MONTHYEARML23279A1202023-10-0606 October 2023 Response to NRC Inspection Report and Preliminary White Finding ML22320A0432022-11-15015 November 2022 Response to NRC Inspection Report and Preliminary White Finding IR 05000317/20164032016-11-10010 November 2016 Errata for Calvert Cliffs Nuclear Power Plant - Baseline Security Inspection Report 05000317/2016403, 5000318/2016403; Independent Spent Fuel Storage Security Inspection Report 07200008/2016401; and Exercise of Enforcement Discretion (Lette ML16159A2682016-06-14014 June 2016 Cover Letter - Calvert Cliff Nuclear Power Plant - NRC Security Baseline Inspection Report 05000317/2016201 and 05000318/2016201 ML12100A2172012-04-0909 April 2012 NRC Investigation Report No. I-2011-047, Letter to Constellation Energy IR 05000317/20114032011-07-26026 July 2011 IR 05000317-11-403, IR 05000318-11-403; 01/26/2011-07/13/2011; Calvert Cliffs Nuclear Power Plant; Special Inspection, Dated July 26, 2011 (Letter Only) ML1020704062010-07-26026 July 2010 Notification of Conduct of a Triennial Fire Protection Baseline Inspection While Transition to 10 CFR Part 50.48(c) Is in Progress ML0811601542008-04-23023 April 2008 Notification of Inspection of the Implementation of B.5.b Phase 2 and 3 Mitigating Strategies Using Temporary Instruction 2515/171 IR 05000317/20074032007-06-15015 June 2007 IR 05000317-07-403, and IR 05000318-07-403, on 05/14/2007 - 05/17/2007, Calvert Cliffs Nuclear Power Plant, Material Control and Accounting (Mc&A) Program. Cover Letter IR 05000003/20180062006-10-12012 October 2006 IR 05000317-06-301 and IR 05000318-06/301 on 08/25, 08/28 - 09/01, 09/13 and 09/05-29/2006, Calvert Cliffs Nuclear Power Plant, Units 1 and 2; Initial Operator Licensing Examination IR 05000317/20030062004-01-16016 January 2004 IR 05000317-03-006, 05000318-03-006; 9/28/2003-12/31/2003; Calvert Cliffs Nuclear Plant, Units 1 and 2; Operability Evaluations IR 05000317/20010122002-01-28028 January 2002 IR 05000317/2001-012, IR 05000318/2001-012, Calvert Cliffs Nuclear Plant Inc.; Calvert Cliffs Nuclear Power Plant, Units 1 & 2, Inspection on 11/11/2001 - 12/29/2001 Re Problem Identification and Resolution. Two Noncited Violations Noted ML0202805052002-01-28028 January 2002 IR 05000317/2001-012, IR 05000318/2001-012, on 11/11-12/29/2001, Calvert Cliffs Nuclear Plant, Inc.; Calvert Cliffs Nuclear Power Plant, Units 1 & 2. Problem Identification and Resolution. Three Non-Cited Violations Noted IR 05000317/20010132002-01-14014 January 2002 IR 05000317/2001-013, Calvert Cliffs Nuclear Plant, Inc, Calvert Cliffs Nuclear Power Plant Units 1&2, Supplemental Inspection on 12/10-12/13/2001 Re Degraded Cornerstone in Mitigating Systems & One Degraded Cornerstone 2023-10-06
[Table view] Category:Letter
MONTHYEARIR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000318/LER-2023-004, Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-16016 January 2024 Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-002, Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-0808 January 2024 Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 ML23318A4722023-11-14014 November 2023 Supplement to License Amendment Request to Adopt TSTF-59-A ML23317A1032023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23310A0442023-11-0707 November 2023 Project Manager Assignment IR 05000317/20230402023-11-0202 November 2023 95001 Supplemental Inspection Report 05000317/2023040 and Follow-Up Assessment Letter IR 05000317/20230032023-11-0101 November 2023 Integrated Inspection Report 05000317/2023003 and 05000318/2023003 IR 05000317/20230902023-10-26026 October 2023 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000317/2023090 ML23289A1202023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23279A1202023-10-0606 October 2023 Response to NRC Inspection Report and Preliminary White Finding IR 05000317/20230502023-09-29029 September 2023 Special Inspection Report 05000317/2023050 and Preliminary White Finding and Apparent Violation ML23272A1032023-09-29029 September 2023 Condition Prohibited by Technical Specifications Due to Inoperable Nuclear Instrumentation at Very Low Power IR 05000317/20234012023-09-18018 September 2023 Cyber Security