Category:Inspection Plan
MONTHYEARIR 05000456/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2024005 and 05000457/2024005) ML24225A1112024-08-13013 August 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML24164A2132024-06-13013 June 2024 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Braidwood Nuclear Plant IR 05000456/20230062024-02-28028 February 2024 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2023006 and 05000457/2023006) ML23339A0452023-12-0505 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000546/2024010 IR 05000456/20230052023-08-30030 August 2023 Updated Inspection Plan for Braidwood Station Report 05000456/2023005 and 05000457/2023005 IR 05000456/20220062023-03-0101 March 2023 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2022006 and 05000457/2022006) IR 05000456/20220052022-08-22022 August 2022 Updated Inspection Plan for Braidwood Station Units 1 and 2 (Report 05000456/2022005; 05000457/2022005) ML22111A0752022-04-21021 April 2022 Information Request Letter for 2022 Problem Identification and Resolution Inspection at Braidwood Station IR 05000456/20210062022-03-0202 March 2022 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2021006 and 05000457/2021006) IR 05000456/20224022022-02-0404 February 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000456/2022402 05000457/2022402 ML21350A4372021-12-16016 December 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team) Inspection Report 05000456/2022010 and 05000457/2022010 IR 05000456/20210052021-09-0101 September 2021 Updated Inspection Plan for Braidwood Station, Units 1 and 2 (Report 05000456/2021005 and 05000457/2021005) ML21193A0942021-07-12012 July 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21057A1022021-02-25025 February 2021 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000456/2021010; 05000457/2021010 ML21020A1292021-01-20020 January 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000456/2021002; 05000457/2021002 IR 05000456/20200052020-09-0101 September 2020 Updated Inspection Plan for Braidwood Station Units 1 and 2 (Report 05000456/2020005 and 05000457/2020005) ML20183A3912020-07-0101 July 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000456/2020012 and 05000457/2020012 IR 05000456/20190062020-03-0303 March 2020 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2019006 and 05000457/2019006) IR 05000456/20190052019-08-28028 August 2019 Updated Inspection Plan for Braidwood Station, Units 1 and 2 (Report 05000456/2019005; 05000457/2019005) ML19154A6152019-06-0303 June 2019 Ltr. 06/03/19 Braidwood Station, Unit 1 - Notification of NRC Inspection and Request for Information; Inspection Report 05000456/2019004; 05000457/2019004 (DRS-J.Bozga) ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000456/20180062019-03-0404 March 2019 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000457/2018006 and 05000456/2018006) ML18305A3542018-10-31031 October 2018 Ltr. 10/31/18 Braidwood Station, Units 1 and 2 - Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000456/2019010; 05000457/2019010 (DRS-J.CorujoSandin) IR 05000456/20180052018-08-28028 August 2018 Updated Inspection Plan for Braidwood Station, Units 1 and 2 (Report 05000456/2018005 and 05000457/2018005) IR 05000456/20170062018-03-0202 March 2018 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2017006 and 05000457/2017006) IR 05000456/20170052017-08-28028 August 2017 Updated Inspection Plan for Braidwood Station, Units 1 and 2 (Report 05000456/2017005 and 05000457/2017005) IR 05000456/20160062017-03-0101 March 2017 Annual Assessment Letter for Braidwood Station Units 1 and 2 (Report 05000456/2016006 and 05000457/2016006) ML16265A5772016-09-20020 September 2016 E-Mail; Braidwood Station, Unit 1 - Baseline Inservice Inspection Onsite Information Request (Msh) IR 05000456/20160052016-08-31031 August 2016 MID-CYCLE Assessment Letter for Braidwood Station Units 1 and 2 (Report 05000456/2016005; 05000457/2016005) ML16174A0852016-06-21021 June 2016 Notification of NRC Inspection and Request for Information 05000456/2016004; 05000457/2016004 IR 05000456/20150062016-03-0202 March 2016 Annual Assessment Letter for Braidwood Station Units 1 and 2 (Inspection Report 05000456/2015006 and 05000457/2015006) ML15328A5022015-11-24024 November 2015 Request for Information for an NRC Triennial Baseline Component Design Bases Inspection; Inspection Report 05000456/2016008; 05000457/2016008 (Bxj) IR 05000456/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Braidwood, Units 1 and 2 (Report 05000456/2015005; 05000457/2015005) ML15231A1492015-08-17017 August 2015 Ltr. 08/17/15 Braidwood Station, Unit 2 - Notification of NRC Inspection and Request for Information (Txb) IR 05000456/20140012015-03-0404 March 2015 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2014001; 05000457/2014001) ML15021A2322015-01-20020 January 2015 U1 ISI Request for Information ML14245A0692014-09-0202 September 2014 Mid-Cycle Assessment Letter for Braidwood Station, Units 1 and 2 ML14223B2132014-08-11011 August 2014 Heat Sink Request for Information IR 05000456/20130012014-03-0404 March 2014 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2013001; 05000457/2013001) IR 05000456/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter (IR 05000456-13-006 & 05000457-13-006) ML13120A5842013-04-29029 April 2013 Request for Information for an NRC Triennial Baseline Component Design Bases Inspection (CDBI) Inspection Report 05000456-13-007 05000457-13-007 IR 05000456/20120012013-03-0404 March 2013 Annual Assessment Letter - Braidwood Station, Units 1 and 2, 05000456/2012001 