RNP-RA/14-0134, Response (90-Day) to Request for Additional Information Associated with License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805
| ML15005A073 | |
| Person / Time | |
|---|---|
| Site: | Robinson |
| Issue date: | 12/22/2014 |
| From: | Glover R Duke Energy Carolinas |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| RNP-RA/14-0134 | |
| Download: ML15005A073 (46) | |
Text
R. Michael Glover DUKE H. B. Robinson Steam Electric Plant Unit 2 Site Vice President Duke Energy Progress 3581 West Entrance Road Hartsville, SC 29550 DEC 2 2 2014 0:843857 1704 F: 843 857 1319 Mike. Gloi'er(a duke-energ,. corn Serial: RNP-RA/14-0134 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261 / RENEWED LICENSE NO. DPR-23 RESPONSE (90-DAY) TO REQUEST FOR ADDITIONAL INFORMATION ASSOCIATED WITH LICENSE AMENDMENT REQUEST TO ADOPT NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) STANDARD 805
REFERENCES:
- 1. Letter from W. R. Gideon (Duke Energy Progress) to U. S. Nuclear Regulatory Commission (USNRC) (Serial: RNP-RA/1 3-0090), License Amendment Request (LAR) to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition), dated September 16, 2013, ADAMS Accession No. ML13267A211
- 2. Letter from Martha Barillas (USNRC) to Site Vice President, H. B. Robinson Steam Electric Plant (Duke Energy Progress), H. B. Robinson Steam Electric Plant, Unit 2 - Request for Additional Information on License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection (TAC No.
MF2746), dated October 23, 2014, ADAMS Accession No. ML14289A260
- 3. Letter from R. Michael Glover (Duke Energy Progress) to U. S. Nuclear Regulatory Commission (USNRC) (Serial: RNP-RA/14-0122), Response (60-Day) to Request for Additional Information Associated with License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805, dated November 24, 2014
Dear Sir/Madam:
By letter dated September 16, 2013 (Reference 1) Duke Energy Progress, Inc. submitted a license amendment request to adopt a new risk-informed performance-based fire protection licensing basis for the H. B. Robinson Steam Electric Plant, Unit No. 2 (HBRSEP2).
During the week of September 22, 2014, the NRC conducted an audit at HBRSEP2 to support development of questions regarding the license amendment request. On October 23, 2014 the NRC provided a set of requests for additional information regarding the license amendment request (Reference 2). That letter divided the requests for additional information into 60-day, 90-day, and 120-day required responses. The Duke Energy Progress 60-Day responses were conveyed to the NRC Document Control Desk via letter from R. Michael Glover on November 24, 2014 (Reference 3). Enclosed as agreed are the Duke Energy Progress responses to the 90-day requests for A additional information.
U. S. Nuclear Regulatory Commission Serial: RNP-RA/14-0134 Page 2 Please address any comments or questions regarding this matter to Mr. Richard Hightower, Manager - Nuclear Regulatory Affairs at (843) 857-1329.
There are no new regulatory commitments made in this letter.
I declare under penalty of perjury that the foregoing is true and correct. Executed on December
-.".-, 2014.
Sincerely, R. Michael Glover Site Vice President RMG/jmw Enclosure cc: Mr. V. M. McCree, NRC, Region II Ms. Martha C. Barillas, NRC Project Manager, NRR NRC Resident Inspector, HBRSEP2 Ms. S. E. Jenkins, Manager, Infectious and Radioactive Waste Management Section (SC)
U. S. Nuclear Regulatory Commission to Serial: RNP-RA/14-0134 44 Pages (including this cover page)
RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING VOLUNTARY FIRE PROTECTION RISK INITIATIVE
REQUEST FOR ADDITIONAL INFORMATION VOLUNTARY FIRE PROTECTION RISK INITIATIVE DUKE ENERGY PROGRESS H. B ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261 Fire Protection Engineering (FPE) RAI 02 NFPA 805, Section 3.4.3(b) requires that plant personnel who respond with the industrial fire brigade be trained for their responsibilities, potential hazards to be encountered, and interfacing with the industrial fire brigade. LAR Attachment A, Table B-i, Section 3.4.3(b) indicates that guidance for non-industrial fire brigade members is found in FP-001. The procedure defines the actions needed to be taken by personnel discovering a fire, security personnel actions, and duty health physics contact actions. Provide a more detailed description of the elements of this procedure and training that demonstrates compliance with the requirements for training on responsibilities, potential hazards to be encountered, and interfacing with the industrial fire brigade. Additionally, identify what element of compliance is being "clarified" in the LAR statement "complies with clarification."
Response
RNP has a dedicated fire brigade and does not have personnel responding who are not active fire brigade members. The clarification element which is being addressed is how a non-industrial fire brigade member is trained in the event a fire is discovered or indication/suspicion of a fire by plant personnel.
The following steps per Plant Operating manual FP-001 "Fire Emergency", should be taken; the event should be reported immediately to the Unit 2 Control Room and the following information should be given:
Your name and location of fire Nature of fire, materials involved (electrical, oil, contaminated material, etc.)
Severity of fire (smoldering, small blaze, room engulfed in flames, etc.)
The following detailed information is associated with the compliance statement "complies with clarification." When the fire has been reported to the Unit 2 Control Room, then a person who is knowledgeable in fire extinguisher use, may attempt to extinguish a NON-PLANT EQUIPMENT (i.e., trash can fire) related fire with an appropriate fire extinguisher. If the fire cannot be readily extinguished, then remain in the vicinity at a safe distance until arrival of the Fire Brigade and inform the Fire Brigade Incident Commander of the circumstances.
Page 2 of 44
FPE RAI 03 LAR Attachment A, Section 3.4.1(c) states that fire brigade members are plant operators and "qualifications of individuals in the fire protection organization are administratively controlled to ensure qualification of the individual commensurate with the position being held and activities being performed." NFPA 805 Section 3.4.1(c) requires that the fire brigade leader and at least two brigade members have sufficient training and knowledge of nuclear safety systems to understand the effects of fire and fire suppressants on nuclear safety performance criteria. In NRC Regulatory Guide (RG) 1.189, "Fire Protection for Nuclear Power Plants", Revision 2, September 2009 (ADAMS Accession No. ML092580550), Section 1.6.4.1 "Qualifications," the NRC staff acknowledged the following example for the fire brigade leader as sufficient:
The brigade leader should be competent to assess the potential safety consequences of a fire and advise control room personnel. Such competence by the brigade leader may be evidenced by possession of an operator's license or equivalent knowledge of plant systems.
Provide additional detail regarding the training provided to the fire brigade leader and brigade members that addresses their ability to assess the effects of fire and fire suppressants on NFPA 805 nuclear safety performance criteria. Include the justification for how the training meets NFPA 805 Section 3.4.1.
Response
RNP utilizes a fire brigade where during every shift the brigade leader and at least two brigade members shall have sufficient training and knowledge of nuclear safety systems to understand the effects of fire and fire suppressants on nuclear safety performance. This is consistent with NFPA 805 Chapter 3 (Section 3.4.1(c)) and procedure AD-EG-ALL-1530, Fire Brigade Training. Note that the information in NSD 112 as referenced in LAR Attachment A, Section 3.4.1(c) has been superseded by AD-EG-ALL-1530.
An equivalent knowledge of plant systems is provided for under procedure AD-EG-ALL-1530, Fire Brigade Training, Section 5.5, 5.6 and Attachment 3. Attachment 3 specifies the plant systems for either a PWR or BWR that represent the minimum plant knowledge for a Non-Licensed Operator (NLO) fire brigade member or leader to understand the effects of fire and fire suppressants on nuclear safety performance criteria (ref. NFPA 805 Section 3.4.1(c)). Specifics from AD-EG-ALL-1530 are as follows:
Page 3 of 44
5.5 Fire Brigade Leader Training
- 1.
The Fire Brigade Leader is required to complete:
Fire Brigade Leader training An in-plant fire drill as fire brigade team leader Fire Brigade Leader qualification
- 2.
In addition to the fire brigade member training and drill requirements (defined in this procedure), Fire Brigade Leader training should address and emphasize the following objectives:
Command structure Roles of Fire Brigade Leader and Fire Chief Command of a fire brigade - Concepts of Incident Command Incident Safety Officer Responsibility Organizational setup for emergency response Coordination of off-site fire company using ICS Managing resources Pre-Incident Information Communications Site Fire Brigade Standard Operating Guidelines Fire brigade checklist and drill review Firefighting survival, strategy, and tactics Site fire strategies Fighting of fires in RCAs and RCZs and potential Radioactive Material Releases Case studies of fire incidents (OE)
Fire Brigade Leader practical to include special problems with fire suppression and leadership 5.6 Safety Systems Training
- 1.
The FBL and at least two other members of the brigade shall have knowledge, training, and understand the effects of fire and fire suppressants on safe shutdown equipment. This training and knowledge may be satisfied by:
- a.
Completing and maintaining a fire brigade qualification and meeting one of the following requirements:
(1) Be a licensed Senior Reactor Operator.
(2) Be a licensed Reactor Operator.
(3) Have successfully completed a reactor operator certification program.
(4) Have successfully completed training on the plant systems listed in Attachment 3, Fire Brigade Safety Systems Individual System Knowledge List.
Page 4 of 44
From Attachment 3:
Fire Brigade Safety Systems Individual System Knowledge List PWR BWR Reactor Coolant System Steam Generator System Auxiliary Feed System Charging and Volume Control System Residual Heat Removal System Safety Injection System Containment Spray System Component Cooling Water System Emergency Service Water System Electrical System Overview - AC & DC Emergency Core Cooling Systems 2035 - Core Spray System 2040 - Standby Liquid Control System 2045 - Residual Heat Removal System 2070 - Containment Atmosphere Control 2095 - High Pressure Coolant Injection 2100 - Reactor Core Isolation Cooling 4060 - Service Water System 4070 - Rx Bldg Closed Cooling Water 5095 - Diesel Generator System 5097 - Supplemental DG System 5098 - SAMG Diesel Generator System 5100 - Diesel Generator Fuel Oil System 5135 - 230KV Switchyard 5145 - SAT, UAT Transformer System 5170 - 4KV AC Distribution 5175 - 480V AC Distribution 5230 - 250V DC Distribution 6175 - Fire Protection System 6195 - Fire Protection C02 System 6205 - Halon Supply System 7071 - Standby Gas Treatment System 7110 - Fuel Pool Cooling System 8075 - Diesel Building HVAC 8185 - Reactor Building HVAC 8220 - Control Building HVAC 8232 - Service Water Building HVAC Page 5 of 44
FPE RAI 04 LAR Section 4.8.1 states that, "a summary of the NFPA 805 compliance basis and the required fire protection systems and features is provided in Attachment C." However, LAR Attachment C only identifies the required suppression and detection systems for a fire area. There appears to be no discussion or description of other fire protection features (e.g., Electrical Raceway Fire Barrier Systems (ERFBS), radiant shields, instamatic coatings, enhanced combustible controls, and transient limitations) that may be credited or required relative to the fire area analyses. Provide the fire protection features, by fire area, that are required by the Fire Probabilistic Risk Assessment (PRA), and their respective compliance bases.
Response
The response to FPE RAI 07, submitted with the 60 day responses, describes the use of Hemyc and MT ERFBS at RNP. The response to FPE RAI 13, submitted with the 60 day responses describes the physical barriers for fire delay in the Electrical Equipment Room and the Cable Spread Room. When these modifications are complete, the Fire Safety Analysis (FSA) for these areas will be updated to reflect the type of barrier credited for the 10 minute time delay assumed by PRA in each room. These are currently the only two areas where the FPRA credits other fire protection features.
A revised Attachment C will be provided with the 120 day responses.
FPE RAI 05 NFPA 805, Section 3.9.2 requires that automatic and manual water-based fire suppression systems be equipped with a water flow alarm. LAR Attachment A, Section 3.9.2 indicates that some automatic water-based fire suppression systems do not have water flow alarms. The LAR also states that these systems are not required to have water flow alarms per NFPA 13, "Standard for the Installation of Sprinkler Systems," which only requires water flow alarms to be provided on sprinkler systems having more than 20 sprinklers. In addition, Nuclear Energy Institute (NEI) 04-02, "Guidance for Implementing a Risk-Informed, Performance-Based Fire Protection Program Under 10 CFR 50.48(c)", Revision 2, (ADAMS Accession No. ML081130188), defines "complies with clarification" as an editorial issue and compliance should be explained in the compliance basis field.
The NRC staff does not consider the lack of water flow alarms an editorial issue. Provide a compliance strategy commensurate with the guidance of NEI 04-02 and provide a compliance strategy with a detailed justification relative to NFPA 805 Section 3.9.2.
Response
The compliance strategy "Complies with Clarification" has been revised to "Complies via Engineering Evaluation", which is sufficient to meet the requirements of National Fire Protection Association (NFPA) 805 Section 3.9.2.
