SD-121023-001, Rev. 1, Seismic Walkdown Report in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Page C-199 Through Page C-296
ML13267A319
Person / Time
Site: Cook  
Issue date: 09/12/2013
From: Stoeva N
Stevenson & Associates
To:
American Electric Power, Indiana Michigan Power Co, Office of Nuclear Reactor Regulation
Shared Package
ML13267A279 List:
References
AEP-NRC-2013-074 SD-121023-001, Rev 1
Download: ML13267A319 (98)


Text

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: []

N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -HV-DGX-1 Equipment Class:

(9) Fans EauiDment

Description:

AB EMERGENCY DIESEL GENERATOR ROOM VENTILATION Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 587.00 ft, 121 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findinqs. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?

SQUG 1-HV-DGX-1 REVO

2.

Is the anchorage free of bent, broken, missing or loose hardware?

Cannot see all bolts - other equipment/piping in area obstruct view.

Visible bolts OK

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

Visible bolts OK

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

CANNOT VERIFY ALL BOLTS

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Yes Yes Yes Not Applicable Not Applicable Yes C-199

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F-Y N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -HV-DGX-1 Equipment Class:

(9) Fans Equipment

Description:

AB EMERGENCY DIESEL GENERATOR ROOM VENTILATION Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by.

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-200

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: r-] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-HV-DGX-1 Equipment Class:

(9) Fans Equipment

Description:

AB EMERGENCY DIESEL GENERATOR ROOM VENTILATION P9130302 C-201

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: -III N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

(9) Fans EauiDment Descriotion:

AB EMEF I -HV-DGX-1 Y DIE MI16U3iU(

C-202

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-HV-SGRS-8 Equipment Class:

(9) Fans Equipment

Description:

4KV ROOM 600V SWITCHGEAR TRANSFORMERS TRI IA AND Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 609.00 ft, 204 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of Yes the 50% of SWEL items requiring such verification)?

SQUG 1-HV-SGRS-8 REVO

2. Is the anchorage free of bent, broken, missing or loose hardware?

Yes

3.

Is the anchorage free of corrosion that is more than mild surface Yes oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the Not Applicable anchors?

Unistrut mounted

5.

Is the anchorage configuration consistent with plant documentation?

Yes (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?

C-203

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-HV-SGRS-8 Equipment Class:

(9) Fans Equipment

Description:

4KV ROOM 600V SWITCHGEAR TRANSFORMERS TR11A AND Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-204

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y-] N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

(9) Fans 1-HV-SGRS-8 4KV ROOM 600V SWITCHGEAR TRANSFORMERS TR11 A A Fu1 IUIbU C-205

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

(9) Fans I -HV-SGRS-8

)V SV C-206

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F-7 N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -IFI-53 Equipment Class:

(18) Instruments on Racks Eauipment

Description:

BORON INJECTION TO REACTOR COOLANT LOOP #3 FLOW Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

CON1, 598.00 ft, 56 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1.

Is anchorage configuration verification required (i.e., is the item one of No the 50% of SWEL items requiring such verification)?

2.

Is the anchorage free of bent, broken, missing or loose hardware?

Yes

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

Yes

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

Yes

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Not Applicable Yes C-207

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: [*

N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -IFI-53 Equipment Class:

(18) Instruments on Racks Equipment

Description:

BORON INJECTION TO REACTOR COOLANT LOOP #3 FLOW Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

-George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-208

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: [Y-I N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-IFI-53 Eauioment Class:

(18) Instruments on Racks Dment Descriotion:

)N INJECTION I C-209

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y-] N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-IMO-222 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

WEST CONTAINMENT SPRAY PUMP DISCHARGE TO Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 573.00 ft, 52 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1.

Is anchorage configuration verification required (i.e., is the item one of No the 50% of SWEL items requiring such verification)?

2.

Is the anchorage free of bent, broken, missing or loose hardware?

