Letter Sequence RAI |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting
Results
Other: CNL-16-008, Update on Progress of Facility Modifications for MSIV Leak Rate, CNL-18-112, Extended Power Uprate - Flow Induced Vibration Summary Report, CNL-18-124, Extended Power Uprate - Replacement Steam Dryer Final Load Definition and Stress Reports, CNL-18-134, Extended Power Uprate - Replacement Steam Dryer Revised Analysis and Limit Curves Report, ML15282A189, ML16085A301, ML16105A297, ML16105A441, ML16168A026, ML16176A316, ML16189A343, ML17062A390, ML17062A403, ML17181A450
|
MONTHYEARML15282A1892015-08-31031 August 2015 ANP-3372NP, Revision 1, Browns Ferry Unit 3 Cycle 19 EPU (120% OLTP) LAR Reference Fuel Cycle Design Project stage: Other ML15282A2252015-08-31031 August 2015 ANP-3409NP, Revision 2, Fuel-Related Emergent Regulatory Issues Project stage: Request ML15282A1822015-08-31031 August 2015 ANP-3403NP, Revision 2, Fuel Uprate Safety Analysis Report for Browns Ferry Units 1, 2, and 3, Attachment 9 Project stage: Request ML15282A1932015-08-31031 August 2015 ANP-3385NP, Revision 1, Mechanical Design Report for Browns Ferry Units 1, 2, and 3 Extended Power Uprate (EPU) ATRIUM-10 Fuel Assemblies, Licensing Report Project stage: Request ML15282A2362015-08-31031 August 2015 NEDO-33824, Revision 0, Engineering Report, Browns Ferry Replacement Steam Dryer Stress Analysis Project stage: Request ML15282A1902015-08-31031 August 2015 ANP-3404NP, Revision 2, Browns Ferry Unit 3 Cycle 19 Representative Reload Analysis at Extended Power Uprate Project stage: Request ML15282A2232015-08-31031 August 2015 ANP-2860NP Revision 2, Supplement 2, Browns Ferry Unit 1 - Summary of Responses to Request for Additional Information, Extension for Use of Atrium 10XM Fuel for Extended Power Uprate Project stage: Supplement ML15282A1882015-08-31031 August 2015 ANP-3342NP, Revision 1, Browns Ferry EPU (120% OLTP) Equilibrium Fuel Cycle Design Project stage: Request ML15282A1872015-08-31031 August 2015 ANP-3384NP, Revision 3, Browns Ferry Units 1, 2 and 3, LOCA-ECCS Analysis MAPLHGR Limits for ATRIUM-10 Fuel (Epu) Project stage: Request ML15282A1852015-08-31031 August 2015 ANP-3378NP, Browns Ferry Units 1, 2 and 3, LOCA-ECCS Analysis MAPLHGR Limits for Atrium 10XM Fuel (Epu) Project stage: Request ML15282A1922015-08-31031 August 2015 ANP-3386NP, Revision 1, Mechanical Design Report for Browns Ferry Units 1, 2 and 3 Extended Power Uprate (EPU) Atrium 10XM Fuel Assemblies, Licensing Report Project stage: Request ML15282A1842015-08-31031 August 2015 ANP-3377NP, Browns Ferry Units 1, 2 and 3 LOCA Break Spectrum Analysis Atrium 10XM Fuel (Epu) Project stage: Request ML15282A1522015-09-21021 September 2015 Submits Proposed Technical Specifications Change TS-505 - Request for License Amendments - Extended Power Uprate Project stage: Request ML15282A2402015-09-21021 September 2015 Startup Test Plan Project stage: Request ML15282A2222015-09-21021 September 2015 Cycle 19 MCPR Safety Limit Analysis with SAFLIM3D Methodology Project stage: Request ML15282A2412015-09-21021 September 2015 List and Status of Plant Modifications Project stage: Request ML15282A1812015-09-21021 September 2015 Non-Proprietary - Safety Analysis Report for Browns Ferry, Units 1, 2 and 3, Extended Power Uprate, Attachment 7 Project stage: Request ML15282A2352015-09-21021 September 2015 RHR Heat Exchange K-values Utilities in EPU Containment Analyses Project stage: Request 05000259/LER-2015-002, Regarding High Pressure Coolant Injection System Inoperable Due to Slow Containment Isolation Valve Closing Time2015-09-21021 September 2015 Regarding High Pressure Coolant Injection System Inoperable Due to Slow Containment Isolation Valve Closing Time Project stage: Request CNL-15-249, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 1, Spent Fuel Pool Criticality Safety Analysis Information2015-12-15015 December 2015 Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 1, Spent Fuel Pool Criticality Safety Analysis Information Project stage: Supplement CNL-15-250, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 2, MICROBURN-B2 Information, Including Enclosures 2, 4, 6, and 72015-12-15015 December 2015 Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 2, MICROBURN-B2 Information, Including Enclosures 2, 4, 6, and 7 Project stage: Supplement CNL-15-261, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 3, Interconnection System Impact Study Information2015-12-18018 December 2015 Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 3, Interconnection System Impact Study Information Project stage: Supplement ML16032A0442016-02-0101 February 2016 Fws to NRC, Updated List of Threatened and Endangered Species That May Occur in Your Proposed Project Location for Browns Ferry EPU Project stage: Request ML16041A3072016-02-18018 February 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI ML16040A2322016-02-25025 February 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI ML16041A0222016-02-25025 February 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI ML16049A4632016-02-29029 February 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI CNL-16-045, Proposed Technical Specifications (Ts)Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 6, Response to Request for Additional Information2016-03-0909 March 2016 Proposed Technical Specifications (Ts)Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 6, Response to Request for Additional Information Project stage: Supplement ML16062A0722016-03-15015 March 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI CNL-16-048, Responses to Requests for Additional Information, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU)2016-03-24024 March 2016 Responses to Requests for Additional Information, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) Project stage: Response to RAI ML16084A3202016-03-25025 March 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI CNL-16-055, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 8, Response to Request for Additional Information2016-03-28028 March 2016 Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 8, Response to Request for Additional Information Project stage: Supplement ML16089A1372016-03-29029 March 2016 NRR E-mail Capture - Correction to Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI ML16064A2862016-04-0404 April 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI ML16091A0712016-04-0707 April 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI ML16085A3012016-04-11011 April 2016 Regulatory Audit Plans for April 19 - 21, 2016, Audit at Excel Facility in Rockville, Maryland, in Support of Extended Power Uprate License Amendment Request Project stage: Other CNL-16-069, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 11, Responses to Requests for Additional Information2016-04-14014 April 2016 Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 11, Responses to Requests for Additional Information Project stage: Supplement ML16102A3392016-04-14014 April 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI ML16085A0792016-04-14014 April 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI ML16104A2452016-04-20020 April 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI ML16105A2972016-04-21021 April 2016 Regulatory Audit Plan for May 3-4, 2016, Audit at Excel Facility in Rockville, Maryland, in Support of Extended Power Uprate License Amendment Request Project stage: Other ML16105A4412016-04-27027 April 2016 Regulatory Audit Plan for May 10-11, 2016, Audit at Excel Facility in Rockville, Maryland, in Support of Extended Power Uprate License Amendment Request Project stage: Other CNL-16-077, For Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Update (EPU) - Supplement 14, Response to Request for Additional Information2016-04-27027 April 2016 For Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Update (EPU) - Supplement 14, Response to Request for Additional Information Project stage: Supplement ML16119A4402016-05-0606 May 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate Project stage: RAI ML16119A1332016-05-0606 May 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate (SNPB-RAI) Project stage: RAI CNL-16-079, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 15, Responses to Requests for Additional Information2016-05-11011 May 2016 Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 15, Responses to Requests for Additional Information Project stage: Supplement ML16120A0722016-05-12012 May 2016 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML16124B1062016-05-12012 May 2016 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML16124A9322016-05-12012 May 2016 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML16123A3352016-05-16016 May 2016 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance 2016-03-29
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3R-C Chattanooga, TN 37402-2801 June 3, 2016
SUBJECT:
BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO LICENSE AMENDMENT REQUEST REGARDING EXTENDED POWER UPRATE (CAC NOS. MF6741, MF6742, AND MF6743)
Dear Mr. Shea:
By letter dated September 21, 2015, as supplemented by letters dated November 13, December 15 (2 letters), and December 18, 2015, Tennessee Valley Authority (TVA) submitted a license amendment request for the Browns Ferry Nuclear Plant, Units 1, 2, and 3. The proposed amendment would increase the authorized maximum steady-state reactor core power level for each unit from 3,458 megawatts thermal (MWt) to 3,952 MWt. This license amendment request represents an increase of approximately 20 percent above the original licensed thermal power level of 3,293 MWt, and an increase of approximately 14.3 percent above the current licensed thermal power level of 3,458 MWt.
