ML13189A095

From kanterella
Jump to navigation Jump to search
Comment (580) of 100 Individuals Opposing Restart of San Onofre, Unit 2, Until NRC Completes Comprehensive Investigation
ML13189A095
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 05/02/2013
From: Burness B
- No Known Affiliation
To: Cindy Bladey
Rules, Announcements, and Directives Branch
References
78FR22576 00580, NRC-2013-0070.
Download: ML13189A095 (100)


Text

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Bruce Burness 1260 Yocum St

Pasadena, CA 91103-1947

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Maxane Goldstein City Industry, CA 91745

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Ivan Light 819 Marymount Ln Claremont, CA 91711-1513

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Ken Hendrickson 16 Reef St Marina Del Rey, CA 90292-6725

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.

We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

N Lowry 6500 Elgin St Los Angeles, CA 90042-2937

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Daniel Margolis 11005 Strathmore Dr Los Angeles, CA 90024-2304

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Bill & Kay Ellis 101 Via Serena Rancho Santa Margarita, CA 92688-1720

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Virginia Krasney 1317 Peppertree Cir West Covina, CA 91792-1465

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Helena Lambert 5712 Eberle St

Lakewood, CA 90713-1839

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Carey Million 5401 Magnolia Ave

Whittier, CA 90601-2749

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Jena Ardell 5455 Zelzah Ave

Encino, CA 91316-2272

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff-proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Amanda Farrand 331 Foothill Rd Beverly Hills, CA 90210-3667

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Gary And Karla Peebles 1740 Tam Oshanter Rd Apt lb Seal Beach, CA 90740-4766

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

K Hill 1234 Redwood View Dr

Pomona, CA 91766-4117

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Gernot Wolfgang CA

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

'I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Chet Spalsky 133 Spring Vly Irvine, CA 92602-0919

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Eileen Rosenfeld 5455 Sylmar Ave Apt 1204 Sherman Oaks, CA 91401-5148

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Zia Islam 20011 Arminta St

Winnetka, CA 91306-2303

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Mary J 9931 Newcastle Ln

Cypress, CA 90630-3631

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Timothy Shanahan 10470 Falcon Ave Fountain Valley, CA 92708-7412

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Kinsey Mclean 2303 Hidalgo Ave Los Angeles, CA 90039-3633

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Leslie Brooks 13480 Wentworth Ln Unit 1251 Seal Beach, CA 90740-4652

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Emeraech Decrescenzi 100 Palmetto Dr Apt 8

Pasadena, CA 91105-2500

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

D Figus 11229 Blix St North Hollywood, CA 91602-1206

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Daniel Saks 10334 Bannockburn Dr Los Angeles, CA 90064-4514

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Scott C Smith 3544 Griffith Park Blvd Los Angeles, CA 90027-1405

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket IDNRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Eugenia Ramirez 1140 W 126th St Los Angeles, CA 90044-1012

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

J.J. Udovch 22486 Caminito Esteban Laguna Hills, CA 92653-1672

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Barbara Ellis 2020 Purdue Ave Los Angeles, CA 90025-6214

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Michael Shannon San Clemente, CA 92672

May 2, 2013 Ms Cindy Bladey.

U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.,

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Gloria Aguirre 27817 Ferguson Dr

Castaic, CA 91384-2518

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Albert Miller 9 Emperor Irvine, CA 92604-1918

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Judie Lewellen PO Box 753 Pearblossom, CA 93553-0753

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Diane Preston 34145 Pch Dana Point, CA 92629

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10-, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Jerry Caldwell 1530 Michigan Ave Santa Monica, CA 90404-4406

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Carollynn Bartosh 27520 Fawnskin Dr Rancho Palos Verdes, CA 90275-3704

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

James Gregory 10808 Eton Ave Chatsworth, CA 91311-1444

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Martina Linden 4509 Grand View Blvd Los Angeles, CA 90066-6232

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Janet Hicks 1156 W 37th St San Pedro, CA 90731-6461

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Curtis Hedges 501 Morris P1 Montebello, CA 90640-2337

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Rod Fisher 51 Emerald Bay Laguna Beach, CA 92651-1251

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Manford Samuelsen 1050 W 10th St San Pedro, CA 90731-3517

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Joel Graves 9934 Peralta River Cir Fountain Valley, CA 92708-3536

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative. Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at.either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Martine Leblanc 5050 Dockweiler St Los Angeles, CA 90019-1654

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Hayim and Joy Zadaca 203 W Stewart Way Long Beach, CA 90807-1927

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Frank Hanrahan 2545 Fairway Dr Costa Mesa, CA 92627-1311

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Hannah Gansen 1725 N Normandie Ave Apt 12a Los Angeles, CA 90027-3916

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Kirk Attebury 1911 17th St Apt 3 Santa Monica, CA 90404-4725

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Fred Naas 30771 Concord Ln Laguna Niguel, CA 92677-2426

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Grant Smith 3813 Huron Ave Apt 1 Culver City, CA 90232-3844

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Biadey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Craig Kleber 345 S Anita Ave Los Angeles, CA 90049-3805

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Raul Anorve 4401 Berkshire Ave Los Angeles, CA 90032-1315

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Cathy Mccann 5 Via Lantana Rancho Santa Margarita, CA 92688-5427

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Kelly Ireland 6566 De Longpre Ave Los Angeles, CA 90028-7803

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Athena Alexander 2210 3rd St Apt 217 Santa Monica, CA 90405-3434

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Randi Mavestrand PO Box 3086 Santa Monica, CA 90408-3086

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

J.

V. Foti 714 Pacific Ave Long Beach, CA 90813-4234

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Shanna Bennington 1907 190th St Redondo Beach, CA 90278-4818

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Jennifer Vladimiroff-Ney 5550 Marquet Ct Yorba Linda, CA 92887-5609

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Sharon Wells 6629 Radford Ave North Hollywood, CA 91606-1643

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Alison Bonn 11803 Goshen Ave Apt 302 Los Angeles, CA 90049-7311

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Jackie Parker 4437 Clayton Ave Los Angeles, CA 90027-5511

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Andy Phillips 2222222449 Rue De Cannes Costa Mesa, CA 92627-1457

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Judith Winston 2016 Euclid St Apt 5 Santa Monica, CA 90405-1544

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Michael McMahan 4892 Maui Cir Huntington Beach, CA 92649-2363

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Julie Adelson 2810 6th St Santa Monica, CA 90405-4340

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Amanda Smith 831 1/2 Kodak Dr Los Angeles, CA 90026-6618

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Jennifer Bakker 131 N Gale Dr Apt 2c Beverly Hills, CA 90211-2310

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Jeff Lambeth CA

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Edris Boyll-Kuzia 684 Aurora Dr Claremont, CA 91711-2924

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Denise Decunzo 1625 N Fairview St

Burbank, CA 91505-1659

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Michelle Tran 11422 Kathy Ln Garden Grove, CA 92840-1717

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

John Burnett-Stuart 5830 Buena Vista Ter Los Angeles, CA 90042-1228

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Tracey Arnold 4235 Pickney Dr Calabasas, CA 91302-4819

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Lydia Moore 584 High Dr Laguna Beach, CA 92651-1558

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Valerie Moore 11121 Haskell Ave Granada Hills, CA 91344-3943

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

If you were driving your car and the engine started smoking, would you consider just slowing down a bit and keep on the highway?

And cars can't threaten the health of 8 million people nor close our harbor.

Thank you for your attention to these concerns.

Roy Tuckman 3661 Regal Pl Apt 5 Los Angeles, CA 90068-1239

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Richelle Ching PO Box 392 Redondo Beach, CA 90277-0392

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license

-eview process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by Physicians for Social Responsibility -

Los

Angeles, Committee to Bridge the Gap, Sierra Club and a host of environmental organizations for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Michael Collins 2820 Arizona Ave Apt 3 Santa Monica, CA 90404-1531

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Adam Sperry 6723 Ben Ave North Hollywood, CA 91606-1512

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Mell Banez 919 Albany St Los Angeles, CA 90015-1211

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Susan Sanocki 18342 E Woodcroft St Azusa, CA 91702-5842

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its.

license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Michael Hemming 17103 Nanette St Granada Hills, CA 91344-1410

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Michael Wiles 6054 Metropolitan Plz Los Angeles, CA 90036-3210

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Barbara Shapiro 2700 Neilson Way Santa Monica, CA 90405-4011

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Linda Smith 16413 Andiron Dr

Whittier, CA 90604-4023

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Frieda Caplan 11651 Montecito Rd Los Alamitos, CA 90720-4054

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Suzanne Camarillo 941 N Orlando Ave Los Angeles, CA 90069-4205

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Julie Greenfield 2306 10th St Santa Monica, CA 90405-2529

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Rebecca Fent 1304 Ancona Dr La Verne, CA 91750-3313

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time; and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

James Cook 711 N Idaho St La Habra, CA 90631-3735

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Mary Kate Ziesmer 10573 W Pico Blvd # 114 Los Angeles, CA 90064-2333

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

J Michael Dargin 7718 Norton Ave West Hollywood, CA 90046-6261

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Helene Smati 8211 San Angelo Dr Apt L12 Huntington Beach, CA 92647-7294

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Toni Scalera Scott Road Burbank, CA 91504

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Peter Friedman 101 Warwick P1 South Pasadena, CA 91030-4062

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Frances Alet 5324 Parkmor Rd Calabasas, CA 91302-3408

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called. "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Courtney Cook Long Beach, CA

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Suzanne Simnick Thurman 4241 1/2 Fulton Ave Sherman Oaks, CA 91423-6246

May 2, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Kate Savage 3779 Colonial Ave Los Angeles, CA 90066-3641