MONTHYEARML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24159A2702024-05-30030 May 2024 R1900-0024-001, Rev. 16, NFPA 805 Nuclear Safety Capability Assessment AEP-NRC-2022-66, Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring2022-12-15015 December 2022 Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2022-46, Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in2022-12-12012 December 2022 Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in ML22340A1992022-11-30030 November 2022 Report of Changes, Tests, Experiments Pursuant to 10 CFR 50.59(d)(2) ML22340A2132022-11-30030 November 2022 R1900-0024-001, Revision 13, NFPA 805 Nuclear Safety Capability Assessment ML22340A1762022-11-30030 November 2022 Commitment Change Summary October 2020 to May 2022 AEP-NRC-2022-58, U1C31 Steam Generator Tube Inspection Report2022-10-24024 October 2022 U1C31 Steam Generator Tube Inspection Report AEP-NRC-2021-44, Form OAR-1, Owner'S Activity Report2021-08-12012 August 2021 Form OAR-1, Owner'S Activity Report ML21125A5582021-04-19019 April 2021 Report 2019, Commitment Change Summary, May 2019 to October 2020 ML21125A5392021-04-19019 April 2021 Report of Changes, Tests, Experiments Pursuant to 10 CFR 50.59(d)(2), Boration System Functionality Requirement Change in Mode 4 EA-21-024, Notice of Enforcement Discretion2021-03-0404 March 2021 Notice of Enforcement Discretion for Donald C. Cook Nuclear Plant, Units 1 and 2 AEP-NRC-2021-07, Supplement to Report Per Technical Specification 5.6.6, Lnoperability of Unit 1, Post Accident Monitoring, Containment Water Level2021-01-28028 January 2021 Supplement to Report Per Technical Specification 5.6.6, Lnoperability of Unit 1, Post Accident Monitoring, Containment Water Level AEP-NRC-2020-28, CFR 72.48(d)(2) Summary Report of Completed Changes, Tests, and Experiments 1O CFR 72.48 Evaluations2020-05-0606 May 2020 CFR 72.48(d)(2) Summary Report of Completed Changes, Tests, and Experiments 1O CFR 72.48 Evaluations AEP-NRC-2020-23, Request for Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography2020-04-30030 April 2020 Request for Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography ML20108E9992020-03-0505 March 2020 Enclosure 7 - LTR-SCS-19-50, Revision 0, D.C. Cook Unit 1 Low Temperature Overpressure Protection System (Ltops) Analysis for 48 EFPY, Dated March 5, 2020, Attachment 2 Only (Non-Proprietary) ML20108F0002020-02-28028 February 2020 Enclosure 5 - WCAP-18455-NP, Revision 1, D.C. Cook Unit 1 Heatup and Cooldown Limit Curves for Normal Operation, Westinghouse Electric Company, February 2020. (Non-Proprietary) ML18274A0952018-09-30030 September 2018 WCAP-18394-NP, Revision 1, Fatigue Crack Growth Evaluations of D. C. Cook Units 1 and 2 RHR, Accumulator, and Safety Injection Lines Supporting Expanded Scope Leak-Before-Break, September 2018 (Non-Proprietary) ML18334A2712018-09-30030 September 2018 WCAP-18394-NP, Revision 1, Fatigue Crack Growth Evaluations of D.C. Cook, Units 1 and 2 RHR, Accumulator, and Safety Injection Lines Supporting Expanded Scope Leak-Before-Break. AEP-NRC-2018-36, Notification of Initial Renewable Operating Permit2018-05-0909 May 2018 Notification of Initial Renewable Operating Permit AEP-NRC-2018-21, 30-Day Report of Changes to or Errors in an Evaluation Model2018-05-0404 May 2018 30-Day Report of Changes to or Errors in an Evaluation Model ML18026A8822018-02-0505 February 2018 Staff Assessment of Flooding Focused Evaluation ML18334A2702018-01-31031 January 2018 WCAP-18309-NP, Revision 0, Technical Justification for Eliminating Safety Injection Line Rupture as the Structural Design Basis for D.C. Cook, Units 1 and 2, Using Leak-Before-Break Methodology. ML18334A2692018-01-31031 January 2018 WCAP-18302-NP, Revision 0, Technical Justification for Eliminating Residual Heat Removal Line Rupture as the Structural Design Basis for D.C. Cook Units 1 and 2, Using Leak-Before-Break Methodology. ML18334A2682018-01-31031 January 2018 WCAP-18295-NP, Revision 0, Technical Justification for Eliminating Accumulator Line Rupture as the Structural Design Basis for D.C. Cook Units 1 and 2, Using Leak-Before-Break Methodology (Non-Proprietary) ML17151A9672017-06-14014 June 2017 Flood Hazard Mitigation Strategies Assessment ML16313A1172016-10-10010 October 2016 1BTl1V001-RPT-01, Donald C. Cook Focused Scope Peer Review - Pre-Initiator Human Reliability Analysis. ML16127A3352016-05-0606 May 2016 Reactor Oversight Process Task Force FAQ Log-April 13, 2016 ML16113A1982016-04-20020 April 2016 Precursor Screening Analysis- Reject ML16169A1182016-03-31031 March 2016 RWA-1313-015, Rev. 1, AST Radiological Analysis Technical Report. ML15308A0932015-10-15015 October 2015 Pressurized Water Reactor Owners Group (Pwrog), 15066-NP, Revision 1, Responses to Follow-Up NRC RAI 2 on the D.C. Cook, Units 1 and 2, Reactor Internals Aging Management Program. AEP-NRC-2015-83, Revision 1 of Final Integrated Plan Regarding March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-10-0101 October 2015 Revision 1 of Final Integrated Plan Regarding March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) ML15233A0242015-08-19019 August 2015 Transmittal of Annual Report of Loss-of-Coolant Accident Evaluation Model Changes ML14253A3172014-09-0404 September 2014 Enclosure 2: I&M CAP Document AR 2010-1804-10, Root Cause Evaluation Attachment, Rx Vessel Core Support Lug Bolting Anomalies ML14147A3292014-06-18018 June 2014 Staff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-ichi Nuclear Power Plant Accident ML14181A5382014-06-0505 June 2014 Enclosure 5 to AEP-NRC-2014-42, Attachment #2 (NP-Attachment) of Westinghouse Letter, LTR-PL-14-22, Westinghouse Responses to NRC, Request for Additional Information on the Application for Amendment to Restore.. ML14073A7592014-03-31031 March 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident ML14092A3302014-03-17017 March 2014 Document No. 13Q3208-RPT-003, Revion 1, Seismic Hazard and Screening Report for the Cook Nuclear Plant (Cnp), Enclosure 2 to AEP-NRC-2014-25 AEP-NRC-2014-15, 30 Day Report of Changes to or Errors in an Evaluation Model2014-02-27027 February 2014 30 Day Report of Changes to or Errors in an Evaluation Model ML13337A3252014-01-24024 January 2014 Interim Staff Evaluation and Audit Report Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) AEP-NRC-2014-08, SD-121023-001, Rev. 2, in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the D. C. Cook Unit 1 and 2, Page D-322 Through Page D-4042014-01-13013 January 2014 SD-121023-001, Rev. 2, in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the D. C. Cook Unit 1 and 2, Page D-322 Through Page D-404 ML14035A3632014-01-13013 January 2014 SD-121023-001, Rev. 2, in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the D. C. Cook Unit 1 and 2, Page C-845 Through Page C-962 ML14035A3682014-01-13013 January 2014 SD-121023-001, Rev. 2, in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the D. C. Cook Unit 1 and 2, Page D-241 Through Page D-321 ML14035A3672014-01-13013 January 2014 SD-121023-001, Rev. 2, in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the D. C. Cook Unit 1 and 2, Page D-170 Through Page D-240 ML14035A3662014-01-13013 January 2014 SD-121023-001, Rev. 2, in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the D. C. Cook Unit 1 and 2, Page D-92 Through Page D-169 ML14035A3642014-01-13013 January 2014 SD-121023-001, Rev. 2, in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the D. C. Cook Unit 1 and 2, Page D-1 Through Page D-91 ML14035A3522014-01-13013 January 2014 SD-121023-001, Rev. 2, in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the D. C. Cook Unit 1 and 2, Cover Through Page B-312 ML14035A3532014-01-13013 January 2014 SD-121023-001, Rev. 2, in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the D. C. Cook Unit 1 and 2, Page C-1 Through Page C-114 ML14035A3552014-01-13013 January 2014 SD-121023-001, Rev. 2, in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the D. C. Cook Unit 1 and 2, Page D-405 Through End 2024-07-25
