ML12104A203

From kanterella
Jump to navigation Jump to search
OL - TVA Letter to NRC_03-13-12_Revision of Fpr Commitment
ML12104A203
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 03/13/2012
From:
- No Known Affiliation
To:
Division of Operating Reactor Licensing
References
Download: ML12104A203 (7)


Text

WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]

Sent: Tuesday, March 13, 2012 3:03 PM To: Epperson, Dan; Poole, Justin; Raghavan, Rags; Milano, Patrick; Campbell, Stephen Cc: Arent, Gordon; Boyd, Desiree L; Hamill, Carol L

Subject:

TVA letter to NRC_03-13-12_Revision of FPR Commitment Attachments: 03-13-12_Revision of FPR Commitment_Final.pdf Please see attached TVA letter that was sent to the NRC today.

Please disregard/delete the previous e-mail.

Thank You,

~*~*~*~*~*~*~*~*~*~*~

Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764 1

Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 682 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF2A11B5E6)

Subject:

TVA letter to NRC_03-13-12_Revision of FPR Commitment Sent Date: 3/13/2012 3:02:59 PM Received Date: 3/13/2012 3:01:37 PM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients:

"Arent, Gordon" <garent@tva.gov>

Tracking Status: None "Boyd, Desiree L" <dlboyd@tva.gov>

Tracking Status: None "Hamill, Carol L" <clhamill@tva.gov>

Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>

Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>

Tracking Status: None "Raghavan, Rags" <Rags.Raghavan@nrc.gov>

Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov>

Tracking Status: None "Campbell, Stephen" <Stephen.Campbell@nrc.gov>

Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 322 3/13/2012 3:01:37 PM 03-13-12_Revision of FPR Commitment_Final.pdf 99812 Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date:

Recipients Received:

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 March 13, 2012 10 CFR 50.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Units 1 and 2 NRC Docket Nos. 50-390 and 50-391

Subject:

WATTS BAR NUCLEAR PLANT (WBN) UNITS 1 AND 2 - FIRE PROTECTION REPORT - REVISION OF COMMITMENTS

References:

1. TVA letter to NRC dated November 30, 2011, Update to the Fire Protection Report
2. TVA letter to NRC dated August 15, 2011, Watts Bar Nuclear Plant (WBN) Unit 2 - Transmittal of Revised Unit 1 / Unit 2 As-Designed Fire Protection Report (TAC NO. ME3091)
3. TVA letter to NRC dated December 18, 2010, Watts Bar Nuclear Plant (WBN) Unit 2 - Fire Protection Program (TAC NO. ME0853) -

Submittal of Revised Fire Protection Report The purpose of this letter is to clarify the actions being taken to address the commitment listed below which TVA made in Reference 1:

TVA commits to provide an updated WBN, Unit 1 FPR within four months of the date of this letter.

In lieu of completing this commitment for the Unit 1 Fire Protection Report (FPR), TVA plans to fulfill the commitment made in References 2 and 3 to submit an as-constructed version of the Unit 1/Unit 2 FPR. This version of the FPR will reflect the updated Fire Hazards Analysis for WBN and will be applicable to both units. Once submitted, the Unit 1/Unit 2 FPR will supersede WBNs previous FPR and the commitments made in correspondence related to the FPR previously submitted by TVA. Based on this, the Unit 1/Unit 2 FPR will be baselined to Revision 0 when it is initially issued.

U.S. Nuclear Regulatory Commission Page 3 March 13, 2012 cc (Enclosure):

U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381

U.S. Nuclear Regulatory Commission Page 4 March 13, 2012 bcc (Enclosure):

Stephen Campbell U.S. Nuclear Regulatory Commission MS 08H4A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Darrell Roberts, Acting Deputy Regional Administrator for Construction U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257

Enclosure Regulatory Commitment

1. The WBN Unit 2 estimated completion schedule will be finalized in the near future. This estimate will include a revised schedule for the submittal of the as-constructed FPR. TVA will communicate the updated schedule for the as-constructed FPR to NRC as soon as it is available.

E-1