COMPLIES VIA ENGINEERING EVALUATION: Several of the automatic water-based fire suppression systems do not have water flow alarms. These systems have less than 20 sprinklers and are not required to have water flow alarms. Per RNP-M/BMRK-1009, "Code Compliance Evaluation NFPA 13 - Standard for Installation for Sprinkler Systems", and RNP-M/BMRK-1011, "Code Compliance Evaluation NFPA 15 -
Water Spray Fixed Systems", all requirements from NFPA 13 and NFPA 15 for water flow alarms are met.
Page 6 of 44
A revision to License Amendment Request (LAR) Attachment A, Table B-i, Section 3.9.2, to include this update, will be submitted with the 120-day Request for Additional Information (RAI) responses.
FPE RAI 06 NFPA 805, Section 3.9.4 requires that the diesel-driven fire pumps shall be protected by automatic sprinklers. LAR Attachment A, Table B-1 indicates that the diesel-driven fire pump is located outdoors and is separated from other important equipment, and therefore "complies with clarification." NEI 04-02 defines "complies with clarification" as an editorial issue and compliance should be explained in the compliance basis field.
The NRC staff does not consider the lack of automatic sprinklers for the diesel fire pump an editorial issue. Provide a compliance strategy and detailed justification commensurate with the guidance in NEI 04-02 and relative to NFPA 805, Section 3.9.4.
Response
The compliance strategy "Complies with Clarification" has been revised to "Complies via Engineering Evaluation" which is sufficient to meet the requirements of National Fire Protection Association (NFPA) 805 Section 3.9.4.
COMPLIES VIA ENGINEERING EVALUATION: The diesel-driven fire pump is installed outdoors at the Intake Structure on Lake Robinson. Per RNP-M/BMRK-1012, "Code Compliance Evaluation NFPA 20-Centrifugal Fire Pumps", all requirements from NFPA 20-1978, for outdoor diesel-driven fire pumps, are met.
A revision to License Amendment Request (LAR) Attachment A, Table B-i, Section 3.9.4, to include this clarification, will be submitted with the 120-day Request for Additional Information (RAI) responses.
FPE RAI 08 LAR Attachment K identifies an existing approved Appendix R exemption that is being transitioned for the installation of fixed fire suppression in the pump bays in lieu of a reactor coolant pump (RCP) lube oil collection system. This exemption credits the installed fire detection system, dikes to contain oil spills, and the containment spray system as a backup fire suppression system.
However, the dikes and the containment spray system are not identified in the LAR Attachment C, Table B-3 as fire protection features or systems credited for this fire area. Provide justification for not including these fire protection features in LAR Attachment C, Table B-3.
Page 7 of 44
Response
As noted in LAR Attachment K, these features are prior exemptions to Appendix R in lieu that a reactor coolant pump lube oil collection system is not provided. The dikes and Containment Spray System should have been included in the LAR Attachment C, Table B-3 and credited for this fire area as they are considered as required fire protection systems/features by NFPA 805 Chapter 3 and the RNP FP program.
A revision to LAR Attachment C, Table B-3, to include these systems as required fire protection system/feature, will be submitted with the 120-day RAI responses.
FPE RAI 14 NFPA 805, Section 3.4.4, "Fire-Fighting Equipment," requires that equipment shall conform to the applicable NFPA standards. LAR Attachment A, Section 3.4.4, "Fire Fighting Equipment" states that the licensee has not committed to following any NFPA standards pertaining to firefighting equipment.
Describe what types of requirements or standards will be established when purchasing replacement protective clothing, hoses, nozzles, fire extinguishers and other equipment for the fire brigade use in order to ensure suitable products are procured. Include a discussion of whether manufacturers' guidelines will be followed, how the licensee intends to ensure the integrity of its equipment over time, and what type of replacement criteria are in place to ensure the equipment remains in good working order.
Response
As noted in LAR Attachment "A" HBRSEP intends to satisfy NFPA 805, Section 3.4.4 in terms of applicability as described in NEI 04-02 Rev 2, and FAQ 06-0020. Where used in NFPA 805, Chapter 3, the term, "applicable NFPA Standards" is considered to be equivalent to those NFPA standards identified in the current license basis (CLB) for procedures and systems in the Fire Protection Program that are transitioning to NFPA 805."
LAR Attachment "A" will be revised to include the following clarification, HBRSEP makes use of Duke Energy fleet procedure AD-EG-ALL-1531, Selection, Care and Maintenance of Fire Fighting Ensembles which follows the guidance found in NFPA standards associated with firefighting Personal Protective Equipment. Standards and requirements associated with installed fire protection equipment such as hoses, nozzles, fire extinguishers and other equipment are maintained in accordance with NFPA standards as described elsewhere in Chapter 3 and evaluated for compliance under the various NFPA Code Compliance Calculations listed for those sections of Chapter 3.
A revised Attachment A will be submitted with the 120 day responses.
Page 8 of 44
FPE RAI 15 LAR Attachment L, Approval Request #3 identifies other non-fire uses of the fire protection system and makes the statement that these have "no adverse impact on the ability of the fire protection system to provide required flow and pressure." Provide more detail to justify that the listed non-fire uses of fire protection water will not impair the ability to deliver the required fire water demand as required by NFPA 805, Section 3.5.16. Include in the response:
a)
Whether any uses are considered to be routine, "non-emergency," or "non-abnormal" operations.
b)
Describe any engineering controls, alarms and indications, and training that supports "no adverse impact" statement.
c)
Describe any of these operations that may be simultaneously in conjunction with the largest fire demand performed or conducted at the expense of the availability of the fire protection water system during the duration of alternative use. Include the largest design demand conditions required for the fire protection water systems. For instance, state whether the fire protection system is relied upon for any of these conditions.
d)
Describe the administrative controls, limitations, allowances, procedures, compensatory actions, dedicated communications, equipment, and work control practices that are in place to preclude interference with the ability of the fire protection systems to meet demand.
Response
a)
It is not routine to use fire water outside of emergent or abnormal operating procedure. The use of fire protection water for non-fire protection plant evolutions is an occurrence that requires Shift Manager review and concurrence, Per OMM-002, Section 8.15.2.4.
b)
As stipulated in OMM-002, Section 8.15.2.4, when fire water use is deemed necessary sufficient justification must be provided to show that the use of the fire water system for the activity does not cause the fire water system to be in a condition outside of the design basis such that the quantity of water does not exceed the supply and pressure requirements in the UFSAR. In the unlikely event fire water is used for a non-fire protection purpose without notification or concurrence from the Shift Manager, the Control Room will get an alarm indicating that the Motor Driven Fire Water Pump has started. An immediate investigation is initiated to determine the unapproved source is in use.
When a need to use fire water is identified, Robinson Engineering Support (RES) Fire Protection Engineering is requested to review the activity in addition to the Shift Manager's final permission. Stipulations are provided to ensure that flow rates for the requested job are not exceeded.
Page 9 of 44
Examples are as follows:
Maximum flow rates allowed are restricted and approved by RES Engineering and the Shift Manager.
ii.
Operations are to be contacted prior to each use.
iii.
Manipulations of valves are to only be completed by Plant Operations or a Plant Fire Brigade Member.
iv.
While the fire water is being used, personnel must be in constant attendance to immediately cease the use of water in the event of a plant fire alarm or at the request of Operations.
c)
The basis for determining the acceptability of a temporary non-fire protection related fire water use is the Updated Final Safety Analysis Report (UFSAR) Section 9.5.1 which specifies the minimum pressure in the plant loop with the largest deluge system in operation including fire hose demand. If a fire alarm is received during the use of the fire water system outside of emergency use, stipulations are provided to cease the use of the fire water system per Operations and RES Engineering. This is strictly adhered to ensure the quantity of water does not drop the supply pressure below the defined limits in the UFSAR, Section 9.5.1.
Since the fire water system is prohibited by procedure for routine usage not related to fire protection plant evolutions, it is not relied upon for any conditions other than fire suppression and emergent or abnormal procedures.
d)
Administrative controls are built into the request on a case by case basis as indicated in the examples in b. above. As previously stated, if a fire alarm is received during the use of the fire water system outside of emergency use, stipulations are provided to cease the use of the fire water system per Operations and RES Engineering. This is strictly adhered to ensure the quantity of water does not drop the supply pressure below the defined limits in UFSAR, Section 9.5.1.
Safe Shutdown Analysis (SSA) Request for Additional Information (RAI) 02 In LAR Attachment G, Table G-1, for Fire Areas AS and C, the staff noted that a DID recovery action may be required to provide portable fans for cooling the Control Room (CR). LAR Attachment G, Table G-1 identifies procedures (DSP-001 and EPP-001) for setup of the portable 4 kW generator and blowers used for this recovery action.
The requirements of General Design Criterion 3 (GDC-3) state for fire protection that structures, systems, and components (SSCs) important to safety shall be designed and located to minimize, consistent with other safety requirements, the probability and effect of fires and explosions. Noncombustible and heat resistant materials shall be used wherever practical throughout the unit, particularly in locations such as the containment and CR. Fire detection and fighting systems of appropriate capacity and capability shall be provided and designed to minimize the adverse effects of Page 10 of 44
fires on SSCs important to safety. Firefighting systems shall be designed to assure that their rupture or inadvertent operation does not significantly impair the safety capability of these SSCs.
The use of fuel-fired generators near the CR does not align with GDC-3. The use and refueling of portable generators presents a hazard to equipment important to nuclear safety. Describe and justify how the use of portable fuel-fired equipment is consistent with the requirements of GDC-3 or provide an approach to resolving the subject variances from deterministic requirements (VFDRs) and providing CR ventilation that is consistent with the requirements of GDC-3.
Response
The equipment associated with providing temporary cooling for the Main Control Room consists of a small generator, twenty inch smoke ejector/fan, (2) twenty foot duct sections, and (2) fifty foot extension cords. The equipment is located on the Turbine Building Mezzanine Level in a metal storage cabinet. When the equipment is used to provide temporary cooling for the MCR, the generator is located on the east end of the Turbine Building Mezzanine level, which is down one level from the MCR.
The fan is placed outside the east MCR entrance door, and the duct sections from the fan are positioned to direct cooling air flow into the control room. The extension cords provide power from the generator on the Turbine Building Mezzanine level to the fan. The Turbine Building is an open structure and this location is open to the atmosphere. Exhaust from the generator and any vapors during refueling of the generator will not accumulate in the area. Also due to the physical distance the generator is located from the MCR and the fan suction, exhaust gases will not be introduced into the MCR.
(Note: These actions are now contained in EOP-ECA-0.0, Loss Of All AC Power, which superseded EPP-1)
When the generator is removed from the storage location and placed on the east end of the Turbine Mezzanine level, transient combustible controls are placed into effect in accordance with AD-EG-ALL-1520, Transient Combustible Control. This procedure addresses minimizing the introduction of transient fire loads and reducing the fire hazards involved with the handling, use, and storage of combustible material to a degree consistent with personnel and plant safety.
SSA RAI 11 LAR Attachment S, Table S-2, Modification Items 10, 11, 12, 13, and 14 identified additional indication and cut-out switches necessary to eliminate self-induced station blackout (SISBO) strategy to allow for necessary operator actions.
a)
Provide a more detailed description of these modifications.
b)
As stated in the risk-informed characterization for each modification, no PRA or recovery credit is given and the modification is to ensure the procedure revisions for SISBO elimination are feasible. Clarify if these modifications are necessary for the NSCA.
c)
Clarify whether the new switching and monitoring actions are included in the LAR Attachment G, and are considered recovery actions, actions in the Control Room, or actions at a primary control station(s).
Page 11 of 44
d)
In LAR Attachment C, the overview for Fire Area B indicates no modification is credited for the area. Provide a clarification for the contradiction with LAR Attachment S, Table S-2, for the above modification items.
Response
- a.
Modifications 10, 11, 12, and 13 are to provide additional indication on a panel in the charging pump room. These new indications will provide the operator cues for the status of system /
equipment at the Charging Pump Panel in support of the NSCA safe shutdown strategy. This is needed should a fire in the main control room propagate to hot gas layer and the potential for the loss of both emergency buses and or supporting equipment exists.
Modification 14 installs isolation switches in the control room for isolation of Auxiliary Panel DC
& GC from the control room. This obviates the need for the time critical manual operator action in the Battery Room applied in the current analysis.
Provide position indication for V6-12A, V6-12B, and V6-12C and operability indication for SW Pumps A, B, C.
Provide B and C Component Cooling Water Pumps with indication at the Charging Pump Room shut down panel 12 Provide SW Pressure Indication 13 Provide voltage indication for E-1, E-2 and DS Bus voltages.
14 Install cut out switch for Auxiliary panels GC and DC in the control room
- b.
While not credited for PRA, the subject modifications are in support of the NSCA to facilitate the change in the safe shutdown strategy from the current SISBO approach to a Non-SISBO approach. The installation of the Isolation / cut out switches in the control room will require a control room action to implement. All other modifications will be installed at the Charging Pump Room Panel which is considered a Primary Control Station.
Specifically, the installation of the Auxiliary Panel DC & GC Isolation Switches in the control room obviates the need for the time critical manual operator action in the Battery Room applied in the current analysis. The current manual operator action requires Operations to open the 125VDC Circuit breakers that supply Auxiliary Panels DC & GC electrical power at 125VDC Distribution Panels A & B. The action is intended to fail close the RCS and Secondary side valves assuming spurious operations of the subject valves. The installation of the Auxiliary Panel DC &
GC Isolation Switches in the control room is intended to allow a control room operator action to perform the function rather than a breaker action in the plant..
The basis for the other proposed modifications was to provide the operator cues for the status of system / equipment at the Charging Pump Panel in support of the NSCA safe shutdown Page 12 of 44
strategy. This is needed should a fire propagate to hot gas layer and the potential for the loss of both emergency buses and or supporting equipment exists.
In general, for the high risk scenarios, it is intended to maintain operators in the control room, at the Charging Pump Room Panel and the Secondary Control Panel as part of the response strategy. The additional modifications will provide the operator at the Charging Pump Room Panel the status of the emergency and dedicated shutdown bus voltages as well as other key system / component statuses as part of the fire response strategy.
This will facilitate the implementation of any additional operator actions in a timely manner. For example, should both emergency buses be damaged by the fire, the transfer to dedicated shutdown becomes more efficient as the operator is on station and has the necessary operator cues to understand the status of the plant. The charging pump room panel is a Primary Control Station if the control room has to be abandoned. For all areas except Fire Area A18, these actions are characterized Defense-In-Depth Recovery Actions.
The additional modifications referenced in LAR Attachment S, Table S-2 (items 10 - 14) are being installed in the Charging Pump Room (Fire Area B, items 10-13) and in the Main Control Room (Fire Area A18, item 14) as part of the elimination of the Self Induced Station Blackout (SISBO) strategy employed under the Appendix R licensing basis.
- c.
The actions for the SISBO modifications will be included in the revised Attachment G submitted with the 120 day responses.
d)
LAR Attachment S, Table S-2 was not meant to imply that the modifications were credited for Fire Area B. Rather, that is where the modifications discussed in Items 10-13 will be installed.
The modifications are being installed as part of the plant's overall efforts to reduce reliance on the SISBO strategy previously credited in several fire areas.
Revisions to Attachment G (part d) and LAR Table S-2 (part b) will be updated with the 120 day responses.
Fire Modeling (FM) Request for Additional Information (RAI) 01.a NFPA 805, Section 2.4.3.3, states that "the PSA [probabilistic safety assessment] approach, methods, and data shall be acceptable to the AHJ [authority having jurisdiction]..."
The NRC staff noted that fire modeling comprised the following:
Fire Dynamics Tools (FDTs) were used for zone of influence (ZOI) calculations of cabinets, pumps, motors, oil fires and transient fire sources, and to evaluate the development and timing of Hot Gas Layer (HGL) conditions in selected compartments.
The Consolidated Fire Growth and Smoke Transport (CFAST) model was used to calculate MCR abandonment times and to determine HGL temperature, optical density and Halon system activation time for a specific analysis in Fire Zone 20.
Page 13 of 44
The FLASH-CAT model was used to calculate the fire propagation in a vertical stack of horizontal cable trays in Fire Zone 20.
The Generic Fire Modeling Treatments (GFMTs) were used to determine 'initial' severity factors.
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the FPRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V
[verification and validation]," for a discussion of the acceptability of the fire models that were used.
Regarding the acceptability of the PRA approach, methods, and data:
- a.
Identify any fire modeling tools and methods that have been used in the development of the LAR and that are not discussed in LAR Attachment J.
Response
- a.
The LAR, Attachment J, Table J-1, has been updated to include the point source radiation model, which was used in P2217-2300-01-03, Rev 3, "Robinson Fire PRA Exposed Structural Steel-Fire Interaction Analysis".
Technical details regarding the fire modeling analysis are have been provided in FM RAI 03.a and FM RAI 03.c. The update to Attachment J, Table J-1 will be provided with the 120-day responses.
All other fire modeling tools and methods that have been used in the development of the LAR are discussed in LAR Attachment J.
FM RAI O1.f NFPA 805, Section 2.4.3.3, states that "the PSA [probabilistic safety assessment] approach, methods, and data shall be acceptable to the AHJ [authority having jurisdiction]
The NRC staff noted that fire modeling comprised the following:
Fire Dynamics Tools (FDTs) were used for zone of influence (ZOI) calculations of cabinets, pumps, motors, oil fires and transient fire sources, and to evaluate the development and timing of Hot Gas Layer (HGL) conditions in selected compartments.
The Consolidated Fire Growth and Smoke Transport (CFAST) model was used to calculate MCR abandonment times and to determine HGL temperature, optical density and Halon system activation time for a specific analysis in Fire Zone 20.
The FLASH-CAT model was used to calculate the fire propagation in a vertical stack of horizontal cable trays in Fire Zone 20.
The Generic Fire Modeling Treatments (GFMTs) were used to determine 'initial' severity factors.
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the FPRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V
[verification and validation]," for a discussion of the acceptability of the fire models that were used.
Page 14 of 44
Specifically, regarding the acceptability of CFAST for the MCR abandonment times study:
- f.
Provide the basis for the assumption in the MCR abandonment time calculations that the fire brigade is expected to arrive within 15 minutes. Describe the uncertainty associated with this assumption; discuss possible adverse effects of not meeting this assumption on the results of the fire PRA and explain how possible adverse effects will be mitigated.
Response
- f.
From RNP-F/PSA-0067, Rev. 1, the RNP Fire PRA-Plant Partitioning and Ignition Frequency calculation, section 3.4.3 describes the fire brigade response time assumption as follows:
Recognizing that manual suppression in some scenarios included suppression activities by nonfire brigade personnel, Section 14 of NUREG/CR-6850, Supplement 1 (FAQ 08-0050) provides guidance for determining the manual nonsuppression probability, without requiring the separate consideration of the fire brigade response time. Part of this approach addresses cases where the fire brigade response time for the analyzed scenario is judged to be comparable to the industry average. FAQ 08-0050 also provided guidance for making adjustments where the fire brigade response time distribution is judged to be significantly different from that underlying the events reported in the EPRI Fire Events Database. In particular, scenario-specific adjustments are appropriate where the fire brigade response time is more than five minutes different from the nominal fire brigade response time.
Consistent with the guidance in Section 9.7 (FPIP-0150, Rev. 1), fire brigade performance during an actual fire is estimated from the measured fire brigade response times during drills, with the use of a correction factor (i.e., 50% or a minimum of 10 minutes) to account for the artificialities associated with drills. The fire brigade response times, as measured during drills conducted over a period of several years, were documented in Attachment 24 (RNP Fire Brigade Response Times 2004-2009). Consistent with the guidance in Section 9.7 (FPIP-0150, Rev. 1), all times less than 10 minutes are assumed to represent fires that were suppressed by the personnel on the scene before the fire brigade arrived and are thus not indicative of the fire brigade performance.
Based on these drill times, the nominal fire brigade response time is estimated to be between 10 and 11 minutes, without any scenarios identified as outliers taking more than approximately five additional minutes. Because this compares very favorably with the 10 minutes for full fire brigade response which was assumed by FAQ 08-0050 to generate the nonsuppression curves, use of the approach described in FAQ 08-0050 is judged to be appropriate.
FM RAI 01.g NFPA 805, Section 2.4.3.3, states that "the PSA [probabilistic safety assessment] approach, methods, and data shall be acceptable to the AHJ [authority having jurisdiction]
The NRC staff noted that fire modeling comprised the following:
Page 15 of 44
Fire Dynamics Tools (FDTs) were used for zone of influence (ZOI) calculations of cabinets, pumps, motors, oil fires and transient fire sources, and to evaluate the development and timing of Hot Gas Layer (HGL) conditions in selected compartments.
The Consolidated Fire Growth and Smoke Transport (CFAST) model was used to calculate MCR abandonment times and to determine HGL temperature, optical density and Halon system activation time for a specific analysis in Fire Zone 20.
The FLASH-CAT model was used to calculate the fire propagation in a vertical stack of horizontal cable trays in Fire Zone 20.
The Generic Fire Modeling Treatments (GFMTs) were used to determine 'initial' severity factors.
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the FPRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V
[verification and validation]," for a discussion of the acceptability of the fire models that were used.
Specifically, regarding the acceptability of CFAST for the MCR abandonment times study:
- g.
The kitchen adjacent to the MCR has been excluded from the computational domain as the door between the kitchen and the MCR is fire rated. Provide technical justification for not considering scenarios, where the kitchen door is blocked open and the fire originates in the kitchen.
Response
- g.
Fire scenarios in the Kitchen with the door propped open are bound by the workstation fire scenarios (severe transient) located within the MCR proper. This is true because the workstation fire is placed directly into the MCR and has a comparable fuel load and expected fire size as a fire in the Kitchen. However, the Kitchen is a sub-enclosure within the MCR and combustion products generated by a fire within the Kitchen must flow out a door opening into the MCR. This introduces a flow restriction as well as additional entrainment as compared to the workstation fire located within the MCR. Accordingly, the workstation fire is bounding and may be used to characterize the effects of a Kitchen fire.
FM RAI 01.h NFPA 805, Section 2.4.3.3, states that "the PSA [probabilistic safety assessment] approach, methods, and data shall be acceptable to the AHJ [authority having jurisdiction]..."
The NRC staff noted that fire modeling comprised the following:
Fire Dynamics Tools (FDTs) were used for zone of influence (ZOI) calculations of cabinets, pumps, motors, oil fires and transient fire sources, and to evaluate the development and timing of Hot Gas Layer (HGL) conditions in selected compartments.
Page 16 of 44
The Consolidated Fire Growth and Smoke Transport (CFAST) model was used to calculate MCR abandonment times and to determine HGL temperature, optical density and Halon system activation time for a specific analysis in Fire Zone 20.
The FLASH-CAT model was used to calculate the fire propagation in a vertical stack of horizontal cable trays in Fire Zone 20.
The Generic Fire Modeling Treatments (GFMTs) were used to determine 'initial' severity factors.
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the FPRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V
[verification and validation]," for a discussion of the acceptability of the fire models that were used.
Specifically, regarding the acceptability of CFAST for the MCR abandonment times study:
- h. The HRR profile of IEEE-383 unqualified thermoplastic cables was used for electrical cabinet fires in the MCR as the small quantities of IEEE-383 qualified thermoset cable do not affect the overall HRR. Show that the assumption of using thermoplastic cable HRR is consistent with the actual cable types used in the MCR electrical cabinets or provide a technical justification for this assumption in the context of the fire modeling analysis.
Response
- h.
As stated in FM RAI 02a, submitted with the 60 day RAI responses, in cases where there is a mixture of thermoset and thermoplastic cables, thermoplastic damage criteria is used. Fire scenarios involving electrical panels containing cables are treated as thermoplastic electrical panels. This generally results in a more adverse risk contribution due to the differences in the severity factor distribution. This may be quantitatively shown by evaluating probability of control room abandonment for the four panel fire scenarios considered in the MCR abandonment report generated using the heat release rate profile, severity factor, and fuel properties for thermoset cables. The results of this computation are summarized in Table RAI H-1. The total probability of control room abandonment in this case is defined as the sum of the product of the non-suppression probability and severity factor for each of the fifteen heat release rate bins. The original thermoplastic risk contribution is based on the heat release rate profiles and severity factors for the NUREG/CR-6850 Appendix E Case 3 (single bundle) and Case 4 (multiple cable bundle) electrical panel ignition sources. The thermoset risk contribution is based on the heat release rate profiles and severity factors for the NUREG/CR-6850 Appendix E Case 1 (single bundle) and Case 2 (multiple cable bundle) electrical panel ignition sources. In this example, Ventilation Configuration 1 from the MCR abandonment report is used, which is normal HVAC with all boundary doors closed. The fuel properties for the thermoset cables are determined using the highest soot yield thermoset cable as listed in Table 3-4.16 of the 4 th Edition of the SFPE Handbook of Fire Protection Engineering.
Page 17 of 44
Table RAI H Comparison of the Risk Contribution for Thermoset and Thermoplastic Electrical Panel Fire Scenarios in the RNP MCR.
Total Probability of Control Room Abandonment for:
Multiple Cable Electical anelMultiple Cable Electrical Panel Single Cable Multiple Cable Bundle Electrical Bundle Electrical Bundle Electrical Bundle Electrical Panel Fire Cable Type Panel Fire Panel Fire Panel Fire Scenario in the Scenario in the Scenario Scenario MCBs MCBs (Propagating)
Thermoplastic 0.00219 0.0151 0.0202 0.0226 (Original)
Thermoset 0.00920 0.0369 0.0174 0.0187 (Sensitivity Case)
Table RAI H-1 shows that a non-MCB fully thermoset panel would have a more adverse effect on the risk. The reverse is true for an MCB panel ignition source fire scenarios. The reason the non-MCB panels result in an increased risk is due to the higher soot yields of the thermoset material coupled with the higher heat release rates for individual heat release rate bins. In these cases, the offsetting severity factor distribution does not fully compensate.