[Table view] Category:Miscellaneous
MONTHYEARML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2022-46, Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in2022-12-12012 December 2022 Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in AEP-NRC-2021-44, Form OAR-1, Owner'S Activity Report2021-08-12012 August 2021 Form OAR-1, Owner'S Activity Report ML21125A5582021-04-19019 April 2021 Report 2019, Commitment Change Summary, May 2019 to October 2020 ML21125A5392021-04-19019 April 2021 Report of Changes, Tests, Experiments Pursuant to 10 CFR 50.59(d)(2), Boration System Functionality Requirement Change in Mode 4 EA-21-024, Notice of Enforcement Discretion2021-03-0404 March 2021 Notice of Enforcement Discretion for Donald C. Cook Nuclear Plant, Units 1 and 2 AEP-NRC-2020-28, CFR 72.48(d)(2) Summary Report of Completed Changes, Tests, and Experiments 1O CFR 72.48 Evaluations2020-05-0606 May 2020 CFR 72.48(d)(2) Summary Report of Completed Changes, Tests, and Experiments 1O CFR 72.48 Evaluations AEP-NRC-2018-36, Notification of Initial Renewable Operating Permit2018-05-0909 May 2018 Notification of Initial Renewable Operating Permit AEP-NRC-2018-21, 30-Day Report of Changes to or Errors in an Evaluation Model2018-05-0404 May 2018 30-Day Report of Changes to or Errors in an Evaluation Model ML18026A8822018-02-0505 February 2018 Staff Assessment of Flooding Focused Evaluation ML17151A9672017-06-14014 June 2017 Flood Hazard Mitigation Strategies Assessment ML16127A3352016-05-0606 May 2016 Reactor Oversight Process Task Force FAQ Log-April 13, 2016 ML16113A1982016-04-20020 April 2016 Precursor Screening Analysis- Reject AEP-NRC-2015-83, Revision 1 of Final Integrated Plan Regarding March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-10-0101 October 2015 Revision 1 of Final Integrated Plan Regarding March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) ML15233A0242015-08-19019 August 2015 Transmittal of Annual Report of Loss-of-Coolant Accident Evaluation Model Changes ML14181A5382014-06-0505 June 2014 Enclosure 5 to AEP-NRC-2014-42, Attachment #2 (NP-Attachment) of Westinghouse Letter, LTR-PL-14-22, Westinghouse Responses to NRC, Request for Additional Information on the Application for Amendment to Restore.. ML14073A7592014-03-31031 March 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident AEP-NRC-2014-15, 30 Day Report of Changes to or Errors in an Evaluation Model2014-02-27027 February 2014 30 Day Report of Changes to or Errors in an Evaluation Model ML12324A4182012-12-20020 December 2012 Review of the 2011 Refueling Outage Steam Generator Tube Inservice Inspection Results AEP-NRC-2012-86, Flooding Walkdown Report in Response to the 50.54(F) Information Request Regarding Near-Term Task Force Recommendation 2.3: Flooding for the D.C. Cook Nuclear Power Plant2012-11-13013 November 2012 Flooding Walkdown Report in Response to the 50.54(F) Information Request Regarding Near-Term Task Force Recommendation 2.3: Flooding for the D.C. Cook Nuclear Power Plant ML12362A0762012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-268 Through C-353 AEP-NRC-2012-87, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-437 Through C-4862012-11-0505 November 2012 Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-437 Through C-486 ML12362A0772012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-354 Through C-436 ML12362A0752012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-200 Through C-267 ML12362A0582012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-487 Through C-548 ML12362A0592012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-549 Through C-620 ML12362A0612012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-698 Through C-776 ML12362A0742012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-157 Through C-199 ML12362A0732012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-113 Through C-156 ML12362A0722012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-47 Through