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Not Applicable Not Applicable Not Applicable Not Applicable

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Yes C-210

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FY] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -IMO-222 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

WEST CONTAINMENT SPRAY PUMP DISCHARGE TO Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Block wall - OK per 12-4025, Wall W-1

9.

Do attached lines have adequate flexibility to avoid damage?

Yes Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-21 1

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F-] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-IMO-222 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

WEST CONTAINMENT SPRAY PUMP DISCHARGE TO

[IV I Utiz C-212

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: LII N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I -IMO-225 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

REFUELING WATER STORAGE TANK TO WEST CONTAINMENT Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 573.00 ft, 52 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1.

Is anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?

No

2.

Is the anchorage free of bent, broken, missing or loose hardware?

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Not Applicable Not Applicable Not Applicable Not Applicable

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Yes C-213

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-IMO-225 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

REFUELING WATER STORAGE TANK TO WEST CONTAINMENT Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Block wall - OK per 12-4025, Wall W-1

9.

Do attached lines have adequate flexibility to avoid damage?

Yes Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-214

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: []

N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

I -IMO-225 (8) Motor-Operated and Solenoid-Operated Valves

\\TER STC F~Ib~~ufdI C-215

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: [Y N

U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -IMQ-320 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

WEST RESIDUAL HEAT REMOVAL PUMP PP-35W SUCTION Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 573.00 ft, 55 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1.

Is anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?

No

2.

Is the anchorage free of bent, broken, missing or loose hardware?

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Not Applicable Not Applicable Not Applicable Not Applicable

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Yes C-216

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FY N

U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-IMO-320 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

WEST RESIDUAL HEAT REMOVAL PUMP PP-35W SUCTION Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-217

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: [ZZ N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-IMO-320 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves r--.

.A-.-OT U.

.A AirC rr

-tAt l

l I

I l IrtRI) rr-C

'Jr%

A IIfT/PI

.RAL FICM I flII~V/AL r-LIIVIrF r-r.JVV OJLt.. I I'.JIN

"'Idud-jv C-218

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FY] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I -IMO-331 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Eauioment

Description:

WEST RHR TO UPPER CONTAINMENT SPRAY SHUTOFF VALVE Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 609.00 ft, 6 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments

  • and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of No the 50% of SWEL items requiring such verification)?
2.

Is the anchorage free of bent, broken, missing or loose hardware?

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Not Applicable Not Applicable Not Applicable Not Applicable Yes C-219

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: [*

N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -IMO-331 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

WEST RHR TO UPPER CONTAINMENT SPRAY SHUTOFF VALVE Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

- George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-220

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FY] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -IMO-331 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves TO UPPER C(

C-221

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F]

N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-IMO-331 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves EST RHR TO UPPER CONT/

1"* I0I I I C-222

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: LY N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -IMO-350 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves EauiDment Descrirtion:

WEST RHR HEAT EXCHANGER OUTLET TO SAFETY INJECTION Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 609.00 ft, 6 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1.

Is anchorage configuration verification required (i.e., is the item one of No the 50% of SWEL items requiring such verification)?

2.

Is the anchorage free of bent, broken, missing or loose hardware?

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Not Applicable Not Applicable Not Applicable Not Applicable Yes C-223

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-IMO-350 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

WEST RHR HEAT EXCHANGER OUTLET TO SAFETY INJECTION Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

  • -George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-224

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y-] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

inmeanf 1"ncrrinfinn-I-IMO-350 (8) Motor-Operated and Solenoid-Operated Valves

AT EX(

r-I' 10 1 1 I0 C-225

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FY-I N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-IMO-350 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

WEST RHR HEAT EXCHANGER OUTLET TO SAFETY INJECTION IU-10 01 1 f C-226

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: jY N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I -IMO-52 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

BORON INJECTION TO REACTOR COOLANT LOOP #2 SHUTOFF Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

CON1, 598.00 ft, 59 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?