The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the licensee's submittals and determined that additional information is needed. On May 6, 2016, the NRC staff forwarded, by electronic mail, a draft request for additional information (RAI) to TVA. On May 12, 2016, Mr. Daniel Green of TVA informed the NRC staff that a clarification call is not requested and the draft RAI does not contain any sensitive or proprietary information. As agreed to by the NRC and TVA staff, TVA will respond to the enclosed RAI by June 24, 2016.
If you have any questions, please contact me at 301-415-1447 or Farideh.Saba@nrc.gov.
Docket Nos. 50-259, 50-260, and 50-296
Enclosure:
Request for Additional Information cc w/enclosure: Distribution via Listserv Sincerely, Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST REGARDING EXTENDED POWER UPRATE TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3 DOCKET NOS. 50-259, 50-260, AND 50-296 By letter dated September 21, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15282A152), as supplemented by letters dated November 13, December 15 (2 letters), and December 18, 2015 (ADAMS Accession Nos. ML15317A361, ML15351A097, ML15351A113, and ML15355A413, respectively), Tennessee Valley Authority (TVA, the licensee) submitted a license amendment request (LAR) for Browns Ferry Nuclear Plant (BFN), Units 1, 2, and 3. The proposed amendment would increase the authorized maximum steady-state reactor core power level for each unit from 3,458 megawatt thermal (MWt) to 3,952 MWt. This LAR represents an increase of approximately 20 percent above the original licensed thermal power level of 3,293 MWt, and an increase of approximately 14.3 percent above the current licensed thermal power level of 3,458 MWt.
The NRC staff from the Balance of Plant Branch (SBPB), Devision of Safety Systems, Office of Nuclear Reactor Regulation reviewed the information the licensee provided and determined that the following additional information is required in order to complete the evaluation.
SBPB-RAI [Request for Additional Information] 4 Regulatory Bases:
The following regulations and requirements are applicable to this RAI:
Section 50. 67, "Accident Source Term," of Title 1 O of Code of Federal Regulations (10 CFR)
Regulatory Guide 1.183 "Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, Regulatory Position 1.5 "Submittal Requirements" as summarized below:
According to 1 O CFR 50.90, an application for an amendment must fully describe the changes desired and should follow, as far as applicable, the form prescribed for original applications. Regulatory Guide 1.70, "Standard Format and Content of Safety Analysis Reports for Nuclear Power Plants (LWR [Light-Water Reactor]
Edition)" (Ref. 16), provides additional guidance. The NRC staff's finding that the amendment may be approved must be based on the licensee's analyses, since it is these analyses that will become part of the design basis of the facility. The amendment request should describe the licensee's analyses of the radiological and non-radiological impacts of the proposed modification in sufficient detail to support review by the NRC staff.
Enclosure Plant Specific Technical Specification (TS) proposed change:
Current Surveillance Requirement (SR):
SR 3.6.3.1.1 "Verify ~ 2500 gal [gallons] of liquid nitrogen are contained in each nitrogen storage tank." (Frequency: 31 days).
Proposed SR:
SR 3.6.3.1.1 "Verify ~ 2615 gal of liquid nitrogen are contained in each nitrogen storage tank." (Frequency: 31 days).
The staff notes that the BFN Updated Final Safety Analysis Report (UFSAR) (BFN-26)
Chapter 5, Section 5.2.6 "Combustible Gas Control in Primary Containment" and Chapter 14, Section 14.6.3.5 "Fission Product Release From Primary Containment" and Section 14.6.3.6 "Fission Product Release to Environs" provides two different values for containment exhaust flow rates for the containment atmosphere dilution (CAD) system. Chapter 5 provides a flow rate of 100 ft3/min (cubic feet per minute (cfm)), whereas Chapter 14 provides a flow rate of 139 cfm. In particular, Section 14.6.3.6d reads "The Containment Atmospheric Dilution (CAD) system operates for a period of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> at a flow rate of 139 cfm at 10 days, 20 days, and 29 days post-accident. This flow is filtered via the SGTS [Standby Gas Treatment System]
filters."