and 05000457/2012001 ML12248A3062012-09-0404 September 2012 Mid-Cycle Assessment Letter for Braidwood Station Units 1 and 2 IR 05000456/20110072012-03-0505 March 2012 Annual Assessment Letter for Braidwood Station, Units 1 & 2 (Report 05000456-11-007 and 05000457-11-007) IR 05000456/20110062011-09-0101 September 2011 Mid-Cycle Letter for Braidwood Station, Units 1 and 2, - 05000456/2011-006; 05000457/2011-006 ML1024401002010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Braidwood Nuclear Power Plant IR 05000456/20100012010-03-0303 March 2010 Braidwood Power Plant EOC Annual Assessment Letter (05000456-10-001; 05000457-10-001) ML0924404022009-09-0101 September 2009 Braidwood - Mid-Cycle Performance Review and Inspection Plan ML0906302842009-03-0404 March 2009 Annual Assessment Letter - Braidwood (05000456/2010-001; 05000457/2010-001) 2024-08-29
[Table view] Category:Letter
MONTHYEARIR 05000456/20240032024-11-12012 November 2024 Integrated Inspection Report 05000456/2024003 and 05000457/2024003 ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums RS-24-098, Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality2024-10-23023 October 2024 Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality ML24291A0012024-10-17017 October 2024 Submittal of Core Operating Limits Report, Cycle 25 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-095, Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals2024-10-10010 October 2024 Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary IR 05000456/20240112024-09-12012 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000456/2024011 and 05000457/2024011 ML24164A0032024-09-10010 September 2024 Issuance of Amendment Nos. 235 and 235 Revision of Technical Specifications for the Ultimate Heat Sink ML24227A0522024-08-29029 August 2024 Audit Plan for LAR to Remove ATWS Mtc Limit IR 05000456/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2024005 and 05000457/2024005) ML24225A1112024-08-13013 August 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000456/20240022024-08-0808 August 2024 Integrated Inspection Report 05000456/2024002 and 05000457/2024002 ML24172A1252024-07-26026 July 2024 Environmental Assessment and Finding of No Significant Impact Related to a Requested Increase in Ultimate Heat Sink Temperature (EPID L-2024-LLA-0075) - Transmittal Letter ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24163A3922024-06-25025 June 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, & Opportunity for a Hearing (EPID L-2024-LLA-0075)- Letter RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24164A2132024-06-13013 June 2024 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Braidwood Nuclear Plant RS-24-057, License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink2024-06-0404 June 2024 License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink IR 05000456/20240102024-05-31031 May 2024 License Renewal Phase 1 Report 05000456/2024010 RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24136A2452024-05-15015 May 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000457/2024004 ML24136A0132024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report ML24128A1212024-05-0707 May 2024 Response to Braidwood and Dresden FOF Dates Change Request (2025) ML24122A6522024-05-0101 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests IR 05000456/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000456/2024301; 05000457/2024301 RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML24116A0052024-04-25025 April 2024 Transmittal of Braidwood Station, Unit 1, Core Operating Limits Report, Braidwood Unit 1 Cycle 25 IR 05000456/20240012024-04-24024 April 2024 Integrated Inspection Report 05000456/2024001 and 05000457/2024001 ML24113A1272024-04-22022 April 2024 Audit Plan in Support of Review of LAR Revision of TS 3.7.15, 3.7.16, and 4.3.1 (EPID: L-2023-LLA-0136) (Non-Proprietary) IR 05000457/20240902024-04-19019 April 2024 Final Significance Determination for 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Dilution Issue - NRC Inspection Report 05000457/2024090 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-034, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-04-10010 April 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors ML24094A2692024-04-0303 April 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Report, WCAP-17451-P, Revision 2, Reactor Internals Guide Tube Wear Westinghouse Domestic Fleet Operational Projections RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24057A0372024-03-26026 March 2024 Proposed Alternative from Certain Requirements Contained in the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI RS-24-024, Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-22022 March 2024 Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML24067A3252024-03-0707 March 2024 U.S. Department of Energy, Office of Legacy Management, 2023 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites ML24066A0122024-03-0606 March 2024 Operator Licensing Examination Approval Braidwood Station, Units 1 and 2, March 2024 IR 05000456/20244012024-03-0505 March 2024 Cyber Security Inspection Report 05000456/2024401 and 05000457/2024401 (Public) IR 05000456/20230062024-02-28028 February 2024 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2023006 and 05000457/2023006) ML24057A3022024-02-26026 February 2024 Regulatory Conference Supplemental Information ML24047A2382024-02-20020 February 2024 Regulatory Conference to Discuss Risk Associated with 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Leak 2024-09-23
[Table view] |