Other: CNL-14-085, Documents for the Environmental Review of License Renewal Application - Env 3, ML13067A244, ML13123A175, ML13282A585, ML13289A095, ML13289A096, ML13289A097, ML13289A098, ML13289A099, ML13289A100, ML13289A101, ML13289A108, ML13289A111, ML13289A112, ML13289A113, ML13289A114, ML13289A115, ML13289A116, ML13289A117, ML13289A118, ML13289A119, ML13289A120, ML13289A121, ML13289A122, ML13289A123, ML13289A124, ML13289A125, ML13289A126, ML13289A127, ML13289A129, ML13289A130, ML13289A132, ML13289A133, ML13289A134, ML13289A136, ML14198A610, ML15051A453, ML15051A473
|
MONTHYEARML13289A1342009-01-31031 January 2009 WR2009-1-45-151, Ambient Temperature and Mixing Zone Studies for Sequoyah Nuclear Plant as Required by NPDES Permit No. TN0026450 of September 2005 Project stage: Other ML13289A0982009-11-30030 November 2009 Potential Impact of Climate Change on Natural Resources in the Tennessee Valley Authority Region Project stage: Other ML13289A0972011-02-0202 February 2011 NPDES Permit No. TN0026450 Soddy Daisy, Hamilton County, Tennessee Project stage: Other ML12150A0442012-05-17017 May 2012 Location Change for Forthcoming Meeting with Tennessee Valley Authority Regarding Flooding/Hydrology Licensing Basis at Watts Bar, Unit 1 and Sequoyah Nuclear Plant Project stage: Request ML12244A0182012-08-23023 August 2012 Transmittal of Final Safety Analysis Report (Fsar), Amendment 109 Project stage: Request ML13067A2442013-03-26026 March 2013 Lr Environmental Site Audit Regarding Sequoyah Nuclear Plant Project stage: Other ML13108A1072013-04-16016 April 2013 Commitment to Install Improved Flood Mitigation Systems Project stage: Request ML13289A1002013-04-30030 April 2013 WR2013-1-45-152, Study to Confirm the Calibration of the Numerical Model for the Thermal Discharge from Sequoyah Nuclear Plant as Required by NPDES Permit No. TN0026450 of March 2011 Project stage: Other ML13289A0952013-04-30030 April 2013 WR2013-1-45-152, Study to Confirm the Calibration of the Numerical Model for the Thermal Discharge from Sequoyah Nuclear Plant as Required by NPDES Permit No. TN0026450 of March 2011 Project stage: Other ML13289A0942013-05-0202 May 2013 Plan (SQN) NPDES Permit No. TN0026450 - Application for Renewal Project stage: Request ML13108A1272013-05-0808 May 2013 Summary of Public Scoping Meetings Conducted Related to the Review of the Sequoyah Nuclear Plant, License Renewal Application (TAC Nos MF0057 & TAC MF0058) Project stage: Meeting ML13123A1752013-05-22022 May 2013 PM Change for the Lr of Sequoyah Nuclear Plant, Units 1 and 2 Project stage: Other ML13227A0032013-07-17017 July 2013 Response to NRC Request for Additional Information Regarding the Environmental Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML13206A3852013-07-23023 July 2013 Response to NRC Request for Additional Information Regarding the Environmental Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML13120A1982013-08-0707 August 2013 Summary of Site Audit Related to the Review of the License Renewal Application for Sequoyah Nuclear Generation Station, Units 1 and 2, Project stage: Approval ML13289A1212013-09-20020 September 2013 Enclosutemps 2009 Project stage: Other ML13289A1302013-09-20020 September 2013 Enclosutemps 2008 Project stage: Other ML13289A1292013-09-20020 September 2013 Enclosutemps 2007 Project stage: Other ML13289A1272013-09-20020 September 2013 Enclosuflows & Stage 2012 Project stage: Other ML13289A1262013-09-20020 September 2013 Enclosuflows & Stage 2011 Project stage: Other ML13289A1252013-09-20020 September 2013 Enclosuflows & Stage 2010 Project stage: Other ML13289A1242013-09-20020 September 2013 Enclosuflows & Stage 2009 Project stage: Other ML13289A1232013-09-20020 September 2013 Enclosutemps 2011 Project stage: Other ML13289A1222013-09-20020 September 2013 Enclosutemps 2010 Project stage: Other ML13289A1362013-09-20020 September 2013 Enclosuchart on Missing Record from 2000 Through 2003 Project stage: Other ML13289A1202013-09-20020 September 2013 Enclosuflows & Stage 2008 Project stage: Other ML13289A1192013-09-20020 September 2013 Enclosuflows & Stage 2007 Project stage: Other ML13289A1182013-09-20020 September 2013 Enclosugraphics and Charts on Diffuser Discharge Temperature for Years 2007 Through 2012 Project stage: Other ML13289A1172013-09-20020 September 2013 Enclosugraphics and Charts on Years 2007 Through 2013 Project stage: Other ML13289A1322013-09-20020 September 2013 Enclosutemps 2012 Project stage: Other ML13289A1332013-09-20020 September 2013 Enclosutemps 2013 Project stage: Other ML13289A1162013-09-20020 September 2013 Enclosure 1: Chart on Temperture 2013 Project stage: Other ML13289A1152013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2012 Project stage: Other ML13289A1142013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2011 Project stage: Other ML13289A1132013-09-20020 September 2013 Enclosuchart on Temperature 2010 Project stage: Other ML13289A1122013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2009 Project stage: Other ML13289A1112013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2008 Project stage: Other ML13289A1012013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2007 Project stage: Other ML13289A0992013-09-20020 September 2013 Enclosudata and Chart on Drybulb Temperature (F) Project stage: Other ML13282A5852013-09-20020 September 2013 Submittal of Sensitive Documents for the Environmental Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application - Env 2.A Project stage: Other ML13289A1082013-09-20020 September 2013 Documents for the Environmental Review of the License Renewal Application - Env 2.B Project stage: Other ML13289A0962013-09-20020 September 2013 Enclosuriver Temperature, 2007-2013 - Daily Max TUS_Comp_24-hr Project stage: Other ML14007A4702014-02-10010 February 2014 Schedule Revision for Review of Sequoyah Nuclear Plant License Renewal Application Project stage: Approval ML14064A4842014-04-24024 April 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Application by Tennessee Valley Authority for Sequoyah Nuclear Plant, Units 1 and 2 - Page 26 Through End Project stage: Approval ML14041A1182014-04-24024 April 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of Application by Tennessee Valley Authority for Sequoyah Nuclear Plant, Units 1 and 2 (Tac Nos. MF0057 and MF0058)- Page Continue Project stage: Approval CNL-14-085, Documents for the Environmental Review of License Renewal Application - Env 32014-05-27027 May 2014 Documents for the Environmental Review of License Renewal Application - Env 3 Project stage: Other ML14211A4542014-07-31031 July 2014 NUREG-1437 Supp 53 Dfc Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding Sequoyah Nuclear Plant, Units 1 and 2, (Draft Report for Comment) Project stage: Draft Other ML14198A6102014-08-0101 August 2014 License Renewal Application for Sequoyah Nuclear Plant, Units 1 and 2 - FRN Project stage: Other ML14198A6192014-08-0707 August 2014 Notice of Availability of the Draft Plant-Specific Supplement 53 to the Generic Environmental Impact Statement for License Renewal of the Nuclear Plants Regarding Sequoyah Nuclear Plant, Units 1 and 2 (TAC Nos. MF0057 and MF0058) Project stage: Draft Other ML14225A1572014-08-12012 August 2014 Maintenance of Draft Supplemental Environmental Impact Statement at the Downtown Branch of the Chattanooga-Hamilton County Library in Regards to the Review of the Sequoyah Nuclear Plant, License Renewal Application (Tac. MF0057 and MF0058) Project stage: Draft Approval 2013-05-08
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-Q001 Mr. John T. Carlin Site Vice President Sequoyah Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Soddy-Da1sy, TN 37384 February 10, 2014
SUBJECT:
SCHEDULE REVISION FOR THE REVIEW OF THE SEQUOYAH NUCLEAR PLANT LICENSE RENEWAL APPLICATION (TAG NOS. MF0057 AND MF0058)
Dear Mr. Carlin:
By letter dated January 7, 2013, Tennessee Valley Authority (TVA) submitted an application pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR) Part 51 and 10 CFR Part 54, to renew Sequoyah Nuclear Plant (SQN) operating licenses DPR-77 and DPR*79, for review by the U.S. Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the schedule for the SQN license renewal review.
