ML052030088

From kanterella
Jump to navigation Jump to search
U1R28 OCC Interactive Turnover Meeting Agenda
ML052030088
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 05/24/2004
From:
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2004-0282
Download: ML052030088 (5)


Text

I Comnmnitted to Nuclear Excellence II EY O Itaf KM Uln2a Point Beach Nuclear Plant U1R28 OCC Interactive Turnover Meeting Agenda Monday, May 24,2004 Start Time: 0600 NSB Cafeteria BRIEFING NOTES ATTENDEES Shift Outage Directors Shift Outage Managers (SOM)

Operations Coordinators (SOC)

Maintenance Coordinators (MOC)

Engineer/ Projects Coordinators (EOM)

Rad Protection Manager (RPM)

Site Safety Coordinator (SSC)

Shutdown Safety Assessor (SSA)

Site Management (SSM)

General Supervisors First Une Supervisors Agenda

1. Safety Issue Discussion (SSC)
2. Radiation Protection (RPM)
3. Operations Coordinator Turnover (SOC)
4. Shutdown Safety Assessment (SSA)
a. Containment Fire Loading SAT / UNSAT -+ Review Deficiencies S. Maintenance Coordinator Turnover (MOC)
6. Engineering Coordinator Turnover (EOM)
7. Major Projects Update (EOM) .-
8. Schedule Review (SOM)
9. Management Expectations (SSM)
10. ACEMAN Assessment Results (SOM)
11. Shift Goals (SOM)

Items Included In Daily Package:

- Site Communication

- Safety Snippet

  • Outage Alara Report

- Outage Status Report

- Shutdown Safety Assessment

- Defined Critical Path

- Work Activity Risk Assignment

- Outage Schedule _ _ _ _ ___ __

IA ,

1

I Committed to Nuclear ExILei"nc) *UIR3F Point Beach Nuclear Plant U1R28 Refueling Outage

- Safety Topic for week of May 23 - 29, 2004 Theme for the week This week's theme deals with odds and ends for Completing the Outage. We are almost done.

A number of critical work activities will be conducted this week in containment and we will begin a major battery change out. It is time to review industry OE from other sites to make sure we've learned from their experiences. Nothing will stop our progress faster than a serious injuryl Daily Safety Snippets Sunday

'Is there an obstmvctionin your way that miqht not stay:'

OE1 3857 May 2002, Fort Calhoun -While moving the reactor vessel head assembly during a refueling outage, the control pendant for the polar crane caught a handrail vertical support pipe, lifting the pipe out of its mount and causing it to fall 20 ft to the walkway below. Individuals were inthe area at the time, but not injured. A review indicated the pendant caught on nearby equipment many times during past refueling outages and corrective actions were not put inplace.

Are there any Items were our equipment gets caught during moves that we have not resolved?

Monday The big picture do we see? And communication is the key. -

OE12357 January 2001, River Bend - A worker focused on a moving load and did not pay attention to the movement of the crane. He ended up being forced against a handrail by the cab of the crane, luckily resulting only inminor injuries.

The entire crew was focused on the load with no one person having oversight of the whole evolution.

During crane operations, do we designate an Individual to Watch the big picture?'

Tuesday SPeer checks - do we use them?'

December 1997, Byron - An electrician was taken to the hospital for treatment of second-degree bums on his hand and flash bums to his eyes as a result of a mishap. He was one of three electricians assisting a system engineer during a battery discharge test on a new battery bank when he accidentally shorted across the battery with one of the cables used to connect the battery to a resistor bank. An Investigation showed that the electricians and the system engineer had not verified the correct cable configuration. Also, the injured electrician was not wearing low voltage gloves and had rolled up the sleeves of the long-sleeve shirt he was required to wear for this job.

What PPE do we wear during baffery work?

Wednesday

.7ust a reminder to be told, balance that JoadP OE1 0902 March 2000, Seabrook - Electricians were offloading battery cells from a metal pallet on a forklift. The offload sequence went from Inside, closest to the forklift, to the outside, furthest from It The result - Instability In the load and the pallet tipped under the weight of the batteries. The cells fractured spilling 19 gallons of sulfuric acidkwater electrolyte In the switchgear room. This OE is not just for battery removal. Balance al your loads!

Thursdav "Make sure the scaffolddoesn't slip and come down too quick. -

OE14551 July 2002, Davis-Besse -A diamond deck plate slipped through a gap between two pieces of ficor grating and dropped 20 ft to the level below, damaging an Instrument ine. The rest of our scaffolding Iscoming down.

Are we aware of the potential holes' for material to go through?

Friday

'Before heat up, make sure someone has done the clean-upi" OE57698 April 2004, Palo Verde - Two mechanics received second degree bums to the face as the result of a flash fire that occurred as they began pre-heating for welding. Isopropyl alcohol was used to clean and liquid had accumulated in the casing of the equipment. The oncoming crew was not aware of this buildup as they began work.

Saturday "Always remember to verify first, or you may take a ride in a hearse.-.