A simple but bounding estimate of the maximum thermoset cable fraction that may be present without causing significant change in the risk contribution may be made by adjusting the fuel composition while leaving the heat release rate profile unchanged. This is conservative because the heat release rate would either remain constant or decrease in combination with the improved fuel properties as the thermoset fraction is reduced. An iterative solution shows that an eight percent thermoset cable fraction produces a fifteen percent or lower change in the risk for the single and multiple cable bundle non-MCB electrical panel ignition source fire scenarios.
Since this is smaller than the uncertainty in the heat release rate input parameter per Section 3-2 of the SFPE Handbook of Fire Protection Engineering, the variation is not considered significant. The maximum fraction of thermoset cables in the main control room is less than eight percent given that the cables are predominantly thermoplastic. Accordingly, the results as based on thermoplastic electrical panels are representative of the abandonment conditions or are within the uncertainty of the heat release rate, which is the primary input parameter.
FM RAI O1.i NFPA 805, Section 2.4.3.3, states that "the PSA [probabilistic safety assessment] approach, methods, and data shall be acceptable to the AHJ [authority having jurisdiction]...
The NRC staff noted that fire modeling comprised the following:
Page 18 of 44
Fire Dynamics Tools (FDTs) were used for zone of influence (ZOI) calculations of cabinets, pumps, motors, oil fires and transient fire sources, and to evaluate the development and timing of Hot Gas Layer (HGL) conditions in selected compartments.
The Consolidated Fire Growth and Smoke Transport (CFAST) model was used to calculate MCR abandonment times and to determine HGL temperature, optical density and Halon system activation time for a specific analysis in Fire Zone 20.
The FLASH-CAT model was used to calculate the fire propagation in a vertical stack of horizontal cable trays in Fire Zone 20.
The Generic Fire Modeling Treatments (GFMTs) were used to determine 'initial' severity factors.
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the FPRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V
[verification and validation]," for a discussion of the acceptability of the fire models that were used.
Specifically, regarding the acceptability of CFAST for the MCR abandonment times study:
- i.
Provide details about the flow opening used between the MCR volume and the interstitial space above the MCR acoustic ceiling. Demonstrate that this opening is consistent with the actual plant configuration, and if not, provide technical justification for this opening size.
Response
- i.
The flow connection between the MCR and the interstitial space connects, as shown in Figure 5-5, and described in Table 5-5, is 0.0253 m2 (0.273 ft2) for boundary leakage and 8.64 m 2 (93 ft 2) for the opening in the false ceiling above the MCB electrical panels. The basis for this is the actual configuration of the MCR. Specifically, the boundary leakage is determined from leakage fractions and does not specifically credit any individual flow paths in the ceiling. The larger opening above the MCBs is determined from the plan dimensions of the MCB panels.
Note that when fires are postulated in the MCBs, the large flow opening dominates and a single volume representation of the interstitial space and the MCR area is used (i.e., no direct model of the flow opening). Conversely, for fires are postulated elsewhere, only the smaller boundary leakage opening is used. There are localized areas where tiles were missing at time the walkdowns, which provide a larger flow opening than assumed in the analysis for boundary leakage; however, these larger openings were not credited because they are expected to be variably present. The sensitivity analysis provided in Section A.2.2.1 of the MCR abandonment report provides confirmation that a configuration with the false ceiling in place provides a more conservative result for fires outside the MCBs.
Page 19 of 44
FM RAI 01.j NFPA 805, Section 2.4.3.3, states that "the PSA [probabilistic safety assessment] approach, methods, and data shall be acceptable to the AHJ [authority having jurisdiction]...
The NRC staff noted that fire modeling comprised the following:
Fire Dynamics Tools (FDTs) were used for zone of influence (ZOI) calculations of cabinets, pumps, motors, oil fires and transient fire sources, and to evaluate the development and timing of Hot Gas Layer (HGL) conditions in selected compartments.
The Consolidated Fire Growth and Smoke Transport (CFAST) model was used to calculate MCR abandonment times and to determine HGL temperature, optical density and Halon system activation time for a specific analysis in Fire Zone 20.
The FLASH-CAT model was used to calculate the fire propagation in a vertical stack of horizontal cable trays in Fire Zone 20.
The Generic Fire Modeling Treatments (GFMTs) were used to determine 'initial' severity factors.
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the FPRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V
[verification and validation]," for a discussion of the acceptability of the fire models that were used.
Specifically, regarding the acceptability of CFAST for the MCR abandonment times study:
- j.
A uniform leakage fraction of 5 x 10-5 m2/m 2 for the walls, floors and ceiling boundaries and 1.7 x 1 0-4 m2/m 2 for the acoustic ceiling has been used in the MCR abandonment analysis. The values were adopted from the data provided in Table 4-14.1 of the Society of Fire Protection Engineers (SFPE) Handbook of Fire Protection Engineering, 4th Edition (SFPE Handbook).
However, the table lists different leakage factors for the wall and floor. Justify using a uniform leakage factor for the bounding walls, floor, and ceiling of the MCR.
Response
- j.
The intent was to use different leakage factors that corresponded to walls and ceiling surfaces; however, a single factor was in fact used. The differences in the wall and ceiling factors are comparable to the differences considered in Section A.2.2.2, which addresses model sensitivity in the assumed boundary leakage and shows it is a minor parameter with a maximum non-conservative bias in the abandonment times of 6 - 12 seconds. It is readily seen that the use of a single leakage factor for both the walls and ceilings does not affect the abandonment time results by more than approximately one percent when examining the results provided in Table A2-2. The sensitivity analysis considers variations of up to fifty percent in the boundary leakage fraction. The wall components in the leakage areas, which are correctly assumed in the baseline model, are approximately 50 - 75 % of the total leakage, depending on whether a one or two room model is used. If it is assumed that the ceiling/floor leakage fraction is 0.0, the maximum effect for this parameter, the decreased boundary leakage values in Table A2-2 provide an indication of the overall effect, which is on the order of one percent or less. Note Page 20 of 44
that the boundary leakage computation will be clarified in the MCR abandonment report when it is updated.
FM RAI 01.k NFPA 805, Section 2.4.3.3, states that "the PSA [probabilistic safety assessment] approach, methods, and data shall be acceptable to the AHJ [authority having jurisdiction]..."
The NRC staff noted that fire modeling comprised the following:
Fire Dynamics Tools (FDTs) were used for zone of influence (ZOI) calculations of cabinets, pumps, motors, oil fires and transient fire sources, and to evaluate the development and timing of Hot Gas Layer (HGL) conditions in selected compartments.
The Consolidated Fire Growth and Smoke Transport (CFAST) model was used to calculate MCR abandonment times and to determine HGL temperature, optical density and Halon system activation time for a specific analysis in Fire Zone 20.
The FLASH-CAT model was used to calculate the fire propagation in a vertical stack of horizontal cable trays in Fire Zone 20.
The Generic Fire Modeling Treatments (GFMTs) were used to determine 'initial' severity factors.
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the FPRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V
[verification and validation]," for a discussion of the acceptability of the fire models that were used.
Specifically, regarding the acceptability of CFAST for the MCR abandonment times study:
- k.
A sensitivity study conducted to demonstrate the effect of leakage fraction was done by varying the parameter by 50%. However, Table 4-14.1 of the SFPE Handbook shows that the leakage fraction varies by orders of magnitude between different levels of wall tightness. Justify why the sensitivity study did not evaluate the effect of more realistic variations of wall tightness.
Response
- k.
A tight leakage fraction was assumed based on observations during the survey (sealed penetrations, concrete boundaries). The goal of this section was to determine whether or not uncertainties in this parameter can affect the results. It is shown that varying this parameter by a factor 0.5 - 1.5 does not cause a change in the abandonment times by more than 6 - 12 seconds, except for one case that improves by a factor of three or more minutes. The results converted to risk show that increasing the leakage fraction has a slight improvement on the risk, and in the most adverse case would still be acceptable with a tenfold increase in the risk consequence. The uncertainty in the leakage fraction is in the direction of more leakage, not less leakage and as noted may be an order of magnitude larger than what was considered. However, given that increased leakage improves the risk, there was no further need to investigate uncertainty in this parameter based on the conservative bias included in the baseline Page 21 of 44
assumption. Note that the results are nominally bound by the fully open door scenario, which is among those considered in the PRA when determining the most adverse configuration.
FM RAI 01.1 NFPA 805, Section 2.4.3.3, states that "the PSA [probabilistic safety assessment] approach, methods, and data shall be acceptable to the AHJ [authority having jurisdiction]...
The NRC staff noted that fire modeling comprised the following:
Fire Dynamics Tools (FDTs) were used for zone of influence (ZOI) calculations of cabinets, pumps, motors, oil fires and transient fire sources, and to evaluate the development and timing of Hot Gas Layer (HGL) conditions in selected compartments.
The Consolidated Fire Growth and Smoke Transport (CFAST) model was used to calculate MCR abandonment times and to determine HGL temperature, optical density and Halon system activation time for a specific analysis in Fire Zone 20.
The FLASH-CATmodel was used to calculate the fire propagation in a vertical stack of horizontal cable trays in Fire Zone 20.
The Generic Fire Modeling Treatments (GFMTs) were used to determine 'initial' severity factors.
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the FPRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V
[verification and validation]," for a discussion of the acceptability of the fire models that were used.
Specifically, regarding the acceptability of CFAST for the MCR abandonment times study:
- 1.
Clarify whether 10 or 15 minutes was assumed for fire propagation between adjacent electrical cabinets and provide the technical justification on why the guidance in Appendix S of NUREG/CR-6850, "EPRI/NRC-RES Fire PRA Methodology for Nuclear Power Facilities, Volume 2:
Detailed Methodology," September 2005 (ADAMS Accession No. ML052580118) (i.e., 10 minutes, was not used).
Response
- 1. The propagation time between panels is ten minutes. Figure 5-10 provides confirmation of this (10 minute interval between inflections). There are two incorrect notations in the preceding paragraph that state fifteen minutes and will be corrected when the MCR abandonment report is updated.
Page 22 of 44
FM RAI 01.m NFPA 805, Section 2.4.3.3, states that "the PSA [probabilistic safety assessment] approach, methods, and data shall be acceptable to the AHJ [authority having jurisdiction]...
The NRC staff noted that fire modeling comprised the following:
Fire Dynamics Tools (FDTs) were used for zone of influence (ZOI) calculations of cabinets, pumps, motors, oil fires and transient fire sources, and to evaluate the development and timing of Hot Gas Layer (HGL) conditions in selected compartments.
The Consolidated Fire Growth and Smoke Transport (CFAST) model was used to calculate MCR abandonment times and to determine HGL temperature, optical density and Halon system activation time for a specific analysis in Fire Zone 20.
The FLASH-CAT model was used to calculate the fire propagation in a vertical stack of horizontal cable trays in Fire Zone 20.
The Generic Fire Modeling Treatments (GFMTs) were used to determine 'initial' severity factors.
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the FPRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V
[verification and validation]," for a discussion of the acceptability of the fire models that were used.
Specifically, regarding the acceptability of CFAST for the MCR abandonment times study:
- m. The heat of combustion and soot yield of cables specified in the CFAST calculations for electrical panel fire scenarios are reported to be based on the data for neoprene or ethylene propylene rubber cables in Tewarson's Chapter of the SFPE Handbook, (Section 3, 4th Edition.) However, there was no data for cables with this combination of insulation and jacket material in this referenced chapter. Also, the carbon monoxide (CO) and soot yield for wood was used in the CFAST calculations in the transient fire scenarios that were those reported for polyethylene in the SFPE Handbook. Explain in detail how the fuel properties used in the CFAST calculations were derived. Confirm that these values are representative of the cable materials and Class A materials in the MCR, or that they are otherwise bounding.
Response
- m. The fuel properties for electrical panels are characterized using Polyethylene (PE)/Polyvinyl Chloride (PVC) cables as described in Sections 5.1.1.3 and 5.1.4 of the MCR abandonment report and listed in Plant Specification CX-67. The fuel properties for the PE/PVC cables are obtained from Table 3-4.16 of the 4 th Edition of the SFPE Handbook of Fire Protection Engineering. The fuel properties are a composite derived using the method described in Section 5.1.4 in order to maximize the soot production. Specifically, the heat of combustion and soot to carbon dioxide production rate are obtained from PE/PVC Cable 5 and the carbon monoxide to carbon dioxide production rate is obtained from PE/PVC Cable 4.
The transient fuel package is assumed to be composed of equal portions of wood and plastic (PE) materials, consistent with the definition of a transient fuel package provided in Page 23 of 44
NUREG-1934. The soot and carbon monoxide to carbon dioxide production rates for the wood and PE transient components are reversed in Table 5-6 of the MCR abandonment report.
However, the averaged values used in the CFAST model are not affected by this reversal.
In sections A.2.2.3 and A.2.2.6 of the MCR abandonment study, a sensitivity evaluated the models sensitivity to potential uncertainty in the transient and electrical cable fuel properties. It is shown that the baseline abandonment times are either conservative or are not sensitive to uncertainties in the fuel properties, depending on the particular case considered. Additional clarification on the fuel properties will be provided when the MCR abandonment report is updated.
FM RAI 01.n NFPA 805, Section 2.4.3.3, states that "the PSA [probabilistic safety assessment] approach, methods, and data shall be acceptable to the AHJ [authority having jurisdiction]...
The NRC staff noted that fire modeling comprised the following:
Fire Dynamics Tools (FDTs) were used for zone of influence (ZOI) calculations of cabinets, pumps, motors, oil fires and transient fire sources, and to evaluate the development and timing of Hot Gas Layer (HGL) conditions in selected compartments.
The Consolidated Fire Growth and Smoke Transport (CFAST) model was used to calculate MCR abandonment times and to determine HGL temperature, optical density and Halon system activation time for a specific analysis in Fire Zone 20.
The FLASH-CAT model was used to calculate the fire propagation in a vertical stack of horizontal cable trays in Fire Zone 20.
The Generic Fire Modeling Treatments (GFMTs) were used to determine 'initial' severity factors.
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the FPRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V
[verification and validation]," for a discussion of the acceptability of the fire models that were used.
Specifically, regarding the acceptability of CFAST for the MCR abandonment times study:
- n.
The self-contained breathing apparatus stored at the corner of the MCR in polyethylene containers were modeled as a transient fire and the HRR specified in Table E-9 of NUREG/CR-6850 was used. Provide technical justification to demonstrate that the HRR values specified in this table bound the HRR expected from these containers.
Page 24 of 44
Response
- n.
A fire scenario involving the self-contained breathing apparatus (SCBA) gear is evaluated in Section A.2.2.10 of the MCR abandonment report. It is shown that the predicted abandonment time for a SCBA fire scenario (2.11 min) and a severe transient (i.e., workstation) fire scenario (2.02 min) are nearly identical. As such, the baseline fire scenario involving the severe transient is applicable to the SCBA fuel packages.
FM RAI 01.o NFPA 805, Section 2.4.3.3, states that "the PSA [probabilistic safety assessment] approach, methods, and data shall be acceptable to the AHJ [authority having jurisdiction]...
The NRC staff noted that fire modeling comprised the following:
Fire Dynamics Tools (FDTs) were used for zone of influence (ZOI) calculations of cabinets, pumps, motors, oil fires and transient fire sources, and to evaluate the development and timing of Hot Gas Layer (HGL) conditions in selected compartments.
The Consolidated Fire Growth and Smoke Transport (CFAST) model was used to calculate MCR abandonment times and to determine HGL temperature, optical density and Halon system activation time for a specific analysis in Fire Zone 20.
The FLASH-CAT model was used to calculate the fire propagation in a vertical stack of horizontal cable trays in Fire Zone 20.
The Generic Fire Modeling Treatments (GFMTs) were used to determine 'initial' severity factors.
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the FPRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V
[verification and validation]," for a discussion of the acceptability of the fire models that were used.
Specifically, regarding the acceptability of CFAST for the MCR abandonment times study:
- o.
Section 5.1.3.1 of the MCR abandonment analysis report indicates that some electronic equipment is not separated per the guidelines in NUREG/CR-6850 Appendix S and that fire may propagate from the initial electrical panel to one or more adjacent electrical panels. However, Section 5.3.1 lists the fire types simulated in the MCR abandonment analysis and it does not include scenarios where fire propagates between back panel electrical cabinets. Provide the technical justification for not considering fire spread between back panel electrical cabinets in the MCR abandonment analysis.
Response
- o.
The statement in Section 5.1.3.1 refers to the MCBs and the cabinets located at the ends of the horseshoe that have the same configuration as the MCBs (In-Core Instrument Racks, Radiation Control Panels, and Nuclear Instrument Racks). Fire scenarios involving these panels are Page 25 of 44
characterized using fires that propagate to adjacent panels and those that do not (i.e., third and fourth bullets in Section 5.3.1). These are baseline fire scenarios as seen in Section 5.4. The other panels within the MCR are individual panels that are effectively separated by double wall construction. In these cases, non-propagating fire scenarios are applicable (i.e., first and second bullets in Section 5.3.1).
FM RAI 03.a NFPA 805, Section 2.7.3.2, "Verification and Validation," states that "each calculational model or numerical method used shall be verified and validated (V&Ved) through comparison to test results or comparison to other acceptable models."
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the Fire PRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V,"
for a discussion of the V&V of the fire models that were used.
Furthermore, LAR Section 4.7.3 "Compliance with Quality Requirements in Section 2.7.3 of NFPA 805" states that, "calculational models and numerical methods used in support of compliance with 10 CFR 50.48(c) were verified and validated as required by Section 2.7.3.2 of NFPA 805."
Regarding the V&V of fire models:
- a.
The point source model is used in the structural steel analysis report, to determine the minimum separation distance between electrical cabinet or transient fires and structural members required to avoid damage. The point source model is not included in LAR Attachment J, Table J-1, although it is included in LAR Attachment J, Table J-2, which deals with the GFMTs.
However, the licensee doesn't seem to use the GFMTs for the purpose of calculating ZOL.
Provide technical details to demonstrate that the point source model as used in the structural steel analysis has been applied within the validated range of input parameters, or to justify the application of the model outside the validated range reported in NUREG-1824, "Verification and Validation of Selected Fire Models for Nuclear Power Plant Applications" (ADAMS Accession No. ML071650546) or other V&V basis documents.
Response
- a.
The LAR, Attachment J, Table J-1, has been updated to include the point source radiation model, which was used in P2217-2300-01-03, Rev 3, "Robinson Fire PRA Exposed Structural Steel-Fire Interaction Analysis". Technical details have been provided to demonstrate that the point source model as used in the structural steel analysis has been applied within the validated range of input parameters, or to justify the application of the model outside the validated range reported in NUREG-1824. The report RNP-M/MECH-1884, Verification and Validation of Fire Models Supporting the Robinson Nuclear Plant (RNP) Fire PRA, has also been updated to include the V&V for the point source radiation model.
A revised Attachment J will be submitted with the 120 day responses.
Page 26 of 44
FM RAI 03.c NFPA 805, Section 2.7.3.2, "Verification and Validation," states that "each calculational model or numerical method used shall be verified and validated (V&Ved) through comparison to test results or comparison to other acceptable models."
LAR Section 4.5.1.2, "Fire PRA," states that fire modeling was performed as part of the Fire PRA development (NFPA 805 Section 4.2.4.2). Reference is made to LAR Attachment J, "Fire Modeling V&V,"
for a discussion of the V&V of the fire models that were used.
Furthermore, LAR Section 4.7.3 "Compliance with Quality Requirements in Section 2.7.3 of NFPA 805" states that, "calculational models and numerical methods used in support of compliance with 10 CFR 50.48(c) were verified and validated as required by Section 2.7.3.2 of NFPA 805."
Regarding the V&V of fire models:
- c.
Provide the V&V basis for the fire models identified in the response to FM RAI 01 (a). Provide technical details to demonstrate that these models were applied within the validated range of input parameters, or to justify the application of the model outside the validated range in the V&V basis documents.
Response
- c.
The verification of the models used in support of calculation P2217-2300-01-03, Rev 3, "Robinson Fire PRA Exposed Structural Steel-Fire Interaction Analysis" is provided in NUREG-1805, which contains pre-programmed Microsoft Excel Spreadsheets. The spreadsheets from NUREG-1805 are used directly in P2217-2300-01-03, Rev 3, (Attachment B) and therefore additional verification is not needed.
The vertical ZOI calculations for the Fire Froude number present several "out of range" results.
Most of the "out of range" cases are due to calculations exceeding the upper limit of the range, suggesting high intensity fires for the selected fire diameter. One reason for exceeding the upper limit is the use of the 98th percentile heat release rates for the corresponding fire diameters. Based on the guidance in Chapter 8 of NUREG/CR-6850, 98th percentile heat release rate values are used for screening and can be considered on the high end of the values assigned to ignition sources. In addition, setting the Froude number calculation to the upper range limit of 2.4 for the 98th percentile heat release rate values would result in a larger diameter. With a larger diameter, the flame height calculation would result in shorter flame lengths, and plume temperature calculations would suggest lower temperatures. The "out of range" results are based on conservative ZOI calculations for the Fire PRA.
In the transient case, with the fire in the center of the room, the Fire Froude number is out of range on the lower limit. The other two transient cases, with a fire on the wall and in the corner, have higher HRR values and are within the validation range of the Fire Froude number.
Both of these scenarios (wall and corner) are more conservative than the transient fire in the center of the room. Since all three of the transient scenarios were screened out in the structural steel-impact analysis (P2217-2300-01-03, Rev 3), including the more conservative wall and corner scenarios, the use of the model for the transient scenarios is justified.
Page 27 of 44
Flame length ratio is within the validation range for all scenarios.
Parameters are "out of range" for the use of the point source radiation model. The reason for number of ZOI results are "out of range" is because the ZOI distances are close to the flames and the experiments selected for validation purposes measured radiation at longer distances from the flames. This is a limitation on the available data for validation and not necessarily a limitation on the use of the point source radiation model for calculating horizontal components of the ZOI for Fire PRA applications. The model limitations presented in Chapter 5.5 of NUREG-1805, indicate that the point source radiation model overestimates the intensity of thermal radiation at target locations close to the fire. Therefore, the results are conservative and no further justification for the use of the point source radiation model is required.
The report RNP-M/MECH-1884, Verification and Validation of Fire Models Supporting the Robinson Nuclear Plant (RNP) Fire PRA, has been updated to include the V&V for the point source radiation model.
Attachment J will be revised and submitted with the 120 day responses.
FM RAI 04 NFPA 805, Section 2.7.3.3, "Limitations of Use," states that "acceptable engineering methods and numerical models shall only be used for applications to the extent these methods have been subject to verification and validation. These engineering methods shall only be applied within the scope, limitations, and assumptions prescribed for that method."
LAR Section 4.7.3, "Compliance with Quality Requirements in Section 2.7.3 of NFPA 805, states that "engineering methods and numerical models used in support of compliance with 10 CFR 50.48(c) were applied appropriately as required by Section 2.7.3.3 of NFPA 805."
Regarding the limitations of use:
- a.
The NRC staff notes that algebraic models cannot be used outside the range of conditions covered by the experiments on which the model is based. NUREG-1805, "Fire Dynamics Tools (FDTs): Quantitative Fire Hazard Analysis Methods for the U.S. Nuclear Regulatory Commission Fire Protection Inspection Program," December 2004 (ADAMS Accession No. ML043290075) includes a section on assumptions and limitations that provides guidance to the user in terms of proper and improper use for each FDT.
Identify uses, if any, of the FDTs outside the limits of applicability of the model and explain how the use of the FDT was justified.
- b.
Identify uses, if any, of CFAST outside the limits of applicability of the model and explain how the use of CFAST was justified.
Page 28 of 44
- c.
Identify uses, if any, of GFMTs outside their limits of applicability and explain how the use of GFMTs in those cases was justified.
Response
- a.
The Fire Dynamics Tools (FDTs) were used within their range of applicability following the guidance available in NUREG-1824 and NUREG-1934. Technical justifications have been provided for fire modeling analysis applied in fire scenarios where the results are outside the validated range and documented in RNP-M/MECH-1884.
- b.
Consolidate Model of Fire Growth and Smoke Transport (CFAST) was used within the range of applicability following the guidance available in NUREG-1824 and NUREG-1934. Technical justifications have been provided for fire modeling analysis applied in fire scenarios where the results are outside the validated range and documented in RNP-M/MECH-1884.
- c.
The Generic Fire Modeling Tools (GFMTs) were used within their range of applicability following the guidance available in NUREG-1824 and NUREG-1934. Technical justifications have been provided for fire modeling analysis applied in fire scenarios where the results are outside the validated range and documented in RNP-M/MECH-1884.
FM RAI 06 NFPA 805, Section 2.7.3.5, "Uncertainty Analysis," states that "an uncertainty analysis shall be performed to provide reasonable assurance that the performance criteria have been met."
LAR Section 4.7.3, "Compliance with Quality Requirements in Section 2.7.3 of NFPA 805, states that "uncertainty analyses were performed as required by Section 2.7.3.5 of NFPA 805 and the results were considered in the context of the application. This is of particular interest in fire modeling and Fire PRA development."
Regarding the uncertainty analysis for fire modeling:
- a.
Describe how the uncertainty associated with the fire model input parameters was accounted for in the fire modeling analyses.
- b.
Describe how the "model" and "completeness" uncertainties were accounted for in the fire modeling analyses.
Response
a, Parameter uncertainty is addressed by: (1) using conservative inputs, or (2) varying inputs in sensitivity cases.
- 1.
The fire model input parameters were selected to be conservative, and each instance is addressed in the individual fire modeling calculations.
- 2.
The Main Control Room Abandonment Study describes specific treatments of parameter uncertainty throughout the analysis when varying inputs in sensitivity cases. In Report 0004-0042-412-002 Rev. 1, Evaluation of Main Control Room Abandonment Times at Page 29 of 44
the H.B. Robinson Nuclear Plant, heat release rates are varied over the range of the probability distribution described in Appendix E of NUREG/CR-6850. In addition, in the Main Control Room (MCR) abandonment study uncertainties are addressed through the following sensitivity analyses documented in Appendix B of 0004-0042-412-002 Rev. 1:
- 1) The presence of the suspended ceiling; 2) The leakage fractions assumed for the boundaries and across closed doors; 3) The burning regime (well ventilated vs. poorly ventilated burning); 4) The height of the fire base; 5) The radiant fraction of the source fire; 6) The heat of combustion of the burning materials;7) The initial ambient conditions (temperature); 8) The effect of the assumed boundary thermal diffusivity; 9) The effect of opening multiple boundary doors; 10) The effect of a pool fire on the predicted severe transient fire abandonment time; and 11) The effect of including the lightly loaded cable tray in the Main Control Board (MCB) fire scenarios.
- b.
The fire modeling Verification and Validation (V&V) analysis is documented in calculation RNP-M/MECH-1884, Verification and Validation of Fire Models Supporting the Robinson Nuclear Plant (RNP) Fire PRA. This analysis covers all the fire modeling, including Consolidated Model of Fire Growth and Smoke Transport (CFAST) and hand calculations used in the RNP Fire Probabilistic Risk Assessment (PRA). The V&V analysis determines whether models are used within their validated range. If the models are found to be used outside of the range, justifications are provided describing how the model is utilized conservatively as suggested in NUREG-1934. In summary, the concept of model uncertainty is addressed in the RNP Fire PRA through the V&V studies documented in calculation RNP-M/MECH-1884 and the sensitivity analysis supporting the Fire PRA.
Completeness associated with fire models is addressed in the RNP Fire PRA within the overall quantification process, as the Fire PRA is an integrated analysis. Fire Modeling provides inputs to a broad comprehensive Fire PRA which includes modeling of electrical systems, operator actions, and the plant systems and components needed to shut down the plan. One of the first steps in the fire modeling process is to identify the fire scenarios that will be analyzed. In general, three situations can be encountered:
Fire scenarios requiring no fire modeling analysis, in which full target sets assigned to physical analysis units are assumed failed by fire at the time of ignition. This is not typically used.
Fire scenarios requiring detailed analysis for which fire modeling tools specifically designed for the application are available, and Fire scenarios requiring fire modeling capabilities that are not currently available (i.e.,
outside the state of the art).
The last two cases listed above require some level of fire modeling analysis. For the case in which fire models are fully capable for addressing the scenario condition (second case listed above), parameter and model uncertainty considerations should address the modeling requirements.
Page 30 of 44
The third case listed above generates the completeness uncertainty situation described in the question. When the fire modeling does not provide a full answer or an answer with sufficient resolution, the scenario definition and target mapping within the Fire PRA conservatively compensates for the lack of information. The Fire PRA allows the analyst to conservatively compensate for the lack of fire modeling capabilities outside the fire modeling analysis so that the scenario is properly modeled in the Fire PRA. Some examples are listed below:
The determination of time to automatic suppression. The detection or suppression activation models may not be fully applicable to some of the postulated scenarios; therefore, as part of the scenario definition, targets are failed intentionally before the automatic suppression is credited.
Both zones of multi-compartment combinations are failed conservatively when fire modeling propagation calculations from one compartment to another are not conducted.
Full main control board panels are failed due to the lack of analytical fire modeling methods, with appropriate V&V studies, to predict flame propagation within a panel.
The examples above illustrate how the completeness uncertainty associated with fire modeling calculations is addressed "outside of the fire modeling" by conservatively failing targets in the fire scenarios such that the risk contribution is bounding.
Radiation Release RAI 01 LAR Section 4.4.2, "Results of the Evaluation Process," states that certain plant features (i.e., engineering controls), such as curbs and ventilation systems or actions, control smoke management or fire suppression water run-off to ensure fire suppression activities are contained and monitored prior to release to unrestricted areas. LAR Attachment E, "Radioactive Release Transition," states that forced air ventilation and damming were considered in "Generic Assumptions/Discussions" for each fire pre-plan.
- a.
Given that ventilation may be secured during a fire event (e.g., Radwaste Facility), explain how forced air ventilation is used and the release pathway for radioactive gaseous effluent from fire suppression activities such that a release would meet the radiological performance criteria.
- b.
In LAR Attachment E, "Training Review," identify where forced air ventilation and damming are addressed in fire brigade lesson plans which provide training guidance and information relative to radioactive releases.
Response
- a.
For areas where containment/confinement is relied upon, the methodology for Radioactive Release review consisted of a qualitative review on a building and fire area-by-fire area basis utilizing the fire pre-plans as a guide and documented in the LAR Attachment "E". Specifically for RNP, a review was conducted by a review panel to ensure specific steps are included for Page 31 of 44
containment and monitoring of potentially contaminated materials so as to limit the potential for release of radioactive materials due to firefighting operations. The review panel consisted of representatives from Operations, Engineering (i.e., Fire Protection Systems & Programs, HVAC Systems), Operations Training, and Radiation Protection. A review of engineering controls to ensure containment of gaseous and liquid effluents (i.e., smoke and fire fighting agents) was conducted. This review included all plant operating modes (i.e., including full power and non-power conditions).
Fire pre-plans that address fire areas where there is no possibility of radioactive materials being present were screened from further review. All other fire pre-plans were reviewed to ascertain whether existing engineering controls are adequate to ensure that radioactive materials (contamination) generated as a direct result of fire suppression activities are contained and monitored before release to unrestricted areas, such that the release would meet the NFPA 805 radioactive release performance criteria.
The review determined that existing engineering controls, such as curbs and forced air ventilation, were qualitatively adequate based on panel member expertise and plant knowledge to meet the NFPA 805 radioactive release requirements. In addition, RNP each of the fire pre-plans addressing fire areas where radioactive materials may be present to include general guidance for containment and monitoring of smoke and fire suppression agent runoff should the effectiveness of the installed engineering controls be challenged or impacted by fire suppression activities.
The review panel determined Engineering Controls are adequate to ensure that radioactive materials (radiation) generated as a direct result of fire suppression activities is contained and monitored prior to release to unrestricted areas such that such release would be as low as reasonable achievable and would not exceed applicable 10 CFR, Part 20 limits. Engineering controls such as use of forced air ventilation and damming for fire suppression agent run off was considered during review of fire pre-plans, for areas in which this is the anticipated response identified in the pre-fire plan. Consideration was given to ensuring forced air would not produce an unmonitored release point due to firefighting actions. In general the philosophy of "containment until monitored and cleared" was utilized. No new engineering controls were identified or established as a result of this review and all present controls are as currently in place under the approved pre-transitional fire protection program.
- b.
Qualitative discussion of liquid and gaseous effluent capabilities can be found in LAR Attachment "E" and Table E-1. No operator actions specific for control of radioactive release due to firefighting operations were specified under the evaluation. General containment of run-off and ventilation discharge of smoke and combustion by-products are addressed on a precautionary level in the fire pre-plans.
Radiation Release RAI 02 For the following compartments (miscellaneous areas) or other potential radiological release areas listed in LAR Attachment E, "Radioactive Release Transition," please provide: 1) examples of engineering controls or actions considered in fire pre-plans as standard statements concerning airborne Page 32 of 44.
contamination and water run-off such that a release would meet the radiological performance criteria; and 2) the bounding analysis, quantitative analysis, or other analysis performed and the administrative controls ensured to demonstrate that the instantaneous release limits specified in the unit's Technical Specifications (or 10 CFR Part 20 public dose limits) will not be exceeded as a result of fire suppression activities.
- a.
Outside Yard areas where Radioactive Materials Areas (RMAs) and Sea-Land type containers may be present;
- b.
Purge Inlet Room (G4/FZ-39);
- c.
Oil Dispensing Building (YARD/FZ-43);
- d.
Northern Street Metal Building Adjacent to the Reactor Auxiliary Building (RAB) and Protected Water Storage Tank (PWST) (YARD/FZ-45);
- e.
Building 230 Contaminated Storage Building; and
- f.
Building 250 Outage Contaminated Storage Building
Response
- 1.
Examples of engineering controls or actions considered in fire pre-plans as standard statements concerning airborne contamination and water run-off such that a release would meet the radiological performance criteria were reviewed as part of the Radioactive Release Screening process for the fire pre-plans. Fire pre-plans that address fire areas where there is no possibility of radioactive materials being present were screened from further review. All other fire pre-plans were reviewed to ascertain whether existing engineering controls are adequate to ensure that radioactive materials (contamination) generated as a direct result of fire suppression activities are contained and monitored before release to unrestricted areas, such that the release would meet the NFPA 805 radioactive release performance criteria. The review determined that existing engineering controls, such as curbs and forced air ventilation, were qualitatively adequate based on panel member expertise and plant knowledge to meet the NFPA 805 radioactive release requirements. In addition, RNP updated each of the fire pre-plans addressing fire areas where radioactive materials may be present to include general guidance for containment and monitoring of smoke and fire suppression agent runoff should the effectiveness of the installed engineering controls be challenged or impacted by fire suppression activities.
The following are examples of standard statements used in the fire pre-plans relating to both gaseous and liquid effluents resulting from firefighting operations or activities.
Airborne contamination levels will need to be monitored before and during venting operations.
Ensure that the liquid run off from any fire is monitored and sampled for any possible radioactive, chemical and/or oil contamination.
- 2.
Calculation RNP-M/MECH-1901 is a bounding calculation that demonstrates that the radioactive releases from a fire in a container stored in outside areas will not exceed the applicable 10 CFR Part 20 limits. This analysis has determined that a fire in a cargo container would be representative or bounding of the radioactive material storage conditions of the areas described below, which contain the maximum quantity of procedurally allowed radioactivity, will result in a dose at the site boundary of 0.38 mrem in one hour.
Page.33 of 44
- a.
Outside Yard areas where Radioactive Materials Areas (RMAs) and Sea-Land type containers may be present;
- b.
Purge Inlet Room (G4/FZ-39);
- c.
Oil Dispensing Building (YARD/FZ-43);
- d.
Northern Sheet Metal Building Adjacent to the Reactor Auxiliary Building (RAB) and Protected Water Storage Tank (PWST) (YARD/FZ-45);
- e.
Building 230 Contaminated Storage Building; and
- f.
Building 250 Outage Contaminated Storage Building Probabilistic Risk Assessment (PRA) RAI 01.c Section 2.4.3.3 of NFPA 805 states that the PSA (PSA is also referred to as PRA) approach, methods, and data shall be acceptable to the AHJ, which is the U.S. Nuclear Regulatory Commission (NRC). RG 1.205, "Risk-Informed, Performance-Based Fire Protection for Existing Light-Water Nuclear Power Plants,"
Revision 1, December 2009 (ADAMS Accession No. ML092730314), identifies NUREG/CR-6850 as documenting a methodology for conducting a fire PRA and endorses, with exceptions and clarifications, NEI 04-02, Revision 2, as providing methods acceptable to the staff for adopting a fire protection program consistent with NFPA-805. RG 1.200, "An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk Informed Activities," Revision 2, March 2009 (ADAMS Accession No. ML090410014), describes a peer review process utilizing an associated American Society of Mechanical Engineers/American Nuclear Society (ASME/ANS) standard (currently ASME/ANS-RA-Sa-2009, "Addenda to ASME/ANS RA-S-2008, Standard for Level 1/Large Early Release Frequency Probabilistic Risk Assessment for Nuclear Power Plant Applications") as one acceptable approach for determining the technical adequacy of the PRA once acceptable consensus approaches or models have been established for evaluations that could influence the regulatory decision. The primary results of a peer review are the F&Os recorded by the peer review and the subsequent resolution of these F&Os.
