MONTHYEARML0633803172006-12-0505 December 2006 Enclosure 1 - Addressee List Project stage: Request ML0634604402006-12-13013 December 2006 Response Date for Request for Additional Information Regarding Resolution of Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power (TAC Nos. MD0947 Through MD1050) Project stage: RAI ML0703300512007-01-31031 January 2007 2 & 3; Sequoyah, Units 1 & 2 and Watts Bar, Unit 1 - Request for Additional Information Regarding Resolution of Generic Letter 2006-02, Grid Reliability and Impact on Plant Risk & Operability of Offsite Power Project stage: Request ML0703701932007-01-31031 January 2007 Response to Request for Additional Information Regarding Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power. Project stage: Response to RAI ML0718701522007-07-0909 July 2007 Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power Project stage: Other 2006-12-05
[Table View] |
|
---|
Category:Letter
MONTHYEARML24311A1882024-11-0808 November 2024 Request to Remove Document from Public Availability and Withhold Proprietary Information from Public Disclosure, Mcguire Nuclear Station, Unit No. 1 ML24304A9602024-11-0505 November 2024 Proposed Alternative for the Inspection of Reactor Vessel Closure Head Penetrations IR 05000369/20240032024-11-0404 November 2024 Integrated Inspection Report 05000369/2024003 and 05000370/2024003 ML24303A4212024-10-30030 October 2024 Mcguire Nuclear Station, Units 1 & 2, Notification of an NRC Fire Protection Team Inspection FPTI NRC 05000369/2025010, 05000370/2025010 and Request for Information RFI IR 05000369/20244022024-10-0808 October 2024 Security Baseline Inspection Report 05000369/2024402 05000370/2024402 IR 05000369/20240052024-08-26026 August 2024 Updated Inspection Plan for McGuire Nuclear Station, Units 1 and 2, (Report 05000369-2024005 and 05000370-2024005) IR 05000369/20244042024-08-0101 August 2024 Cover Letter Security Baseline Inspection Report 05000369/2024404 and 05000370/2024404 IR 05000369/20253012024-07-29029 July 2024 Notification of Licensed Operator Initial Examination 05000369/2025301 and 05000370/2025301 IR 05000369/20244032024-07-25025 July 2024 – Cyber Security Inspection Report 05000369/2024403 and 05000370/2024403 Rev IR 05000369/20240022024-07-24024 July 2024 Integrated Inspection Report 05000369/2024002 and 05000370/2024002 ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000369/20244012024-07-0303 July 2024 – Security Baseline Inspection Report 05000369/2024401 and 05000370/2024401 ML24176A2802024-06-26026 June 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000369-2024404 and 05000370-2024404) IR 05000369/20240112024-06-0404 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000369/2024011 and 05000370/2024011 ML24149A1772024-05-28028 May 2024 NRC Response to Duke Energy 2025 FOF Schedule Change Request (Catawba and McGuire) IR 05000369/20240012024-05-0808 May 2024 Integrated Inspection Report 05000369-2024001 and 05000370-2024001 and 07200038-2024001 ML24110A0382024-04-30030 April 2024 – Correction to Issuance of Amendment Nos. 330 and 309, Regarding Implementation of Technical Specifications Task Force (TSTF) Traveler TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf ML24100A8742024-04-10010 April 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000369/2024403; and 05000370/2024403 ML24052A3062024-04-0808 April 2024 Issuance of Amendment Nos. 331 & 310, Regarding Adoption of Title 10 of Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Plants ML24031A5402024-03-26026 March 2024 Issuance of Amendment Nos. 330 and 309 Regarding Implementation of TSTF 505,Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B ML24085A2402024-03-21021 March 2024 Requalification Program Inspection - McGuire Nuclear Station IR 05000369/20230062024-02-28028 February 2024 Annual Assessment Letter for McGuire Nuclear Station, Units 1 and 2 - NRC Inspection Report 05000369/2023006 and 05000370/2023006 ML24024A2182024-02-0505 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000369/20230042024-01-31031 January 2024 Integrated Inspection Report 05000369/2023004 and 05000370/2023004 ML24019A1392024-01-25025 January 2024 TSTF 505 and 50.69 Audit Summary ML24019A2002024-01-24024 January 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000369/20234022023-12-14014 December 2023 – Material Control and Accounting Program Inspection Report 05000369/2023402 