No

2.

Is the anchorage free of bent, broken, missing or loose hardware?

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Not Applicable Not Applicable Not Applicable Not Applicable

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Yes C-227

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y-] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-IMO-52 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

BORON INJECTION TO REACTOR COOLANT LOOP #2 SHUTOFF Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures?

Yes

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-228

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: []

N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

(8) Mot 1 -IMO-52 or-Operated and Solenoid-Operated Valves

-CTION TO P9110347 C-229

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: 7Y N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-IMO-52 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves r-'*..:..

l,'

IIK I i 1

KI l

r A r Trr-r-r'Pf.ýI A KI I

ý nlt

'I 11

ý C-230

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F-] N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

I -IMO-52 (8) Motor-Operated and Solenoid-Operated Valves ON INJECTION TO C-231

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y] N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -IMO-911I Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Ecluipment

Description:

REFUELING WATER STORAGE TANK TO CVCS CHARGING Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 587.00 ft, 40 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1.

Is anchorage configuration verification required (i.e., is the item one of No the 50% of SWEL items requiring such verification)?

2.

Is the anchorage free of bent, broken, missing or loose hardware?

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Not Applicable Not Applicable Not Applicable Not Applicable

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Yes C-232

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: [Y-] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-IMO-911 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Eauipment

Description:

REFUELING WATER STORAGE TANK TO CVCS CHARGING Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Deficiency tag on valve - leakage - see photo Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-233

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y-] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-IMO-911 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves ipment

Description:

REFUELING WATER STORAGE TANK TO CVCS C-234

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-IMO-911 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves r'-

i r~rn---

ir-I~Ui nkt-AI A Tr---

Tf "*r*~ A f 1"

T A Ekll/

TP"* r.'.

,r"'"

rflu i Afrlt"li If"l VI\\ 1 tN 1 UM

r 1 M-I'J\\ 1 U3 kV%..O ~f~¶,I C-235

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y N I

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-MCAB Equipment Class:

(14) Distribution Panels Equipment

Description:

250VDC DISTRIBUTION PANEL MCAB Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 609.00 ft, 200 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of Yes the 50% of SWEL items requiring such verification)?

SQUG 1-MCAB Rev. 1. CANNOT OPEN OR SEE ANY ANCHORAGE A

2.

Is the anchorage free of bent, broken, missing or loose hardware?

Unknown

3.

Is the anchorage free of corrosion that is more than mild surface Unknown oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the Unknown anchors?

5.

Is the anchorage configuration consistent with plant documentation?

Unknown (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of Unknown potentially adverse seismic conditions?

CANNOT OPEN OR SEE ANY ANCHORAGE C-236

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y N L-]

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-MCAB Equipment Class:

(14) Distribution Panels Equipment

Description:

250VDC DISTRIBUTION PANEL MCAB Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Unknown could adversely affect the safety functions of the equipment?

Could not open due to safety concern Comments Evaluated by:

--- George G Thomas Date:

08/15/2013 Neda Stoeva 08/15/2013 Photos C-237

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y N I-*

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

1-MCAB (14) Distribution Panels ION F C-238

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y N -- ]

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-MCAB Equipment Class:

(14) Distribution Panels JTION PAP tIV -I I u t UO C-239

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: EY-N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I -MCM-221 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

MAIN STEAM LEAD #2 TO AUXILIARY FEED PUMP TURBINE Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

ABI, 633.00 ft, 9 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findincls. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1.

Is anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?

No

2.

Is the anchorage free of bent, broken, missing or loose hardware?

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Not Applicable Not Applicable Not Applicable Not Applicable

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Yes C-240

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FY N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -MCM-221 Equipment Class:

(8) Motor-Operated and Solenoid-Operated Valves Equipment

Description:

MAIN STEAM LEAD #2 TO AUXILIARY FEED PUMP TURBINE Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-241

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Yj N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

-+rnnt I-Arri,+inm I -MCM-221 (8) Motor-Operated and Solenoid-Operated Valves IAAIKI LEAD #2 TO AUXILIARY FEED PUMP TURBINE Il

/UU41 C-242

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FY] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I -MRV-230 Equipment Class:

(0) Other Eauipment

Description:

STEAM GENERATOR OME-3-3 STOP VALVE Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 633.00 ft, 9 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?

No

2.

Is the anchorage free of bent, broken, missing or loose hardware?

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Not Applicable Not Applicable Not Applicable Not Applicable Yes C-243

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: jY] N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -MRV-230 Equipment Class:

(0) Other Equipment

Description:

STEAM GENERATOR OME-3-3 STOP VALVE Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Scaffold by valve (top) tagged and histalled per seismic scaffold procedure

9.

Do attached lines have adequate flexibility to avoid damage?

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Yes Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-244

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FY N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-MRV-230 Equipment Class:

(0) Other

\\TOR C-245

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F]

N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

(0) Other 1~,

r~,irm+, r QTIZ A I -MRV-230 TOR OME-3-3 STOP VALVE C-246

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: [-7 N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-MRV-243 Equipment Class:

(7) Fluid-Operated Valves Equipment

Description:

STEAM GENERATOR OME-3-4 POWER OPERATED RELIEF Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1,621.00 ft, 10 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findinas. Additional snace is provided at the end of this checklist for documentina other comments.

Anchorage

1.

Is anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?

No

2.

Is the anchorage free of bent, broken, missing or loose hardware?

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Not Applicable Not Applicable Not Applicable Not Applicable

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Yes C-247

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-MRV-243 Equipment Class:

(7) Fluid-Operated Valves Equipment

Description:

STEAM GENERATOR OME-3-4 POWER OPERATED RELIEF Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-248

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F]

N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-MRV-243 Equipment Class:

(7) Fluid-Operated Valves TOR C-249

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: -

N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-NLP-153 Equipment Class:

(18) Instruments on Racks Equipment

Description:

PRESSURIZER OME-4 PROTECTION CHANNEL 3 LEVEL Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

CON1, 612.00 ft, 67 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1.

Is anchorage configuration verification required (i.e., is the item one of Yes the 50% of SWEL items requiring such verification)?

DWG. 1-5571H, REV. 0.

1 A

2.

Is the anchorage free of bent, broken, missing or loose hardware?

Yes Cannot see top bolts of U bolts

3.

Is the anchorage free of corrosion that is more than mild surface Yes oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the Yes anchors?

5.

Is the anchorage configuration consistent with plant documentation?

Yes (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?

C-250

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y-] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-NLP-153 Equipment Class:

(18) Instruments on Racks Equipment

Description:

PRESSURIZER OME-4 PROTECTION CHANNEL 3 LEVEL Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

08/15/2013 Neda Stoeva 08/15/2013 Photos C-251

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-NLP-153 Equipment Class:

(18) Instruments on Racks Equipment

Description:

PRESSURIZER OME-4 PROTECTION CHANNEL 3 LEVEL I-IL4 -I Ii IAV I 'X"~5 F*IUlljb C-252

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F-Li N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-NPS-111 Equipment Class:

(18) Instruments on Racks Equipment

Description:

REACTOR VESSEL TRAIN 'B' WIDE RANGE PRESSURE Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1,612.00ft, 12 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of Yes the 50% of SWEL items requiring such verification)?

DWG 1-5570H REV9

2.

Is the anchorage free of bent, broken, missing or loose hardware?

Yes

3.

Is the anchorage free of corrosion that is more than mild surface Yes oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the Yes anchors?

5.

Is the anchorage configuration consistent with plant documentation?

Yes (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?

C-253

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F N

U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-NPS-111 Equipment Class:

(18) Instruments on Racks Equipment

Description:

REACTOR VESSEL TRAIN 'B' WIDE RANGE PRESSURE Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures?
8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

9.

Do attached lines have adequate flexibility to avoid damage?

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Yes Yes Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-254

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: [-Y N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-NPS-111 Equipment Class:

(18) Instruments on Racks 11 C-255

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-NPS-11I Equipment Class:

(18) Instruments on Racks L TR/

C-256

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F]

N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-NPS-111 Equipment Class:

(18) Instruments on Racks C-257

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y N

U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-OME-150-AB Equipment Class:

(17) Engine-Generators Equipment

Description:

AB EMERGENCY DIESEL GENERATOR Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 587.00 ft, 121 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of Yes the 50% of SWEL items requiring such verification)?

SQUG 1-OME-150-AB REVO

2.

Is the anchorage free of bent, broken, missing or loose hardware?

Yes

3.

Is the anchorage free of corrosion that is more than mild surface Yes oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the Yes anchors?

Grout pad OK concrete ok

5.

Is the anchorage configuration consistent with plant documentation?

Yes (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?

C-258

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FT] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-OME-150-AB Equipment Class:

(17) Engine-Generators Equipment

Description:

AB EMERGENCY DIESEL GENERATOR Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

(Secondary smaller bolts - some corrosion)

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

9.

Do attached lines have adequate flexibility to avoid damage?

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Yes Yes Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-259

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: []

N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-OME Equipment Class:

(17) Engine-Generators Eauiment DescriDtion:

AB EMERGENCY DIESI

"-150-AB C-260

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y-] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-OME-150-AB Equipment Class:

(17) Engine-Generators tIlUjz*Uu C-261

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F-] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

1-OME-150-AB (17) Engine-Generators P9130292 P9130293 C-262

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-OME Equipment Class:

(17) Engine-Generators iinmAnt fnlacrrinfinn-AR F::AIri:F::KIrY 1"ir1,q E-1 50-AB C-263

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I1-PP-l ow Equipment Class:

(5) Horizontal Pumps Equipment

Description:

WEST COMPONENT COOLING WATER PUMP Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB2, 609.00 ft, 609 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?

No

2.

Is the anchorage free of bent, broken, missing or loose hardware?

Yes

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

Yes

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

Yes

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Not Applicable

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Yes C-264

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F]

N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-lOW Equipment Class:

(5) Horizontal Pumps Equipment

Description:

WEST COMPONENT COOLING WATER PUMP Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Fire protection piping well supported, rod hung small fire lines will not collapse, and are depressurized

9.

Do attached lines have adequate flexibility to avoid damage?

Yes Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-265

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-10W Equipment Class:

(5) Horizontal Pumps WEST COMPONENT COOLING WAT C-266

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-26S Equipment Class:

(5) Horizontal Pumps Equipment

Description:

SOUTH SAFETY INJECTION PUMP Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 587.00 ft, 43 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of No the 50% of SWEL items requiring such verification)?
2.

Is the anchorage free of bent, broken, missing or loose hardware?

Yes Thread engagement on 2nd from end bolt on right side of skid, and 3rd from front (middle on left side of skid). 2 bolts flush with nut -

Identified during SQUG - SEWS show it

3.

Is the anchorage free of corrosion that is more than mild surface Yes oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the Yes anchors?

5.

Is the anchorage configuration consistent with plant documentation?

Not Applicable (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?

C-267

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FY] N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -PP-26S Equipment Class: (5) Horizontal Pumps Equipment

Description:

SOUTH SAFETY INJECTION PUMP Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Block wall with grate - OK per DWG 12-4026, Wall W-9

9.

Do attached lines have adequate flexibility to avoid damage?

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Yes Yes Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-268

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-26S Equipment Class:

(5) Horizontal Pumps nma=nt noerrinfi~n-qOI ITH qAFI:TY INKIPr."

/

i C-269

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-26S Equipment Class:

(5) Horizontal Pumps tUI-iJfij5~

1 C-270

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y] N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

I -PP-26S (5) Horizontal Pumps ZnI ITl TY INJECTION PUMP rýwulbiiz C-271

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I -PP-35W Equipment Class:

(6) Vertical Pumps Equipment

Description:

WEST RESIDUAL HEAT REMOVAL PUMP Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 573.00 ft, 55 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findincis. Additional space is provided at the end of this checklist for documentina other comments.

Anchorage

1.

Is anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?

No

2.

Is the anchorage free of bent, broken, missing or loose hardware?

Paint peeling off - very minor oxidation

3.

Is the anchorage free of corrosion that is more than mild surface oxidation?

Yes Yes

4.

Is the anchorage free of visible cracks in the concrete near the anchors?

Yes

5.

Is the anchorage configuration consistent with plant documentation?

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Not Applicable

6.

Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?

Yes C-272

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I -PP-35W Equipment Class:

(6) Vertical Pumps Equipment

Description:

WEST RESIDUAL HEAT REMOVAL PUMP Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Block wall - reinforced - OK per DWG 12-4025, Wall W-4

9.

Do attached lines have adequate flexibility to avoid damage?

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Yes Yes Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-273

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-35W Equipment Class:

(6) Vertical Pumps C-274

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F-] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-35W Equipment Class:

(6) Vertical Pumps Equipment

Description:

WEST RESIDUAL HEAT REMOVAL PUMP C-275

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: *Y] N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-3W Equipment Class:

(5) Horizontal Pumps Equipment

Description:

WEST MOTOR DRIVEN AUXILIARY FEEDWATER PUMP Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

TB1, 591.00 ft, 51 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of Yes the 50% of SWEL items requiring such verification)?

SQUG 1-PP-3W, Rev. I A

2.

Is the anchorage free of bent, broken, missing or loose hardware?

Yes

3.

Is the anchorage free of corrosion that is more than mild surface Yes oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the Yes anchors?

5.

Is the anchorage configuration consistent with plant documentation?

Yes (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?

C-276

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: []

N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-3W Equipment Class:

(5) Horizontal Pumps Equipment

Description:

WEST MOTOR DRIVEN AUXILIARY FEEDWATER PUMP Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

08/15/2013 Neda Stoeva 08/15/2013 Photos C-277

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F]

N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-PP-3W Equipment Class: (5) Horizontal Pumps OR DRIVEN AUXILIARY FEEDWA' FuIIUUUo C-278

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FYj N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-3W Equipment Class:

(5) Horizontal Pumps C-279

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: LIII N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-PP-3W Equipment Class: (5) Horizontal Pumps C-280

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y F-] U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-4 Equipment Class:

(5) Horizontal Pumps Equipment

Description:

TURBINE DRIVEN AUXILIARY FEED PUMP Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

TBI,591.00 ft, 50 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of No the 50% of SWEL items requiring such verification)?
2.

Is the anchorage free of bent, broken, missing or loose hardware?

Yes Can only see 7 out of 8 bolts, 1 bolt not visible because of other equipment in area

3.

Is the anchorage free of corrosion that is more than mild surface Yes oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the Yes anchors?

5.

Is the anchorage configuration consistent with plant documentation?

Not Applicable (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?

C-281

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y L-i1 U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1 -PP-4 Equipment Class:

(5) Horizontal Pumps Equipment

Description:

TURBINE DRIVEN AUXILIARY FEED PUMP Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that No could adversely affect the safety functions of the equipment?

Wet fire protection, rod hung threaded pipe - may develop leakage at threaded joints post seismic event. AR 2012-11738 issued to address issue.