Clarify the following dispositions to the fire F&Os and Supporting Requirement (SR) assessments identified in LAR Attachment V that have the potential to impact the fire PRA results and do not appear to be fully resolved:
c) CS-All-01 and FSS-E4-01 (Undetermined cable routing)
The responses to F&O CS-All-01 and FSS-E4-01 state that, where specific cable routing could not be determined, "the cable was assumed failed throughout the entire compartment that it was known to traverse through," and that any ignition source within a given fire zone was assumed to "impact all cables." These statements indicate assumed cable routes were modeled conservatively. Conservative modeling can lead to calculation of non-conservative ACDF and ALERF if risk-reduction modifications are made in the post-transition model that affect conservative compliant plant scenarios. Explain whether conservative modeling of the compliant plant case contributes to underestimating ACDF and ALERF. If so, evaluate or remove this conservatism as part of the integrated analysis performed in response to PRA RAI 3.
Response
The approach for treating assumed cable routing is to include these cables for all scenarios unless otherwise justified. This will result in potentially conservative CDF and LERF values for both the variant and compliant cases. A sensitivity study unrelated to the aggregate PRA RAI 3 was done on the Hot Gas Layer (HGL) scenarios to determine what potential impact the unknown cable routings would have on Page 34 of 44
risk. The result indicated that the impact from the unknown cable routings should be minimal. As a part of the aggregate PRA RAI 3, a one-time sensitivity study will be completed on all fire scenarios to determine impact on the ACDF and ALERF. Robinson has already performed extensive cable toning in order to minimize the impact of assumed cable routing. In most cases, the assumptions are limited to a small number of cables in a given compartment.
PRA RAI 01.h Section 2.4.3.3 of NFPA 805 states that the PSA (PSA is also referred to as PRA) approach, methods, and data shall be acceptable to the AHJ, which is the U.S. Nuclear Regulatory Commission (NRC). RG 1.205, "Risk-Informed, Performance-Based Fire Protection for Existing Light-Water Nuclear Power Plants,"
Revision 1, December 2009 (ADAMS Accession No. ML092730314), identifies NUREG/CR-6850 as documenting a methodology for conducting a fire PRA and endorses, with exceptions and clarifications, NEI 04-02, Revision 2, as providing methods acceptable to the staff for adopting a fire protection program consistent with NFPA-805. RG 1.200, "An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk Informed Activities," Revision 2, March 2009 (ADAMS Accession No. ML090410014), describes a peer review process utilizing an associated ASME/ANS standard (currently ASME/ANS-RA-Sa-2009, "Addenda to ASME/ANS RA-S-2008, Standard for Level 1/Large Early Release Frequency Probabilistic Risk Assessment for Nuclear Power Plant Applications") as one acceptable approach for determining the technical adequacy of the PRA once acceptable consensus approaches or models have been established for evaluations that could influence the regulatory decision. The primary result of a peer review are the facts and observations (F&Os) recorded by the peer review and the subsequent resolution of these F&Os.
Clarify the following dispositions to the fire F&Os and Supporting Requirement (SR) assessments identified in LAR Attachment V that have the potential to impact the fire PRA results and do not appear to be fully resolved:
- h.
FSS-D7-01 and FSS-F3-02 (Detection and suppression system outlier behavior)
The disposition to this F&O states there is no evidence of outlier behavior for fire suppression and detection systems, explaining that the System Health Reports, covering the last 12 months of operation, indicate these systems performed well. The disposition does not address specific concerns cited in the F&O, namely whether: 1) suppression and detection systems credited in the Fire PRA are maintained and installed in accordance with codes and standards, and 2) statements in the System Health Report imply declining system performance for the detection, C02 and Halon systems. Given that these concerns suggest evidence of outlier behavior in fire suppression and detection systems, provide:
- i.
Explanation of whether credited suppression and detection systems are maintained and installed in accordance with codes and standards. Include discussion of the deficiency noted in the F&O concerning the Turbine Lube Oil Deluge system. Note that per the disposition to F&O FSS-F3-02 that the unavailability for the Turbine Lube Oil Deluge system was increased to 0.05 based on "engineering judgment" (the suggested NUREG/CR-6850, Appendix P value).
Page 35 of 44
ii.
Explanation of statements in the System Health Report about the need to replace detection, C02 and Halon systems in the near future.
iii.
Explanation of whether System Health Reporting data or other data indicate outlier behavior for the credited suppression and detection systems in periods prior to the 12-month window considered in the System Health report.
iv.
An update of the detection and suppression system unavailabilities with plant specific information, if there is evidence of outlier behavior. If detection and suppression system unavailabilities need to be updated, then address these updated values into the integrated analysis provided in response to PRA RAI 3.
Response
Per the Robinson Nuclear Plant (RNP) National Fire Protection Association (NFPA) Code Compliance Evaluations (e.g., RNP-M/BMRK-1005, -1006, -1007, -1008) and the RNP inspection, testing, and system health programs (i.e., OMM-002, Fire Protection Manual, FP-012, Fire Protection Systems Minimum Equipment and Compensatory Actions, and FP-013, Fire Protection Systems Surveillance Requirements), credited suppression and detection systems are installed and maintained in accordance with the applicable codes and standards.
Engineering Change (EC) 84207 (currently in progress) removed and replaced the existing Turbine Lube Oil Fire Protection and Detection System. This modification provides separation of the water spray (deluge) and closed (pre-action) sprinkler system supporting the Turbine Lube Oil Reservoir and Tank, resolving the deficiency noted in Fact and Observation (F&O) FSS-D7-01.
ii.
The age and obsolescence of the systems result in a burden to procurement and engineering in obtaining replacement and spare parts. There have been numerous spurious alarms received which are attributed to the obsolescence of the fire detection system.
Long Term Asset Management (LTAM) strategies have been generated which study and replace the detection, carbon dioxide (C02), and Halon Systems. These LTAMs will be evaluated and prioritized based on station needs. All replacement strategies will be in accordance with the applicable existing plant modification procedures and practices.
The following LTAM strategies are in long range planning and address the obsolescence and performance concerns:
RNP-10-0503 System 6195 - Emergency Diesel Generator (EDG) Cardox System Strategic Plan RNP-10-0504 System 6195 - Cable Vault C02 System Strategic Plan RNP-10-0505 System 6205 - Halon Supply System Strategic Plan RNP-11-0396 - Study & Implement Upgrade to Site Fire Detection Page 36 of 44
Although LTAMs have been initiated, the Fire Probabilistic Risk Assessment (FPRA) treatment reflects and will continue to reflect the current systems, as described in the responses to Part iii and iv.
iii.
Crediting fire detection and suppression systems and the use of generic estimates of total system unavailability was based on system installation and operation in accordance with applicable NFPA Codes and Standards. Detection and suppression systems are strictly controlled in terms of operability and compensatory actions during plant operations as described in FP-012, Fire Protection Systems Minimum Equipment and Compensatory Actions. System performance is monitored and maintained at a high level as part of the System Health Reporting and System Notebook processes. Post-transition this is part of the NFPA 805 Monitoring Program as described in procedure AD-EG-ALL-1503. Outlier behavior with respect to system availability would be evident to the system engineer and plant management through this program and corrective actions implemented.
In support of the FPRA Peer Review, a review of the then current health data for fire protection systems (for the previous 12 months) indicated Material Condition and Online Corrective Backlog showing Excellent (Green) performance. This focus on a 1-year period provided an overview of the most current system performance, measured against specific parameter/attributes, and helped to confirm the effectiveness of preventative and corrective maintenance. To further support the response to this RAI, the most recent 3-years of System Health Report information was reviewed and found to show sustained acceptable performance levels, again with no "outlier behavior" noted for the Fire Detection and Suppression systems.
Additionally, a Condition Report (CR) search was performed on suppression and detection features in the plant over the past 3-years. Normal plant testing and maintenance is evident and appropriate corrective actions were taken and noted in the system notebooks. No adverse trend was found.
iv.
The most recent 3-years of System Health Report information was reviewed and found to show sustained acceptable performance levels, again with no "outlier behavior" noted for the Fire Detection and Suppression systems, therefore, an update of the detection and suppression system unavailabilities with plant specific information is not required.
PRA RAI 14 Section 2.4.3.3 of NFPA 805 states that the PRA approach, methods, and data shall be acceptable to the NRC. RG 1.205 identifies NUREG/CR-6850 as documenting a methodology for conducting a fire PRA and endorses, with exceptions and clarifications, NEI 04-02, Revision 2, as providing methods acceptable to the staff for adopting a fire protection program consistent with NFPA-805. In letter dated July 12, 2006, to NEI (ADAMS Accession No. ML061660105), the NRC established the ongoing FAQ process where official agency positions regarding acceptable methods can be documented until they can be included in revisions to RG 1.205 or NEI 04-02. Methods that have not been determined to be acceptable by the NRC staff or acceptable methods that appear to have been applied differently than described require additional justification to allow the NRC staff to complete its review of the proposed method.
Page 37 of 44
Section 4.8.3.1.3 of the LAR explains that for a selected set of risk significant Air Operated Valves and Solenoid Operated Valves the licensee assumed that given a hot short that these valves would return to their fail-safe position once the hot short clears. Section 4.8.3.1.3 of the LAR explains that the probability that the spurious hot short would clear after 15 minutes was 0.06. Should this state that the probability that the hot short "does not clear" in 15 minutes is 0.06? NRC staff notes that guidance about how to analyze hot short duration has recently been issued in Volume 2 of NUREG/CR-7150,"
Joint Assessment of Cable Damage and Quantification of Effects from Fire.". Given these observations, provide the following:
a)
Clarify the probability used in the Fire PRA of the failure of the cited hot shorts to clear and the duration the hot short was assumed to exist.
b)
Explain whether the approach taken to modeling hot short durations is consistent with new NRC guidance, and describe the basis (e.g., thermohydraulic basis) for assuming a hot short duration of 15 minutes. Note that NUREG/CR-7150, Vol. 2, addresses hot short duration and includes guidance about treatment of multiple spurious operations (MSO) hot shorts.
c)
Provide an assessment of the assumptions used in the Fire PRA relative to the updated guidance in NUREG-7150, Volume 2. If the Fire PRA assumptions are not bounded by the new guidance, provide justification for each difference or provide updated risk results as part of the integrated analysis provided in response to PRA RAI 03 utilizing the guidance in NUREG-7150.
Response
a) The statement in Section 4.8.3.1.3 of the LAR should be that the probability that the hot short does not clear is 0.06.
NUREG/CR-7150 was not available in time to support the submittal. A value of 0.06 was used to characterize the likelihood that a hot short condition does not clear in 15 minutes for specific valves that had spurious operations identified. In order to credit the clearing of a hot short;
- 1) the valves would return to their failsafe position (opposite the spurious failure mode) if the spurious signal to these valves cleared, and 2) minimal impact due to valves in the spurious position was supported by thermal hydraulic analysis.
Recently performed thermal hydraulic analysis for the MSIV and Steam Dump valves showed that these components could remain in their spurious position for 5 minutes, without detrimental effects to the plant. The disposition of this time difference is addressed in PRA RAI 14b.
b)
NUREG/CR-7150 was not available in time to support the submittal. Consequently, the hot short duration methodology found in FAQ 08-0051 was used as the approach to modeling hot short durations in the analysis. This is a conservative approach as the 0.06 hot short duration probability used in the analysis equates to a less than 5 minutes rather than 15 minutes, hot short duration per NUREG/CR-7150 for both AC and DC circuits.
Thermal hydraulic information was provided as the basis for the 15 minute hot short duration value. The time in which the failed components associated with the hot short event could Page 38 of 44
remain in their failed position was evaluated and provided for all components. Recent thermal hydraulic analysis associated with the MSIV and Steam Dump valves indicated that these components could remain in their spurious position for 5 minutes, rather than 15 minutes, without detrimental effects to the plant. Per NUREG/CR-7150, the hot short duration probability at 5 minutes is 4.51E-02 for both AC and DC circuits and therefore is bounded by the 0.06 probability used in the current analysis. As previously stated, the 0.06 hot short duration probability used in the analysis equates to a less than 5 minute hot short duration in NUREG/CR-7150.
c)
With the updated NUREG/CR-7150, Vol. 2 guidance, two assumptions used in the Fire PRA require examination. It was assumed that hot shorts resulting in spurious operations of valves would have a probability of 0.06 to clear at 15 minutes. The updated guidance gives probabilities of 7.10E-03 and 2.20E-2, for AC and DC respectively, at 15 minutes, which are the respective floor values reached at 9 minutes and 7 minutes. The 0.06 value applied in the current analysis bounds the NUREG/CR-7150 values. A second assumption is that the CFMLA as applied is bounding for the updated NUREG/CR-7150, Vol. 2 guidance values. The Circuit Failure Mode Likelihood Analysis (CFMLA), Task 10 of NUREG/CR-6850, currently uses Option #1 and does not credit Current Power Transformer (CPTs). All numbers in the Task 10 CFMLA bound the updated NUREG/CR-7150 Vol. 2 CFMLA values with exception to Ground Fault Equivalent Hot Shorts (GFEHS). GFEHS was not addressed in NUREG/CR-6850 and was therefore not considered in the initial analysis. To maintain a bounding analysis, a minimum spurious probability of 0.17 will be used for components with ungrounded DC power supplies.
NUREG/CR-7150, Vol. 2 recommends the use of aggregate values for panel wiring and trunk cables, which would be bounded by the 0.6 applied. Hot short probabilities are not applicable to instrument cables; therefore, a 1.0 failure probability is applied. Any additional reductions in CDF and LERF would reduce the ACDF and ALERF, therefore the values provided in the Fire PRA are conservative. Additional discussion of the application of spurious signal clearing durations is addressed in PRA RAI 14a and 14b.
An exception is made for the cables with an assigned probability of 5E-8. These cables were determined to require a three phase hot short, which under the updated guidance is listed as "Incredible".
PRA RAI 17 Section 2.4.3.3 of NFPA 805 states that the PRA approach, methods, and data shall be acceptable to the NRC. RG 1.205 identifies NUREG/CR-6850 as documenting a methodology for conducting a fire PRA and endorses, with exceptions and clarifications, NEI 04-02, Revision 2, as providing methods acceptable to the staff for adopting a fire protection program consistent with NFPA-805. In letter dated July 12, 2006, to NEI (ADAMS Accession No. ML061660105), the NRC established the ongoing FAQ process where official agency positions regarding acceptable methods can be documented until they can be included in revisions to RG 1.205 or NEI 04-02.
The licensee's analysis appears to indicate that spatial separation is used as justification for plant partitioning (e.g., Turbine Building areas). Explain whether spatial separation is used as justification for Page 39 of 44
the plant partitioning used in the Fire PRA.
If it was used to identify the fire areas for which this approach is applied, describe how its use impacted the fire modeling for those areas.
Response
As described in Attachment 2 of the Plant Partitioning and Ignition Frequency Calculation (RNP-F/PSA-0067, Rev. 1), spatial separation was used for partitioning of certain Fire Compartments with open partitioning elements based on the absence of intervening combustibles or fire ignition sources observed during the walkdowns. In some cases, spatial separation was used in combination with other factors (e.g., non-rated walls or doors, lack of fixed ignition sources or combustibles in the compartment) as the basis for partitioning. Open partitioning elements were not used to exclude potential targets for the ZOI fire scenarios for any ignition source. For the multi-compartment analysis, as documented in Section 5.4 of RNP-F/PSA-0089, open partitioning elements were assigned a barrier failure probability of 1.0, consistent with Chapter 11 of NUREG/CR-6850.
PRA RAI 20 Section 2.4.3.3 of NFPA 805 states that the PRA approach, methods, and data shall be acceptable to the NRC. RG 1.205 identifies NUREG/CR-6850 as documenting a methodology for conducting a fire PRA and endorses, with exceptions and clarifications, NEI 04-02, Revision 2, as providing methods acceptable to the staff for adopting a fire protection program consistent with NFPA-805. In letter dated July 12, 2006, to NEI (ADAMS Accession No. ML061660105), the NRC established the ongoing FAQ process where official agency positions regarding acceptable methods can be documented until they can be included in revisions to RG 1.205 or NEI 04-02.
Discuss how fire-induced failure of instrumentation is addressed for human reliability analysis (HRA) by addressing the following:
- a.
Identify guidance used for differences approaches (e.g., screening, scoping, detailed analysis) that may have been used;
- b.
Explain how fire-induced instrument failure (including no-readings, off-scale readings, and incorrect/misleading readings) is addressed in the fire HRA, including a discussion of the implicit or explicit modeling of instrumentation for HRA in the Fire PRA; and,
- c.
Confirm that instrumentation credited in the HRA has been verified to be available for the fire scenarios in which they are credited.
Response
a)
As noted in NUREG-1921, the Fire Human Reliability Analysis defines Subtask 3 as the Quantitative Evaluation of Human Error Probability (HEP) using one of the following approaches:
Screening Scoping Detailed evaluation Of these three approaches, Screening and Detailed Evaluation were used, Scoping was not. The screening approach used for the RNP FPRA was based on a simplified version of section 5.1 of NUREG-1921 with the following factors.
Page 40 of 44
Internal events human failure events (HFEs) not concerned with fire sequences were given a value of 1.0 HFEs for which instrumentation was failed were given a value of 1.0 (logical true via explicit modeling of instrumentation)
New HFEs identified for Fire were give a screening value of 1.0 HFEs for actions outside the control room were given a value of 1.0 HFEs for main control room (MCR) actions required to be performed in the first hour were screened using 10 times the nominal internal events value.
HFEs for MCR actions not required in the first hour were screened using 2 times the nominal internal events value.
The existing dependency analysis was evaluated for impacts from the updated screening HEPs to perform the screening quantification. To avoid HFE loss due to truncation during quantification, a separate assessment was performed that identified the highest value of either the calculated screening value or the highest calculated dependency factor associated with the HFE. The higher of the two values was used during quantification to assure no loss of cutsets. The cutsets were post processed using rule based recovery to apply the identified screening HEP value or dependent HEP value.
For unacceptable cutset probabilities resulting from the HEP screening values, a detailed evaluation of the HEPs was performed in accordance with NUREG-1921, Appendix B, for the EPRI HRA Approach with specific consideration for fire impact on performance shaping factors (PSFs).
b) A detailed investigation was performed of all annunciator panel alarms and their associated instruments to identify misleading spurious alarms or indications which would result in possible errors of commission. Operators are trained to verify the accuracy of instrumentation on diverse and redundant instrumentation as discussed during operator interviews. Procedures include cautions regarding fire location and potential spurious indication response.
Furthermore, Auxiliary Operators can be dispatched to locally read instrumentation and verify conditions if needed. No potential undesired operator response actions resulting from spurious indications or alarms in the MCR were identified.
The required instrumentation for each operator action credited in the FPRA was reviewed and explicit fault trees for that instrumentation were added to the fault tree models with logic that would fail the operator actions (i.e., placed as a logical OR to the operator action event). If an instrument was affected by fire, no credit was given for that instrument toward the success of that operator action, regardless of how the instrument failed. In cases where multiple redundant and diverse instruments were available for the same information, the minimum required indication was determined for the action with the model logic reflecting the allowed number of failures. Indication was assumed to be failed in the most adverse manner that would cause the operator to fail to perform the required actions, such as no indication, off-scale low, off-scale high, or misleading. For parameters with multiple diverse indication, but with only a subset failed, indication failed in a misleading manner was assumed to be challenged or verified, based on knowledge of fire location, affected trains, and expected plant response, as was confirmed by operator interviews.
Page 41 of 44
c)
As discussed in response "b)", the instrumentation loops required for performing operator actions credited in the FPRA were modeled explicitly in the fault tree model. For these instrument loops, the cable routing was identified, and the associated fire sources affecting those cable routes were identified. From this information, fire scenario effects on plant instrumentation were appropriately modeled in the FPRA.
PRA RAI 22 Section 2.4.3.3 of NFPA 805 states that the PRA approach, methods, and data shall be acceptable to the NRC. RG 1.205 identifies NUREG/CR-6850 as documenting a methodology for conducting a fire PRA and endorses, with exceptions and clarifications, NEI 04-02, Revision 2, as providing methods acceptable to the staff for adopting a fire protection program consistent with NFPA-805. In letter dated July 12, 2006, to NEI (ADAMS Accession No. ML061660105), the NRC established the ongoing FAQ process where official agency positions regarding acceptable methods can be documented until they can be included in revisions to RG 1.205 or NEI 04-02. Methods that have not been determined to be acceptable by the NRC staff or acceptable methods that appear to have been applied differently than described require additional justification to allow the NRC staff to complete its review of the proposed method.
The licensee's analysis indicates that a minimum joint Human Error Probability (HEP) of 1E-6 was used. NUREG-1921, "EPRI/NRC-RES Fire Human Reliability Analysis Guidelines" July 2012 (ADAMS Accession No. ML12216A104), indicates, and NUREG-1792, "Good Practices for Implementing Human Reliability Analysis (HRA)" (ADAMS Accession No. ML051160213) (Table 2-1) states, that joint HEP values should not be below 1E-5. Confirm that each joint HEP value used in the Fire PRA below 1E-5 includes its own justification that demonstrates the inapplicability of the NUREG-1792 lower value guideline. Provide an estimate of the number of these joint HEPs below 1E-5 and at least two different examples of the justification.
Response
The dependency analyses are individually developed and reviewed with explicit criteria that are used to assess the degree of dependence between multiple human actions for recovery. None of the joint HEP values produced by the dependency analyses are below 1E-6. All of the recovery values applied have justification. The majority of the 16 joint human error probabilities (HEP) with values below 1E-5 are based on two criteria. The first criterion is an intervening successful human action between the other recovered actions. The second criterion is a very long duration between two human actions. Generally under this criterion, the time separation between two human actions is greater than an operator's shift.
An example of the first criterion is XOPER-T08. This scenario involves the failure of actions to refill the condensate storage tank and initiate swap over to recirculation mode following successful initiation of feed and bleed. The first failed human actions are the methods to make up inventory to the condensate storage tank (OPER-18A and OPER-18B) which fail the use of the steam generators for decay heat removal. The action to refill the condensate storage tank would be alarmed approximately 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> later and need to be completed approximately 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> after the start of the transient, which is well after the fire should be extinguished. This failure to make up Condensate Storage Tank inventory is followed by a successful operator action to initiate feed and bleed. (OPER-03) The initiation of feed and bleed is followed by a failure to initiate swap over following depletion of the Refueling Water Storage Tank (OPER-OlT). The operator action to successfully initiate feed and bleed is assumed to break the dependency between the condensate storage tank inventory makeup and the swap over to recirculation mode.
Page 42 of 44
An example of the second criterion is XOPER-D04. This scenario involves the human actions to provide service water cooling to plant components using service water pump D powered by the dedicated shutdown (DS) bus (OPER-25DS) and actions to refill the Condensate Storage Tank (OPER-18A). The action to power service water pump D from the DS bus and use for cooling of plant equipment would occur early in the transient. The failure of service water would prevent the use of feed and bleed cooling for decay heat removal. The action to refill the condensate storage tank would be alarmed approximately 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> later and need to be completed approximately 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> after the start of the transient. Since the cues, procedures, type of action and timing are very different; zero or low dependency is assessed for these cases.
PRA RAI 29 Section 2.4.3.3 of NFPA 805 states that the PRA approach, methods, and data shall be acceptable to the NRC. Section 2.4.4.1 of NFPA-805 further states that the change in public health risk arising from transition from the current fire protection program to an NFPA-805 based program, and all future plant changes to the program, shall be acceptable to the NRC. RG 1.174 provides quantitative guidelines on CDF, LERF, and identifies acceptable changes to these frequencies that result from proposed changes to the plant's licensing basis and describes a general framework to determine the acceptability of risk-informed changes. The NRC staff review of the information in the LAR has identified the following information that is required to fully characterize the risk estimates.
Section 4.8.3.1.2 of the LAR states that the "strategy going forward is to use a symptom based operator response approach" opposed to the current strategy referred to as self-induced station blackout (SISBO). Section 4.8.3.1.2 of the LAR states that Attachment G recovery actions reflect the new strategy of symptom based operator response in case of fire. FAQ 09-0057, "New Shutdown Strategy," describes one acceptable method to simplify transition from a SISBO strategy. The FAQ states, "[t]he F[fire]PRA performed for the non-SISBO case would constitute the baseline PRA for all fire risk evaluations performed to support the NFPA 805 transition." In other words, the change in risk is estimated by modifying the post-transition model, not modelling the current plant. Yet, Section 4.8.3.1.2 of the LAR makes the statement that the "current PRA conservatively modeled the plant using the current load shed strategy." Explain the meaning of this statement including whether the term "current PRA" refers to the post-transition or compliant fire PRA models discussed in Section W.2.1. Confirm that FAQ 09-0057 has been used or describe and justify any differences between the FAQ and your method.
Response
Section 4.8.3.1.2 of the LAR states that the "current PRA conservatively modeled the plant using the current load shed strategy" because the Fire PRA Human Reliability Analysis (HRA) was based on the current Dedicated Shutdown Procedures (DSPs) that utilize the load shed strategy to prevent spurious operations for fires in certain, risk significant areas. As used in this statement, the term "current PRA" would apply equally well to both the post-transition FPRA and the compliant FPRA. No credit is given in the Fire PRA for prevention of fire-induced hot shorts leading to spurious operations as a result of implementing the load shed strategy.
Although not available in time to support the development of the original Fire HRA, revised DSPs with the load shed strategy removed have now been drafted to sufficient detail to support revision of the Fire PRA HRA, which is currently underway.
Implementing these changes to the Fire PRA will be consistent with the guidance of FAQ 09-0057 in that Fire PRA model will reflect the post-transition plant.
Page 43 of 44
These changes to the HRA will be reflected in the Fire PRA results used in response to PRA RAI 03, and in the CDF, LERF, ACDF, and ALERF values provided in LAR Attachment W, submitted with the 120 day response.
Page 44 of 44