and 05000370/2023402 05000369/LER-1923-001, Automatic Actuation of the 1A Motor Driven Auxiliary Feedwater Pump Due to Human Error2023-12-13013 December 2023 Automatic Actuation of the 1A Motor Driven Auxiliary Feedwater Pump Due to Human Error ML23317A2272023-11-17017 November 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Transmittal of Dam Inspection Report - Non-Proprietary ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230032023-10-24024 October 2023 Integrated Inspection Report 05000369/2023003 and 05000370/2023003; and Inspection Report 07200038/2023001 IR 05000369/20240102023-10-13013 October 2023 Notification of McGuire Nuclear Station Comprehensive Engineering Team Inspection – U.S. Nuclear Regulatory Commission Inspection Report 05000369, 370/2024010 IR 05000369/20230102023-10-13013 October 2023 Age Related Degradation Inspection Report 05000369/2023010 and 05000370/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23230A0652023-08-31031 August 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Relief Request Use of Later Edition of ASME Code ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230052023-08-25025 August 2023 Updated Inspection Plan for McGuire Nuclear Station Units 1 and 2 (Report 05000369/2023005 and 05000370/2023005) IR 05000369/20234012023-08-0404 August 2023 – Security Baseline Inspection Report 05000369/2023401 and 05000370/2023401 (OUO-SRI) Cover IR 05000369/20230022023-07-28028 July 2023 Integrated Inspection Report 05000369/2023002 and 05000370/2023002 IR 05000369/20234202023-07-24024 July 2023 – Security Baseline Inspection Report 050003692023420 and 050003702023420 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23159A2712023-06-20020 June 2023 William B. McGuire Nuclear Station, Unit 1 - Relief Request Impractical Reactor System Welds ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined ML23115A2122023-05-0101 May 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report IR 05000369/20230012023-05-0101 May 2023 Integrated Inspection Report 05000369/2023001 and 05000370/2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23094A1832023-04-18018 April 2023 Audit Plan TSTF-505, Rev. 2, RITSTF Initiative 4B & 10 CFR 50.69, Risk-Informed Categorization & Treatment of Structures, Systems & Components for Nuclear Power Reactors (EPIDs L-2023-LLA-0021 & L-2023-LLA-0022) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000369/20220062023-03-0101 March 2023 Annual Assessment Letter for McGuire Nuclear Station Units 1 and 2 (NRC Inspection Report 05000369/2022006 and 05000370 2022006) 2024-08-26
[Table view] |
Text
July 9, 2007 Mr. G. R. Peterson Vice President McGuire Nuclear Station Duke Power Company LLC 12700 Hagers Ferry Road Huntersville, NC 28078
SUBJECT:
MCGUIRE NUCLEAR STATION, UNITS 1 AND 2, RESPONSE TO GENERIC LETTER 2006-02, GRID RELIABILITY AND THE IMPACT ON PLANT RISK AND THE OPERABILITY OF OFFSITE POWER (TAC NOS. MD0997 AND MD0998)
Dear Mr. Peterson:
On February 1, 2006, the U.S. Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power (Agencywide Documents Access and Management System (ADAMS) Accession No. ML060180352), to all holders of operating licenses for nuclear power reactors except those who have permanently ceased operations and have certified that fuel has been removed from the reactor vessel.
GL 2006-02 notified licensees of the NRC staffs need for information in four areas as follows:
(1) use of protocols between the nuclear power plant (NPP) and the transmission system operator (TSO), independent system operator (ISO), or reliability coordinator/authority (RC/RA) and the use of transmission load flow analysis tools (analysis tools) by TSOs to assist NPPs in monitoring grid conditions to determine the operability of offsite power systems under plant technical specifications (TSs). (The TSO, ISO, or RC/RA is responsible for preserving the reliability of the local transmission system. In this GL the term TSO is used to denote these entities);
(2) use of NPP/TSO protocols and analysis tools by TSOs to assist NPPs in monitoring grid conditions for consideration in maintenance risk assessments; (3) offsite power restoration procedures in accordance with Section 2 of NRC Regulatory Guide (RG) 1.155, Station Blackout; and (4) losses of offsite power caused by grid failures at a frequency equal to or greater than once in 20 site-years in accordance with RG 1.155.
