Letter Sequence Other |
|---|
|
Results
Other: CNL-14-085, Documents for the Environmental Review of License Renewal Application - Env 3, ML13067A244, ML13123A175, ML13282A585, ML13289A095, ML13289A096, ML13289A097, ML13289A098, ML13289A099, ML13289A100, ML13289A101, ML13289A108, ML13289A111, ML13289A112, ML13289A113, ML13289A114, ML13289A115, ML13289A116, ML13289A117, ML13289A118, ML13289A119, ML13289A120, ML13289A121, ML13289A122, ML13289A123, ML13289A124, ML13289A125, ML13289A126, ML13289A127, ML13289A129, ML13289A130, ML13289A132, ML13289A133, ML13289A134, ML13289A136, ML14198A610, ML15051A453, ML15051A473
|
MONTHYEARML13289A1342009-01-31031 January 2009 WR2009-1-45-151, Ambient Temperature and Mixing Zone Studies for Sequoyah Nuclear Plant as Required by NPDES Permit No. TN0026450 of September 2005 Project stage: Other ML13289A0982009-11-30030 November 2009 Potential Impact of Climate Change on Natural Resources in the Tennessee Valley Authority Region Project stage: Other ML13289A0972011-02-0202 February 2011 NPDES Permit No. TN0026450 Soddy Daisy, Hamilton County, Tennessee Project stage: Other ML12150A0442012-05-17017 May 2012 Location Change for Forthcoming Meeting with Tennessee Valley Authority Regarding Flooding/Hydrology Licensing Basis at Watts Bar, Unit 1 and Sequoyah Nuclear Plant Project stage: Request ML12244A0182012-08-23023 August 2012 Transmittal of Final Safety Analysis Report (Fsar), Amendment 109 Project stage: Request ML13067A2442013-03-26026 March 2013 Lr Environmental Site Audit Regarding Sequoyah Nuclear Plant Project stage: Other ML13108A1072013-04-16016 April 2013 Commitment to Install Improved Flood Mitigation Systems Project stage: Request ML13289A1002013-04-30030 April 2013 WR2013-1-45-152, Study to Confirm the Calibration of the Numerical Model for the Thermal Discharge from Sequoyah Nuclear Plant as Required by NPDES Permit No. TN0026450 of March 2011 Project stage: Other ML13289A0952013-04-30030 April 2013 WR2013-1-45-152, Study to Confirm the Calibration of the Numerical Model for the Thermal Discharge from Sequoyah Nuclear Plant as Required by NPDES Permit No. TN0026450 of March 2011 Project stage: Other ML13289A0942013-05-0202 May 2013 Plan (SQN) NPDES Permit No. TN0026450 - Application for Renewal Project stage: Request ML13108A1272013-05-0808 May 2013 Summary of Public Scoping Meetings Conducted Related to the Review of the Sequoyah Nuclear Plant, License Renewal Application (TAC Nos MF0057 & TAC MF0058) Project stage: Meeting ML13123A1752013-05-22022 May 2013 PM Change for the Lr of Sequoyah Nuclear Plant, Units 1 and 2 Project stage: Other ML13227A0032013-07-17017 July 2013 Response to NRC Request for Additional Information Regarding the Environmental Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML13206A3852013-07-23023 July 2013 Response to NRC Request for Additional Information Regarding the Environmental Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML13120A1982013-08-0707 August 2013 Summary of Site Audit Related to the Review of the License Renewal Application for Sequoyah Nuclear Generation Station, Units 1 and 2, Project stage: Approval ML13289A1212013-09-20020 September 2013 Enclosutemps 2009 Project stage: Other ML13289A1302013-09-20020 September 2013 Enclosutemps 2008 Project stage: Other ML13289A1292013-09-20020 September 2013 Enclosutemps 2007 Project stage: Other ML13289A1272013-09-20020 September 2013 Enclosuflows & Stage 2012 Project stage: Other ML13289A1262013-09-20020 September 2013 Enclosuflows & Stage 2011 Project stage: Other ML13289A1252013-09-20020 September 2013 Enclosuflows & Stage 2010 Project stage: Other ML13289A1242013-09-20020 September 2013 Enclosuflows & Stage 2009 Project stage: Other ML13289A1232013-09-20020 September 2013 Enclosutemps 2011 Project stage: Other ML13289A1222013-09-20020 September 2013 Enclosutemps 2010 Project stage: Other ML13289A1362013-09-20020 September 2013 Enclosuchart on Missing Record from 2000 Through 2003 Project stage: Other ML13289A1202013-09-20020 September 2013 Enclosuflows & Stage 2008 Project stage: Other ML13289A1192013-09-20020 September 2013 Enclosuflows & Stage 2007 Project stage: Other ML13289A1182013-09-20020 September 2013 Enclosugraphics and Charts on Diffuser Discharge Temperature for Years 2007 Through 2012 Project stage: Other ML13289A1172013-09-20020 September 2013 Enclosugraphics and Charts on Years 2007 Through 2013 Project stage: Other ML13289A1322013-09-20020 September 2013 Enclosutemps 2012 Project stage: Other ML13289A1332013-09-20020 September 2013 Enclosutemps 2013 Project stage: Other ML13289A1162013-09-20020 September 2013 Enclosure 1: Chart on Temperture 2013 Project stage: Other ML13289A1152013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2012 