Other: CNL-14-085, Documents for the Environmental Review of License Renewal Application - Env 3, ML13067A244, ML13123A175, ML13282A585, ML13289A095, ML13289A096, ML13289A097, ML13289A098, ML13289A099, ML13289A100, ML13289A101, ML13289A108, ML13289A111, ML13289A112, ML13289A113, ML13289A114, ML13289A115, ML13289A116, ML13289A117, ML13289A118, ML13289A119, ML13289A120, ML13289A121, ML13289A122, ML13289A123, ML13289A124, ML13289A125, ML13289A126, ML13289A127, ML13289A129, ML13289A130, ML13289A132, ML13289A133, ML13289A134, ML13289A136, ML14198A610, ML15051A453, ML15051A473
|
MONTHYEARML13289A1342009-01-31031 January 2009 WR2009-1-45-151, Ambient Temperature and Mixing Zone Studies for Sequoyah Nuclear Plant as Required by NPDES Permit No. TN0026450 of September 2005 Project stage: Other ML13289A0982009-11-30030 November 2009 Potential Impact of Climate Change on Natural Resources in the Tennessee Valley Authority Region Project stage: Other ML13289A0972011-02-0202 February 2011 NPDES Permit No. TN0026450 Soddy Daisy, Hamilton County, Tennessee Project stage: Other ML12244A0182012-08-23023 August 2012 Transmittal of Final Safety Analysis Report (Fsar), Amendment 109 Project stage: Request ML13067A2442013-03-26026 March 2013 Lr Environmental Site Audit Regarding Sequoyah Nuclear Plant Project stage: Other ML13108A1072013-04-16016 April 2013 Commitment to Install Improved Flood Mitigation Systems Project stage: Request ML13289A1002013-04-30030 April 2013 WR2013-1-45-152, Study to Confirm the Calibration of the Numerical Model for the Thermal Discharge from Sequoyah Nuclear Plant as Required by NPDES Permit No. TN0026450 of March 2011 Project stage: Other ML13289A0952013-04-30030 April 2013 WR2013-1-45-152, Study to Confirm the Calibration of the Numerical Model for the Thermal Discharge from Sequoyah Nuclear Plant as Required by NPDES Permit No. TN0026450 of March 2011 Project stage: Other ML13289A0942013-05-0202 May 2013 Plan (SQN) NPDES Permit No. TN0026450 - Application for Renewal Project stage: Request ML13108A1272013-05-0808 May 2013 Summary of Public Scoping Meetings Conducted Related to the Review of the Sequoyah Nuclear Plant, License Renewal Application (TAC Nos MF0057 & TAC MF0058) Project stage: Meeting ML13123A1752013-05-22022 May 2013 PM Change for the Lr of Sequoyah Nuclear Plant, Units 1 and 2 Project stage: Other ML13227A0032013-07-17017 July 2013 Response to NRC Request for Additional Information Regarding the Environmental Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML13206A3852013-07-23023 July 2013 Response to NRC Request for Additional Information Regarding the Environmental Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application Project stage: Response to RAI ML13120A1982013-08-0707 August 2013 Summary of Site Audit Related to the Review of the License Renewal Application for Sequoyah Nuclear Generation Station, Units 1 and 2, Project stage: Approval ML13289A1212013-09-20020 September 2013 Enclosutemps 2009 Project stage: Other ML13289A1302013-09-20020 September 2013 Enclosutemps 2008 Project stage: Other ML13289A1292013-09-20020 September 2013 Enclosutemps 2007 Project stage: Other ML13289A1272013-09-20020 September 2013 Enclosuflows & Stage 2012 Project stage: Other ML13289A1262013-09-20020 September 2013 Enclosuflows & Stage 2011 Project stage: Other ML13289A1252013-09-20020 September 2013 Enclosuflows & Stage 2010 Project stage: Other ML13289A1242013-09-20020 September 2013 Enclosuflows & Stage 2009 Project stage: Other ML13289A1232013-09-20020 September 2013 Enclosutemps 2011 Project stage: Other ML13289A1222013-09-20020 September 2013 Enclosutemps 2010 Project stage: Other ML13289A1362013-09-20020 September 2013 Enclosuchart on Missing Record from 2000 Through 2003 Project stage: Other ML13289A1202013-09-20020 September 2013 Enclosuflows & Stage 2008 Project stage: Other ML13289A1192013-09-20020 September 2013 Enclosuflows & Stage 2007 Project stage: Other ML13289A1182013-09-20020 September 2013 Enclosugraphics and Charts on Diffuser Discharge Temperature for Years 2007 Through 2012 Project stage: Other ML13289A1172013-09-20020 September 2013 Enclosugraphics and Charts on Years 2007 Through 2013 Project stage: Other ML13289A1322013-09-20020 September 2013 Enclosutemps 2012 Project stage: Other ML13289A1332013-09-20020 September 2013 Enclosutemps 2013 Project stage: Other ML13289A1162013-09-20020 September 2013 Enclosure 1: Chart on Temperture 2013 Project stage: Other ML13289A1152013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2012 Project stage: Other ML13289A1142013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2011 Project stage: Other ML13289A1132013-09-20020 September 2013 Enclosuchart on Temperature 2010 Project stage: Other ML13289A1122013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2009 Project stage: Other ML13289A1112013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2008 Project stage: Other ML13289A1012013-09-20020 September 2013 Enclosure 1: Chart on Temperature 2007 Project stage: Other ML13289A0992013-09-20020 September 2013 Enclosudata and Chart on Drybulb Temperature (F) Project stage: Other ML13282A5852013-09-20020 September 2013 Submittal of Sensitive Documents for the Environmental Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application - Env 2.A Project stage: Other ML13289A1082013-09-20020 September 2013 Documents for the Environmental Review of the License Renewal Application - Env 2.B Project stage: Other ML13289A0962013-09-20020 September 2013 Enclosuriver Temperature, 2007-2013 - Daily Max TUS_Comp_24-hr