APPLICATIONS FOR NUCLEAR POWER PLANTS Regulatory Guide 1.206 [Revision]

Draft Revision February 27, 2015 A. Introduction B. Discussion C. Guidance C.1 Application Format & Content

1. Part 1 - General & Financial Information
2. Part 2 - Safety Analysis Report
3. Part 3 - Environmental Report
4. Part 4 - Technical Specifications
5. Part 5 - Emergency Plans
6. Part 6 - Security Plans
7. Part 7 - Exemptions / Departures / Variances
8. Part 8 - License Conditions; Inspections, Tests, Analyses, & Acceptance Criteria
9. Part 9 - Withheld Information
10. Part 10 - Quality Assurance Program Description
11. Part 11 - Supplemental Information C.2 Application Regulatory Topics
1. Pre-application Activities
2. Pre-application Readiness Assessment
3. Small Modular Reactors and Design-Specific Review Standards
4. Application Electronic Submittal
5. Application Acceptance Review
6. Request for Additional Information Process
7. Operational Programs for COLs
8. 10 CFR Parts 30, 40 & 70 Materials Licenses for COLs
9. Inspections, Tests, Analyses, and Acceptance Criteria - ITAAC
10. Change Processes (Tier 1, 2, and 2*)
11. Final Safety Analysis Report (FSAR) Numbering Scheme
12. Finalizing Licensing-basis Information DC/COL ISG-011
13. Technical Reports Referenced in DC - marking content as Tier 2/2*
14. Finality of Environmental Issues for COL referencing ESP and/or DC
15. Incorporation by Reference - DC and ESP
16. Limited Work Authorization Additional topic(s) - to be determined Appendices: Safety Analysis Report Format & Content A. Combined License - Final Safety Analysis Report (FSAR)

B. Early Site Permit Site - Safety Analysis Report (SSAR)

C. Standard Design Certification - FSAR (Design Control Document)

D. Combined License - FSAR if COL incorporates by reference a Standard Design Certification and/or Early Site Permit