C-112 ML12362A0712012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Cover Through Appendix C, Page C-46 ML12362A0692012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix D, Page D-388 Through End ML12362A0682012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix D, Page D-337 Through Page D-387 ML12362A0672012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix D, Page D-276 Through Page D-336 ML12362A0662012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix D, Page D-220 Through Page D-275 ML12362A0602012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-621 Through C-697 ML12362A0622012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix C, Page C-777 Through Appendix D, Page ML12362A0632012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix D, Page D-54 Through Page D-114 ML12362A0642012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix D, Page D-115 Through Page D-175 ML12362A0652012-11-0505 November 2012 Donald C. Cook, Units 1 & 2, Seismic Walkdown Report SD-121023-001, Rev. 0 in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Appendix D, Page D-176 Through Page D-219 AEP-NRC-2012-83, Communications Assessment Requested by Nuclear Regulatory Commission Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulation 50.54(f) Regarding Recommendation 2.1, 2.3, and 9.3.2012-10-31031 October 2012 Communications Assessment Requested by Nuclear Regulatory Commission Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulation 50.54(f) Regarding Recommendation 2.1, 2.3, and 9.3. AEP-NRC-2012-38, Response to Request for Information, 10 CFR 50.46 Report for Emergency Core Cooling System Model Change or Error Associated with Thermal Conductivity Degradation2012-06-11011 June 2012 Response to Request for Information, 10 CFR 50.46 Report for Emergency Core Cooling System Model Change or Error Associated with Thermal Conductivity Degradation AEP-NRC-2009-25, Small Break Loss-of-Coolant Accident Evaluation Model Reanalysis2009-03-30030 March 2009 Small Break Loss-of-Coolant Accident Evaluation Model Reanalysis ML0807400532008-02-29029 February 2008 Response to Request for Additional Information Regarding Reanalysis of Small Break Loss-Of-Coolant Accident ML0807703952008-02-29029 February 2008 AEP:NRC:8054-02, Attachment 1, References, Through Attachment 3, Supplemental Response to GL 2004-02 and Request for Additional Information. ML0807200622008-02-29029 February 2008 License Amendment Request to Revise Ice Condenser Licensing Basis ML0807703962008-02-29029 February 2008 AEP:NRC:8054-02, Attachment 3, I&M Response to Information Item 3.f.4, to NRC Information Item 3 - Conclusions. ML0807704002008-02-29029 February 2008 AEP:NRC:8054-02, Attachment 4, Figure A4-1, General Arrangement of Recirculation Sump to Attachment 5, Figure A5-40, Scotch 77 Fire Retardant Tape Test 1 Pre-Test Picture. ML0807704042008-02-29029 February 2008 AEP:NRC:8054-02, Attachment 5, Figure A5-41, Scotch 77 Fire Retardant Tape Test 1 Post-Test Picture to Attachment 7, Regulatory Commitments. 2024-07-25
[Table view] |
Text
DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y LN-] U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 37 -AB1, 586, 24 Instructions for Completing Checklist This checklist may be used to document the results of the Area Walk-By near one or more SWEL items. The space below each of the following questions may be used to record the results of judgments and findings.Additional space is provided at the end of this checklist for documenting other comments.1. Does anchorage of equipment in the area appear to be free of potentially No adverse seismic conditions (if visible without necessarily opening cabinets)?
1-QLA-590 support -I bolt which also anchors support for 1-AV-2440, has very little thread engagment (approximately 20-25%) A V-2440 is only anchored through that bolt -AR 2012-11612 was written to address this finding.2. Does anchorage of equipment in the area appear to be free of significant Yes degraded conditions?