Comments Evaluated by:

George G Thomas Date:

08/15/2013

(

A Neda Stoeva 08/15/2013 Photos C-282

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y

] U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

Equipment Class:

(5) Hor 1-PP-4 izontal Pumps AL C-283

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y

] U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-4 Equipment Class:

(5) Horizontal Pumps

-N AL C-284

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y N--N]

U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-4 Equipment Class:

(5) Horizontal Pumps Equipment

Description:

TURBINE DRIVEN AUXILIARY FEED PUMP C-285

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: FY N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-50W Equipment Class:

(5) Horizontal Pumps Equipment

Description:

WEST CENTRIFUGAL CHARGING PUMP Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

AB1, 587.00 ft, 41 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of Yes the 50% of SWEL items requiring such verification)?

SQUG 1-PP-50WREVO

2.

Is the anchorage free of bent, broken, missing or loose hardware?

Yes PAINTED

3.

Is the anchorage free of corrosion that is more than mild surface Yes oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the Yes anchors?

5.

Is the anchorage configuration consistent with plant documentation?

Yes (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?

C-286

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-PP-50W Equipment Class:

(5) Horizontal Pumps Eauioment DescriDtion:

WEST CENTRIFUGAL CHARGING PUMP Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Yes

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting,

. and masonry block walls not likely to collapse onto the equipment?

Yes

9.

Do attached lines have adequate flexibility to avoid damage?

Yes

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-287

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-50W Equipment Class: (5) Horizontal Pumps T CENTRIFUGAL CHARGING PUMP C-288

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: [-ý N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-50W Equipment Class:

(5) Horizontal Pumps

-UGAL C C-289

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-7W Equipment Class:

(6) Vertical Pumps Equipment

Description:

WEST ESSENTIAL SERVICE WATER PUMP Project:

DC Cook 1 SWEL Location (Bldg, Elev, Room/Area):

SH1, 591.00 ft, 136 Manufacturer/Model:

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is anchorage configuration verification required (i.e., is the item one of Yes the 50% of SWEL items requiring such verification)?

DWG 12-3684 REV14

2.

Is the anchorage free of bent, broken, missing or loose hardware?

Yes

3.

Is the anchorage free of corrosion that is more than mild surface Yes oxidation?

4.

Is the anchorage free of visible cracks in the concrete near the Yes anchors?

5.

Is the anchorage configuration consistent with plant documentation?

Yes (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6.

Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?

C-290

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F]

N U

Seismic Walkdown Checklist (SWC)

Equipment ID No.:

I-PP-7W Equipment Class:

(6) Vertical Pumps Equipment

Description:

WEST ESSENTIAL SERVICE WATER PUMP Interaction Effects

7.

Are soft targets free from impact by nearby equipment or structures?

Permanent Scaffold around pump - Ref DWG 1-3113C. General Notes.

8.

Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?

Lights rod hung

9.

Do attached lines have adequate flexibility to avoid damage?

10.

Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Yes Yes Yes Yes Other Adverse Conditions

11.

Have you looked for and found no adverse seismic conditions that Yes could adversely affect the safety functions of the equipment?

Comments Evaluated by:

George G Thomas Date:

10/18/12 Neda Stoeva 10/18/12 Photos C-291

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: 7Y N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-7W Equipment Class:

(6) Vertical Pumps I"-,,

& ~t..

Al*fr T

-e-r r l-e ~~-KI~l IAI C *r l'

WA/A-Irr'r'i r-1l IKJl-'

I IML C-292

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: F-] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-7W Equipment Class:

(6) Vertical Pumps M1 I IAL Sl-VIV I'UJUUU4 C-293

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-7W Equipment Class: (6) Vertical Pumps C

C-294

DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status:

Y-ý N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-7W Equipment Class:

(6) Vertical Pumps

- SER C-295

DC Cook Unit I & Unit 2 SD-121023-001 Rev. 1, 09/12/13 Status: Y] N U Seismic Walkdown Checklist (SWC)

Equipment ID No.:

1-PP-7W Equipment Class:

(6) Vertical Pumps Eauipment

Description:

WEST ESSENTIAL SERVICE WATER PUMP C-296