Project stage: Other ML13289A1142013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2011 Project stage: Other ML13289A1132013-09-20020 September 2013 Enclosuchart on Temperature 2010 Project stage: Other ML13289A1122013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2009 Project stage: Other ML13289A1112013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2008 Project stage: Other ML13289A1012013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2007 Project stage: Other ML13289A0992013-09-20020 September 2013 Enclosudata and Chart on Drybulb Temperature (F) Project stage: Other ML13282A5852013-09-20020 September 2013 Submittal of Sensitive Documents for the Environmental Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application - Env 2.A Project stage: Other ML13289A1082013-09-20020 September 2013 Documents for the Environmental Review of the License Renewal Application - Env 2.B Project stage: Other ML13289A0962013-09-20020 September 2013 Enclosuriver Temperature, 2007-2013 - Daily Max TUS_Comp_24-hr Project stage: Other ML14007A4702014-02-10010 February 2014 Schedule Revision for Review of Sequoyah Nuclear Plant License Renewal Application Project stage: Approval ML14064A4842014-04-24024 April 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Application by Tennessee Valley Authority for Sequoyah Nuclear Plant, Units 1 and 2 - Page 26 Through End Project stage: Approval ML14041A1182014-04-24024 April 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of Application by Tennessee Valley Authority for Sequoyah Nuclear Plant, Units 1 and 2 (Tac Nos. MF0057 and MF0058)- Page Continue Project stage: Approval CNL-14-085, Documents for the Environmental Review of License Renewal Application - Env 32014-05-27027 May 2014 Documents for the Environmental Review of License Renewal Application - Env 3 Project stage: Other ML14211A4542014-07-31031 July 2014 NUREG-1437 Supp 53 Dfc Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding Sequoyah Nuclear Plant, Units 1 and 2, (Draft Report for Comment) Project stage: Draft Other ML14198A6102014-08-0101 August 2014 License Renewal Application for Sequoyah Nuclear Plant, Units 1 and 2 - FRN Project stage: Other ML14198A6192014-08-0707 August 2014 Notice of Availability of the Draft Plant-Specific Supplement 53 to the Generic Environmental Impact Statement for License Renewal of the Nuclear Plants Regarding Sequoyah Nuclear Plant, Units 1 and 2 (TAC Nos. MF0057 and MF0058) Project stage: Draft Other ML14225A1572014-08-12012 August 2014 Maintenance of Draft Supplemental Environmental Impact Statement at the Downtown Branch of the Chattanooga-Hamilton County Library in Regards to the Review of the Sequoyah Nuclear Plant, License Renewal Application (Tac. MF0057 and MF0058) Project stage: Draft Approval 2013-05-08
[Table View] |
Text
90 100 Q_WBH_1-hr_avg Q_APH_1-hr-avg Q O1H 1-hr avg 80 Q_
g Q_CHH_1-hr_avg 60 70 0 cfs) 40 50 Discharge (1000 30 D
10 20 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2011
685 686 HWEL_CHH_Inst Top of gates 685.44 683 684 vel)
Guide curve 681 682 et mean sea lev 679 680 ce elevation (fee 677 678 Water Surfac 675 676 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 674 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2011
Parameter Location Definition Q_WBH_1-hr_avg TRM_529.9 Hourly average total release from Watts Bar Dam on the Tennessee River into Chickamauga Reservoir.
Q_APH_1-hr-avg HRM_66.0 Hourly average total release from Apalachia Dam on the Hiwassee River. The Hiwassee River empties into Chickamauga Reservoir.
Q_O1H_1-hr_avg ORM_11.9 Hourly average total release from Ocoee 1 Dam on the Ocoee River. The Ocoee River empties into the Hiwassee River downstream of Apalachia Dam.
Q_CHH_1-hr_avg TRM_471.0 Hourly average total release from Chickamauga Dam (i.e., out or Chickamauga Reservoir) on the Tennessee River into Nickajack Reservoir.
HWEL_CHH_Inst TRM_471.0 Instantaneous headwater elevation at Chickamauga Dam, recorded at the end of the hour.
Units cfs cfs cfs cfs feet msl
Jan 0
-100000 0
685.44 Top of gates Jan 31 31
-100000 20 685.44 Top of gates Feb 31 100000 Feb 28 59 100000 Julian Lower Band Guide Curve Upper Band Mar 59
-100000 0
675.0 676.0 677.0 Mar 31 90
-100000 90 675.0 676.0 677.0 Apr 90 100000 96 678.0 679.0 679.5 Apr 30 120 100000 134 681.5 682.3 682.5 May 120
-100000 246 681.5 682.3 682.5 May 31 151
-100000 272 680.5 681.0 681.5 Jun 151 100000 334 675.0 676.0 677.0 Jun 30 181 100000 365 675.0 676.0 677.0 Jul 181
-100000 Jul 31 212
-100000 Aug 212 100000 Aug 31 243 100000 Sep 243
-100000 Sep 30 273
-100000 Oct 273 100000 Oct 31 304 100000 Nov 304
-100000 Nov 30 334
-100000 Dec 334 100000 Dec 31 365 100000 Julian Gridlines