- 3. Based on a visual inspection from the floor, do the cable/conduit raceways and Yes HVAC ducting appear to be free of potentially adverse seismic conditions (e.g., condition of supports is adequate and fill conditions of cable trays appear to be inside acceptable limits)?4. Does it appear that the area is free of potentially adverse seismic spatial Yes interactions with other equipment in the area (e.g., ceiling tiles and lighting)?
- 5. Does it appear that the area is free of potentially adverse seismic interactions Yes that could cause flooding or spray in the area?6. Does it appear that the area is free of potentially adverse seismic interactions Yes that could cause a fire in the area?7. Does it appear that the area is free of potentially adverse seismic interactions Yes associated with housekeeping practices, storage of portable equipment, and temporary installations (e.g., scaffolding, lead shielding)?
D-176 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y L1-J U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 37 -AB1, 586, 24 8. Have you looked for and found no other seismic conditions that could Yes adversely affect the safety functions of the equipment in the area?Comments Evaluated by: George G Thomas Neda Stoeva Date: 10/18/12 10/18/12 D-177 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y U Area Walk-By Checklist (AWC)D-178 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y [INI U Area Walk-By Checklist (AWC)D-179 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y [-N U Area Walk-By Checklist (AWC)D-180 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y LII U Area Walk-By Checklist (AWC)I (Pim Ijw 0-1A D-181 I DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y LNI1 U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 38 -AB1, 587, 587 -HALLWAY Instructions for Completing Checklist This checklist may be used to document the results of the Area Walk-By near one or more SWEL items. The space below each of the following questions may be used to record the results of judgments and findings.Additional space is provided at the end of this checklist for documenting other comments.1. Does anchorage of equipment in the area appear to be free of potentially Yes adverse seismic conditions (if visible without necessarily opening cabinets)?
12-TK-6 Chemical drain tank thread engagment
-4 out of 8 anchor bolts -Component is non-safety so not a concern under this walkdown.2. Does anchorage of equipment in the area appear to be free of significant Yes degraded conditions?
- 3. Based on a visual inspection from the floor, do the cable/conduit raceways and Yes HVAC ducting appear to be free of potentially adverse seismic conditions (e.g., condition of supports is adequate and fill conditions of cable trays appear to be inside acceptable limits)?4. Does it appear that the area is free of potentially adverse seismic spatial No interactions with other equipment in the area (e.g., ceiling tiles and lighting)?
Fire extinguisher on short hook -AR 2012-11669 was issued.5. Does it appear that the area is free of potentially adverse seismic interactions Yes that could cause flooding or spray in the area?6. Does it appear that the area is free of potentially adverse seismic interactions Yes that could cause a fire in the area?7. Does it appear that the area is free of potentially adverse seismic interactions Yes associated with housekeeping practices, storage of portable equipment, and temporary installations (e.g., scaffolding, lead shielding)?
Ops shift electrical safety locker not anchored or tied by C-4501 -concentrator (not a safety component)
-so this is not critical.D-1 82 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y LNI U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 38 -AB1, 587, 587 -HALLWAY 8. Have you looked for and found no other seismic conditions that could Yes adversely affect the safety functions of the equipment in the area?Comments Evaluated by: Evalatedby:George G Thomas Neda Stoeva Date: 10/18/12 10/18/12 D-183 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y FLNI U Area Walk-By Checklist (AWC)D-184 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y N U Area Walk-By Checklist (AWC)1,587, D-185 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y LI1 U Area Walk-By Checklist (AWC)Location Bid Elev, Room/Area Area 38 -AB1, 587, 587 -HALLWAY 2012109/19 D-1 86 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y U Area Walk-By Checklist (AWC)D-187 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y L-] U Area Walk-By Checklist (AWC)D-188 DC Cook Unit I & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y LU U Area Walk-By Checklist (AWC)D-189 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y EN- U Area Walk-By Checklist (AWC)1,587, D-1 90 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y LKý U Area Walk-By Checklist (AWC)D-191 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y [] U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 38 -AB1, 587, 587 -HALLWAY D-192 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: V N U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 39 -AB1, 609, 140 Instructions for Completing Checklist This checklist may be used to document the results of the Area Walk-By near one or more SWEL items. The space below each of the following questions may be used to record the results of judgments and findings.Additional space is provided at the end of this checklist for documenting other comments.1. Does anchorage of equipment in the area appear to be free of potentially Yes adverse seismic conditions (if visible without necessarily opening cabinets)?