Project stage: Other ML14007A4702014-02-10010 February 2014 Schedule Revision for Review of Sequoyah Nuclear Plant License Renewal Application Project stage: Approval ML14064A4842014-04-24024 April 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Application by Tennessee Valley Authority for Sequoyah Nuclear Plant, Units 1 and 2 - Page 26 Through End Project stage: Approval ML14041A1182014-04-24024 April 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of Application by Tennessee Valley Authority for Sequoyah Nuclear Plant, Units 1 and 2 (Tac Nos. MF0057 and MF0058)- Page Continue Project stage: Approval CNL-14-085, Documents for the Environmental Review of License Renewal Application - Env 32014-05-27027 May 2014 Documents for the Environmental Review of License Renewal Application - Env 3 Project stage: Other ML14211A4542014-07-31031 July 2014 NUREG-1437 Supp 53 Dfc Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding Sequoyah Nuclear Plant, Units 1 and 2, (Draft Report for Comment) Project stage: Draft Other ML14198A6102014-08-0101 August 2014 License Renewal Application for Sequoyah Nuclear Plant, Units 1 and 2 - FRN Project stage: Other ML14198A6192014-08-0707 August 2014 Notice of Availability of the Draft Plant-Specific Supplement 53 to the Generic Environmental Impact Statement for License Renewal of the Nuclear Plants Regarding Sequoyah Nuclear Plant, Units 1 and 2 (TAC Nos. MF0057 and MF0058) Project stage: Draft Other ML14225A1572014-08-12012 August 2014 Maintenance of Draft Supplemental Environmental Impact Statement at the Downtown Branch of the Chattanooga-Hamilton County Library in Regards to the Review of the Sequoyah Nuclear Plant, License Renewal Application (Tac. MF0057 and MF0058) Project stage: Draft Approval ML14225A1582014-08-12012 August 2014 Maintenance of Draft Supplemental Environmental Impact Statement at the Signal Mountain Library in Regards to the Review of the Sequoyah Nuclear Plant License Renewal Application (TAC MF0057 and MF0058) Project stage: Draft Approval 2013-07-17
[Table View] |
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-327 and 50-328; NRC-2013-0037]
Sequoyah Nuclear Plant, Units 1 & 2 AGENCY: Nuclear Regulatory Commission.
ACTION: Supplemental environmental impact statement; issuance.
SUMMARY
- The U.S. Nuclear Regulatory Commission (NRC) is issuing a final plant-specific supplement, Supplement 53, to NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), regarding the renewal of Tennessee Valley Authority (TVA) operating licenses DPR-77 and DPR-79 for an additional 20 years of operation for Sequoyah Nuclear Plant, Units 1 & 2 (SQN).
DATES: The supplemental environmental impact statement referenced in this document is available on [INSERT DATE OF PUBLICATION IN THE FEDERAL REGISTER].
ADDRESSES: Please refer to Docket ID NRC-2013-0037 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods:
- Federal Rulemaking Web Site: Go to http://www.regulations.gov and search for Docket ID NRC-2013-0037. Address questions about NRC dockets to Carol Gallagher; telephone: 301-415-3463; e-mail: Carol.Gallagher@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
- NRCs Agencywide Documents Access and Management System (ADAMS):
You may obtain publicly-available documents online in the ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ADAMS Public Documents and then select Begin Web-based ADAMS Search. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. The final Supplement 53 to the GEIS is available in ADAMS under Accession No. ML15075A438.
- NRCs PDR: You may examine and purchase copies of public documents at the NRCs PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
- Chattanooga-Hamilton County Library, Northgate Branch: The final Supplement 53 to the GEIS is available for public inspection at 520 Northgate Mall Road, Chattanooga, TN 37415.
FOR FURTHER INFORMATION, CONTACT: David Drucker, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone:
800-368-5692, ext. 6223, e-mail: David.Drucker@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Background.
In accordance with § 51.118 of Title 10 of the Code of Federal Regulations, the NRC is issuing the final Supplement 53 to the GEIS regarding the renewal of TVA operating licenses DPR-77 and DPR-79 for an additional 20 years of operation for SQN. Draft Supplement 53 to the GEIS was noticed by the NRC in the Federal Register on August 11, 2014 (79 FR 46878),
and noticed by the Environmental Protection Agency on August 15, 2014 (79 FR 48140). The public comment period on draft Supplement 53 to the GEIS ended on September 29, 2014, and the comments received are addressed in final Supplement 53 to the GEIS.
II. Discussion.
As discussed in Chapter 5 of the final Supplement 53 to the GEIS, the NRC determined that the adverse environmental impacts of license renewal for SQN are not so great that preserving the option of license renewal for energy-planning decisionmakers would be unreasonable. This recommendation is based on: 1) the analysis and findings in the GEIS;
- 2) information provided in the environmental report and other documents submitted by TVA;
- 3) consultation with Federal, State, local, and Tribal agencies; 4) the NRC staffs independent environmental review; and 5) consideration of public comments received during the scoping process and on the draft supplemental environmental impact statement.
Dated at Rockville, Maryland, this 19th day of March, 2015.
For the Nuclear Regulatory Commission.
/RA/
Brian D. Wittick, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation