Comment (589) of 100 Individuals Opposing the Restart of San Onofre, Unit 2, Until the NRC Completes a Comprehensive Investigation
ML13191A120
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 05/03/2013
From: Black D
- No Known Affiliation
To: Bladey C K
Rules, Announcements, and Directives Branch
References
78FR22576 00589, NRC-2013-0070
Download: ML13191A120 (100)


Text

May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves protection from the folly of SCE thinking.SCE deserves public censure and probationary status given their idea of restarting unsafe generators.

Restart of either failed generator should not be considered at all.I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time. SCE deserves public censure and the San Onofre plant should be permanently closed.Thank you for your attention to these concerns.Daren Black 11664 National Blvd Los Angeles, CA 90064-3802 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Bradley Colden 13526 Tedemory Dr Whittier, CA 90602-3112 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Alena Jorgensen 5941 Kauffman Ave Temple City, CA 91780-2235 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Ina Mitchell 15501 Lanark St, #222 Van Nuys, CA 91406-1412 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Stephen Telesmanic 12 W Grand Ave Alhambra, CA 91801-2466 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Toni Scalera Scott Road Burbank, CA 91504 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Lucia Marano 1161 Hyperion Ave Los Angeles, CA 90029-2227 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jason Vick 39 Finisterra Irvine, CA 92614-5381 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Georgia Brewer 5518 Ventura Canyon Ave Sherman Oaks, CA 91401-5228 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Hillary Melin 3411 Helms Ave Culver City, CA 90232-2333 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Sean Winston 1226 W 84th P1 Los Angeles, CA 90044-2214 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Carlos Salazar 17328 Ventura Blvd # 318 Encino, CA 91316-3904 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Katherine Doberne 20253 Keswick St Apt 329 Winnetka, CA 91306-4432 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review Thank you for your attention to these concerns.Michael Moran 10428 Oso Ave Chatsworth, CA 91311-2544 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Ron Prado 22482 Alma Aldea Rancho Santa Margarita, CA 92688-2831 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Dario Garcia CA May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Meghan McKenzie 1037 Arcadia Ave Apt D Arcadia, CA 91007-7174 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures istotally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Nancy Mohler 20911 Fontaine Rd Topanga, CA 90290-3612 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Leann Moore 1201 W Durness St West Covina, CA 91790-4764 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Dana Timms May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.John Burnett-Stuart 5830 Buena Vista Ter Los Angeles, CA 90042-1228 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Angeles Chapter CA 92652 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jane Weissman 1633 Amberwood Dr Apt 8 South Pasadena, CA 91030-5100 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any.restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Sheri Lochner 231 Oaks Ave Monrovia, CA 91016-2114 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Marissa Moritz May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Matthew Kerschner 315 Hobart P1 Los Angeles, CA 90004-1807 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.darynne jessler CA May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Lauren Martinson 1861 N Van Ness Ave Apt 107 Los Angeles, CA 90028-5679 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.We do not want a Chernobyl or Fukushima Danchi event here in the United States!JUST SAY NO!Thank you for your attention to these concerns.Glenna Young May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Mary Nelson 26401 Via Galicia Mission Viejo, CA 92691-2927 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Monteque Pope-Le Beau 6678 Drexel Ave Los Angeles, CA 90048-4209 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Sarah Nolan 5530 E Mezzanine Way Long Beach, CA 90808-3621 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Linda Nerney 1249 S Gertruda Ave Redondo Beach, CA 90277-5125 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.j angell May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Joshua Sapkin 928 N Malden Ave Fullerton, CA 92832-1237 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Joan Singleton 21702 Branta Cir Huntington Beach, CA 92646-8205 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator..

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.D. Singer 1233 Pine St Oakland, CA 94607-1460 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded nunerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given that there is no safe amount of radiation exposure to humans; add earthquakes and tsunamis .... Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Restart? Are you crazy?Thank you for your attention to these concerns.paul templeman 7300 Baird Ave Apt 204 Reseda, CA 91335-8102 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We 'were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jeffery Dorer 5818 Fayette St Apt 1 Los Angeles, CA 90042-2651 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Scott Boller 4545 Orin Ave La Crescenta, CA 91214-2722 May 3, 2013 Ms Cindy Bladey.U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures isltotally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Sahar Abassi 33811 Valle Rd San Juan Capistrano, CA 92675-4830 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Anita Youabian 153 S Palm Dr Apt 1 Beverly Hills, CA 90212-3532 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current conditi'on of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Robert Wisehart 1710 E. Ave. R-3 Palmdale, CA 93550-5472 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Tanya Desloover 8132 Forelle Dr Apt 3 Huntington Beach, CA 92646-1698 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Daniel Margolis 11005 Strathmore Dr Los Angeles, CA 90024-2304 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken itg license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Rebekka Helford 12540 Pacific Ave Apt 6 Los Angeles, CA 90066-4320 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Svetha S--

May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Cristina Paul 3150 Curts Ave Los Angeles, CA 90034-3204 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Karen Cleaver 29330 Lakeshore Dr Agoura Hills, CA 91301-2876 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numnerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Kent Minault 13214 Magnolia Blvd Sherman Oaks, CA 91423-1531 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Pat Pinkston 25539 Hardy Pl Stevenson Ranch, CA 91381-1584 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Alida Montanez-Salas 2871 Stanbridge Ave Long Beach, CA 90815-1060 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Nicole Slater 43241 Crestwood Ct Lancaster, CA 93536-5425 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Raj Rajkumar 98 Kent Street Epping, Nsw 2121, CA 90254 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Daniel Margolis 11005 Strathmore Dr Los Angeles, CA 90024-2304 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate..