Most equipment in area -panels -internally anchored.
External anchorages OK 2. Does anchorage of equipment in the area appear to be free of significant Yes degraded conditions?
- 3. Based on a visual inspection from the floor, do the cable/conduit raceways and Yes HVAC ducting appear to be free of potentially adverse seismic conditions (e.g., condition of supports is adequate and fill conditions of cable trays appear to be inside acceptable limits)?4. Does it appear that the area is free of potentially adverse seismic spatial Yes interactions with other equipment in the area (e.g., ceiling tiles and lighting)?
- 5. Does it appear that the area is free of potentially adverse seismic interactions Yes that could cause flooding or spray in the area?6. Does it appear that the area is free of potentially adverse seismic interactions Yes that could cause a fire in the area?7. Does it appear that the area is free of potentially adverse seismic interactions Yes associated with housekeeping practices, storage of portable equipment, and temporary installations (e.g., scaffolding, lead shielding)?
Scaffolding in area -tagged seismic signed on 9/14/12 D-193 DC Cook Unit I & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: [-Y N U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 39- AB1, 609, 140 8. Have you looked for and found no other seismic conditions that could Yes adversely affect the safety functions of the equipment in the area?Comments Evaluated by: TI, George G Thomas EG Neda Stoeva Date: 10/18/12 10/18/12 D-194 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: [YE N U Area Walk-By Checklist (AWC)Location (Bida. Elev. Room/A E D-195 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: FY N U Area Walk-By Checklist (AWC)D-196 DC Cook Unit I & Unit 2 SD-1 21023-001 Rev. 0, 11/05/12 Status: Y N U Area Walk-By Checklist (AWC)D-1 97 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: FY- N U Area Walk-By Checklist (AWC)D-198 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y N U Area Walk-By Checklist (AWC)D-199 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Table D-2: Summary of Area Walk-By Checklists Area Pg Nmer Room -Area -Desc. Elevation Page Number 1 CONTAINMENT BUILDING UNIT 2 -ROOM 74 625 D-202 2 CONTAINMENT BUILDING UNIT 2 -ROOM 75 612 D-206 3 CONTAINMENT BUILDING UNIT 2 -ROOM 59 598 D-211 4 CONTAINMENT BUILDING UNIT 2 -ROOM 67 612 D-220 5 CONTAINMENT BUILDING UNIT 2 -ROOM 56 598 D-227 6 CONTAINMENT BUILDING UNIT 2 -ROOM 73 612 D-234 7 AUXILIARY BUILDING UNIT 2 -ROOM 70 609 D-240 8 AUXILIARY BUILDING UNIT 2 -ROOM 140 621 D-250 10 AUXILIARY BUILDING UNIT 2 -ROOM 10 621,633 D-257 11 AUXILIARY BUILDING UNIT 2 -ROOM 12 612 D-262 13 AUXILIARY BUILDING UNIT 2 -ROOM 4 609 D-269 14 AUXILIARY BUILDING UNIT 2 -ROOM 40 587 D-276 15 AUXILIARY BUILDING UNIT 2 -ROOM 41 587 D-279 16 AUXILIARY BUILDING UNIT 2 -ROOM 43 587 D-283 17 AUXILIARY BUILDING UNIT 2 -ROOM 52 573 D-287 18 AUXILIARY BUILDING UNIT 2 -ROOM 55 573 D-292 19 AUXILIARY BUILDING UNIT 2 -ROOM 6 609 D-296 21 AUXILIARY BUILDING UNIT 2 -EL 633 BY 2-CFI-429 633 D-302 and 2-WMO-716 22 AUXILIARY BUILDING UNIT 2 -ROOM 8 633 D-307 23 AUXILIARY BUILDING UNIT 2 -ROOM 126 587 D-311 24 AUXILIARY BUILDING UNIT 2 -ROOM 122 587 D-314 25 AUXILIARY BUILDING UNIT 2 -ROOM 123 633 D-320 26 SCREEN HOUSE UNIT 2 -ROOM 135 591 D-337 27 AUXILIARY BUILDING UNIT 2 -EL 609 BY 2-PP-10W 609 D-340 28 AUXILIARY BUILDING UNIT 2 -ROOM 200 609 D-346 29 AUXILIARY BUILDING UNIT 2 -ROOM 202 609 D-349 30 AUX BUILDING UNIT 2 -EL 633 GENERAL AREA 633 D-352 31 AUXILIARY BUILDING UNIT 2- ROOM 205 613 D-357 32 SCREEN HOUSE UNIT 