The environmental review milestone "Issue draft supplemental environmental impact statement (SEIS)" is revised from February to July 2014. The NRC staff requires additional time to allow for the internal review of the SEIS in a manner which balances internal workload across numerous ongoing reviews and works through significant SEIS format changes associated with the recently revised "Generic Environmental Impact Statement for License Renewal of Nuclear Plants." The environmental review milestones "Public meeting-draft SEIS meeting" and "Issue final SEIS" are revised from March to August 2014, and October 2014 to March 2015.
respectively, because of the revision to the draft SEIS milestone.
In addition, the safety review milestone due dates for: "Issue safety evaluation report (SER) with open items" due March 2014; "Advisory Committee on Reactor Safeguards (ACRS)
Subcommittee meeting" due May 2014; "Issue final SER" due October 2014; and "ACRS full committee meeting" due December 2014, are revised to "To Be Determined (TBD)." To support the issuance of a revised schedule, your response to the NRC staffs request for additional Information (RAI) B.1.34-9, dated December 6, 2013 (ADAMS Access1on No ML13323A097},
concerning reactor vessel internals program action item 1, must be complete and provided to the NRC in a timely manner. After receiving the RAI response, the NRC staff will review the response and, if acceptable, incorporate the response in the safety review, and new ACRS dates will be determined.
Enclosed is the NRC staffs revised review schedule for the SON license renewal application.
If you have any questions related to this revised schedule, please contact Mr. David Drucker, for
the environmental review milestone changes by telephone at 301-415-6223 or by e-mail at david.drucker@nrc.gov or Mr. Richard Plasse, for the safety review milestone changes, by telephone at 301-415-1427 or by e-mail at richard.plasse@nrc.gov.
Sincerely, J
n
. Lubinsk irector Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-327 and 50-328
Enclosure:
Revised Schedule cc w/encl: Listserv
- ML14007A470 john.pelchat@nrc.gov gena.woodruff@nrc.gov caudle.julian@nrc.gov scott. shaeffer@nrc.gov jeffrey.hamman@nrc.gov OFFICE LA:DLR PM: RPB2:DLR PM: RPB1 :DLR BC:RPB1 :DLR BC:RPB2:DLR NAME I King DDrucker RPiasse YDiaz-Sanabria BWittick DATE 2/4/14 1/14/14 2/3/14 2/6/14 2/7/14
SEQUOYAH NUCLEAR PLANT LICENSE RENEWAL APPLICATION SCHEDULE REVISION Milestone Schedule Receive license renewal application (LRA) 1/2013 Publish Federal Register Notice (FRN) - LRA availability 2/2013 Publish FRN - acceptance/rejection and opportunity for hearing 3/2013 Publish FRN - environmental seeping meeting 3/2013 Audit-Seeping & Screening Methodology 3/11/13 Audit -Aging Management Programs 3/18/13 Public Meeting License Renewal Overview and Environmental Seeping 4/03/13 meeting Audit-Environmental 4/08/13 Deadline for filing hearing requests and petitions for intervention 5/2013 Environmental seeping period ends 5/2013 Inspection-Regional 11/18/13&
12/08/13 Issue draft supplemental environmental impact statement (SEIS) 7/2014 U.S. Environmental Protection Agency FRN Published draft SEIS 8/2014 available for comment Public Meeting -draft SEIS meeting 8/2014 Issue safety evaluation report (SER) with open items TBD End of draft SEIS comment period 9/2014 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee TBD meeting Issue final SEIS 3/2015 U S. Environmental Protection Agency FRN Published availability of final 4/2015 SEIS Issue final SER TBD ACRS full committee meeting TBD Decision-Director, NRR 6/2015 Commission decision (if hearing is granted)
TBD Actual 1/15/13 2/22/13 3/05/13 3/08/13 3/11/13 3/18/13 4/03/13 4/08/13 5/06/13 5/03/13 11/18/13&
12/08/13 ENCLOSURE