to the Division I distribution system from
115 kV line 6.
The factors affecting their decision were:
1) continued
loss of all control room overhead annunciators;
2) dropping air pressure
resulting in the possibility of leaking main steam line plug and refuel
cavity seals, which could have led to a loss of water in the reactor
cavity and spent fuel pool; 3) known delays, of at least one half hour,
to restore the normal electrical power to reserve station service
transformer "A" from the offsite 115 kV switchyard; 4) the auxiliary
boiler transformer was electrically isolated (the overcurrent relay that
was inadvertently tripped was a protective device for the auxiliary
boiler transformer); 5)
when asked by the assistant
station shift
supervisor (ASSS), the relay personnel informed the operators that
14
there was no threat to 115 kV line 6 ifthey used Line 6 to restore
power to reserve station service transformer 1A; 6) the relay senior
tester had ten years experience at NMP-2, was familiar with the relay
protective trips, and was the technical expert in the area of relay
knowledge.
The restoration of power was good even though the electrical system
operating procedures
were cumbersome.
The procedure problems
details are discussed in section 3.2.
The station shift supervisor (SSS) exhibited good command and control
while conducting the plant restoration.
Specifically, the restoration of
the residual heat removal (RHR) shutdown cooling system was timely.
The operators'ecisions
for plant restoration were influenced by some
circumstances
beyond their control.
Examples are listed below.
~
The restoration of the 115 KV electrical power required a
traveling operator, based out of Fulton, New York.
~
The overhead annunciator alarms were lost 20 seconds after the
loss of 115 kV line 5.
~
The plant did not have a backup contingency for the loss of
instrument and service air.
4.0
ENERI
IMPLI ATI N
F THI EVENT
The AIT reviewed this event for generic implications and identified one item that has
potential generic implications,
The trip of the Division IIIEDG (see Section 3.1.3)
demonstrated
that a sequential LOOP might be more limiting, in some cases,
than an
'nstantaneous
LOOP.
5.0
LI EN EE
RRE TIVE A TI N
5.1
Immediate
rrective A i n
1.
Immediately following the event, the plant manager issued a stop work
order with respect to all relay work.
2.
A review of all relay work requests
was ordered.
15
3.
An assessment
organization was formed to investigate the circumstances
leading to this event, plant response
and personnel action before,
during, and after the transient, and the root cause of the event.
These
actions included assessing
possible modifications to prevent recurrence
of the Division IIIEDG trip.
5.2
h
T rm
n
T rm
iv A'
In addition to the immediate actions described in Section 5.1, the licensee
implemented or announced
planned corrective actions to address
weaknesses
and concerns identified following the event.
These short term and long term
corrective actions were in the following areas:
work control, meter and test
technician job performance,
operator performance, Division IIIEDG
reliability, and control room annunciator power supply reliability.
The licensee was requested
to document and discuss these short term and long
term corrective actions by letter to the NRC within 30 days of receipt of this
report.
The effectiveness of the corrective actions will be reviewed as part of
the routine inspection program.
6.0
NL
I N
The AIT concluded that the cause of the initiating event (relay trip of line 5) was an
inadvertent technician performance error caused, in part, by human factors problems.
The loss of control room annunciators
was caused due to a continued vulnerability in
the current design during shutdown or transient conditions.
Delays in addressing
a
known problem in one source of power to the annunciators
(UPS-1A) indicates a need
for review of oversight of prioritization and scheduling.
The AIT identified the following weaknesses
in management
support of operations:
1)
Acceptance of delays in operation of offsite power supply breakers inherent in
the use of a travelling operator based in Fulton, New York.
2)
Absence of a backup air supply during the refueling outage with air 'pressure
being used in reactor vessel and main steam line seals.
3)
Acceptance of cumbersome,
generic procedures which require operators to use
concurrently several procedures during an event such as a LOOP.
16
The Division IIIEDG was not required to mitigate this event, but the trip of the EDG
demonstrated
a generic and previously not recognized vulnerability (see Section 3.1.3)
that requires followup.
II
The consequences
of this event were minimal because the reactor core and the reactor
coolant were unaffected by this event, there was no equipment or structural damage,
and no radiation was released.
7.0
ANA EMENT MEETIN
The licensee management
was informed of the scope of this AITduring an entrance
meeting on Tuesday, March 24, 1992.
The licensee management
was briefed of the
inspection observations routinely and at the conclusion of onsite review on Saturday,
March 28, 1992.