2 -ROOM 221 594 D-362 33 AUXILIARY BUILDING UNIT 2 -ROOM 129 650 D-365 34 AUXILIARY BUILDING UNIT 2 -ROOM 121 587 D-369 35 AUXILIARY BUILDING UNIT 2 -ROOM 126 587 D-375 36 AUXILIARY BUILDING UNIT 2 -ROOM 204 609 D-377 37 AUXILIARY BUILDING UNIT 2 -ROOM 96 609 D-382 38 AUXILIARY BUILDING UNIT 2 -ROOM 24 586 D-388 D-200 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Table D-2: Summary of Area Walk-By Checklists Area Pg Nmer Room -Area -Desc. Elevation Page Number 39 AUXILIARY BUILDING UNIT 1 -ROOM 35 587 D-392 40 AUXILIARY BUILDING UNIT 2 -ROOM 9 633 D-401 41 TURBINE BUILDING UNIT 2 -ROOM 49 591 D-408 42 TURBINE BUILDING UNIT 2 -ROOM 51 591 D-414 43 SCREEN HOUSE UNIT 1 -ROOM 670 591 D-420 44 SCREEN HOUSE UNIT 2- ROOM 136 591 D-424 D-201 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: LII N U Area Walk-By Checklist (AWC)Location (Blda. Elev. Room/Area):
Area 01 -CON2 EL. 625'. Room 74 Instructions for Completing Checklist This checklist may be used to document the results of the Area Walk-By near one or more SWEL items. The space below each of the following questions may be used to record the results of judgments and findings.Additional space is provided at the end of this checklist for documenting other comments.1. Does anchorage of equipment in the area appear to be free of potentially adverse seismic conditions (if visible without necessarily opening cabinets)?
Yes 2. Does anchorage of equipment in the area appear to be free of significant degraded conditions?
Yes 3. Based on a visual inspection from the floor, do the cable/conduit raceways and HVAC ducting appear to be free of potentially adverse seismic conditions (e.g., condition of supports is adequate and fill conditions of cable trays appear to be inside acceptable limits)?Yes 4. Does it appear that the area is free of potentially adverse seismic spatial interactions with other equipment in the area (e.g., ceiling tiles and lighting)?
Yes 5. Does it appear that the area is free of potentially adverse seismic interactions that could cause flooding or spray in the area?Yes 6. Does it appear that the area is free of potentially adverse seismic interactions that could cause a fire in the area?Yes 7. Does it appear that the area is free of potentially adverse seismic interactions associated with housekeeping practices, storage of portable equipment, and temporary installations (e.g., scaffolding, lead shielding)?
Yes D-202 M DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: FY-] N U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 01 -CON2 EL. 625', Room 74 8. Have you looked for and found no other seismic conditions that could Yes adversely affect the safety functions of the equipment in the area?Comments Evaluated by: George G Thomas Neda Stoeva Date: 10/18/12 10/18/12 D-203 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: L N U Area Walk-By Checklist (AWC)1 -C(D-204 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: l N U Area Walk-By Checklist (AWC)D-205 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: IY- N U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 02 -CON2, EL. 612', Room 75 Instructions for Completing Checklist This checklist may be used to document the results of the Area Walk-By near one or more SWEL items. The space below each of the following questions may be used to record the results of judgments and findings.Additional space is provided at the end of this checklist for documentinq other comments.1. Does anchorage of equipment in the area appear to be free of potentially adverse seismic conditions (if visible without necessarily opening cabinets)?
