NRC RAI Clinton Power Station, Unit No. 1 - 13R-01
ML102360672
Person / Time
Site: Clinton Constellation icon.png
Issue date: 08/23/2010
From: Nicholas Difrancesco
Plant Licensing Branch III
To: Matthew Mitchell
Exelon Corp
DiFrancesco N, NRR/DORL/LPL3-2, 415-1115
References
TAC ME2987
Download: ML102360672 (2)


Text

From: DiFrancesco, Nicholas Sent: Monday, August 23, 2010 10:58 AM To: Mitchel.Mathews@exeloncorp.com Cc: jeff.hansen@exeloncorp.com; DiFrancesco, Nicholas

Subject:

NRC RAI Re: Clinton Power Station, Unit No. 1 - Relief Request - I3R-01 (Tac No. ME2987)

Mr. Mathews, By letter dated December 30, 2009, as supplemented by letter dated July 14, 2010 (Agencywide Documents and Management System ((ADAMS) Accession Nos. ML093650139 and ML101960011, respectively), Exelon Generation Company, LLC (EGC), the licensee for the Clinton Power Station (CPS), Unit No. 1, submitted relief requests (RR) I3R-01 through I3R-05.

The Probabilistic Risk Assessment Licensing Branch have reviewed the information provided and determined that in order to complete its evaluation, additional information may be required.

The request for additional information related to I3R-01 is provided below.

Please feel free to contact me at 301-415-1115 if a teleconference is needed to support your response.

Respectfully, Nick DiFrancesco Project Manager Nuclear Regulatory Commission Division of Operating Reactor Licensing nicholas.difrancesco@nrc.gov Tel: (301) 415-1115 Fax: (301) 415-1222 REQUEST FOR ADDITIONAL INFORMATION RELIEF REQUEST I3R-01 CLINTON POWER STATION (CPS)

EXELON GENERATION COMPANY, LLC DOCKET NO.: 50-461 By letter dated December 30, 2009, as supplemented by letter dated July 14, 2010, Exelon Generation Company, LLC submitted for staff review and approval ISI Program Relief Request I3R-01, which requests an alternative risk-informed inservice inspection (RI-ISI) selection and examination criteria for Category B-F, B-J, C-F-1 and C-F-2 pressure retaining piping welds for CPS. To complete its review, the staff requests the following additional information.

I3R-01

1. Page 3 of Attachment 1 in the letter dated December 30, 2009, states that the change in risk was reassessed for the Third Interval RI-ISI program. Please confirm that the results of this risk impact assessment continue to meet the acceptance guidelines in RG 1.174 and EPRI TR-112657.