A public exit meeting was conducted on April 1, 1992 at 1:00 p.m. at the licensee's
training facilities with licensee representatives
identified in Appendix C to discuss the
preliminary inspection findings.
The licensee acknowledged the inspection findings
and provided the results of their assessment
of the event and the short and long term
corrective actions for both units.
TABLE 1
HR N L
Y
3/09/92
UPS 1A transferred automatically to maintenance power supply due to voltage fluctuation
associated
with energization of main turbine EHC system.
Attempts to manually transfer UPS 1A back to its normal source were unsuccessful.
Work
Request (WR) 201538 was initiated with a seven-day priority to resolve problem.
3/20/92
Meter and test technicians began calibrating relays using electrical preventive maintenance
procedure (No. S-EPM-GEN-2Y070)
3/23/92
E
Initial Plan
n itions:
The plant was in the refueling mode with the reactor vessel head removed and the reactor,
cavity flooded to normal refuel level.
Approximately on-third of the core had been
transferred to the spent fuel pool, but no refueling activities were in progress.
Emergency
diesel generator (EDG-EGS1) and associated
ECCS systems were out-of-service for planned
maintenance.
All'other equipment was in a normal shutdown lineup for existing plant
conditions.
The electrical lineup is shown on Figure 2.
1008
Auxiliary boiler overcurrent protection relay actuated during cover replacement by
technician following calibration,
At this time offsite 115 kV power line 5 tripped
which deenergized
UPS-1A and the Division I and the Division IIIsafety-related
boards.
Loss of the 4 kV boards stopped the Division I service water pump (SWP-
1A) and instrument air compressor (C1A).
After about 10 seconds,
EDG-EG2 successfully completed an automatic start and
restored power to the Division III4 kV board.
After about 20 seconds,
control room
annunciators were deenergized
due to inability of the remaining power supply (UPS-
1B) to sustain the load.
1009
Operator sent to refuel floor, confirmed no drop in water level, established
communications with the control room, and remained there to monitor level.
1016
Licensee declared Alert in accordance with the emergency plan due to loss of control
room annunciators.
1018
The remaining running air compressor
(C1B) tripped due to loss of cooling water,
Table
1
1026
Operators closed MDS-20 in attempt to reenergize UPS-1A and the Division I 4 kV
board from offsite 115 kV power line 6.
This resulted in loss of line 6 due to failure
to first reset relay which initiated the original trip of line 5. At this time, the site had
'ost all offsite power (LOOP).
Loss of line 6 deenergized
the Division II 4 kV board which tripped SWP-1B (the
only remaining service water pump) and RHS-P1B (the pump providing shutdown
cooling). About 10 seconds later, EGS-EG3 successfully completed-on automatic
start and restored power to the Division II 4 kV boards.
1027
SWP-1B automatically restarted per design, restoring service water for Division II
, loads.
1028
RHS-P1B restarted
(shutdown cooling restored).
1033
EDG-EG2 tripped on high jacket water temperature.
1044
Operations personnel reset auxiliary boiler overcurrent protection relay which had
initiated trip of line 5 and, later, line 6.
1046
Offsite power available to Division II 4 kV board (powered at this time from the
running EDG-EG3).
1055
Initial attempts to restore power to UPS-1A, the Division I 4 kV board and the
Division III4 kV board were not successful
(MDS-3 would not close);
1131
UPS-1A restored which restored control room annunciators,
1136
Instrument air pressure
restored to normal.
1144
Division I 4 kV board reenergized
(via line 6 through the auxiliary boiler
transformer).
1221
Division III4 kV board reenergized
(via line 6 through RTX-1B).
1245
EDG-EG3 removed from Division II 4 kV board (powered at this time from line 6);
I
1307
SWP-P1A restarted.
1317
Alert terminated.
~0.8 RINGO
4
O
if***4
APPENDIX A
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION I
475 ALLENDALEROAD
KING OF PRUSSIA, PENNSYLVAN(A19406.1415
MAR 24 892
MEMORANDUMFOR:
Marvin W. Hodges, Director
Division of Reactor Safety
Charles W. Hehl, Director
Division of Reactor Projects
FROM:
SUBJECT:
Thomas T. Martin
Regional Administrator
AUGMENTED INSPECTION TEAM (AIT) CHARTER - LOSS
OF OFFSITE POWER WITH COMPLICATIONS
You are directed to perform an Augmented Inspection Team (AIT)review of the causes,
safety
implications, and associated
licensee actions which led to the inadvertent loss of offsite power
and control room annunciations
at Nine Mile Point Station Unit 2.