Yes 2. Does anchorage of equipment in the area appear to be free of significant degraded conditions?
Yes 3. Based on a visual inspection from the floor, do the cable/conduit raceways and HVAC ducting appear to be free of potentially adverse seismic conditions (e.g., condition of supports is adequate and fill conditions of cable trays appear to be inside acceptable limits)?4. Does it appear that the area is free of potentially adverse seismic spatial interactions with other equipment in the area (e.g., ceiling tiles and lighting)?
Yes Yes Yes 5. Does it appear that the area is free of potentially adverse seismic interactions that could cause flooding or spray in the area?6. Does it appear that the area is free of potentially adverse seismic interactions that could cause a fire in the area?Yes 7. Does it appear that the area is free of potentially adverse seismic interactions associated with housekeeping practices, storage of portable equipment, and temporary installations (e.g., scaffolding, lead shielding)?
Yes D-206 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: riii N U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 02 -CON2, EL. 612', Room 75 8. Have you looked for and found no other seismic conditions that could Yes adversely affect the safety functions of the equipment in the area?Comments George G Thomas Evaluated by: Date: 10/18/12 Neda Stoeva 10/18/12 D-207 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: V N U Area Walk-By Checklist (AWC)02 -C(D-208 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: [-] N U Area Walk-By Checklist (AWC)D-209 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: F N U Area Walk-By Checklist (AWC)D-210 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: T N U Area Walk-By Checklist (AWC)Location (Bldai. Elev. Room/Area):
Area 03 -CON2, EL. 598', Room 59 Instructions for Completing Checklist This checklist may be used to document the results of the Area Walk-By near one or more SWEL items. The space below each of the following questions may be used to record the results of judgments and findings.Additional space is provided at the end of this checklist for documentinq other comments.1. Does anchorage of equipment in the area appear to be free of potentially adverse seismic conditions (if visible without necessarily opening cabinets)?
Yes 2. Does anchorage of equipment in the area appear to be free of significant degraded conditions?
Yes 3. Based on a visual inspection from the floor, do the cable/conduit raceways and HVAC ducting appear to be free of potentially adverse seismic conditions (e.g., condition of supports is adequate and fill conditions of cable trays appear to be inside acceptable limits)?4. Does it appear that the area is free of potentially adverse seismic spatial interactions with other equipment in the area (e.g., ceiling tiles and lighting)?
Yes Yes Yes 5. Does it appear that the area is free of potentially adverse seismic interactions that could cause flooding or spray in the area?6. Does it appear that the area is free of potentially adverse seismic interactions that could cause a fire in the area?Yes 7. Does it appear that the area is free of potentially adverse seismic interactions associated with housekeeping practices, storage of portable equipment, and temporary installations (e.g., scaffolding, lead shielding)?
Yes D-21 1 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: E-i N U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 03 -CON2, EL. 598', Room 59 8. Have you looked for and found no other seismic conditions that could Yes adversely affect the safety functions of the equipment in the area?Comments 2-IPX-129-IV boric acid, 2-RH-137 boric acid, 2-1CM-111 boric acid Evaluated by: Evaluated by: -George G Thomas Neda Stoeva Date: 10/18/12 10/18/12 D-212 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: EZ] N U Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
Area 03 -CON2, EL. 598', Room 59 P9120125 P9120126 D-213 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: [] N U Area 03 -CON2, EL. 598', Room 59 Area Walk-By Checklist (AWC)Location (Bldg, Elev, Room/Area):
P9120131 P9120132 D-214 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: Y-] N U Area Walk-By Checklist (AWC)D-215 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: EZ- N U Area Walk-By Checklist (AWC)D-216 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: [] N U Area Walk-By Checklist (AWC)D-217 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: LY N U Area Walk-By Checklist (AWC)D-218 DC Cook Unit 1 & Unit 2 SD-121023-001 Rev. 0, 11/05/12 Status: EIIJ N U Area Walk-By Checklist (AWC)D-219