The staff reviewed Section 2.6.4 "Combustible Gas Control in Containment" and Figures 2.6-1 through 2.6-4 of LAR Attachments 8 (proprietary) and 9 (non-proprietary). Attachment 9 reads in part:
Technical Specification (TS) 3.6.3.1 "Containment Atmospheric Dilution (CAD)
System," requires that 2500 gallons of liquid nitrogen (191,000 scf [standard cubic feet]) be stored in each of two tanks to meet the CAD system inerting requirements. As a result of increased production rate of radiolytic gas following EPU [extended power uprate], the required 7-day volume of nitrogen to satisfy TS 3.6.3.1 increases to 2615 gallons (200,000 scf) from 2108 gallons (161,200 scf) under CL TP [current licensed thermal power] conditions, which exceeds the available 2500 gallons (191,000 scf) supply required by TS 3.6.3.1.
Analysis of the containment pressure buildup as a result of continuing CAD operation, under EPU conditions, shows that the containment repressurization limit of 30 psig [pounds per square inch gauge] is reached 15 days post-LOCA
[loss-of-coolant accident], compared to 18 days under CL TP conditions.
The NRC staff could not determine from the information contained in the LAR submittal of September 21, 2015, the BFN Alternate Source Term LAR, or the subsequent license amendment, whether the increase in required liquid nitrogen volume (i.e., from 2500 to 2615 gal) per SR 3.6.3.1.1 factored into the Chapter 14 CAD system flowrate of 139 cfm to the SGTS and ultimately to the plant environs via the plant stack.
REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST REGARDING EXTENDED POWER UPRATE TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2. AND 3 DOCKET NOS. 50-259, 50-260, AND 50-296 By letter dated September 21, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15282A152), as supplemented by letters dated November 13, December 15 (2 letters), and December 18, 2015 (ADAMS Accession Nos. ML15317A361, ML15351A097, ML15351A113, and ML15355A413, respectively), Tennessee Valley Authority (TVA, the licensee) submitted a license amendment request (LAR) for Browns Ferry Nuclear Plant (BFN), Units 1, 2, and 3. The proposed amendment would increase the authorized maximum steady-state reactor core power level for each unit from 3,458 megawatt thermal (MWt) to 3,952 MWt. This LAR represents an increase of approximately 20 percent above the original licensed thermal power level of 3,293 MWt, and an increase of approximately 14.3 percent above the current licensed thermal power level of 3,458 MWt.
The NRC staff from the Balance of Plant Branch (SBPB), Devision of Safety Systems, Office of Nuclear Reactor Regulation reviewed the information the licensee provided and determined that the following additional information is required in order to complete the evaluation.
SBPB-RAI [Request for Additional Information] 4 Regulatory Bases:
The following regulations and requirements are applicable to this RAI:
Section 50.67, "Accident Source Term," of Title 10 of Code of Federal Regulations (10 CFR)
Regulatory Guide 1.183 "Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors," Regulatory Position 1.5 "Submittal Requirements" as summarized below:
According to 10 CFR 50.90, an application for an amendment must fully describe the changes desired and should follow, as far as applicable, the form prescribed for original applications. Regulatory Guide 1. 70, "Standard Format and Content of Safety Analysis Reports for Nuclear Power Plants (LWR [Light-Water Reactor]
Edition)" (Ref. 16), provides additional guidance. The NRC staff's finding that the amendment may be approved must be based on the licensee's analyses, since it is these analyses that will become part of the design basis of the facility. The amendment request should describe the licensee's analyses of the radiological and non-radiological impacts of the proposed modification in sufficient detail to support review by the NRC staff.
Enclosure
ML16145A158 OFFICE NRR/DORL/LPLI 1-2/PM NRR/DORL/LPLll-2/LA NAME FSaba BClavton DATE 6/03/2016 6/02/2016 OFFICE NRR/DORL/LPLll-2/BC NRR/DORL/LPLll-2/PM NAME (PBuckberg for) BBeasley FSaba DATE 6/03/2016 6/03/2016 ASallman, NRR RidsNrrDssSbpb
- by memorandum NRR/DSS/SBPB/BC*
RDenniq 5/02/2016