Letter Sequence Request |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement
Administration
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
|
MONTHYEARML0506900352005-03-0303 March 2005 Response to NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request ML0515100172005-05-31031 May 2005 Draft RAI on Response to Generic Letter 2004-02 Project stage: Draft RAI ML0515303042005-06-0303 June 2005 6/3/05, Calvert Cliffs - RAI Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors Project stage: RAI ML0520200572005-07-15015 July 2005 Response to NRC Request for Additional Information Re NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Response to RAI ML0603803582006-02-0909 February 2006 RAI, Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at Pressurized-Water Reactors Project stage: RAI ML0609500512006-04-12012 April 2006 Approval of Extension Request for Completion of Corrective Actions in Response to Generic Letter 2004-02 Project stage: Other ML0618702222006-06-30030 June 2006 Update of Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Basis Accidents at Pressurized Water Reactors Project stage: Other ML0626405472006-09-20020 September 2006 Update of Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML0633407022006-12-18018 December 2006 Unit No.1 - Approval of Extension Request for Completion of Corrective Action in Response to Generic Letter 2004-02 Project stage: Other ML0712703722007-05-0202 May 2007 Revision to Generic Letter 2004-02 Response Project stage: Other ML0734504992007-12-10010 December 2007 Attachment (1) Request for Extension of the Completion Date for Corrective Actions Related to Generic Letter 2004-02 Project stage: Request ML0734504982007-12-10010 December 2007 Request for Extension for Completion of Activities Related to Generic Letter 2004-02 Project stage: Request ML0811307392008-04-22022 April 2008 Revision to Generic Letter 2004-02 Response Project stage: Other ML0817101052008-06-18018 June 2008 Attachment 1, Request for Extension of the Completion Date for Corrective Actions Related to Generic Letter 2004-02 Project stage: Request ML0827404892008-09-30030 September 2008 Supplemental Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors Project stage: Supplement ML0827404972008-09-30030 September 2008 Attachment 2, ECCS and CS System Figures Project stage: Other ML0833003202008-12-0404 December 2008 Request for Additional Information Supplemental Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors-Calvert Cliffs Unit 1 & 2 Project stage: RAI ML0906807672009-03-0404 March 2009 Request for Additional Information: Supplemental Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors Project stage: Supplement ML1009500782010-04-12012 April 2010 Request for Additional Information Generic Letter 2004-02 Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2- Project stage: RAI ML1011903842010-05-0606 May 2010 Notice of Forthcoming Conference Call with Calvert Cliffs to Discuss Supplemental Responses to Generic Ltr. 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors Project stage: Request ML1014708982010-06-0707 June 2010 Summary of Meeting with Calvert Cliffs Nuclear Power Plant, LLC, to Discuss Supplement to Responses to Generic Letter 2004-02 Project stage: Meeting ML1028701002010-09-30030 September 2010 Draft Responses to NRC Request for Additional Information Related to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents on Pressurized-Water.. Project stage: Draft Response to RAI ML1029306502010-10-20020 October 2010 Notice of Forthcoming Conference Call with Duke Energy Carolinas, LLC Regarding McGuire Nuclear Station, Units 1 and 2 and Catawba Nuclear Station, Units 1 and 2, Project stage: Other ML1030810242010-11-10010 November 2010 Summary of November 1, 2010, Meeting with Duke to Discuss Responses to Generic Letter (GL) 2004-02 (Tac Nos. MC4673, MC4674, MC4692, and MC4693) Project stage: Meeting ML1031903612010-11-10010 November 2010 Response to Request for Additional Information Regarding Generic Letter 2004-02 Project stage: Response to RAI ML12356A0852012-12-27027 December 2012 January 8, 2013 - Notice of Teleconference with Calvert Cliffs Nuclear Power Plant, LLC Project stage: Meeting ML13038A5432013-01-24024 January 2013 Chemical Effects Head Loss Experiment (Chle) Test Protocol for Calvert Cliffs Nuclear Power Plant (CCNPP-CHLE-002, Revision 0d) Project stage: Request ML13038A6042013-01-24024 January 2013 PIRT Item Summary Project stage: Request ML13038A4872013-01-24024 January 2013 CCNPP-CHLE-001, Revision 0c, Chemical Effects Head Loss Experiment (Chle) Test Plan for Calvert Cliffs Nuclear Power Plant Project stage: Request ML13038A5782013-01-24024 January 2013 Chemical Effects Pirt Considerations for Calvert