The basis of the NRC
concern is the management
control of maintenance
activities that allowed the event to occur.
,The inspection shall be conducted
in accordance
with NRC Manual Chapter 0513, Part III,
Inspection Procedure 93800, Regional Instruction 1010.1
and additional instructions
in this
memorandum.
DRS is assigned
responsibility for the overall conduct of this inspection.
DRP is assigned
responsibility for resident
inspector
and clerical support and coordination with other NRC
offices. J. Beall is designated
as the onsite Team Leader.
Team composition is described
at the
end of this memorandum.
Team members are assigned to this task until the report is completed
and will report to Mr. Beall.
OBBJR
V
The general objectives of this AITare to:
Conduct a timely, thorough, and systematic review of the circumstances surrounding the
event, including the sequence ofevents that led to and followed the March 23, 1992, loss
of offsite power and control room annunciator panels;
b.
Collect, analyze,
and document relevant data and factual information to determine the
causes,
conditions, and circumstances
pertaining to the event, including the response
to
the event by the licensee's operating staff;
MAR 2 4 1392
Marvin W. Hodges
Assess
the
safety
significance of the
event
and
communicate
to
Regional
and
Headquarters
management
the facts
and
safety
concerns
related
to the problems
identified; and
d.
Evaluate the appropriateness
of the licensee's review of and response
to the event and
implemented corrective actions.
FTHEIN P
The AIT should identify and document the relevant facts and determine the probable causes of
the event.
It should also critically examine the licensee's
response
to the event.
The Team
Leader shall develop and implement a specific, detailed plan addressing
this event.
The AIT should:
a.
b.
Develop a detailed chronology of the event;
Determine the root causes of the event and document equipment problems,
failures,
and/or personnel errors which directly or indirectly contributed to the event.
Potential items to be considered:
~
Operator actions during and following the event;
~
Outage
planning includirig adherence
to controls
and
schedule
to minimize
shutdown risk.
~
Management and administrative controls in place before, during and following the
event.
Coordination of maintenance
activities before and during the event, including
worh planning and control.
Assess the performance of the UPS system during the event.
Sensitivity to plant conditions.
~
Communications among plant personnel
and with/within control room.
I
~
~
VAR 2 4 1992
Marvin W. Hodges
C.
Determine the expected
response of the plant and compare it to the actual response.
Assess plant response including but not limited to the following:
~
EDG IIItripping
~
Cause of delays in restoring offsite line five
~
Cause of the reactor building sump alarms
d.
e.
Assess the adequacy of the responses of the operations and technical support staffs to the
event and the initial licensee analysis.
Assess licensee actions in restoring power.-
I
Determine the management response including the scope and quality ofshort-term actions
and gather information related to the long-term actions intended to prevent recurrence of
this event, including internal and external communications/dissemination
of licensee-
identified concerns and corrective actions.
f.
Determine the relationship ofprevious events or precursors, including site-related, ifany,
to this event.
g.
Determine the potential generic implications of this event, such as recommend
lessons
learned, and the necessity for generic industry communications.
,"i~HEDULE
The AIT shall be dispatched
to Nine Mile Point Station Unit 2 so as to arrive and commence
the inspection on March 24, 1992. A written report on this inspection shall be provided to me
within three weeks of completion of the onsite inspection.
TEAM
ITI N
The assigned Team members are as follows:
Team Manager:
Onsite Team Leader:
Onsite Team Members:
M. Hodges, DRS
J. Beall, DRS
S. Hansell, DRS
D. Brinkman, NRR
J. Ibarra, AEOD
homas T. Martin
Regional Administrator
MAR 24 892
'arvin
W. Hodges
CC:
W. Kane, DRA
W. Hehl, DRP
C. Cowgill, DRP
L. Nicholson, DRP
Team Members
R. Lobel, OEDO
J. Calvo, NRR
R. Capra, NRR
K. Abraham, PAO
L. Spessard,
E. Rossi, NRR
W. Lanning, DRS
J. Durr, DRS
L. Bettenhausen,
SRI NMP-1
APPENDIX B
PER
N
NTA TED
MhawkP wr
ti n
~Nme
C. Beckham
J. Burton
T. Collins
M. Conway
R. Crandall
K. Dahlberg
J. Darling
A. DeGracia
S. Doty
E. Dragomer
J. Endries
M. Eron
C. Gerberich
D. Hanczyk.
D. Hosmer
A. Julka
D. Kinney
H. Lockwood
D. Lomber
M. McCormick, Jr.
R. Menikheim
J. Pavel
F. Peters
L. Pisano
R. Reynolds
R. Slade
J. Spadafore
R. Sylvia
C. Terry
T. Tomlinson
D. White
S. Wilczek, Jr.
/itin
, Unit 2
Unit 2
4
Manager, QA Operations, Unit 2
Manager, QA Operations, Unit 1
Technician, Meter and Test
Station Shift Supervisor, Unit 2
System Engineer
Unit 1 Plant Manager
Technician, Meter and Test
Operations Manager, Unit 2
General Supervisor, Electrical Maintenance
Station Shift Supervisor, Unit 2
President,
Niagara Mohawk Corporation
Assistant Station Shift Supervisor, Unit 2
Control Room Operator, Unit 2
Control Room Operator, Unit 2
Unit 2 Manager Outage/Wk Control
Supervisor, Electrical Design, Unit 2
Operations Planner
Technician, Meter and Test
Control Room Operator, Unit 2
Unit 2 Plant Manager
Supervisor, Meter and Test
Site Licensing Engineer
Technician, Meter and Test
Unit 1 Outage Manager
Control Room Operator, Unit 2
General Supervisor, Training Operations,
Program Director, ISEG
Executive V.'. - Nuclear
V. P. - Nuclear Engineering
Supervisor, Reactor Engineering, Unit 2
Assistant to the Plant Manager, Unit 2
V. P. - Nuclear Support
Appendix B
N
l
R
l
mmi
i n
R, Capra
C. Cowgill
M. Hodges
~ L. Nicholson
- W. Schmidt
Project Director, NRR
Branch Chief, RI
Director, DRS
Section Chief, DRP
Senior Resident Inspector
- Denotes those present at the exit meeting on April 1, 1992, attended by the public and
news media.
The team also held discussions with other licensee management,
operations,
. maintenance,
engineering and quality assurance
personnel.
~
~
APPENDIX
D
ENT
REVIEWED
1.
Chief Shift Operator and Station Shift Supervisor logs for March 23, 1992.
2.
Copies of written statements provided by personnel involved in the event.
3.
Computer alarm logs for 1008 hours0.0117 days <br />0.28 hours <br />0.00167 weeks <br />3.83544e-4 months <br /> - 1308 hours0.0151 days <br />0.363 hours <br />0.00216 weeks <br />4.97694e-4 months <br /> on 03/23/92
4.
Administrative Procedure AP-5.2.5, Rev.01, Work In Progress (WIP)
5.
Administrative Procedure AP-5.4, Rev.04, Conduct of Maintenance
6.
Administrative Procedure AP-5.4.2, Rev. 02, Troubleshooting,
7.
Administrative Procedure AP-5.5, Rev. 02, Work Control
8.
Administrative Procedure AP-5.5.1, Rev. 06, Work Request
9.
Nuclear Division Interfacing Procedure NIP-ECA-01, Rev. 03, Deviation Event Report
10,
Generation Administrative Procedure GAP-OPS-01, Rev. 00, Administration of
Operations
1 1,
Electrical Preventive Maintenance Procedure S-EPM-GEN-2Y070, Revision 1, dated
05/17/88; with Data Sheet (Attachment 10.3) for Equipment Piece No. 2 ABS-X1,
dated 03/23/92; Test Results Information Sheet for 2ABS-X1, dated 03/23/92; and
Work- In Progress
Data Sheet for 2 ABS-X1, dated 03/20/92.
12.
Work Control Monitoring Program Plan for Nine Mile Point Unit One and Unit Two,
.
Revision 0, March 17, 1992.
13.
Nine Mile Point Unit 2 Outage/Work Control Department Instruction Shutdown Safety,
Revision 00 (draft).
14.
Administrative Procedure AP-5.2.3, Revision 03 "Preventive Maintenance Program.
15.
Surveillance Reports 92-15000 dated 03/12/92 and 92-15001 dated 03/20/92.
16.
Surveillance Reports 92-23001 dated 03/12/92 and 92-23002 dated 03/20/92.
17.
Deviation/Event Reports 1-92-Q-0770, 1-92-Q-0771, 1-92-Q-0772, 1-92-Q-0786, 1-92-
Q-0787, 1-92-Q-0818, 1-92-Q-0819, 2-92-Q-0949, 2-92-Q-0950,
1-92-Q-0812, 2-92-Q-0802.
Appendix C
.
2
18.
Training Plans for March 9, 1992 Site Management Meeting for training on the Work
Control Process Monitoring Program.