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Dennis Lew 4571 Don Rodolfo P1 Los Angeles, CA 90008-2813 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

I, William 0. Martin, am a long standing member of the Sierra Club, and I DO NOT SUPPORT.THE ABOVE STATED POSITION OF THE CLUB..I believe there should be a major role for safe nuclear enegy, and that San Onofre should be returned to FULL POWER after scientifically appropriate revisions, if needed, have been made.William 0.Martin Thank you for your attention to these concerns.William Martin 13 Viejo Irvine, CA 92612-2616 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Andy Phillips 2222222449 Rue De Cannes Costa Mesa, CA 92627-1457 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Helena Lambert 5712 Eberle St Lakewood, CA 90713-1839 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when. on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Luz Delgado 86 N San Marino Ave Pasadena, CA 91107-3533 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.George I.3 Vista Sierra Rancho Santa Margarita, CA 92688-1007 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.jamie muniz irvine, CA 92603 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through, a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Emeraech Decrescenzi 100 Palmetto Dr Apt 8 Pasadena, CA 91105-2500 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Manjula Perera 27550 Hillcrest Mission Viejo, CA 92691-7450 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Michael Comstock 6320 W 82nd St Los Angeles, CA 90045-2838 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Cecelia Lynch 3645 Myrtle Ave Long Beach, CA 90807-4145 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.carolyn manley 10220 Stanwin Ave Arleta, CA 91331-4450 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Dale Jaffe 3387 Barham Blvd Los Angeles, CA 90068-1446 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Liz Wexler 21319 Las Pilas Rd Woodland Hills, CA 91364-5912 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Virginia Bernal 830 Freeman St Santa Ana, CA 92703-2314 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Dixie Lee English 21544 Wesley Dr Apt 4 Laguna Beach, CA 92651-8102 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Barbara & John Goldthwait 21273 Entrada Rd Topanga, CA 90290-3536 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

My husband and I both worked at SONGS back in the '80's. It was a good place to work but always felt a bit dangerous.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Laurel Tucker 676 W 9th St Claremont, CA 91711-3741 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Tony Barona May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Dona van Bloemen CA 90403 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Carole Weller 8344 Calendula Dr Buena Park, CA 90620-2010 May 3, 2013 M2 Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Angela Vanthaneeyakul 1029 S 5th Ave Arcadia, CA 91006-4331 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Sincerely, Cort Stricker Thank you for your attention to these concerns.cort stricker May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Judy Ballerino 902 N Florence St Burbank, CA 91505-2615 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Ann Uzdavinis 1011 N Orange Grove Ave Apt 1 West Hollywood, CA 90046-6161 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Solar, wind and geothermal offer safe, affordable options. Germany had the good sense, after the Japan nuclear disaster to close their plants permanently.

Let's do the same.Thank you for your attention to these concerns.Jeanette Vosburg 4124 East Blvd Los Angeles, CA 90066-4610 May 3, 2013 Ms-Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Michael Todisco 25085 Sanoria St Laguna Niguel, CA 92677-8813 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jeffrey Findeis 200 E. Anaheim Street Apt 529 Long Beach, CA 90813 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Calahan Miller 1335 1/2 Roxbury Dr Los Angeles, CA 90035-4708 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Tracey Arnold 4235 Pickney Dr Calabasas, CA 91302-4819 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Mark Gallegos 3211 Gleason Ave Los Angeles, CA 90063-3033 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Stephen Kubick 1122 Chelsea Ave Apt A Santa Monica, CA 90403-4656 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Michelle Hayden 1284 S Ridgeley Dr Los Angeles, CA 90019-2654 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.We don't need a Fukushima here in California Thank you for your attention to these concerns.Jeffrey Upton 12532 La Bella Dr Santa Ana, CA 92705-3407 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Eugene Whitehead May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Linda Oeth CA 92525 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Anne Palmer May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Alexandra Hopkins 2748 Prospect Ave La Crescenta, CA 91214-3820 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Latha Sarakki CA May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Norma Faith Rockman May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.carmelo valone 4258 Lexington Ave Los Angeles, CA 90029-2122 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Rosemary Graham-Gardner PO Box 3335 Manhattan Beach, CA 90266-1335 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jackie Parker 4437 Clayton Ave Los Angeles, CA 90027-5511 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Athena Alexander 2210 3rd St Apt 217 Santa Monica, CA 90405-3434 May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Patricia Lauer 1857 Stanley Ave Signal Hill, CA 90755-6013