Cliffs Nuclear Power Plant (CCNPP-CHLE-003, Revision 0b) Project stage: Request ML13086A5512013-01-24024 January 2013 MC4672 & MC4673 - CCNPP-CHLE-003, Rev 0c Chemical Effects PIRT Considerations Excerpts with Respect to GL2004-02, GSI-191 Project stage: Other ML13030A3482013-02-0707 February 2013 Summary of Teleconference with Calvert Cliffs Nuclear Power Plant, Units 1 and 2 to Discuss Proposed Risk-Informed Approach to the Resolution of Generic LTR 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Des Project stage: Meeting ML13045A1822013-02-19019 February 2013 March 20, 2013, Notice of Forthcoming Teleconference with Calvert Cliffs and Nrc/Nrr Staff to Have Additional Discussions of Licenseess Proposed Path for Resolution of Generic Letter 2004-02 Project stage: Meeting ML13050A5112013-02-19019 February 2013 MC4672-3 Corrected Notice -Public Meeting on March 20, 2013 Re-GL2004-02 Project stage: Request ML13086A5502013-03-0101 March 2013 MC4672 & MC4673, CCNPP-CHLE-002, Rev 0e Chemical Effects Experimental Protocol with Respect to GL2004-02, GSI-191 Project stage: Request ML13088A2202013-03-18018 March 2013 MC4672 & MC4673 - CCNPP-CHLE-005, Rev 1 Chemical Effects Autoclave Experimental Plan with Respect to GL2004-02, GSI-1 91 Project stage: Request ML13086A5492013-03-20020 March 2013 MC4672 & MC4673 - Licensee Presentation-Category 1, Public Meeting on March 20, 2013 with Respect to GL2004-02, GSI-191 Project stage: Meeting ML13091A0552013-04-10010 April 2013 Summary of Meeting on March 20, 2013, with Calvert Cliffs Nuclear Power Plant, LLC, to Discuss the Proposed Risk-Informed Approach to the Resolution of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation D Project stage: Meeting ML13149A3942013-05-20020 May 2013 Chemical Effects Head Loss Experiment (Chle) Test Protocol for Calvert Cliffs Nuclear Power Plant, CCNPP-CHLE-002, Revision 0 May 20, 2013 Project stage: Request ML13149A3992013-05-20020 May 2013 Chemical Effects Autoclave Experiment Test Plan for Calvert Cliffs Nuclear Power Plant CCNPP-CHLE-005, Revision 2, May 20, 2013 Project stage: Request ML13149A4052013-05-23023 May 2013 Metals BENCH-TOP Autoclave Experiment Test Plan for Calvert Cliffs Nuclear Power Plant, CCNPP-CHLE-006, Revision 0, May 23, 2013 Project stage: Request ML13148A3962013-05-29029 May 2013 Forthcoming Meeting with Calvert Cliffs Nuclear Power Plant, LLC to Discuss Licensees Proposed Plan for Resolution of GL 2004-02 Project stage: Meeting ML13179A3132013-07-11011 July 2013 June 12, 2013 Summary of Meeting with Constellation Energy Group, Inc., to Continue Discussions on the Proposed Risk-Informed Approach to the Resolution of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculati Project stage: Meeting ML13224A0942013-08-0606 August 2013 Chemical Effects PIRT Considerations for Calvert Cliffs Nuclear Power Plant, CCNPP-CHLE-003, Revision 0c Project stage: Request ML13224A1032013-08-0808 August 2013 CCNPP-CHLE-007, Revision 0c, Coatings Bench-Top Autoclave Experiment Test Plan for Calvert Cliffs Nuclear Power Plant Project stage: Request ML13226A0902013-08-14014 August 2013 Notice of Forthcoming Meeting with Constellation Energy Nuclear Group, LLC Project stage: Meeting ML13304B4032013-11-0101 November 2013 Notice of Forthcoming Meeting with Constellation Energy Nuclear Group, LLC, Project stage: Meeting ML13319A9392013-11-13013 November 2013 Ri GSI-191 November 2013 Meeting with NRC Rev 0 Project stage: Request ML13310B9292013-12-0606 December 2013 Summary of Meeting with Constellation Energy Group, Inc., to Continue Discussions on the Proposed Risk-Informed Approach to the Resolution of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During . Project stage: Meeting ML14014A0392014-01-29029 January 2014 Summary of Meeting with Constellation Energy Group, Inc., to Continue Discussions on the Proposed Risk-Informed Approach to the Resolution of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Project stage: Meeting 2010-06-07
[Table View] |
Text
Calvert Cliffs Nuclear Power Plant 0
Co tellatio ergy' Nuclear Generation Group U. S. Nuclear Regulatory Commission Washington, DC 20555 1650 Calvert Cliffs Parkway Lusby, Maryland 20657 December 10, 2007 ATTENTION:
SUBJECT:
REFERENCES:
Document Control Desk Calvert Cliffs Nuclear Power Plant Unit Nos. 1 & 2; Docket Nos. 50-317 & 50-318 Request for Extension for Completion of Activities Related to Generic Letter 2004-02 (a)
Letter from G. Vanderheyden (CCNPP) to Document Control Desk (NRC), dated March 3, 2005, Response to NRC Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors" (b)
Letter from J. A. Spina (CCNPP) to Document Control Desk (NRC), dated September 20, 2006, Update of Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors (TAC Nos.