1992, Palisades -An experienced electrical technician at Palisades was electrocuted when he failed to install a circuit jumper before removing test equipment from a current transformer. The existing circuit configuration had not been anticipated during work planning, and the decision to use jumpers to maintain energized current transformer circuits during testing had not been reviewed by supervision.

2

Point Beach Nuclear Plant Outage 1R28 Path Picture DAY 49 Meets Supporting Operational Excellence 1,A I

Outaae Radiation Performance I

M-_4 IA--$

Ljvual I & IVIC~I 0-_A L;AL~UUU 3.n gaig0ga This indicator measures cumulative dose radiation exposure and Day 49 - May 22 Actual = 1.034 total number of personnel-contamination events (PCE's > 5000 Cumulative = 74.083 cpm) during refueling outages. The dose indicator is measured in Cumulative Forecast =74.184 Rem and individual PCE events.

Daily PCE goal reforecast on 4123. Daily dose reforecast on 5123104.

Meets: <=92 Rem Actual Cum. Dose reforecast on 5123104 combining dose received for the RV Head Exceeds: <=88 Rem Dose: 74.083 Rem repairs and also adding 17 rem to the outage goal to reflect the dose received for the repair.

Meets: <= 18 Exceeds: <= 12 Actual PCE's: 10 I*6 t .S 6 -

Stu Thomas I Personnel Contamination Events Cummulative Dose Exposure a

E 0

- Actual - -Actual 0U) .Forecast . . . . Forecast

- Goal 0 Goal 0

04 t0 ED0 0 2 6 102 1416120f24221)02)46380424464S05545386 o22 0 5 10 15 20 25 30 35 40 45 50 55 60

Committed to Nuclear Excellence Outage Status Report Plant: Point Beach Unit 1 Day: Monday Today's Date / Time: 5/24/04 0400 Outage Duration: Day 51 Of Refueling Outage Number U1R28 Safety Status Industrial - Within the last 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> OSHA Recordables 0 First Aid cases 0 Near misses 0 Total for this outage I Summary I Radiological Dose to date 74.083 Projected to date *74.184 Outage Goal S92 R Difference -.101

  • Reforecast on 5/23 Number of PCEs 10 Summary: Dose reforecast on 5/23/04 combining dose received for the RV Head repairs and also adding 17 rem to the outage goal to reflect the dose received for the repair.

Nuclear O-.,

Significant human performance errors and events in last 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> 0 Summary Plant Status Mode: a Hot Standby (Mode 3) a Hot Shutdown (Mode 4) D Cold Shutdown (Mode 5) 0 Refueling Shutdown (lmode 6)

RCS: Temperature: 80 Pressure: Vented to Atmosphere RV Level: 24 Y2%

Time to Boil: 106 minutes A Shutdown Safety Assessment Protected Equipment:

MiMajor Activities Completed In Last 24 Hours Critical Path and Near Critical Path Activities (Next 24 Hours)

  • Drained RCS to 70% Reactor Vessel Level
  • Reactor Head Penetration #26 Relief Request Issues I
  • Replaced RV Head O-Rings
  • Upper Cavity Decon

. Set Reactor Vessel Head

  • Primary Man ylnstallation _
  • Drain RCS to 22% Reactor Vessel Level (Midloop)
  • Exit Midloo and Reduced Inventor
  • Nozzle Dam Removal
  • Remove Cavity Seal Ring
  • Move IP-IB RCP Motor
  • Commence Reactor Head Assembly Significant Outstanding Issues .

Date Issue Due Responsibility 5/17/04 Rx Head Relief Request 5/25/04 Jim Schweitzer 5/20/04 DD105/D106 Station Battery 5/27/04 Harv Hanneman 5/22/04 Reactor Trip Relays 5/27/04 Mike Miller 5/24/04 1 "A" S/G Hotleg Potential FME 5/24/04 Felicia Hennessy Upcoming Ma or Milestones .

Scheduled Actual Scheduled Actual Date Time Date Time Date Time Date Time Cooldown <200° 4/03/04 2100 4/03/04 2230 RCS Fill & Vent 4/23/04 1500 Head Lift 4/09/04 0900 4/21/04 1550 Heatup >2000 4/25/04 0900 Refueled 4/14/04 0300 5/02/04 1848 Reactor Critical 4/28/04 0800 RV Headset 4/18/04 I 1900 5/23/04 1338 On-Line 4/30/04 0100 4

I Point Beach Nuclear Plant PBNP SHUTDOWN'N SAFETY ASSESSMENT AND FIRE CONDITION CHECKLIST OUTAGE SAFETY ASSESSMENT UNIT: 1 DATE: May 24.2004 TIME: 0200 KEY SAFETY FUNCTIONS:

REACTIVITY: GREEN CORE COOLING: ORANGE PONER AVAILABLE: GREEN INVENTORY: ORANGE CONTAINMENT: GREEN STP COOLING: NA PROTECTED EOUIPMENT:

COMMENTS: Fire Protection Condition III: Credit is taken for fire rounds as fire prevention contingency.

PBF-1562 Rercrences: NP 10.3.6 Revision2 10130/02 Page 5 of 9 NP 1W.2.1 5