Inspection Report 05000317/2023401 and 05000318/2023401 ML23254A0012023-09-0505 September 2023 Registration of Use of Casks to Store Spent Fuel IR 05000317/20230052023-08-31031 August 2023 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2023005 and 05000318/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23241A8412023-08-29029 August 2023 Response to Request for Additional Information - Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping ML23240A3872023-08-28028 August 2023 Senior Reactor and Reactor Operator Initial License Examinations ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration ML23219A1662023-08-16016 August 2023 Request for Additional Information Regarding Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping (EPID: L-2023-LLR-0006) - Non-proprietary ML23228A1002023-08-15015 August 2023 Notification of Readiness for NRC 95001 Inspection ML23188A0402023-08-0808 August 2023 Issuance of Amendment Nos. 346 and 324 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 ML23214A1572023-08-0707 August 2023 Correction to the Renewed Facility Operating License Page 3 in Amendment No 345 IR 05000317/20230022023-08-0303 August 2023 Integrated Inspection Report 05000317/2023002 ML23188A0512023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 336 and 314 ML23186A0372023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 340 and 318 IR 05000317/20233012023-07-12012 July 2023 Initial Operator Licensing Examination Report 05000317/2023301 and 05000318/2023301 IR 05000317/20230122023-07-10010 July 2023 Commercial Grade Dedication Report 05000317/2023012 and 05000318/2023012 ML23180A2362023-06-29029 June 2023 Correction of Errors on Technical Specification Pages RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators ML23156A6752023-06-20020 June 2023 Request for Withholding Information from Public Disclosure for Proposed Alternative to the Requirements for Repair/Replacement of Saltwater System Buried Piping 2024-02-01
[Table view] |
Text
April 23, 2008 Mr. James A. Spina, Vice President Calvert Cliffs Nuclear Power Plant, Inc.
Calvert Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, Maryland 20657-4702
SUBJECT:
CALVERT CLIFFS NUCLEAR POWER PLANT - NOTIFICATION OF INSPECTION OF THE IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES USING TEMPORARY INSTRUCTION 2515/171
Dear Mr. Spina:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC) staff will conduct an inspection at Calvert Cliffs Nuclear Power Plant the week of May 19, 2008. The inspection team will be led by Mr. William Cook from the NRC Region I office. The team will be composed of the resident inspector, an NRR inspector/contractor, and the team leader. The inspection will be conducted in accordance with NRC Temporary Instruction 2515/171, Verification of Site Specific Implementation of B.5.b Phase 2 and 3 Mitigation Strategies.
In order for the NRC to adequately prepare for this inspection, please furnish the documents listed in Enclosure 1 to the NRC team lead, resident inspector, and NRR inspector (one copy each) at least two weeks prior to the planned on site inspection.
Please have available on site at the beginning of the inspection the documents listed in . Ms. Susan Reichard, of your staff, has been advised of this request and other inspection team support needs, including the names and addresses of the inspectors assigned to this inspection.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018, which expires on June 30, 2009.
Mr. James A. Spina 2 Your cooperation and support during this inspection will be appreciated. If you have any questions regarding this inspection, please contact Mr. Cook at (610)337-5074, or me at (610)337-5146.
Sincerely,
/RA/
John F. Rogge, Chief Engineering Branch 3 Division of Reactor Safety Docket Nos.: 50-317, 50-318 License Nos.: DPR-53, DPR-69
Enclosures:
- 1. Documentation Requested Prior to the Inspection
- 2. Arrangements/Documents Requested to be Available Onsite During the Inspection Week
Mr. James A. Spina 2 Your cooperation and support during this inspection will be appreciated. If you have any questions regarding this inspection, please contact Mr. Cook at (610)337-5074, or me at (610)337-5146.