MC4672 and MC4673)
(c)
Letter from P. D. Milano (NRC) to J.
A.
Spina (CCNPP), dated December 18, 2006, Calvert Cliffs Nuclear Power Plant, Unit No. 1 -
Approval of Extension Request for Completion of Corrective Actions in Response to Generic Letter 2004-02 (TAC Nos. MC4672)
In Reference (a), Calvert Cliffs Nuclear Power Plant Inc. (Calvert Cliffs) submitted a response to NRC Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors."
In that letter, Calvert Cliffs committed to completing corrective actions required by GL 2004-02 to resolve Nuclear Regulatory Commission (NRC)
Generic Safety Issue (GSI) 191, "Assessment of Debris Accumulation on PWR Sump Performance," by December 31, 2007 for Unit 2 and requested an extension for Unit I. In a subsequent letter (Reference b)
Calvert Cliffs modified the extension request for Unit I to permit the completion of the installation of the passive containment sump strainer system during the spring 2008 refueling outage. The NRC approved the Unit I extension request in Reference (c).
Calvert Cliffs is fully committed to ensuring that GSI-191 is completely and thoroughly resolved. This is evidenced by the significant amount of work that has been completed to date to address the sump performance concern, including the installation of passive strainers on Unit 2 to substantially increase the available strainer surface area. However, it has recently become evident that certain required activities
Document Control Desk December 10, 2007 Page 2 cannot be completed by the December 31, 2007 due date for Unit 2 or the spring 2008 refueling outage for Unit 1.
Attachment (1) provides the bases for the proposed extensions of the corrective action completion dates required by GL 2004-02 for Units 1 and 2.
The extension basis provides adequate assurance that safe continued operation during the requested extension period is maintained.
Calvert Cliffs Units I and 2 currently meet, and will continue to meet during the period of the requested extensions, the current plant licensing bases regarding the function and operability of the containment sump.
As a result of the remaining required activities discussed in Attachment (1), an extension to June 30, 2008 is requested for Calvert Cliffs Units 1 and 2 to complete the GL 2004-02 corrective actions.
Should you have questions regarding this matter, please contact Mr. Jay S. Gaines at (410) 495-5219.
STATE OF MARYLAND TO WIT:
COUNTY OF CALVERT I, Douglas R. Bauder, being duly sworn, state that I am Plant General Manager - Calvert Cliffs Nuclear Power Plant, Inc. (CCNPP), and that I am duly authorized to execute and file this response on behalf of CCNPP. To the best of my knowledge and belief, the statements contained in this document are true and correct. To the extent that these statements are not based on my personal knowledge, they are based upon information provided by other CCNPP employees and/or consultants.
Such information has been reviewed in accordance with company practice and [ believ~
Subscribed and sworn before me, a Notary Public in and for the State of Maryland and County of Co.-I "e..t~:L
, this ~ day of :DecembeR
,2007.
WITNESS my Hand and Notarial Seal:
My Commission Expires:
DRB/PSF/bjd
Attachment:
(1)
Request for Extension of the Completion Date for Corrective Actions Related to Generic Letter 2004-02