19.
Work In Progress Data Sheets 2TMI-TE157, 2TMB-T1CIA, 2TMI-TE153, Remote
Shutdown 2CES~PNL405, 2FNR-CRNI, 2SFC-STRS, 2MSS~V1A, 2CND-IPNL287,
2TMI-SE133, 2HDL-LT22A, 2TMI-TE152, Remote Shutdown 2CES~PNL405.
20.
Work Requests
Nos. 190344, 199188, 200401; 201294, 201292, 201538, 200568,
199163, 184946, 177320, 195594, 200150, 200347, 198008, 200523, 200140, 193168,
177162, and 200182.
21.
Operating Procedure N2-OP-70, Rev. 2, Station Electrical Feed and 115KV
22.
Operating Procedure N2-OP-71, Rev. 3, 13.8KV/4160V/600V A.C. Distribution
System
23.
Operating Procedure N2-OP-72, Rev. 4, Standby and Emergency A.C. Distribution
System
P
24.
NMP-2 Training Response
to the NMP-2 Alert on March 23, 1992
25.
Alarm Response
Procedures
(ARP)
852426.Aux Boiler Transformer BU LKO Relay Trip
852434 Reserve Station Transformer 1A Loss of Voltage
852431 Motor Operated Circuit Switcher 2YUC-MDS5 Open
852533 Aux Boiler Transformer Loss of
Voltage'52453
Aux Boiler Transformer Backup Transfer Trip
26,
Drawing 12177-ESK-8YUC05, 115KV Transfer Trip 2nd Alternate, Sh.
1 and 2
27.
Drawing 12177-ESK-8YUC03, 115KV Ckt Switcher 2YUC-MDS5 Cont
28.
Drawing 12177-ESK-8YUC04, 115KV Transfer Trip 1st Alternate, Sh.
1 and 2
29.
~ Drawing 12177-ESK-8SPR14, XFMR 2ABS-X1 RLY
30.
Drawing 12177-ESK-8SPR10,
XFMR 2ABS-Xl Backup Prot
5
31.
Drawing 12177-ESK-8SPR12, XFMR 2ABS-X1 Pri Prot
32.
Drawing 12177-ESK-8SPR11,
XFMR 2ABS-Xl Fault Press Prot
33.
Drawing 12177-EE-1EA-10, 115KV Swyd One Line Diagram
~
~
4
Appendix C
3
34.
Drawing 12177-ESK-8NNS07, XFMR 2ABS-X1 4KV Winding Prot
35.
Drawing 12177-ESK-SNPS07,
BUS 2NPS-SWG002 Supply ACB2-5
'6.
Drawing 12177-ESK-SNNS16, BUS 2NNS-SWG018 Supply CB18-2
37.
Drawing LSK-24-8.2N, Normal Station Service (13.8 KV) Breaker Controls
38.
Drawing LSK-24-5.3A, Auxiliary Boiler Transfer Protection
39.
Drawing LSK-24-7.2C, 115KV Motor Operated Circuit-Switcher Control
40.
Drawing LSK-24-5.2C, '115KV Line Protection Transfer Trip
k
41.
Drawing LSK-24-8.60, 4.16KV Normal Station Service Breaker Control
42.
Nine Mile Point Nuclear Station Unit 2, One Line Diagram, 115KV Switchyard Offsite
Power Sources Backup Protection, Sheets
1 and 2, Provided on March 26, 1992
43.
Nine Mile Point Nuclear Station Unit 2, One Line Diagram, Present Arrangement
.
UPS1A & 1B Power Feeds to NSSS Annunciator Panel 2CEC-PNL630, Provided on
March 26, 1992
44.
Nine Mile Point Nuclear Station. Unit 2, One Line Diagram, Present Arrangement
UPS1A & 1B Power Feeds to BOP Annunciator Panels 2CEC-PNL858 & 2CEC-
PNL833, Provided on March 26, 1992
45.
Exide Electronic Drawing C1061373, Logic Supply and Relay Panel UPS MKII-A
FIGURE
1
NINE MILE POINT UNIT 2
SIMPLIFIED ELECTRICAL DISTRIBUTION
LINE 5
LINE 6
SCRIBA
NMP-2
SITE
R-50
MDS10
MDS-20
R-60
. MDS-5
MDS-3
TRANSFORMER
MDS-4
RSST-A
TRANSFORMER
AUX BOILERS
RSST-B
TRANSFORMER
DIVISION I
DIVISION III
DIVISION II
=