Subsequent to the GL, the NRC issued a Request For Additional Information (RAI), (ADAMS Accession No. ML063380308) regarding the resolution of GL 2006-02 to 63 of 65 holders of operating licenses for nuclear power reactors. The RAI requested licensees respond to questions in the following areas:
G. Peterson (1) Switchyard Minimum Voltage; (2) Loss of Real-Time Contingency Analysis (RTCA) Capability; (3) Verification of RTCA Predicted Post-Trip Voltage; (4) Identification of Applicable Single Contingencies; (5) Seasonal Variation in Grid Stress (reliability and Loss-of-offsite power (LOOP) Probability; (6) Interface With Transmission System Operator During Extended Plant Maintenance.
By letters dated March 30, 2006 (ADAMS Accession No. ML06102020168), and January 31, 2007 (ADAMS Accession No. ML070440175), you responded to the information request of GL 2006-02 and the subsequent RAI. Based on the information you provided, the staff has concluded that compliance is being maintained with NRC regulatory requirements governing electric power sources and associated personnel training and considers your response to GL 2006-02 complete.
If you have any questions, please contact me 301-415-1345.
Sincerely,
/RA/
John Stang, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-369 and 50-370 cc: See next page
ML06102020168), and January 31, 2007 (ADAMS Accession No. ML070440175), you responded to the information request of GL 2006-02 and the subsequent RAI. Based on the information you provided, the staff has concluded that compliance is being maintained with NRC regulatory requirements governing electric power sources and associated personnel training and considers your response to GL 2006-02 complete.
If you have any questions, please contact me 301-415-1345.
Sincerely,
/RA/
John Stang, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-369 and 50-370 cc: See next page Distribution:
Public RidsNrrDorlLpl2-1(EMarinos)
LPL2-1 R/F RidsNrrPMLJStang (hard copy)
JRobinson, NRR RidsNrrDprPgcb RidsAcrsAcnwMailCenter RidsNrrLAMOBrien (hard copy)
RidsOgcRp RidsRgn2MailCenter(JMoorman)
Accession Number: ML071870152 OFFICE NRR/LPL2-1/PM NRR/LPL2-1/LA NRR/LPL2-1/BC NAME JStang:nc MOBrien EMarinos DATE 7/9/07 7/9/07 7/9/07 McGuire Nuclear Station, Units 1 & 2 cc:
Vice President Manager McGuire Nuclear Station Nuclear Regulatory Issues &
Duke Power Company, LLC Industry Affairs 12700 Hagers Ferry Road Duke Energy Corporation Huntersville, NC 28078 526 S. Church St.
Mail Stop EC05P Associate General Counsel and Managing Charlotte, NC 28202 Attorney Duke Energy Carolinas, LLC Division of Radiation Protection 526 South Church Street - EC07H NC Dept of Environment, Health & Natural Charlotte, North Carolina 28202 Resources 3825 Barrett Dr.
County Manager of Mecklenburg County Raleigh, NC 27609-7721 720 E. Fourth St.
Charlotte, NC 28202 Owners Group (NCEMC)
Duke Energy Corporation Regulatory Compliance Manager 4800 Concord Road Duke Energy Corporation York, SC 29745 McGuire Nuclear Site 12700 Hagers Ferry Road Group Vice President, Nuclear Generation Huntersville, NC 28078 & Chief Nuclear Officer P.O. Box 1006-EC07H Senior Resident Inspector Charlotte, NC 28201-1006 U.S. Nuclear Regulatory Commission 12700 Hagers Ferry Road Senior Counsel Huntersville, NC 28078 Duke Energy Carolinas, LLC 526 South Church Street - EC07H Mecklenburg County Charlotte, NC 28202 Department of Environmental Protection 700 N. Tryon St Charlotte, NC 28202 Vice President Customer Relations and Sales Westinghouse Electric Company 6000 Fairview Road, 12th Floor Charlotte, NC 28210 NCEM REP Program Manager 4713 Mail Service Center Raleigh, NC 27699-4713 Assistant Attorney General NC Department of Justice P.O. Box 629 Raleigh, NC 27602