ML060950051

From kanterella
Jump to navigation Jump to search

Approval of Extension Request for Completion of Corrective Actions in Response to Generic Letter 2004-02
ML060950051
Person / Time
Site: Calvert Cliffs Constellation icon.png
Issue date: 04/12/2006
From: Milano P
Plant Licensing Branch III-2
To: Spina J
Calvert Cliffs
Milano P, NRR/DLPM , 415-1457
References
GL-04-002, TAC MC4672
Download: ML060950051 (6)


Text

April 12, 2006 Mr. James A. Spina, Vice President Calvert Cliffs Nuclear Power Plant, Inc.

Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702

SUBJECT:

CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NO. 1 - APPROVAL OF EXTENSION REQUEST FOR COMPLETION OF CORRECTIVE ACTIONS IN RESPONSE TO GENERIC LETTER 2004-02 (TAC NO. MC4672)

Dear Mr. Spina:

In its letter dated March 3, 2005, as supplemented on July 15, 2005, Calvert Cliffs Nuclear Power Plant, Inc. (the licensee) provided its 90-day response to Nuclear Regulatory Commission (NRC) Generic Letter (GL) 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors, for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 (Calvert Cliffs 1 and 2). In GL 2004-02, the NRC indicated that the primary objective of its technical assessment of Generic Safety Issue (GSI) 191, Assessment of Debris Accumulation on PWR Sump Performance, was to assess the likelihood that the emergency core cooling system and containment spray system pumps at domestic pressurized-water reactors would experience a debris-induced loss of net positive suction head (NPSH) margin during sump recirculation. The NRC also discussed the need to complete corrective actions, including any plant modifications, to address the concerns in GL 2004-02. In addition, the NRC staff stated that all actions should be initiated during the first refueling outage after April 1, 2006, and completed by December 31, 2007. If all corrective actions will not be completed by December 31, 2007, the licensee was to describe how the regulatory requirements would be met until the corrective actions were completed.

In its March 3, 2005, letter, the licensee stated that the information responding to GL 2004-02 contained its request for an extension of the completion date for the corrective actions at Calvert Cliffs 1 from December 31, 2007, to May 31, 2008. The licensees rationale for the extension was the complexities involved in installing a dual train self-cleaning strainer device designed by General Electric Company (an active strainer whose functionality is largely independent of debris load). In an August 30, 2005, response to GL 2004-02, the licensee reiterated its request but changed the extension date to February 24, 2008. In Attachment 2 to the August 30 letter, as supplemented on November 29, 2005, and February 3, 2006, the licensee provided the following justifications for the extension request at Calvert Cliffs 1:

  • A calculation concluding that only small fines of suspended fibrous insulation would be transported to the sump, with the suction flow stream off of the floor where the insulation debris will have settled due to a curb;
  • Applicability of the leak-before-break principle to Calvert Cliffs 1;

J. Spina

  • The existence of uncredited containment overpressure, leading to a clear screen NPSH of approximately 20 feet during a loss-of-coolant accident (LOCA) event;
  • High standards of containment cleanliness at Calvert Cliffs 1; and

The NRC notes the licensees statement that the existing Calvert Cliffs 1 sump screen is of relatively large size at 229 sq. ft., and that, although Calvert Cliffs 1 uses trisodium phosphate as a containment pH buffer, the calcium silicate insulation material, with which the trisodium phosphate might react to form calcium phosphate precipitate, is actually outside of LOCA zones of influence. The licensee concluded that chemical precipitate would not form, and that the calcium silicate insulation would not be dislodged and therefore, could not transport to the sump screen.

The NRC has confidence that the licensee has a plan that will result in the installation of final GSI 191 modifications that provide acceptable strainer function with adequate margin for uncertainties. Further, the NRC has concluded that the licensee has put mitigation measures in place to adequately reduce risk for the requested short extension period, and it is, therefore, acceptable to extend the completion date for the corrective actions for the issues discussed in GL 2004-02 until the completion of the Calvert Cliffs 1 spring 2008 refueling outage, scheduled to begin by February 24, 2008. Should it elect to begin the outage more than 30 days after February 24, 2008, the licensee will need to provide the NRC additional justification for further delay in completing corrective actions for GL 2004-02.

If you have any questions, please contact me at 301-415-1457.

Sincerely,

/RA/

Patrick D. Milano, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-317 cc: See next page

ML060950051 OFFICE LPLI-1\PM LPLI-1\LA SSIB\BC PSPB\BC LPLI-1\BC NAME PMilano SLittle MScott DCollins RLaufer DATE 04/12/06 04/12/06 04/05/06 04/10/06 04/12/06 DISTRIBUTION:

PUBLIC LPLI-1 Reading File C. Haney RidsNrrDorl C. Holden RidsNrrDorl T. Martin RidsNrrDss R. Laufer RidsNrrDorlLplI-1 M. Scott RidsNrrDssSsib D. Collins RidsNrrDprPspb P. Milano RidsNrrPMPMilano L. Whitney S. Little RidsNrrLASLittle B. McDermott, R-I RidsRgn1MailCenter OGC RidsOgcRp ACRS RidsAcrsAcnwMailCenter cc: Plant service list

Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 cc:

President Ms. Patricia T. Birnie, Esquire Calvert County Board of Co-Director Commissioners Maryland Safe Energy Coalition 175 Main Street P.O. Box 33111 Prince Frederick, MD 20678 Baltimore, MD 21218 Mr. Carey Fleming, Esquire Mr. Roy Hickok Sr. Counsel - Nuclear Generation NRC Technical Training Center Constellation Generation Group, LLC 5700 Brainerd Road 750 East Pratt Street, 17th floor Chattanooga, TN 37411-4017 Baltimore, MD 21202 Mr. Louis Larragoite Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685 Mr. R. I. McLean, Manager Nuclear Programs Power Plant Research Program Maryland Department of Natural Resources 580 Taylor Avenue (B wing, 3rd floor)

Tawes State Office Building Annapolis, MD 21401 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Ms. Kristen A. Burger, Esquire Maryland People's Counsel 6 St. Paul Centre Suite 2102 Baltimore, MD 21202-1631