Sincerely,
/RA/
John F. Rogge, Chief Engineering Branch 3 Division of Reactor Safety Docket Nos.: 50-317, 50-318 License Nos.: DPR-53, DPR-69
Enclosures:
- 1. Documentation Requested Prior to the Inspection
- 2. Arrangements/Documents Requested to be Available Onsite During the Inspection Week SUNSI Review Complete: JR (Reviewers Initials)
DOCUMENT NAME: T:\DRS\DIRECTOR\Cook\Calvert Cliffs Request Letter for B5b info.doc ADAMS ACC#ML081160154 After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS RI/DRS RI/DRP NAME WCook/WC JRogge/JR GDentel/GD DATE 04/23/2008 04/23/2008 04/23/2008 OFFICIAL RECORD COPY
Mr. James A. Spina 3 cc w/encl:
M. J. Wallace, President, Constellation Generation J. M. Heffley, Senior Vice President and Chief Nuclear Officer President, Calvert County Board of Commissioners C. W. Fleming, Esq., Senior Counsel, Nuclear Generation Group J. Gaines, Director, Licensing Director, Nuclear Regulatory Matters R. McLean, Manager, Nuclear Programs K. Burger, Esquire, Maryland People's Counsel R. Hickok, NRC Technical Training Center S. Pattison, SLO (2)
Mr. James A. Spina 4 Distribution w/encl: (via E-mail)
S. Collins, RA M. Dapas, DRA M. Gamberoni, DRS D. Roberts, DRS S. Williams, RI OEDO (Acting)
J. Lubinski, NRR D. Pickett, PM, NRR A. Muniz, NRR G. Dentel, DRP B. Bickett, DRP J. Hawkins, DRP S. Kennedy, DRP, Senior Resident Inspector M. Davis, DRP, Resident Inspector C. Newgent, DRP, Resident OA J. Rogge, DRS W. Cook, DRS Region I Docket Room (with concurrences)
ROPreports@nrc.gov
DOCUMENTATION REQUESTED PRIOR TO THE INSPECTION Please provide the items below two weeks prior to the onsite inspection week. For any items below not supplied prior to the onsite inspection week, please have the item available at the start of the onsite inspection. Please provide as much as possible in electronic format. You are reminded to properly identify and handle all Official Use Only-Security-Related Information and/or Proprietary Information in accordance with current guidance.
- 1. Copies of procedures/guidelines that were revised or generated to implement the mitigation strategies. These could be Extensive Damage Mitigation Guidelines (EDMGs), SAMGs, EOPs, AOPs, etc.
- 2. A matrix that shows the correlation between the mitigation strategies identified in NEI 06-12 and the site-specific procedures or guidelines that are used to implement the strategy.
- 3. Engineering evaluations/calculations that were used to verify engineering bases for the mitigation strategies.
- 4. Simplified flow diagrams for systems relied upon in the mitigation strategies.
These diagrams could be the type used for training.
- 5. Simplified drawings/descriptions of modifications that were made to plant systems to implement the mitigation strategies.
Enclosure 1
ARRANGEMENTS/DOCUMENTS REQUESTED TO BE AVAILABLE ONSITE DURING THE INSPECTION WEEK
- 1. Provide a conference room to accommodate up to four (4) NRC staff. Preferably this would be outside the protected area.
- 2. Site B.5.b contact person(s) should be available for the week
- 3. B.5.b engineering persons(s) should be on call for questions about any engineering calculations.
- 4. Appropriate Operations staff should be available, as needed, for plant walkdowns throughout the week.
- 5. Modification packages for any plant modifications performed as a result of B.5.b.
- 6. Detailed drawings (e.g., P&IDs) of systems used to implement mitigating strategies.
- 7. Copies of procedures/guidelines that were revised or generated to implement the mitigation strategies. These could be Extensive Damage Mitigation Guidelines (EDMGs), SAMGs, EOPs, AOPs, etc. This is the same as Item 1 to Enclosure 1, except that hard copies of these procedures/guidelines should be made available for each member of the inspection team.
- 8. Copies of procedures used to inventory equipment used in the mitigation strategies (e.g., hoses, fittings, pumps, etc.).
- 9. Training records/ training matrix/ lesson plans related to B.5.b.
- 10. Copies of Memoranda of Understanding (MOUs) with local fire departments or other emergency services that are required to implement any mitigating strategies.
- 11. Copies of any evaluations performed to document that enough equipment is available to implement the mitigating strategies (e.g., enough fire hose or electrical cable is available based on a plant walkdown or review of drawings).
- 12. You are reminded to properly identify and handle all Official Use Only - Security-Related Information and/or Proprietary Information in accordance with current guidance.